Progress Description of work January & February, 2023 S No. Road Segment/Chainage Track Road Construction Work A B/S All works like Sub Base Course Aggregate Base Course, Kerb Blocks with Hunching and Asphalt Base Course have been done. Whereas the Asphalt Wearing Course Work is also completed. 50% work on shoulders up to laying of Sub Base Course and Aggregate Base Course has been done and work on DST is shortly to be undertaken. Work on Machli Chowk / Roundabout like Sub Base Course Aggregate Base Course, Kerb Blocks with Hunching and Carpeting (Asphalt Base Course) have been done. B/S All works like Sub Base Course Aggregate Base Course, Kerb Blocks with Hunching and Asphalt Base Course have been done. Whereas the Asphalt Wearing Course Work is also completed. From Machli Chowk to Kanuup 1. Between 1 KM to 6 KM 0+050 to 5+950 From Kanuup to Machli Chowk 2. Description of Activities Between 1 KM to 6.45 KM 5+950 to 6+450 Culverts Construction Work B From Machli Chowk to Kanupp Between 1 KM to 6.45 KM 1. 0 - 050 2. 1+109 3. 1+350 3. 1+525 4. 1+681 5. 1+773 6. 2+144 7. 2+231 8. 2+484 All 21 nos. Culverts have been constructed. Whereas, work on Wing Walls of the Culverts is also completed. 9. 2+626 10. 2+761 11. 2+888 12. 3+007 13. 3+325 14. 3+350 15. 4+450 16. 4+477 17. 5+714 18. 5+900 19. 6+150 20. 6+350 Drain Construction Work C From Machli Chowk to Kanuup Between 2 KM to 3 KM 1. 2+050 to 3+100 (Built up Area) B/S The Construction Work on RCC Drain has been completed. New Jersey Barrier From Machli Chowk to Kanupp D 1. E 2+100 to 3+100 Median Between 2 KM to 3 KM The work on Construction of New Jersey Barrier stands completed. Electrification/Lighting From Machli Chowk to Kanupp Between 1 KM to 6 KM 0+050 to 1+500 1. 1+500 to 5+950 From Machli Chowk to Kanuup From Kanupp to Machli Chowk F 1. The octagonal hard dip Galvanized Electric Poles (Eight Meter with RCC foundation) have been installed from Median 0+050 to 1+500. Pole Foundation works is in progress and have been done up to 5+000. The work is in progress at a desirable pace. Horticultural & Plantation 0+050 to 2+000 Median Between 1 KM to 2 KM Lignum tree have been planted as proposed by the Consultants of the project. Besides, 70% grass work has been done in the median after laying of sweet earth and cow dung.