ELECTRIC SERVICE CONNECTION: WHAT’S NEW? Service Standards Team Power Services OUTLINE ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 1. Where to apply for electric service? • • Business Centers (for loads < or = 50 kw) Sales Offices (for loads >50 kw, underground Distribution system service, network area service) 2. What service voltages are available? (Secondary Service): • Single-phase: 230 volts • Three-phase: 230 volts, 460 volts, 400 volts Service Standards Team Power Services OUTLINE ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 2. What service voltages are available? (Primary Service): • Three-phase: 13.8 kv, 34.5 kv, 115 kv 3. Transformer types for Secondary service voltage • Pole-mtd transformers • Pad-mtd transformers (outdoor) • Transformer vault room: pad-mtd, Deadfront DT Service Standards Team Power Services OUTLINE ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 4. Transformer Bank Capacities (secondary service) • • 1000 kva: 230 volts, 400 volts 2000 kva: 460 volts 5. Transformer vault room locations • Ground level • Second level • 1st basement level (for multiple basements) Service Standards Team Power Services OUTLINE ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 6. Secondary metering schemes • • Single-metered Multiple-metered: common meter center, meter center per floor (optional) 7. Initial requirements for electric service • Application Letter • Electrical Plans • Valid ID • Authority to Occupy Service Standards Team Power Services OUTLINE ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 8. Project-Covered Application (installation of new / or upgrade of distribution facilities) • • • General Process Flow Roles, Responsibilities Timelines Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 1.Where to apply for electric service? • Business Centers (for loads < or = 50 kw) • Sales Offices (for loads >50 50 kw, underground Distribution system service, network area service) North Sales – Valenzuela, M.M. Central Sales – Meralco Center, Pasig City South Sales – Sta. Rosa, Laguna Service Standards Team Power Services Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 1.Where to apply for electric service? Sales Office: • Connected load per meter must be > 50 kw • site will be served / sourced from an underground distribution system • site is located within the Network Area (portion of Binondo, Quiapo, Sta. Cruz..) Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 2. What service voltages are available? (Secondary Service): • Single-phase: 230 volts -maximum of 75kva only • Three-phase: Three phase: 230 volts, 460 volts, 400 volts -Transformers / meters owned by Meralco (Primary Service): • Three-phase: 13.8 kv, 34.5 kv, 115 kv -Meter owned by Meralco, transformers customer-owned -usually applicable to loads beyond serving capacity of secondary-metered services Service Standards Team Power Services Primary Metering Legend: Red Ink / Asterisk - Meralco-Owned Black Ink Blue Ink Customer Owned Service Standards Team Power Services Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 3. Transformer types for Secondary service voltage • Pole-mtd transformers -applicable up to 300 kva maximum only • Transformer vault room: pad pad-mtd, mtd, Deadfront DT -applicable for loads > 300 kva -used in underground distribution system -used in Network area • Pad-mtd transformers (outdoor) Service Standards Team Power Services Overhead Distribution Transformers Service Standards Team Power Services Service Standards Team Power Services Secondary Metering Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 4. Transformer Bank Capacities (secondary service) 1000 kva: 230 volts, 400 volts 2000 kva: 460 volts 5. Transformer vault room locations Ground level Second level 1st basement level (for multiple basements) Note:also applies to primary-metering vault room Service Standards Team Power Services Vault Requirement for Deadfront DTs MINIMUM VAULT DIMENSION LOCATION 1-BANK Ground Floor 2nd Floor (W) 5 m X (D) 4 m X (H) 3 m 1st Basement NOTE: W = Width D = Depth H = Height (Headroom) Service Standards Team Power Services GROUND FLOOR TRANSFORMER VAULT (SIDE ELEVATION) 4000 2000 2000 EXHAUST FAN 8 800 TO T 1000 000 DEADFRONT DT ! $ $ # # " " # # !! !! 