% Divisional Engineer, Telecom Project 62-Napier Road, Coaxial Station, Ambala Cantt 133001 Ph # 0171-2645618 Fax 2644025. (A Govt. of India Enterprise) SURVEY REPORT FOR PROVISION OF 24 FIBER NEW OFC ROUTE FROM TELEPHONE EXCHANGE JIND TO TELEPHONE EXCHANGE ASSANDH VIA NAGOORA This Survey Report Contains Following Details: S. No. Item 1 Page No. 1. Index 1 2. Introduction/Justification of Scheme 2 3. System Engineering Specifications 3 4. Details of available Equipment site wise 4 5. Details of Proposed Equipment site wise 5 6. Requirement of Material/Broad Material list 6 7. Permissions required 7 8. Route Survey Summary 8 9. Route Survey Diagram 9-16 Checked By Prepared By Harish Kumar DE (TP), Ambala Bhagat Ram SDE (TP), Ambala % Divisional Engineer, Telecom Project 62-Napier Road, Coaxial Station, Ambala Cantt 133001 Ph # 0171-2645618 Fax 2644025. (A Govt. of India Enterprise) 2 JUSTIFICATION FOR THIS SURVEY REPORT 1.0 General: - With Reference to the D. O. No. 4-23/2012 TP/RTPC Dated at ND the 27.10.2014, it was decided to complete the survey on priority bases to lay new Optical Fiber Cable, which is required between Telephone Exchange Jind and Telephone Exchange Assandh section for new upcoming systems. Therefore a new alternate route is planned and surveyed accordingly for this section. 2.0 In accordance, the Survey of Jind to Assandh, OFC alternate route work was undertaken by Sh. Shri Harish Kumar DE TP, Ambala and Shri Bhagat Ram SDE TP, Ambala jointly with Shri Raj Kumar DE (NTR), Karnal and Shri Nitin Kumar JTO (NTR) Jind. 3.0 The 24 Fiber new OFC route will connect Jind, and Assandh. 4.0 The Proposed OFC Cable will be laid from T.E. JInd to T.E. Assandh via Nagoora by making provision of T-Joints for SSA Exchange/BTS falls on the route. Proposed OFC will be laid on the extreme edge of the road boundary through PLB pipe with HDD method in built up area. Soil is soft & difficulty will be anticipated in trenching and cable laying in some of the area where ever road land is encroached by the formers & road land is water logged. The detail summary is as follows. 1 Open Trench = 22.5KM 2 HDD in built up area = 10.0KM 3 HDD where the work has to be = 9.5KM executed on berm because of the un availability of space after berm. 4 Manual Boring = 400M 5 G.I for canal = 100M Checked By Harish Kumar DE (TP), Ambala Prepared By Bhagat Ram SDE (TP), Ambala 3 2.0 ROUTE SURVEY SUMMARY S. No. Item Sec.1 1. 2. Name of Section Jind to Assandh 42.5 Km 3. Jurisdiction 4. 5. Strata No. of Railway Crossing No. of River/Canals No of Bridges/culverts (GI/CC) No. of NH/SH Crossing Built-up area/water logging & encroached area length 6. 6.1. 7. 8. 9 9. 10. Section Length The area where after road berm there is no space i.e the work has to be executed on berm and on berm open trench is not possible because of the busy road. Forest, NH, PWD, and MC of Jind Nagoora & Assandh. Soft Soil, Built up area 2 N0. 1 No. 1 No. Nil 10.0 Km 9.5KM Existing Duct to be Utilized Nil PLB pipe to be laid in RKM 42.5Km 11. Open trenching in KMs (Approx.) 22.50Km 12. 