ALAI KHWAR POWER HOUSE SWITCHYARD TSG North NTDC DISTANCE, AUTO RECLOSER & EARTH FAULT TEST REPORT Auto Recloser Relay Set-1 (Internal Feature of SEL 421 Distance Relay) installed on 220kV Alai – Mansehra Circuit 1 Bus CB AR Dead time = 1.3 sec (Live Line / Live Bus reclosing condition) Middle CB AR Dead time = 10 Sec (Live Line /Live Bus reclosing condition) Reclaim Time = 180 sec or Maximum available Auto Recloser Set-I (Internal Feature of SEL 421) tested and following conditions applied from Distance Set-I (SEL 421). Sr. Conditions of CB before No. Fault Injection 1 D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) Fault Injected 2 D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) Aided Trip Phase to Ground 3 D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) Aided Trip Phase to Phase Fault 4 D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) Aided Trip three Phase Fault D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) D1Q1 C.B Closed (Dead Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) Z1 three Phase Fault 5 6 7 8 9 Z1 Phase to Ground Condition of C.B after fault injection D1Q1 C.B tripped and reclosed after 1.3 sec, D1Q3 tripped and reclosed after 10 seconds. D1Q1 C.B tripped and reclosed after 1.3 sec, D1Q3 tripped and reclosed after 10 seconds. D1Q1 C.B tripped and reclosed after 1.3 sec, D1Q3 tripped and reclosed after 10 seconds. D1Q1 & D1Q3 CB Tripped only. Z1 Phase to Ground fault injected in Reclaim time D1Q1 & D1Q3 CB Tripped only. Z1 Phase to Phase Fault D1Q1 C.B tripped and reclosed after 1.3 sec, D1Q3 tripped and reclosed after 10 seconds. D1Q1 & D1Q3 CB Tripped only. Z2 Phase to Ground + Z2 Phase to Phase +Z3 Phase to Ground + Z3 Phase to Phase+ SOTF Faults injected Z1 Phase to Ground D1Q1 & D1Q3 CB Tripped only. D1Q1 CB Tripped and not reclosed. While D1Q3 reclosed immediately after the 10 11 D1Q1 C.B Open(Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus) (Priority Reversal) D1Q1 C.B Closed (Live Line and Live Bus), D1Q3 C.B Closed (Live Line and Live Bus), AR Out of Service Z1 Phase to Ground Z1 Phase to Ground Fault sync supervision time of Q1 i.e 5 seconds and did not wait for 10 seconds to reclose due to dynamic selection of Leader and Follower breaker by the relay. D1Q3 CB reclosed after 1.3 seconds as the Leader breaker. D1Q1 & D1Q3 CB Tripped only. Remarks / Observations: 1. Distance Set 1 (SEL 421) relay is initiating and blocking Auto Recloser Set I (Internal Feature of SEL 421) as per Protection and Control Department Setting. PUTT scheme of the relay is also tested and found satisfactory. 2. End to End Tele protection scheme (PUTT & DTT) testing have been done. 3. Distance Zone reach and timing report & Earth Fault relay (SEL 351) testing report is attached separately with this report. Tested By: Mr. Sumair Memon Sb Designation: D.M (P&M) TSG NTDC Tested By: Mr. Fahimuddin Qureshi Designation: A.M (P&M) TSG NTDC Witnessed By: Mr. Hidaya ul Allah Designation: Senior Engineer (EME) Alai Khwar Power House Switchyard