METHOD STATEMENT FOR HDPE PIPE LAYING WORK PROJECT : LAYING OF 500 DIA HDPE TWO PIPE LINE IN A COMMON TRENCH FOR SEA WATER INTAKE AND DISCHARGE LINE FROM PROPOSED POWER PLANT TO INTAKE OF 350 MW LNG FIRED COMBINED CYCLE POWER PLANT PROJECT EMPLOYER : LAKDHANAVI LTD. PREPARED BY : CEYLEX ENGINEERING (PVT) LTD Method Statement for HDPE Pipe Laying 1 GENERAL APPROACH Ceylex Engineering (Pvt) Ltd, (Contractor) will carry out the project with optimum approach and methodology for client. This document has been prepared by Ceylex Engineering, to explain how the Contractor approaches to execute the project to meet the client’s needs. The successful completion of the project will depend on the ability of implementing optimum methodology that leads to integrating the required solutions through timely & technically optimum outcome of the project. 1.1 PROGRAM OF SUBMISSIONS The civil work contractor will submit the detail program to the client after receiving the client’s input on equipment installation and finalizing the method of construction with finalized conceptual design. However, should the client and contractor accept to have a kick-off meeting to expedite the progress of subsequent major dependent activities of the contract upon “the date of site possession” to be given by the client & consultant prior to the commencement date. Project manager of the contractor will make presentation of “program of submissions” in the said meeting. In this case, Ceylex Engineering will submit the aforementioned documents with enough periods for review by the consultant prior to the date of “the site possession”. Otherwise, Ceylex Engineering will submit the “programme of submissions” on the earliest date after the contract of this project. 1.2 PROCUREMENT SERVICES Procurement services will be supervised for review the procurement engineer under the control of the Project Manager. 1.3 QUALITY ASSURANCE AND QUALITY CONTROL Ceylex Engineering will carry out the construction strictly according to the quality procedures prepared by the company in accordance with international standards and practices. The detail QA and QC procedure will be submitted after the contract is finalized. Ceylex Engineering (Pvt) Ltd. Page 1 Original Method Statement for HDPE Pipe Laying 2 SETTING OUT WORK Setting out on the ground will be done by a competent person with total station/theodolite as per approved construction drawings. Correct coordinates and levels shall be taken referring to TBMs established along the road. Pipe line trace shall be marked on the ground as per the construction drawings and agreed by the Engineer. After finalizing the trace, trial pit investigation and other studies shall be carried out. Final setting out work shall be done as per the Engineer instructions after the trial pit excavation. 2.1 PROCEDURE OF SETTING OUT The line and the level of the trenches shall be as per the drawing. The route of the trenching shall be pegged out accurately. Strong sight rails shall be fixed and maintained at every change in gradient and also at as many intermediate points as may be required. Centreline and level to which the excavation shall be carried out shall be marked on these rails. Sight rails shall not be more than 15m apart unless otherwise it is agreed by the engineer. Setting out shall be checked and approved by the engineer before commencing the work. If any objection arises from the vicinity on a marked pipe trace, the excavation shall be hold until the matter is settled by the engineer/employer. 3 Any deviation of the line and/or grade shall be permitted by the engineer. Nominal trench width shall be as indicated in the drawings. AUTHORITIES TO BE CONTACTED BEFORE COMMENCING WORK Sri Lanka Telecom Ceylon Electricity Board Lanka Electricity Company National Water Supply & Drainage Board Department of Wild Life Conservation (if required) Sri Lanka Police Road Development Authority (for major roads) Provincial Road Development Authority (for secondary roads) Ceylex Engineering (Pvt) Ltd. Page 2 Original Method Statement for HDPE Pipe Laying Residents in the vicinity Sri Lanka Forces Local Government (relevant) (for minor roads) Irrigation Department Contractor coordinates the above listed authorities and relevant other parties through the employer and obtains permission for the excavation and pipe laying. SLTB and private bus companies shall be informed at least one week earlier if any traffic re-routing happens due to the excavation and pipe laying work. In such case alternative routes shall be provided and at the both ends of the closed roads signs shall be placed. Traffic Police shall be informed and arrow symbols shall be shown the alternative route for the road users. 4 4.1 HANDLING OF MATERIALS AND EQUIPMENTS MATERIAL The attention shall be paid at the stage of transportation of the material to the site and the method of transportation shall be provided in advance to the engineer for the approval. Protection shall be provided, to the approval of the engineer, for the ends of all pipes and fittings prior to the pipes and fittings leaving the place of manufacture and shall maintain the protection until the items reach their destination in order to guard effectively against damage during transit and storage and the ingress of foreign matter inside the pipes and fittings. Ceylex Engineering shall procure DI pipes and fittings from approved suppliers which ever locally available, since the quantity of material is comparably a smaller amount. Therefore, inspection is not considered for such smaller amount. For transporting bulk loads, vehicles shall be provided with a clean flat bed, free from nails/other projections. All material shall be carefully inspected at the time of delivery and any defective material identified shall be set aside before accepting the delivery into stores/storage yard. Any such defects shall be notified to the supply source immediately and shall be stored separately and returned to the supplier. Material from the different suppliers shall be stored separately for clear identifying. Caps/plugs are to be provided to protect the joining surfaces during the transportation and storage. Pipes and fittings shall be stored well away from exhaust system/other heat sources and possible Ceylex Engineering (Pvt) Ltd. Page 3 Original Method Statement for HDPE Pipe Laying from material such as diesel oil shall be avoided. Care shall also be taken to avoid contact with lubricating/hydraulic oil, gasoline, solvent and other aggressive chemical. As far as practicable protective packaging (pallets, strapping, bags, etc) shall be kept intact until the material is required for use. Temporary capping/plugging of pipe ends shall be done for hygiene purposes. Pipes and fittings likely to be stored outside for a long period longer than 12 months shall be covered by a tarpaulin/black polyethylene sheeting