PRE-BID AND BIDDING PROCESS
Detailed Engineering Design (DED)
No bidding and/or award of contract for a construction project shall be made unless
the detailed engineering investigations, surveys and designs for the project have been
sufficiently carried out in accordance with the standards and specifications prescribed
by the Head Office/agency/corporation concerned.
Electronic Procurement
PhilGEPS
“To promote transparency and information and communications technology shall be
utilized in the conduct of procurement procedures. Accordingly, there shall be a single
portal that shall serve as the primary source of information on all government
procurement.”
BIDDING PROCESS:
Pre-Procurem
ent
Conference
Bid
Submission
Bid Evaluation
Advertisement
and/or Posting
Opening of
Technical
Proposal (incl.
Eligibility docs)
Post-qualificatio
n
Pre-Bid
Conference
Opening of
Financial
Proposal
Contract
Award
Pre-Procurement Conference
- Its main purpose is to determine the readiness to proceed with the bidding process.
- Conducting before advertisement/posting of the Invitation to Bid
- Mandatory for Procurement of Goods with ABC above 2 MILLION PESOS.
- Attended by the following:
1. BAC
2. BAC Secretariat
3. TWG
4. Consultant
Invitation to Bid
The Invitation to Bid shall contain, among others:
a. A brief description of the subject matter of the Procurement
b. A general statement on the criteria to be used by the PE for eligibility check.
c. The Approved Budget for the Contract to be bid.
d. The source of funds
e. The period of availability of the bidding document
f. The contract duration.
PRE-BID CONFERENCE
For ABC ˃ 1M at least 1 pre-bid conference
For ABC < 1M discretion of BAC to conduct pre-bid or any prospective bidder can submit
a written request to conduct pre-bid conference subject for approval
Conference shall be held 12 CD before deadline of submission & receipt of bids but not
earlier than 7 CD from the PhilGEPS posting
Attendance is optional but only those who purchase bidding documents can participate
Discussed in the conference:
-Eligibility Requirements
-Technical Components
-Financial Components)
BID OPENING
Opening of bids is according to the time of submission.
-Technical components – indicate PASSED or FAILED if complete/incomplete
submission
-Financial components – if bid is ABOVE the ABC, automatically DISQUALIFIED
Winning bidder shall submit within 3 days the following:
-ITR
-PhilGEPS
-Licenses & permits stated in the bidding documents
POST QUALIFICATION
If passed, Lowest Calculated Responsive Bid (LCRB) for Goods & Infrastructures or
Highest Rated Responsive Bid (HRRB) for Consulting Services If not (‘post-disqualified’),
BAC will proceed to the second LCB or HRB for post qualification procedure If the bidder
with the second LCB or HRB is post-disqualified, the same procedure shall be repeated
until the LCRB or HRRB is finally determined.
Post qualification procedure must be completed within 7 days or it can be extended by
HOPE by not more than 30 days.
NOTICE OF AWARD
-BAC shall recommend to HoPE the LCRB or HRRB subject for approval.
-BAC shall also notify the losing bidders of the HOPE’s decision.
-If approved, HoPE will issue Notice of Award immediately
-If disapproved, HoPE shall issue a written justification to BAC of the decision based only
on VALID, REASONABLE, and JUSTIFIABLE grounds.
Within 10 CD from receipt of NOA, winning bidder shall submit:
-PCAB license
-Performance security
-JVA (if applicable)
-Signed contract
NOTICE TO PROCEED
Procuring entity shall issue NTP with the approved contract within 3 CD from the date
of approval.
If cost is 50million or below, maximum is 2 CD only.
Contract effectivity shall not be later than 7 days from issuance.