Uploaded by olislorenzo26

Meralco

advertisement
ELECTRIC
SERVICE
CONNECTION:
WHAT’S NEW?
Service Standards Team
Power Services
OUTLINE
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
1. Where to apply for electric service?
•
•
Business Centers (for loads < or = 50 kw)
Sales Offices (for loads >50 kw, underground
Distribution system service, network area service)
2. What service voltages are available?
(Secondary Service):
•
Single-phase: 230 volts
•
Three-phase: 230 volts, 460 volts, 400 volts
Service Standards Team
Power Services
OUTLINE
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
2. What service voltages are available?
(Primary Service):
•
Three-phase: 13.8 kv, 34.5 kv, 115 kv
3. Transformer types for Secondary service voltage
•
Pole-mtd transformers
•
Pad-mtd transformers (outdoor)
•
Transformer vault room: pad-mtd, Deadfront DT
Service Standards Team
Power Services
OUTLINE
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
4. Transformer Bank Capacities (secondary service)
•
•
1000 kva: 230 volts, 400 volts
2000 kva: 460 volts
5. Transformer vault room locations
•
Ground level
•
Second level
•
1st basement level (for multiple basements)
Service Standards Team
Power Services
OUTLINE
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
6. Secondary metering schemes
•
•
Single-metered
Multiple-metered: common meter center, meter
center per floor (optional)
7. Initial requirements for electric service
•
Application Letter
•
Electrical Plans
•
Valid ID
•
Authority to Occupy
Service Standards Team
Power Services
OUTLINE
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
8. Project-Covered Application
(installation of new / or upgrade of distribution facilities)
•
•
•
General Process Flow
Roles, Responsibilities
Timelines
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
1.Where to apply for electric service?
•
Business Centers (for loads < or = 50 kw)
•
Sales Offices (for loads >50
50 kw, underground
Distribution system service, network area service)
North Sales – Valenzuela, M.M.
Central Sales – Meralco Center, Pasig City
South Sales – Sta. Rosa, Laguna
Service Standards Team
Power Services
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
1.Where to apply for electric service?
Sales Office:
•
Connected load per meter must be > 50 kw
•
site will be served / sourced from an
underground distribution system
•
site is located within the Network Area
(portion of Binondo, Quiapo, Sta. Cruz..)
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
2. What service voltages are available?
(Secondary Service):
•
Single-phase: 230 volts
-maximum of 75kva only
•
Three-phase:
Three
phase: 230 volts, 460 volts, 400 volts
-Transformers / meters owned by Meralco
(Primary Service):
•
Three-phase: 13.8 kv, 34.5 kv, 115 kv
-Meter owned by Meralco, transformers customer-owned
-usually applicable to loads beyond serving capacity of
secondary-metered services
Service Standards Team
Power Services
Primary Metering
Legend:
Red Ink / Asterisk - Meralco-Owned
Black Ink
Blue Ink
Customer Owned
Service Standards Team
Power Services
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
3. Transformer types for Secondary service voltage
•
Pole-mtd transformers
-applicable up to 300 kva maximum only
•
Transformer vault room: pad
pad-mtd,
mtd, Deadfront DT
-applicable for loads > 300 kva
-used in underground distribution system
-used in Network area
•
Pad-mtd transformers (outdoor)
Service Standards Team
Power Services
Overhead Distribution Transformers
Service Standards Team
Power Services
Service Standards Team
Power Services
Secondary Metering
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
4. Transformer Bank Capacities (secondary service)
1000 kva: 230 volts, 400 volts
2000 kva: 460 volts
5. Transformer vault room locations
Ground level
Second level
1st basement level (for multiple basements)
Note:also applies to primary-metering vault room
Service Standards Team
Power Services
Vault Requirement for Deadfront
DTs
MINIMUM VAULT DIMENSION
LOCATION
1-BANK
Ground Floor
2nd Floor
(W) 5 m X (D) 4 m X
(H) 3 m
1st Basement
NOTE:
W = Width
D = Depth
H = Height (Headroom)
Service Standards Team
Power Services
GROUND FLOOR
TRANSFORMER VAULT
(SIDE ELEVATION)
4000
2000
2000
EXHAUST
FAN
8
800
TO
T
1000
000
DEADFRONT
DT
!
$
$
#
#
"
" #
#
!!
!!