to prevent ultra violet degradation form sunlight. Other than backfilling soil all the materials shall be transported and stored as per the manufacturer’s recommendation in a proper storage yard referring to the approved storing system. For this purpose one/several rented/hired lands shall be used and the location of those lands shall be informed to the engineer in advance. Exact location such lands shall be approved first to the engineer. As the project is spread out through a large area temporary site office shall be located in rented/hired land and the space shall be received for the engineer at the contractor’s site office. All the material other than soil shall be handled as per the manufacturer’s recommendation by using sling wires, cranes and excavators depending on the type of the material, weight, space available, location of the site and other factors to be considered. Metal chains/slings shall not be brought into direct contact with the material if required. Webbed slings of Polypropylene/Nylon shall be used for such cases. Straight pipes shall be fully supported and bound together. For the pipe bundles lengthen than 6m, load spreading beams of a length at least equivalent to one quarter of the length of the pipe/bundle pack shall be employed. Lifting points shall be well spread and evenly spaced which allows some bending in the middle of the lift. All pipe stacks shall be made on sufficient firm, flat ground to support the weight of the pipes and any necessary lifting equipment. Stacking height shall be kept to a minimum and adequate space shall be allocated for lifting machinery. For safety and the convenience of handling, the stacking height shall be maintained to 3m as far as possible. Bundles shall be stored timber to timber to prevent possible deformation of the pipes. The set of recommendations from the manufacturer shall be followed for handling, loading, unloading, transporting and storing of all the sensitive materials. Hooks shall not be used for the lifting of fittings which are generally supplied in cardboard boxes/polythene bags. Ceylex Engineering (Pvt) Ltd. Page 4 Original Method Statement for HDPE Pipe Laying Where the coating of pipes/specials damaged, the surface shall be cleaned and dried and the damaged area shall be painted with a minimum of three coats of approved paint to the full thickness and specification as the original coating. The maximum allowable depth of scoring of the external surface of the pipe is 10% of the wall thickness. Pipes and fittings showing obvious defects/excessive scoring shall be withdrawn, clearly identified as unsuitable and stored separately and returned to the source of supply. Material that can be blown away by the wind during the transportation (soil, sand, etc.) shall be transported by covered trucks. Pipes and fittings shall be inspected before they are transported to the site and records shall be maintained. Engineer shall be notified for the inspection of such material before dispatching to the pipe laying site. Excavated materials that can be used for the backfilling shall be stored in suitable location protecting from weather in a practical manner. 4.2 PACKING OF BOLTS, JOINT RINGS AND GASKETS Bolts of the same length and size shall be packed together in boxes not exceeding 100kg gross weight. Joint Rings and Gaskets shall be packed in boxes and separate packages shall be provided for each size and description of ring/gasket. Each box and package therein shall be clearly labelled stating the number, size and description of the contents. 4.3 MACHINERY AND EQUIPMENTS Utilizing machinery and equipment and their capacities will be varying site wise depending on the ground condition, excavation depths, pipe type, size of the pipe, etc. However as a minimum requirement the sub contractor expect to provide a set of survey instruments, crane (if necessary) and a trailer on sharing basis. Excavator/backhoe loader, dump truck, pile driving equipment (if necessary, water pump, plate compactor, generator shall be generally provided to the sites as the requirement. These equipment shall be maintained periodically by a separate crew. Crew Cab shall be utilized for the transportation needs. Other transportation shall be provided depending on the type of the machinery/equipment to be transported. Parking of the vehicle, storing material/equipment shall be done at the site premises. But in a case of this premises shall not be practicable, a land shall be arranged by the officer-in-charge after discussing with the construction manager. However in a case of cease work for a considerable period all the equipment/machinery shall be stored at the site. Ceylex Engineering (Pvt) Ltd. Page 5 Original Method Statement for HDPE Pipe Laying The engineer shall be informed to inspect shoring material, etc before using them. Such materials shall be listed and the list shall be submitted to the engineer in advance. 5 SAFETY & SECURITY All field personnel will work in accordance with recognized safety standard and codes by government and/or local regulation which may exist or be made. All field personnel will be responsible for adhering to safety and site maintenance rules, and any reasonable recommendation from employer will be closely followed. The identification of the potential treats to safety is necessary. Safety & security plan comprises the following elements: A statement for safety organization of the project. A statement of our corporate and project safety and security policy Identification of the applicable safety regulations, rules and guideline standards Assignment of general and specific responsibilities for safety and security activities to staff, supervisory, foreman and craft personnel and to subcontractors. Requirements for initial safety & security orientation for all employees, subcontractors, if any and their personnel. Identification of work classified as hazardous, and the specification of requirements for hazardous assignment indoctrination and training. Requirements for the issuance, use and care of personnel protective equipment. Requirements for regularly scheduled periodic supervisory and craft safety Requirements for safety & security inspections of work sites and construction tools and equipment. Specifications for required keeping systems. Accident report and record keeping system requirements. Requirements for investigation of accidents. Specifications for standard safety equipments and the usage. Specifications for zero-accident campaign It shall be pay attention to work in the vicinity of followings especially: Fire hazard(naked lights) Work in the vicinity of electrical equipment Portable electrical equipment Ceylex Engineering (Pvt) Ltd. Page 6 Original Method Statement for HDPE Pipe Laying 6 Electrical/ICA test equipment Chlorine TRAFFIC CONTROL PLAN Individual traffic arrangement shall be provided with coordination of relevant police station, traffic division. Night work shall be introduced to the highly congested roads. For the other roads one lane shall be closed and single lane traffic shall be allowed for the pipe laying work. Maximum speed for the vehicle shall be 20kmph where the pipe laying work going on. Barricade Boards Road narrow ahead sign board 25m Approx. 