Uploaded by Michael Boateng

risk management G1

advertisement
1
RISK MANAGEMENT PLAN
SOLAR ELECTRIC MAIZE DRYER
GROUP 1
S.E.M.D
ASHESI UNIVERSITY
ABURI, GHANA
2802/2022
2
TABLE OF CONTENTS
INTRODUCTION .................................................................................................................................3
TOP THREE RISKS .............................................................................................................................3
RISK MANAGEMENT APPROACH .......................................................................................................4
RISK IDENTIFICATION .......................................................................................................................4
RISK QUALIFICATION AND PRIORITIZATION ......................................................................................5
RISK MONITORING ............................................................................................................................5
RISK MITIGATION AND AVOIDANCE .................................................................................................5
3
INTRODUCTION
This project is considered a medium risk project as it has an overall risk score of 45 on a scale from
0 to 100. The project risk score is the average of the risk scores of the most significant risks to this
project. (A risk score below 16 is a low-risk project, a score between 16 and 45 is a medium risk
project and a score above 45 is a high-risk project).
Before our risk management began, it is imperative that a foundation is established for providing
structured project information, thus, the following project elements were completed and defined
prior to developing this Risk Management Plan:
•
Define work scope, schedule, resources, and cost elements
o Developed project WBS o Developed detailed schedules
o Estimate project cost
o Identified the required and available resources
o Established performance metrics
•
Define Risk Management Roles and Responsibilities o
Project Manager chairs the risk assessment meetings
o Project team participates in risk assessment meetings and members serve as meeting
recorder and timekeeper
o Key stakeholders participate in risk assessment meetings o Project Sponsor may
participate in risk assessment meetings
TOP THREE RISKS
The top three high probability and high impact risks to this project are:
Potential Malfunction of Sensors and Equipment:
Components have a tendency to read incorrect values when exposed to drastic temperature
variations. For example, the LM35 Linear Temperature Sensor module, its operating temperature
range is from -55°C to 150°C. The output voltage varies by 10mV in response to every °C rise/fall
in ambient temperature, i.e., its scale factor is 0.01V/°C.
Short Lifespan of Electric Components:
Most of our electronics are suitable for prototyping, hence they have lower lifespans compared to
the more commercial components. All our sensors (humidity, temperature etc.) have a longevity
of about 4-5 years.
Potential Theft of Electronic Components
4
The electrical components that we are using for the project have the dire potential to be stolen as
they may be considered valuable. The solar panel for example costs close to 120ghs. If they get
stolen it would be a heavy blow to the project.
RISK MANAGEMENT APPROACH
The approach we have taken to manage risks for this project included a methodical process by
which the project team identified, scored, and ranked the various risks. The most likely and highest
impact risks were added to the project schedule to ensure that the assigned risk managers take the
necessary steps to implement the mitigation response at the appropriate time during the schedule.
Risk managers will provide status updates on their assigned risks in the bi-weekly project team
meetings, but only when the meetings include their risk’s planned timeframe. Upon the completion
of the project, during the closing process, the project manager will analyze each risk as well as the
risk management process. Based on this analysis, the project manager will identify any
improvements that can be made to the risk management process for future projects. These
improvements will be captured as part of the lessons learned knowledge base.
RISK IDENTIFICATION
For this project, risk identification was conducted in the initial project risk assessment meeting.
The project manager [George Arthur], chaired the risk assessment meeting and distributed
stickynotes to each member of the team and allowed 26 minutes for all team members to record as
many risks as possible.
Expert Interview with Engineers
These interviews revealed several risks which were then mitigated by making changes to the
project plan. The remaining risks are included in the Risk Register.
Literature Review of Similar Projects
There have been previous incarnations of an electric maize dryer, hence we researched on these
designs and evaluated their advantages and disadvantages. By identifying what went wrong in
previous projects, we will be able to prevent any repetition of these issues for our project.
Component Datasheet Review
This risk identification saw the project team members go through the specifications of each
electronic component in the prototype. By looking up this, we were well informed about the
necessary conditions that will trigger a malfunction. Perhaps a component is not to be used within
a certain range, else it may be prone to error-readings. Or sensors not being able to operate beyond
the allowed temperature range (in the manufacturers datasheet).
5
RISK QUALIFICATION AND PRIORITIZATION
In order to determine the severity of the risks identified by the team, a probability and impact factor
was assigned to each risk. This process allowed the project manager to prioritize risks based upon
the effect they may have on the project. The team then identified the impact and likelihood of the
risks occurring.
