Uploaded by harsha prasad

Pedestrian Steel Bridge Construction Method Statement

advertisement
Method Statement for Construction of
Pedestrian Steel Bridge for Cooling Water Pipes
CONTENTS
1. Scope of Works
2. List of equipment
3. Power
1. Scope of work
1. Extend the existing gabion wall.
2. Construction the foundation base
3. Erect the steel bridge.
Extend the existing gabion wall.
For construct the bridge foundation, existing gabion wall should be extending the 4m towards the
cannel.
When extending the existing gabion wall, keep the existing gabion wall height and same structure.
Place temporary sheet piling protection around the new gabion wall and bridge foundation
area. To prevent Materials falling into the cannel. Keep the minimum 600 mm gap as the
working space.
Use the 9m sheet piles for the cannel side and 6m sheet piles for bridge foundation side.
Excavate the depth using mini excavator and hand excavator for place the gabion baskets to
minimize the soil falling down.
Use submersible pumps for dewatering the working space.
Level the ground level using 200mm thick ABC layer.
Place the gabion baskets as per the drawing and refill the soil up to bridge foundation footing
level.
If excavated soils are weak, please use new soil for refilling.
Use the vibrating poker and 1 ton roller for compact the soil.
Construction the foundation base
Place 50 mm concrete screed (Grade 15) for construct the footing.
Set out footings as detailed drawing, ensure steel sheets are in place to prevent water ingress.
Always have a submersible pump in attendance for use if required.
Excavate to required depths using a combination of a mini excavator and hand excavation in
no-dig areas.
Check levels prior to concrete works.
Concrete is to be supplied as per the specification.
Place Shuttering outside to retain concrete.
Place mesh as details. Concrete to level and vibrate as works proceed.
Complete the gabion wall up to existing height.
After complete concrete curing time, remove the shuttering of foundation.
Fill the soil around concrete foundation & gabion wall and compact the soil using vibration
poker & hand roller.
Remove the temporary sheet piling protection.
Erect the steel bridge.
As per the bridge GAD drawing, place the main two I beam using mobile crane and should be anchor
with foundation.
After that install the connecting beams, plates, handrails.
Complete the torque tightening of all bolts.
Complete the welding as per the specification.
Lay the HDPE pipes through the pipe bridge.
2. List of equipment
5-ton Excavator
Vibration porker
1 Ton roller
Submersible pumps
Sheet piles (9m, 6m)
Shoring sheets
25 Ton mobile crane
Generators
Hand tools
3. Power
220v Power or Generators will be required for these works.
Download