100 m Traffic Cones at 5 - 7m intervals Men at Work ahead sign board Ceylex Engineering (Pvt) Ltd. Page 7 Original Method Statement for HDPE Pipe Laying Figure 1: Traffic control plan for pipe laying along the road 6.1 SIGN BOARDS Sign boards shall be used for the road users to inform about the pipe laying. Following sign boards shall be used mainly. Men at work Road narrow ahead or Figure 2: Traffic signs 6.2 METHOD OF TRAFFIC CONTROL Vehicles shall be controlled at the both ends of the construction part of the road. Two men (traffic controllers) shall be allocated at the both ends to signal the vehicles to move/not to. They will carry “GO” and “STOP” boards and shall have communicative equipments (walky-talky) according to the site location and the distance. The traffic will move when the traffic controller shows the board “GO”, and the traffic will stop and allow the opposite traffic to flow while traffic controller shows the board “STOP”. Ceylex Engineering (Pvt) Ltd. Page 8 Original Method Statement for HDPE Pipe Laying Figure 3: Traffic controller carrying the boards The boards shall be used both the day and the night time due to its property of reflecting the light, but where the engineer requests for another arrangement for the night shifts, reflecting lighting guns shall be used for the traffic control. 6.3 CONSIDERATIONS No more than half of the carriageway shall be obstructed due to the pipe laying by the time of single lane traffic is allowed. The contractor shall be responsible for allocating reasonable material/man power to maintain a smooth traffic flow. 7 7.1 CONSTRUCTION EXECUTION PLAN GENERAL Ceylex Engineering execution plan includes the activities to be developed for site erection and measures to be taken to enhance effectiveness and constructability are discussed together with site coordination and interface requirements. The key element to the successful project is depending on the ability how to approach the project with optimum methodology that leads to integrating the required solutions through timely & technically optimum outcome since each solution is interactive and needs decision making which will lead to the outcome of projects. 7.2 CONSTRUCTION EXECUTION In order to ensure that construction is executed in a planned, efficient and safe manner, principal approach would be to use "constructability concept" during planning, design and procurement phases of the project. The constructability concept is the optimum use of construction knowledge and experience in engineering, procurement and field operations to achieve overall objectives. Ceylex Engineering (Pvt) Ltd. Page 9 Original Method Statement for HDPE Pipe Laying Constructability input is realized by involving experience and competent construction personnel from early stage of the project so that construction related issues are properly reflected in up-front activities. The successful completion of the construction phase will depend upon two fundamentals: A comprehensive and realistic construction strategy; An experienced site organization and the requisite labor resources, all motivated to execute the strategy. In order to achieve this goal, it is essential that the correct project balance of trades is maintained throughout the project and the drawings, materials and equipment lead construction requirements. Ceylex Engineering policy to attain this objective is summarized below: Prior to site mobilization, a comprehensive construction execution plan will be prepared. This will allow the construction team to define in detail the requirements of the project. All fabrication and erection work will be carried out under the direct and continuous management of supervisory staff, backed by detailed planning and coordination of site activities. The construction work will proceed under detailed weekly and monthly work plans developed by the project control section. Loss prevention, site security and sanitation during construction activities are given the highest attention. At the outset of construction, the construction chief engineer will implement the employer's project requirements that will be enforced and maintained by all levels of the assigned loss prevention and site security. 7.3 7.3.1. Ceylex HSEQ officer is required to be part of the team MANPOWER The supervisory and craft personnel will be mobilized in local. For the purpose of efficient mobilization, an advance party, consisting of the construction site manager and selected members of his team, will arrive at site prior to actual start of construction activities. Ceylex Engineering will mobilize key construction personnel in accordance with the construction schedule. The first stage in the supervisory staff mobilization program will be the assignment of key personnel during design/procurement phase to input constructability into the design and for a period of familiarization with the project prior to being assigned to the field. Concurrent with their Ceylex Engineering (Pvt) Ltd. Page 10 Original Method Statement for HDPE Pipe Laying familiarization program, all necessary visas, inoculations, etc. required for entry in Local will be completed. 7.4 CONSTRUCTION EQUIPMENT Ceylex Engineering will use existing construction equipment and tools required for the construction of the facilities. However, some of construction equipment and tools required for the project will be transferred from other job sites and/or purchased abroad based upon our plentiful experiences of overseas construction. Size and type of equipment are subject to change depending on market availability at the actual construction stage. 