RISK MONITORING
The most likely and greatest impact risks have been added to the project plan to ensure that they
are monitored during the time the project is exposed to each risk. At the appropriate time in the
project schedule a Risk Manager is assigned to each risk. During the bi-weekly project team
meeting the Risk Manager for each risk will discuss the status of that risk; however, only risks
which fall in the current time period will be discussed. Risk monitoring will be a continuous
process throughout the life of this project. As risks approach on the project schedule the project
manager will ensure that the appropriate risk manager provides the necessary status updates which
include the risk status and identification of trigger conditions.
RISK MITIGATION AND AVOIDANCE
The project manager has led the project team in developing responses to each identified risk. As
more risks are identified, they will be qualified and the team will develop avoidance and mitigation
strategies. These risks will also be added to the Risk Register and the project plan to ensure they
are monitored at the appropriate times and are responded to accordingly.
The risks for this project will be managed and controlled within the constraints of time, scope, and
cost. All identified risks will be evaluated in order to determine how they affect this triple
constraint. The project manager, with the assistance of the project team, will determine the best
way to respond to each risk to ensure compliance with these constraints.
In extreme cases it may be necessary to allow flexibility to one of the project’s constraints. Only
one of the constraints for this project allows for flexibility as a last resort. If necessary, funding
may be added to the project to allow for more resources in order to meet the time (schedule) and
scope constraints.
RISK REGISTER
The Risk Register for this project is a log of all identified risks, their probability and impact to the
project, the category they belong to, mitigation strategy, and when the risk will occur. The register
was created through the initial project risk management meeting led by the project manager.
During this meeting, the project team identified and categorized each risk. The Risk Register also
contains the mitigation strategy for each risk as well as when the risk is likely to occur.
6
RISK REGISTER
ID Date
raised
Risk
description
Likelihood Impact
of the risk if the
occurring risk
occurs
Severity
Rating
based on
impact &
likelihood.
Owner
Person
who will
manage
the risk.
2 19/03/22 Project
design and
deliverable
definition is
incomplete.
Low
High
High
Project
Sponsor
3 19/03/22 Project
schedule is
not clearly
defined or
understood.
Low
Medium Medium
Project
Manager
High
Project
Sponsor
3 19/03/22 Potential
Low
theft of
electronic
components.
Medium
Mitigating
action Actions
to mitigate the
risk e.g.
reduce the
likelihood.
Define the
scope in detail
via design
workshops
with input
from subject
matter
experts.
Hold
scheduling
workshops
with the
project team
so they
understand
the plan and
likelihood of
missed tasks is
reduced.
Include a
failsafe option.
Sensors to
beep when a
certain
condition is
met. Place the
dryer at a
secure location
Contingent
Status
action Action
to be taken if
the risk
happens.
Document
assumptions
made and
associated
risks.
Request high
risk items
that are
illdefined are
removed
from scope.
Share the
plan and go
through
upcoming
tasks at each
weekly
project
progress
meeting.
Open
Have
conversation
with security
staff on the
possible
whereabouts
of the dryer.
Open
Open
7
High
High
Electronics The Electronics
team should
Team
provide a
descriptive
documentation
on how the
machine must
be used.
Monthly
diagnostics
and
maintenance
can be
scheduled by
the team.
5 19/03/22 Short
Low
lifespan of
electric
components.
High
Medium
Electronics The Electronics
team should
Team
provide a
descriptive
documentation
on how the
machine must
be used.
Escalate to
Open
Project
Sponsor, such
that after a
scheduled
time (2
years),
components
can be
revised and
changed.
6 10/04/22 Early delivery High
of electronic
items.
High
High
Electronics Phone the
electronics
Team
suppliers to be
clear on the
exact date that
the
merchandise is
set to arrive.
Plan towards Closed
a positive
risk, by
completing
software
circuitry so
that if the
components
arrive earlier
than
expected, we
are not at a
disadvantage.
We know
exactly what
to do and we
move on!
4 19/03/22 Potential
malfunction
of sensors
and
equipment.
Medium
Open
8
SPONSOR ACCEPTANCE
Approved by the Project Sponsor:
Mr. Paul Date.
Constant: PTB (Physikalisch-Technische Bundesanstalt)
Date:
21/03/22.
Download