2000
EXHAUST
DUCT
LOUVERED
STEEL
DOOR
1000
27KV
ACCESS ROAD
900
600
SETBACK
(VARIES)
SERVICE
CABLES
GROUND
ROD
700
25
700
PRIMARY CABLES
Service Standards Team
Power Services
25
GROUND FLOOR
TRANSFORMER VAULT
(FRONT ELEVATION)
5000
1100
1400
1400
1100
EXHAUST
FAN
EXHAUST
DUCT
3000
MAIN
BREAKER
DEADFRONT
DT
LOW-VOLTAGE
SERVICE CABLESService Standards Team
Power Services
Vault Requirement for
Padmounted DTs
MINIMUM VAULT DIMENSION
LOCATION
NOTE:
2-BANKS
Ground Floor
(W) 8 m X (D) 4 m
X (H) 3 m
2nd Floor
(W) 8 m X (D) 6 m
X (H) 4 m
1st
(W) 8 m X (D) 6 m
X (H) 3 m
Basement
W = Width
D = Depth
H = Height (Headroom)
Service Standards Team
Power Services
G/F Transformer Vault
4000
EXHAUST FAN
AND DUCT
#
#
" #
#
"
!
!
TRANSFORMER
ACCESS DOOR
TRANSFORMER
1000
2500
$
$
CUSTOMER’S
MAIN
SECONDARY
CIRCUIT
BREAKER
3000
0
1500
1100
SIDE VIEW
PRIMARY
CABLE DUCTS
Service Standards Team
Power Services
SECONDARY
CABLE
DUCTS
G/F Transformer Vault
(Double Bank)
1600
CUSTOMER’S MAIN
SECONDARY CIRCUIT
BREAKERS
8000
3300
3100
METER #2
2400
400
METER #1
TRANSFORMER
BANK #2
4000
000
TRANSFORMER
BANK #1
EXHAUST FANS
AND DUCTS
S2
PLAN
PRIMARY
CABLE DUCTS
TRANSFORMER
ACCESS DOORS
2500
3000
Service Standards Team
3000 Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
6. Secondary metering schemes
•
Single-metered
•
Multiple-metered:
-common
common meter center
-meter center per floor (optional)
Service Standards Team
Power Services
Single Metering
Legend:
Red Ink / Asterisk - Meralco-Owned
Black Ink
Blue Ink
Customer Owned
Service Standards Team
Power Services
Multi- Metering – Common
Meter Center
Legend:
Red Ink / Asterisk - Meralco-Owned
Black Ink
Blue Ink
Customer Owned
Service Standards Team
Power Services
Multi- Metering per Floor
G
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
7. Initial requirements for electric service
•
Application Letter
-to formalize the applicant’s request for electric service
•
Electrical Plans
-electrical
electrical load schedules / single
single-line
line diagram / site devt
-transformer vault plans / designs
-customer substation plans / designs
•
Valid ID
-Individual / corporation / business
•
Authority to Occupy
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
8. Project-Covered Application
(installation of new / or upgrade of distribution facilities)
General Process Flow
Roles, Responsibilities
Timelines
Service Standards Team
Power Services
Project-Covered Application:
DISTRIBUTION
TRANSFORMER
EXTENSION OF
FACILITIES
SERVICE
DROP
METER
ADDITIONAL
FACILITY
beyond 30m from the nearest pole
Applying
customer
Service Standards Team
Power Services
Existing
facility
Service Standards Team
Power Services
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
8. Project-Covered Application
(installation of new / or upgrade of distribution facilities)
•
Roles, Responsibilities
Meralco:
1. Receive application
2 Design proposed facilities
2.
3. Advise service entrance construction / location
4. Secure permits / ROW
5. Present contract to applicant
6. Accept payment / charges / signed contract
7. Commence installation of proposed facilities
8. Energize service
Service Standards Team
Power Services
ELECTRIC SERVICE CONNECTION:WHAT’S NEW?
8. Project-Covered Application
(installation of new / or upgrade of distribution facilities)
•
Roles, Responsibilities
Applicant:
1. Apply for electric service / submit requirements
2 Construct service entrance according to specs
2.
3. Accept contract / conditions of electric service
4. Advise Meralco to inspect service entrance
5. Secure CEI
6. Pay required charges / deposit
Service Standards Team
Power Services
8. Project-Covered Application
(installation of new / or upgrade of distribution facilities)
•Timelines:
Project Execution Time Varies:
M Reckoning Date is Completion of ALL Requirements
(Service Entrance, Civil Works, CFEI, Contract,
Payment, etc)
M Factors that affect execution time:
M Scope of Work
M Required Interruption (Local or Pre-Arranged)
M Work Time Restriction
M Permits and Right of Way
M Others (3rd Party, Typhoon, etc)
Service Standards Team
Power Services
Service Standards Team
Power Services
Thank You
Service Standards Team
Power Services
Service Standards Team
Power Services
Download