8 EXCAVATION Trial pits shall be excavated to such depths as necessary to determine and confirm the alignment of the trench. Trial pits shall also be useful for determination of existence of other underground services/utilities. The excavation shall be carried out using backhoe machines/mini excavator/by manually but depending on the type of the pipe, ground condition and depth of the excavation. The excavation in vehicle movable road shall be done using backhoe and mini-excavator. The excavation in footpath shall be done manually. Usually open excavation shall be done with braced cut. Excavated soil shall be directly loaded dump trucks/tractors and transported to separate yard approved by the engineer. The excavated soil suitable for backfilling shall be stock piled in the site/separate locations as required. Any unsuitable excavated shall be legally disposed. Waste disposal lands shall be informed to the engineer later. Excavation for structures such as thrust blocks, valve chambers shall be allowed 300mm working spaces in minimum. Excavation length shall depend on, duration of ground water lowering effect of settlements to adjoining properties width of the road and traffic density Existing services. Ceylex Engineering (Pvt) Ltd. Page 11 Original Method Statement for HDPE Pipe Laying 8.1 PRIOR TO THE EXCAVATION Before starting excavation in any road, the approval shall be obtained from the engineer and the relevant authorities (Listed in section 04) shall be informed with the detailed work program and the relevant details (chainage of the roads, date of commencement, completion date of backfilling, planned dates of completion of temporary reinstatement and the date of handing over). Excavation work shall be started only after, Granting the approval for the program by engineer/relevant authorities. Granting the approval for the pipe and fittings. All the required plants are available for speedy work. The available details of underground services shall be obtained by the relevant authorities and respective residence. The contractor shall protect the underground services and utilities as far as possible. A list of authorities/personnel to be contacted before commencing the excavation work is shown under Section 3 (Authorities to be contacted before commencement of work). 8.2 CONTROL OF WATER The contractor shall keep the excavation free from water during the time of the construction and pipe installation by installing and operating all necessary machinery, appliances and equipments. Disposal of water shall not damage any private property, or should not create any nuisance to the public. A suitable dewatering system shall be used for the excavation depths passes the water table level and for the excavation in the rainy season. The dewatering system shall be supervised and monitored by appropriate qualified personnel. Dewatering system shall be inspected by the engineer if he/she needs. Sump pumping from the edge of the trench shall not be done under any circumstance due to instability of the formation arises. Surface run off shall be controlled so as to prevent entry/collection of water on excavation. Ceylex Engineering (Pvt) Ltd. Page 12 Original Method Statement for HDPE Pipe Laying 8.3 TRENCH WIDTH AND DEPTH The width of trench shall be decided in accordance with the efficient working requirement, ground stability and number and size of pipe to be laid in the trench. The trench dimensions will be maintained as per detail given in table below. Detail of trench for PE pipes 8.4 Dia (mm) Width (m) Depth (m) 90 0.30 1.00 110 0.40 1.12 160 0.45 1.17 225 0.50 1.24 8.3.1 Trench details for OD 500 is missing. Include alongwith OD 250 as well. PIPE BEDDING Before placing the bedding material the excavated surface shall be properly levelled and trimmed. Boulders, loose particles and other impurities shall be removed before compaction and shall be wetted if required for achieving the required CBR value. 8.5 EXCAVATION IN NARROW ROADS Police permission shall be obtained in a rerouting of traffic. Special consideration shall be paid to reroute traffic and make provisions to access adjoining building. Before start of the excavation the existing situation shall be photographed with the consent of property owner. Possible damages to the boundary walls and other properties, the possibilities of repairing such damages with the least inconvenience to the owners and cost effective manner shall be discussed with the owners. The vicinities shall be informed at least one week earlier about the excavation. Excavation length along such roads shall be limited to the minimum. Excavation shall be carried out with an optimum care. Parking spaces and security for the parking premises shall be provided for the residents in case if they cannot use their usual parking place due to construction. Ceylex Engineering (Pvt) Ltd. Page 13 Original Method Statement for HDPE Pipe Laying 8.6 EXCAVATION NEAR UTILITIES Edges of the trench shall be marked on the ground, cut with asphalt cutter and removed by backhoe loader/excavator. Details of house connections for shops, etc shall be inquired and marked on the ground prior to the excavation work. All services lines crossing or along the trench shall be exposed. Such services shall be temporary rerouted/modified wherever possible, to perform trenching operation. Every precaution shall be taken to avoid any damage to the existing services. Under the worst scenario they will be left as they are by providing the supports without disturbing to such services. In case of interrupting water supply due to Contractor’s work, such situation shall be coordinated with the NWS&DB to rectify the situation immediately. Overhead electric wires shall be protected from the construction vehicle operations. Temporary disconnecting the electric services/temporary shifting of electrical wires shall be arranged by coordinating with the relevant authority. 8.7 EXCAVATION NEAR EXISTING STRUCTURES Any existing structures that cannot be temporarily relocated shall be preserved prior to the excavation proceed in the opinion of the engineer. Above mentioned structures shall be carefully protected from damages by the contractor. In order to protect existing structure, the contractor shall do shoring where required. The shoring method shall be submitted for the approval of the engineer. For deep excavation very near to the existing structure, sheet pile shoring shall be used to protect the structures. The arrangement made shall be approved by the contractor and work should be hold until the engineer’s decisions are issued. 8.8 ROCK EXCAVATION Weathered rocks shall be removed by mechanical means as far as possible. 8.9 HANDLING OF EXCAVATED MATERIAL Excavated materials shall be dumped only in locations approved by the engineer and relevant local authorities. Materials that can be reused for backfilling shall be approved by the engineer. Such Ceylex Engineering (Pvt) Ltd. Page 14 Original Method Statement for HDPE Pipe Laying material shall be protected from weather as far as possible. Temporary stock piles at site shall be used along the side of the trenches if there would not be any objection from the relevant authorities. But the disturbance to the public shall be minimized and the rented/hired lands shall be used as temporary stock piles if needed. All the other material shall be dumped legally. 8.10 PRECAUTIONS Breaking of the carriageway shall be done only with the prior approval of the relevant road authorities. Only controlled blasting shall be permitted during the excavation (Refer to the Health, Safety and Environment Programs for more details). Ensure the minimum damage/disturbance to the above/below ground utilities/services. Base and sub base of the road shall be excavated with necessary shoring and ground protecting measures to minimize the collapse/damage to the balance portion of the carriageway. 