Progress Description of work December, 2022

advertisement
Progress Description of work January & February, 2023
S No.
Road
Segment/Chainage
Track
Road Construction Work
A
B/S
All works like Sub Base Course Aggregate Base Course,
Kerb Blocks with Hunching and Asphalt Base Course have
been done.
Whereas the Asphalt Wearing Course Work is also
completed.
50% work on shoulders up to laying of Sub Base Course and
Aggregate Base Course has been done and work on DST
is shortly to be undertaken.
Work on Machli Chowk / Roundabout like Sub Base Course
Aggregate Base Course, Kerb Blocks with Hunching and
Carpeting (Asphalt Base Course) have been done.
B/S
All works like Sub Base Course Aggregate Base Course,
Kerb Blocks with Hunching and Asphalt Base Course have
been done.
Whereas the Asphalt Wearing Course Work is also
completed.
From Machli Chowk
to Kanuup
1.
Between 1 KM to 6
KM
0+050 to 5+950
From Kanuup to
Machli Chowk
2.
Description of Activities
Between 1 KM to 6.45
KM
5+950 to 6+450
Culverts Construction Work
B
From Machli Chowk to Kanupp
Between 1 KM to 6.45 KM
1.
0 - 050
2.
1+109
3.
1+350
3.
1+525
4.
1+681
5.
1+773
6.
2+144
7.
2+231
8.
2+484
All 21 nos. Culverts have been constructed. Whereas, work on Wing
Walls of the Culverts is also completed.
9.
2+626
10.
2+761
11.
2+888
12.
3+007
13.
3+325
14.
3+350
15.
4+450
16.
4+477
17.
5+714
18.
5+900
19.
6+150
20.
6+350
Drain Construction Work
C
From Machli Chowk to Kanuup
Between 2 KM to 3 KM
1.
2+050 to 3+100
(Built up Area)
B/S
The Construction Work on RCC Drain has been completed.
New Jersey Barrier
From Machli Chowk to Kanupp
D
1.
E
2+100 to 3+100
Median
Between 2 KM to 3 KM
The work on Construction of New Jersey Barrier stands
completed.
Electrification/Lighting
From Machli Chowk to Kanupp
Between 1 KM to 6 KM
0+050 to 1+500
1.
1+500 to 5+950
From Machli Chowk to Kanuup
From Kanupp to Machli Chowk
F
1.
The octagonal hard dip Galvanized Electric Poles (Eight
Meter with RCC foundation) have been installed from
Median 0+050 to 1+500.
Pole Foundation works is in progress and have been done
up to 5+000. The work is in progress at a desirable pace.
Horticultural & Plantation
0+050 to 2+000
Median
Between 1 KM to 2 KM
Lignum tree have been planted as proposed by the
Consultants of the project. Besides, 70% grass work has
been done in the median after laying of sweet earth and
cow dung.