19.50 Km 13. HDD in KMs (Approx.) Manual Boring 14. G. I. 400M 100M Checked By Prepared By Harish Kumar DE (TP), Ambala Bhagat Ram SDE (TP), Ambala 4 3.0 SPECIFICATION of O.F. CABLE:- A) BASIC SPECIFICATIONS OF OPTICAL FIBRE CABLE:The basic Characteristics of Optical Fiber Cable adopted for engineering and survey of the route are in accordance with the directives of Telecom Directorate given as under:S. No. 1. 2. 3. B) Item Value Mono mode 1550 nm 0.3dB/KM for new Cable 4. Type of Fiber Utilized Wavelength band Cable attenuation & Splice Loss Construction 5. 6. 7. 8. Additional OF Cable required Drum Length Cable required for jointing Fiber length Metal Free Jelly filled 24 Fiber O F Cable 1% of PLB pipe 2 Km approximately 20 Meter per Joint 102% of O F Cable length BASIC SPECIFICATIONS OF EQUIPMENT ASSUMED:- Parameters of Equipments adopted for loss Budget calculations are as per TEC Generic Requirements No.GISDH-04 of Feb.’95, DOT Letter No. 45-5/95-TPL (OF)/SDG/Pt. dated 15.07.96. Attenuation for SDH Rings has been taken as per DOT letter No.5-46/98ML dated 06.09.99. S. No. Item 1. Optical Trans Power Value +2 to -3dBm 2. Cable/Equipment Operational Margin 4.0dB 3. Nominal Receive Level -12.6dBm 4. Receiver Threshold -28.0dBm 5. Maximum Section Length 42.5Km Checked By Prepared By Harish Kumar DE (TP), Ambala Bhagat Ram SDE (TP), Ambala 5 4.0 DETAILS OF AVAILABLE EQUIPMENT SITE WISE :- S. No. Item TX/RX 1. 2. Equipment. Power Plant & Jind Assandh STM-4, STM-16 & STM-1, STM-4, DWDM working STM-16 & DWDM here are working here Available Available Battery 3. Accommodation Available Available 4. 3 Phase A.C. Available Available Supply 5. 3-Phase E/A Set Available Available 6. Air Conditioner Available Available 7 Earthing Available Available Checked By Prepared By Harish Kumar DE (TP), Ambala Bhagat Ram SDE (TP)Ambala 6 5.0 S. No. DETAILS OF PROPOSED EQUIPMENT SITE WISE:Item Jind Assandh Nil Nil Nil Nil 1. TX/RX Equipment. 2. PP & Battery 3. E/A Set Nil Nil 4. Air Conditioner Nil Nil 5 Earthing Nil Nil Checked By Prepared By Harish Kumar DE (TP), Ambala Bhagat Ram SDE (TP), Ambala 7 REQUIREMENT OF MATERIAL:- 6.0 S. No. MATERIAL REQUIRED QUANTITY A. Duct i) ii.) iii.) PLB Pipe with accessories 24 Fiber Cable ( RKM x 1.1) Straight Joint Closure iv) Branch Joint Closure v) Wall Splice Closure (WSC) vi) FDF (24F) vii) Viii Spare cable box Plastic couplers 2 200 ix) B B1. B2. B3. B4 C. i) Pigtail 50 Power Plant SMPS Type Nil ii) Battery Sets Nil iii) D. i.) ii.) UPS Tools Nil Splicing Machine OTDR 1 1 iii) Power Meter 1 44.625KM 46.750KM 23No. Nil 2No. 2 Infrastructure for Site Accommodation A/C 3 Phase supply 3 Phase Engine Alternator Nil Nil Nil Nil Battery & Power Plant Checked By Harish Kumar DE (TP), Ambala Prepared By Bhagat Ram SDE (TP), Ambala 8 7.0 A. PERMISSIONS REQUIRED: Permissions are required for laying of PLB pipe, from:- i) PWD : Karnal & Jind ii) Local Bodies : M C, KRL, ASD, Nagoora & Jind iii) Railways : 2 No. iv) National Highway : 2 No’s v) Forest deptt. : Karnal & Jind. vi) NP/WLW : Nil Checked By Prepared By Harish Kumar DE (TP), Ambala Bhagat Ram SDE (TP), Ambala