9 SHORING METHOD AND TRENCH SUPPORT Trenches shall be excavated without shoring/with light shoring/with heavy shoring depending on the stability of the ground. Light shoring/no shoring shall be used for shallow trenches in stable ground with lower ground water table. Arrangements for heavy shoring shall be submitted for the approval to the Engineer before using them. Excavated surfaces too steep shall be protected and supported as necessary to safeguard the work and workmen, to prevent sliding or settling of the adjacent ground. Sheeting Bracing Shoring Other support installation The method of shoring shall be pre-planned in accordance with the trial hole soil logs and shall be submitted to the Engineer for prior approval. Excavation above ground water level shall be done without any side supports where possible. Excavation exceed ground water level shall be provided with timbering/sheeting depending on the Ceylex Engineering (Pvt) Ltd. Page 15 Original Method Statement for HDPE Pipe Laying site condition. Sheet piles shall be driven by a drop hammer when it is excavated to the greater depths. GI Pipe Support GI Sheet Jack "H" Iron Figure 4: Trench supporting system Trenches shall be effectively supported including sheet piles where necessary to prevent any fall/run from any portion of the ground outside the excavation into the trench and to prevent settlement/damage to structures adjacent to the excavation. Where battered sides shall be elected there shall be provided with stable slope (height at a slope of not steeper than one to one from point of 300mm above the pipe). The Contractor shall remove all the supporting installation once the work is finished. 10 PIPE LAYING PROCEDURE Pipe laying between two adjacent manholes/chainages shall be started from the lower elevation to higher elevation for easy draining of ground water in the trench. However there can be case where need to lay pipes in opposite direction also. All pipes shall be laid to lines and grades shown on the drawings. Pipes shall be lowered by using a proper lifting mechanism which is approved by the engineer. Pipes shall be bonded to even gradient. Open ends of the installed pipes shall be plugged with a watertight plug/other approved way when there is no pipe laying in progress. When the pipes are to be ready for joining the plug shall be taken off. Ceylex Engineering (Pvt) Ltd. Page 16 Original Method Statement for HDPE Pipe Laying Pipe ends shall be well cleaned. Material used for plugging shall be approved type that shall adequately protect the pipe from damage, prevent dirt, debris and water from entering the pipe. All pipes shall be checked for defects and cleaned before joining. 10.1.1 Pipe Laying for above ground piping is not mentioned. 10.1 PIPE LAYING Specially, the ground needs to be prepared All pipes shall be carefully inspected for defects before installation. and level before laying Proper installation of pipe shall be carried following steps. the pipes. And subsequently the pipes o Excavation has to be covered with o Preparation of the bed for pipe provided soil. (after o Placing the pipe without damage flushing & Hydro test) The section of the pipe shall be fitted together correctly. Pipe shall be laid true to line and grade. As far as possible pipe shall be lowered by a crane. Whenever the work cease for any reason the unfinished end of the pipeline shall be securely closed. Where the water table is encountered, shall be kept below the sockets when joining by pumping or any other mean. Pipe cutting to the required length shall be done by using pipe cutter and cutting edge of the pipe shall be tapered by using a grinder. The spigot socket shall be cleaned and shaped to ensure that there are no any sharpen edges. The rubber ring shall be cleaned, wiped and placed in the groove of the socket. After placing of the pipe inside of the trench, a thin film of lubricant shall be applied to the inside surface of the rubber ring which shall be contacted with the entering spigot. The outside of the pipe spigot shall be cleaned and the portion shall be piled until rough edges removed and a thin film of lubricant shall be applied at the edge of the pipe. To assemble the joint one of the methods which are mentioned, shall be used to suit the site conditions. o Using ratchet o Using the excavator bucket o Manual Ceylex Engineering (Pvt) Ltd. Page 17 Original Method Statement for HDPE Pipe Laying 10.2 CUTTING OF PIPES Cutting shall be basically depending on the instructions given by the manufacturer. 10.3 JOINTING PIPES Manufacturer’s joining instructions shall be followed. HDPE Pipes 10.3.1 Need to stick to Wiik Welding Manual and welding parameters. Butt fusion welding of pipes Ceylex Engineering (Pvt) Ltd. Page 18 Original Method Statement for HDPE Pipe Laying Fig.1. Aligning and clamping the pipes Butt fusion welding is the name given to hot plate welding of thermoplastic pipes. It is one of two main techniques for the fusion joining of PE (HDPE) water pipe. The Process The heating phase, sometimes referred to as 'bead up', is where the pipe ends are pressed against a heated plate for a period of time. This is followed by the 'heat soak' phase where the pressure is reduced to just hold the pipe ends on the hot plate. This allows time for the heat to soak into the material at the pipe ends. After the heat soak phase, the hot plate is removed and the pipe ends brought together. The time taken to do this is called 'dwell time' and needs to be as short as possible. The final phase is the welding/cooling time, predetermined subject to pipe diameter and wall thickness. Machine set up Before making any pipe welds, the butt fusion welding machine needs to be checked for smooth running and set up for the pipe materials to be welded. Selection of the correct clamps or inserts, ensuring all fixings are tight, to reduce the possibility of misalignment due to axial movement. Correct temperature of the hot plate, for the material being welded; this should be checked with a surface temperature probe and digital thermometer in several positions after a Ceylex Engineering (Pvt) Ltd. Page 19 Original Method Statement for HDPE Pipe Laying stabilization period of at least 20 minutes. Between welds the hot plate should be covered by a heatproof bag to protect it from surface contamination and to prevent heat loss. Check the planer blades used to trim and square the pipe ends; they need to be sharp, undamaged and firmly fixed to the planer surface to avoid slippage of the planer during rotation. Check all moving parts for smooth operation and, if using a hydraulic machine, check the hoses and fittings for signs of leakage. Preparing the pipe Fig.2. Planing the pipe ends so they are ready for welding Prior to