2000 EXHAUST DUCT LOUVERED STEEL DOOR 1000 27KV ACCESS ROAD 900 600 SETBACK (VARIES) SERVICE CABLES GROUND ROD 700 25 700 PRIMARY CABLES Service Standards Team Power Services 25 GROUND FLOOR TRANSFORMER VAULT (FRONT ELEVATION) 5000 1100 1400 1400 1100 EXHAUST FAN EXHAUST DUCT 3000 MAIN BREAKER DEADFRONT DT LOW-VOLTAGE SERVICE CABLESService Standards Team Power Services Vault Requirement for Padmounted DTs MINIMUM VAULT DIMENSION LOCATION NOTE: 2-BANKS Ground Floor (W) 8 m X (D) 4 m X (H) 3 m 2nd Floor (W) 8 m X (D) 6 m X (H) 4 m 1st (W) 8 m X (D) 6 m X (H) 3 m Basement W = Width D = Depth H = Height (Headroom) Service Standards Team Power Services G/F Transformer Vault 4000 EXHAUST FAN AND DUCT # # " # # " ! ! TRANSFORMER ACCESS DOOR TRANSFORMER 1000 2500 $ $ CUSTOMER’S MAIN SECONDARY CIRCUIT BREAKER 3000 0 1500 1100 SIDE VIEW PRIMARY CABLE DUCTS Service Standards Team Power Services SECONDARY CABLE DUCTS G/F Transformer Vault (Double Bank) 1600 CUSTOMER’S MAIN SECONDARY CIRCUIT BREAKERS 8000 3300 3100 METER #2 2400 400 METER #1 TRANSFORMER BANK #2 4000 000 TRANSFORMER BANK #1 EXHAUST FANS AND DUCTS S2 PLAN PRIMARY CABLE DUCTS TRANSFORMER ACCESS DOORS 2500 3000 Service Standards Team 3000 Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 6. Secondary metering schemes • Single-metered • Multiple-metered: -common common meter center -meter center per floor (optional) Service Standards Team Power Services Single Metering Legend: Red Ink / Asterisk - Meralco-Owned Black Ink Blue Ink Customer Owned Service Standards Team Power Services Multi- Metering – Common Meter Center Legend: Red Ink / Asterisk - Meralco-Owned Black Ink Blue Ink Customer Owned Service Standards Team Power Services Multi- Metering per Floor G Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 7. Initial requirements for electric service • Application Letter -to formalize the applicant’s request for electric service • Electrical Plans -electrical electrical load schedules / single single-line line diagram / site devt -transformer vault plans / designs -customer substation plans / designs • Valid ID -Individual / corporation / business • Authority to Occupy Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 8. Project-Covered Application (installation of new / or upgrade of distribution facilities) General Process Flow Roles, Responsibilities Timelines Service Standards Team Power Services Project-Covered Application: DISTRIBUTION TRANSFORMER EXTENSION OF FACILITIES SERVICE DROP METER ADDITIONAL FACILITY beyond 30m from the nearest pole Applying customer Service Standards Team Power Services Existing facility Service Standards Team Power Services Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 8. Project-Covered Application (installation of new / or upgrade of distribution facilities) • Roles, Responsibilities Meralco: 1. Receive application 2 Design proposed facilities 2. 3. Advise service entrance construction / location 4. Secure permits / ROW 5. Present contract to applicant 6. Accept payment / charges / signed contract 7. Commence installation of proposed facilities 8. Energize service Service Standards Team Power Services ELECTRIC SERVICE CONNECTION:WHAT’S NEW? 8. Project-Covered Application (installation of new / or upgrade of distribution facilities) • Roles, Responsibilities Applicant: 1. Apply for electric service / submit requirements 2 Construct service entrance according to specs 2. 3. Accept contract / conditions of electric service 4. Advise Meralco to inspect service entrance 5. Secure CEI 6. Pay required charges / deposit Service Standards Team Power Services 8. Project-Covered Application (installation of new / or upgrade of distribution facilities) •Timelines: Project Execution Time Varies: M Reckoning Date is Completion of ALL Requirements (Service Entrance, Civil Works, CFEI, Contract, Payment, etc) M Factors that affect execution time: M Scope of Work M Required Interruption (Local or Pre-Arranged) M Work Time Restriction M Permits and Right of Way M Others (3rd Party, Typhoon, etc) Service Standards Team Power Services Service Standards Team Power Services Thank You Service Standards Team Power Services Service Standards Team Power Services