welding, correct preparation of the pipes is necessary. When measuring pipe lengths, allowance should be made for the trimming and melting sequences to guarantee correct lengths after welding. Before clamping the pipes into the machine, the ends should be checked for irregular shape, damage, or embedded grit. The maximum allowable depth of this must be less than 10% of the wall thickness. Damaged or deeply scored pipe should be discarded. Any loose contamination can be removed by wiping the pipe ends with a lint-free cloth on both inner and outer surfaces. Once cleaned, the pipes are clamped into the machine. To help alignment, it is good practice to clamp the pipes in such a way that their stamped markings are in line. This also helps with identification at a later date if required. Ceylex Engineering (Pvt) Ltd. Page 20 Original Method Statement for HDPE Pipe Laying Once securely fitted in the clamps, the pipe ends should be brought into contact with the rotating planer tool until continuous shavings are cut from each end. The planning process ensures the pipe ends are smooth and square ready for the welding phase. Loose shavings should be removed from the machine and inside the pipes taking care not to touch the planed ends. This ensures that no grease or dirt is transferred from hands to pipe ends. The pipes should then be checked for alignment and adjustments made to the clamps where necessary to ensure there is minimal mismatch in diameter. Welding Fig.3. The hotplate is positioned between the pipes Fig.4. Bead formation needs to be monitored carefully Ceylex Engineering (Pvt) Ltd. Page 21 Original Method Statement for HDPE Pipe Laying Before the welding sequence, heating and cooling times and fusion pressures should be noted for the specific pipe diameter and written down for quick reference during the welding cycle. Some machines have all the relevant tables on them for convenience. A timer or stopwatch should be available for accurate timing. The heatproof bag should be removed from the hotplate, and the temperature should be checked using a digital thermometer and surface probe. It is good practice to complete a dummy weld before undertaking actual welding. This is to ensure the surface area of the hotplate in contact with the pipe ends is totally clean of any dust particles or other contaminants. Place the hotplate between the pipe ends, ensuring that it is properly located and square to the pipe faces. Move the pipes into contact with the surface applying an axial force. The force should be applied smoothly making sure that the required pressure is not exceeded. The force needs to be held securely, allowing the formation of a bead of molten material around the pipe. The bead needs to be even around the pipe circumference, on both sides of the hotplate. This is the 'bead up' phase of the process. The means of applying the force will vary with the type of equipment. On certain types of machine, the force will be applied by mechanical means using a spring loaded mechanism with the force being maintained by a locking screw. On other types of equipment, hydraulic rams are used with the pressure maintained by switching valves in the hydraulic power pack. When the required bead has been achieved, the pressure is reduced for the heat soak phase. The pipes rest on the hot plate which allows the heat to permeate the material, reducing the possibility of cold welds. This time will vary subject to pipe diameter and wall thickness, therefore manufacturers recommended times should be used. Ceylex Engineering (Pvt) Ltd. Page 22 Original Method Statement for HDPE Pipe Laying Fig.5. The pipes should be kept clamped during the welding/cooling phase When this phase is completed, the pipe faces are moved away from the hotplate as smoothly as possible to ensure that none of the molten bead sticks to the surface and the hotplate is removed. The pipes are then brought together as smoothly and quickly as possible to minimize the possibility of temperature drop, taking care not to exceed the required force. The welding/cooling phase begins when the required force has been achieved. The weld force should be maintained throughout this phase, to ensure maximum weld strength. On completion of the cooling time, the pressure can be reduced to zero, and the pipe removed from the clamps. The finished weld can now be visually inspected for uniformity and alignment. PIPE LINE INSTALLATION In handling pipes & fittings every care will be taken to avoid distortion or other damage. Pipes & fittings will not be allowed to drop or strike objects & will be lifted by means of the mobile crane & belts will be used at the correct lifting points along the length of the pipe. Pipes will be stockpiled on timber pieces on level ground, in such a manner as will prevent damage to any part of the pipe. During stacking and removal operations, safe access to the top of the stack will be provided. Stacking type & the maximum stacking height will be maintained in accordance with the manufacturer’s recommendations. All pipes, fittings & accessories will be examined, and no piece which is found to be defective will be installed. All pipes will be laid to lines and to true alignment and gradient as shown on the drawings. Ceylex Engineering (Pvt) Ltd. Page 23 Original Method Statement for HDPE Pipe Laying As far as possible, pipes will be lowered into trench by using either boom truck or excavator. No pipe will be rolled from place to place or into trench except over suitable timber planking free from roughness likely to damage any coating. If the prepared bed is disturbed for any reason, the pipe will be raised and the bed is made good before pipe laying is continued. Pipe & Fitting jointing will be carried out using Butt Fusion Welding Techniques & Electro Fusion Welding Techniques using the Specific Welding Machines following the Heating & Cooling times & procedures defined for respective Pipes & Fitting Sizes. Well experienced Skilled Pipe Fitters will be used to operate these Machines & carry out these works to the Approval of the Engineer. Any pipe which is not in true alignment or shows any undue settlement after laying will be taken up & re-laid correctly. In case of flanged joints, gaskets will be fitted so that no part is projected and obstructs flow of water. The complete joint will be perfectly aligned. Flanged joints will be completed with all nuts, bolts, gaskets and two washers per bolt. Whenever the work ceases for any reason, the unfinished end of the pipeline will be securely closed with a tight fitting wooden plug & will be covered with polythene. 10.4 PIPE LAYING IN CULVERT CROSSINGS Pipe laying in culvert crossings shall be done according to the details of the standard drawings/other drawings specifically prepared for this work. Without Pipe Supports (Short Spans) Excavation shall be done to the minimum depth of 150mm below the deck level by using the backhoe/excavator. If it is not possible for machine excavation, manual excavation shall be done. Length of the pipe between couplings shall be considered as “Width of the Culvert Opening+1800 mm” according to the given drawings. Required pipe lengths shall be placed and couplings shall be fixed by using the boom truck. Lifting belts shall be used for lifting and placing the pipes. Ceylex Engineering (Pvt) Ltd. Page 24 Original Method Statement for HDPE Pipe Laying With Pipe Supports (Long Spans) After completing the pipe support (if it is pipe, the head shall be casted at required height), the bracket shall be fitted on it to hold the pipe. Inclined length shall be determined and cut at the site to suit the incoming and outgoing invert levels as given in the longitudinal sections. Boom truck shall be used to place the pipe and to hold the pipe on the support until it fix to the support. The annular space between pipes shall be filled with stand. 10.5 PIPE LAYING IN BRIDGE CROSSINGS Under crossing/over crossing/offset crossing of the pipe laying shall be carried out in accordance to the approved drawings by the relevant authority. Bore holes shall be done in either sides of the riverbank to identify bed rock level. Type of the foundation for abutments shall be decided on both sides and the pier at the centre by considering bore-hole data. Sheet piling shall be carried out for work for abutments. Sheet piling shall be carried out cofferdam for pier. Foundation construction shall be done at abutments and piers. (Bored insitu piling, pre-cast piling/casing shall be done considering depth to the bed rock). Reinforced concrete abutment and pier construction shall be carried out. Design and construction shall be in accordance to BS 8110. Design and fabrication of pre-fabricated pipe shall be in accordance with BS 5440. Installation of pre-fabricated pipe bridge shall be done by the help of crawler crane of required capacity after providing necessary on abutment and pier. 10.6 PIPE LAYING IN ROAD CROSSING Traffic arrangement shall be introduce for road crossings. Refer to the Chapter 5 (Traffic Control Plan). Ceylex Engineering (Pvt) Ltd. Page 25 Original Method Statement for HDPE Pipe Laying 10.7 INSTALLATION OF VALVES AND ACCESSORIES All sluice valves shall first be tested for smoothness and accuracy of operation and then shall be fixed with their spindles truly vertical except where otherwise directed by the Engineer. Air valve tees shall be carefully laid using a level across the flange to ensure vertically. 11 CONCRETE WORKS VALVE CHAMBERS AND THRUST BLOCKS 11.1 VALVE CHAMBERS There are air, gate, scour and district meter chamber. It is intended to precast value chambers where possible with the approval of the engineer at site the idea, behind this is to expedite work and while laying of pipe this work could be done parallel. 11.2 THRUST BLOCKS Thrust blocks will be carried out at site according to contract drawings or any other drawings on approved by the engineer. 12 PROTECTION OF PIPES Marker Posts Pre-cast concrete marker posts (grade 20 concrete) shall be placed along the pipe traces especially at turning points, special nodal points, branch off, etc. Similar arrangement shall be made for each valve chamber and where it is not possible having marker posts, marker plate shall be introduced. Marker Tapes Marker Tape shall be installed in the trench, 300mm above the crest of the pipe. 13 SAMPLING AND TESTING All testing will be carried out at the independent laboratory. Ceylex Engineering (Pvt) Ltd. Page 26 Original 13.1.1 Hydro testing has to be done as per theMethod SFS 3115 standard andPipe Wiik Statement for HDPE Laying procedure shared. Mutually agreed, section wise hydro testing has to be 13.1 TESTING AND DISINFECTION done before the trench is back filled. The final test can be done with All pipes will be hydrostatically tested according to the approved All tests backfilled trench allmethod. in one final go.will be conducted on the pipe lines in sections after the trench is backfilled, buy before pavement 13.1.2 Pipe flushing has to be construction. done before Hydro test All pipe lines will be thoroughly checked for foreign matters before testing all wash out valves hydrants will be closed when the pipe line is ready for testing. The pipe line will be slowly filled by water, allowing all air pockets to be released, until the pipe is completely filled and under working pressure at which condition it should be allowed to stand for 24 hours, any apparent defects in the pipeline will be noted and rectified. For this purpose pressure pump and standard equipment will be used with the coordination of the engineer. 13.2 DISINFECTION After successful completion of pressure testing, sterilizing process will be commenced. The concentration of chlorine solution applied will be according to the specification and the engineer’s directions. The water used for pipeline testing and disinfecting operations will be disposed without causing any damage to adjacent property. 13.3 PIPES Pressure testing of the pipes shall be done as per the Engineer’s requirements. Pressure testing checklist shall be used for monitoring the pressure testing process. The results shall be recorded to the hydrostatic pressure testing monitoring form. The length of the sections to be tested shall be decided by considering, The availability of suitable water The number of joints to be inspected, and The different elevation between one part of the pipeline and another. Pressure testing shall be carried out in such lengths as convenient and approved by the engineer, but in any circumstance these lengths shall not be greater than 1000 m. 14 BACKFILLING AND COMPACTION Backfilling and compaction shall be done layer by layer. Ceylex Engineering (Pvt) Ltd. Page 27 14.1 For above ground pipe lines covering of soil has to be included. Original Method Statement for HDPE Pipe Laying The thickness of the top layer of soft material free from stones greater than 25mm size shall be deposited in 150mm layer from top of the bedding to a depth not less than 300mm from the crown of the pipe. The other two layers shall be 300mm thick and excavated soil shall be used after the engineer’s approval. Compaction shall be done using a roller compactor/vibrator and excessive/unsuitable material shall be removed from the site. If the pipe is to be laid on carriageway of RDA/PRDA roads, clear sand shall be used for backfilling up to 300mm from the crown of the pipe. Under the wet conditions, clear river sand/other clear granular material approved shall be used to obtain require compaction. Road reinstatement shall be done where required. Backfill shall be compacted to a dry density not less than 95% of the laboratory modified proctor density. 14.1 PIPE BEDDING Pipe bedding shall be placed as per construction drawing with materials complying with the requirements. Water level in the trench shall be kept to a minimum while placing the bedding material. Bedding shall be levelled and compacted to achieve the required level of compaction. Required bedding angle shall be provided by using hand tools. The backfill material shall be compacted with plate compactor/compacting rammer. Soil thickness of each layer shall be 150mm maximum at loose stage. 14.2 PIPE SURROUNDING Soil shall not be dumped directly on the pipe. Protective timber board shall be provided to cover the pipe to avoid damaging it due to the soil dump. Uncompacted/ partially compacted soil remaining in previously placed layers shall be moved to adjoin fill and compact. Hand compaction shall be applied in stages to compact pipe surrounding as well as a reasonable height above the pipe crown as per the manufacturer’s recommendation (if required). Ceylex Engineering (Pvt) Ltd. Page 28 Original Method Statement for HDPE Pipe Laying 14.3 BACKFILLING THE REMAINING PART Maximum depth of each uncompacted soil layer shall not be exceeded 150mm and the number of passes shall be eight. Compaction tests shall be done and the test results shall be available at the site office. 15 REMOVING OF TRENCH SUPPORT Removing of trench support shall be done simultaneously with the backfilling. Lowest bracing shall be removed once completed the backfilling up to that level. So on for bracings for higher levels. The Contractor shall be responsible for removing all the supporting systems that are used for the pipe laying process. Relevant authorities shall be informed soon after the completion of pipe laying in order to undertake the permanent reinstatement of the carriageway. 16 TEMPORARY ROAD REINSTATEMENT Aggregate base course for a thickness as specified and indicated in the drawings shall be placed and levelled it in the trench after carrying out backfilling and then it shall be compacted using approved equipment to 100% of MDD up to the top level of existing road surface. Compaction tests shall be carried out through approved laboratory and test results shall be submitted for the approval of Engineer. Prime coat of bitumen emulsion (CSS 1) at the rate of 1 lit/m2 shall be applied and blinded with sand as necessary. Contractor at his own cost shall maintain the roads so reinstated until they permanently reinstated after completing pipe laying work including pressure testing of pipelines and testing of the backfill of the trenches to the approval of the Engineer. 17 PERMANENT ROAD REINSTATEMENT At the time of permanent road reinstatement is commenced, it shall be required to remove a top layer of ABC up to required depth in the trench so as to accommodate a layer of asphalt concrete in permanent road reinstatement and then remaining layer of ABC shall be compacted using approved equipment to achieve 100% of MDD. Tack coat at a rate of 0.5 lit/m2 shall be applied. Then asphalt concrete shall be laid and compacted using approved equipment to reach the required density and shall be finished up to the top surface level of existing road. Compaction test/any other required shall be carried out through approved laboratory and test results shall be submitted by the contractor as Ceylex Engineering (Pvt) Ltd. Page 29 Original Method Statement for HDPE Pipe Laying directed by Engineer. Upon completion of the reinstatement conforming to the specification, the contractor shall arrange with Engineer to carry out a final inspection and measurements. 18 RESOURCE ALLOCATION Required equipment and manpower shall be allocated for each pipe laying group. However machinery/equipment allocation, number of workers and work allocation method shall be decided depending on the site conditions, type of the pipe and the diameter of the pipe etc. There will be a technical qualified personnel of each working gang and competent enough to handle the job. 19 HEALTH AND SAFETY The care shall be paid for the work underneath electric lines. Safety supervisor shall visit the sites randomly and without any prior notice for safety inspection of the sites. Person-in-charge of each group shall be responsible for following every safety measure introduced by the safety supervisor. Safety supervisor shall conduct weekly safety toolbox meetings and explain the safety procedure to the employees. Special attention shall be paid for the pipe laying along the road. Traffic arrangement shall be discussed with the relevant police station prior to the commencement of work. Road safety shall be among the considerations of the safety precautions. 19.1 ENVIRONMENTAL PROTECTION The identification of the potential treats to environmental impacts is necessary. The main issues to be addressed are: Discharge of water into existing stream Erosion and sediment control River bank and bed protection Dust control Noise and vibration control Air pollution control Hazardous and solid waste management Ceylex Engineering (Pvt) Ltd. Page 30 Original Method Statement for HDPE Pipe Laying The environmental management plan will be prepared. Plan will address the site preparation and clearance, temporary access, trench excavation, material and equipment transportation etc, which will help to respond to the quality of people living standards. 20 QA/QC PLAN Quality of the pipe laying process shall be monitored through the pipe laying trenching log. The contractor shall maintain the quality of the construction work to match the quality of the ISO format. Ceylex Engineering quality manual shall be maintained for quality assurance for the project. The specific QA/QC program will be established so as to ensure that the project requirements will be met for all elements of design, material/service procurement, fabrication, assembly, shipping and installation. Document control Document control covering the requirement for the preparation, review, approval and distribution will be established to ensure that those documents and changes thereto are controlled and distributed as required to locations where applicable work is being performed. Procurement control The procurement of material, equipment and services will be controlled to assure conformance with specified requirements. Materials and equipment control Controls will be established to assure that only correct and accepted items are used and installed Inspection/testing The objective of inspection and test is to ascertain that equipment and materials are manufactured and erected strictly in accordance with QA/QC program as well as client document. Quality assurance records Records that furnish documentary evidence of quality, if required by the client, will be specified, prepared and maintained Audits Planned and scheduled audits will be performed to verify compliance with all aspects of the QA/QC program to evaluate its effectiveness. Ceylex Engineering (Pvt) Ltd. Page 31 Original