INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
FLOWTRONIX ARABIA LTD.
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISO 9001:2015, ISO 14001:2015 & ISO 45001:2018
(ISM-001)
Prepared By:
MR
Reviewed By:
Manager Sales
Approved By:
General Manager
This IMS manual is the property of:
FLOWTRONIX ARABIA LTD.
COPYRIGHT
No part of this IMS manual may be reproduced in any form by print, photocopy, microfilm or any other means wholly
or in part or disclosed to any person outside Flowtronix Arabia Ltd. without the written permission of the General
Manager.
JUNE 2018
Page 1 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Table of Contents
Page 2 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
Page 3 of 39
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
REVISION RECORD
Revision
Date
Section Changed
Summary of Changes
Authorized By
00
20/Jun/2018
All
First Issue as per the requirements of ISO 9001:2015,
ISO 14001:2015 & ISO 45001:2018 standards
General Manager
Page 4 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
INTEGRATED POLICY
It is the policy of Flowtronix Arabia Ltd. to provide services related to “Industrial Electrical, Power, Instrumentation
and Process Control Systems. Design & engineering, material supplies, equipment installation, panel integration,
commissioning and facility maintenance services. Operational safety, IT networking & security solutions and water
treatment for industrial facilities”. Flowtronix Arabia Ltd. is committed to comply with the requirement of the
customers and to continually improve the effectiveness of the Integrated Management System. It must be clearly
understood that this Integrated Policy, Integrated Manual and associated Procedures and systems are mandatory on
all staff.
Undertaking our activities goes along with high responsibility, competency and professionalism, so in order to
realize our commitment and maintain our leadership position in this business we’ve established a structure that
includes all the organization’s activities and describes the processes including the aspects of Quality, Health, Safety
and Environment.
Our policy is established on the following items:
 Conserve and optimally use key resources, provide services leading to customer satisfaction and









implement measures for maintaining safe working & occupational health practices.
Create awareness for occupational health & safety and environment by training & meaningful
communication of Integrated Policy to the employees, persons working on behalf of the organization and
relevant interested parties.
Continually improving the effectiveness of our adopted Integrated Management System in accordance
with ISO 45001:2018, ISO 14001:2015 & ISO 9001:2015.
Review our objectives and achievements periodically for continual performance improvement of our
processes.
We operate our workplaces to comply with requirements of quality, health, safety and environment
applicable local and global regulations, and with the policies of our group using best practice as a guideline.
Plan and evaluate our processes via consideration of the associated business Risk. Risk associated with
our activities and services to employees and other interested parties, surroundings and the information
and goods entrusted to us are known and controlled in a responsible manner.
We’ll maintain the best possible Health, Safety, Quality and Environmental performance, and in order to
achieve this Standard, we prevent occupational injuries and illnesses.
We’ll establish, implement and maintain a framework to measure our objectives and targets and to ensure
the continual improvement of our QHSE program and Documented Management System.
Develop processes and operating conditions that promote environmental protection and reduce the
associated environmental impacts
Provide training and education to all employees to work in a manner, which maximize the environmental
protection, and to understand the implication of the Environmental policy.
____________________________
General Manager
Page 5 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
SCOPE
This is the official Integrated Manual of Flowtronix Arabia Ltd., which describes the elements and requirements of
quality, health, safety and environmental management system, and it is structured to comply with the requirements of
ISO 9001:2015, ISO 14001:2015 & ISO 45001:2018 standards. The Integrated Management System is designed in order
to demonstrate company capabilities and commitment to deliver high quality services with consistency, which conforms
entirely to the customer and applicable statutory and regulatory requirements, thereby ensuring Customer satisfaction,
also to improve occupational health, safety and environment, eliminate OH&S hazards, prevention of pollution,
improvements in quality, health, safety and environment performance, minimize risks (including system deficiencies),
take advantage of opportunities, and addresses Integrated management system nonconformities associated with its
activities.
The Scope of the Integrated Management System activities of Flowtronix Arabia Ltd. is of;
“Industrial Electrical, Power, Instrumentation and Process Control Systems. Design & engineering, material
supplies, equipment installation, panel integration, commissioning and facility maintenance services.
Operational safety, IT networking & security solutions and water treatment for industrial facilities.”
NORMATIVE REFERENCES









International Standard ISO 9001:2015 Quality Management System – requirements
International Standard ISO 14001:2015 Environmental Management System – requirements.
International Standard ISO 45001:2018 Occupational Health & Safety Management System – requirements
List of Procedures, Process Flows & Work Instructions – Appendix-A
Master Process Map – Appendix-B
Integrated Objectives – Appendix-C
Organizational Chart – Appendix-D
List of Forms – Appendix-E
Terms & Definitions – Appendix-F
TERMS AND DEFINITIONS
Terms and Definitions associated with this manual are mentioned in Appendix–F of this Integrated Manual.
Page 6 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
CONTEXT OF FLOWTRONIX ARABIA LTD.
Understanding Flowtronix Arabia Ltd. and its Context
Flowtronix Arabia Ltd. has established, documented, implemented and maintained the information in procedure #
MR-ISP-004 for determining and evaluating the external and internal issues or factors relevant to its operating
environment (context), strategic planning and which affect its ability to achieve its objectives and intended outcomes.
Information relevant to these external and internal factors is effectively maintained, considered while managing the
associated addressed risks and also monitored through defined mechanism in order to ensure smooth and consistent
business execution.
Understanding the Needs and Expectations of Interested Parties
Flowtronix Arabia Ltd. has established, documented, implemented and maintained the information in procedure #
MR-ISP-004 for determining the interested parties relevant to its Integrated Management System and the
requirements of these interested parties.
Information relevant to these external and internal parties is effectively maintained, reviewed and monitored through
defined mechanism in order to ensure smooth and consistent business execution.
Related Document:
Issues with Relevant Interested Parties – ISP-004
Determining the Scope of the Integrated Management System
Flowtronix Arabia Ltd. has determined the boundaries and applicability of its Integrated Management System while
establishing its scope. As documented in clause 01 of this Integrated Manual, Flowtronix Arabia Ltd. scope of work is;
"Industrial Electrical, Power, Instrumentation and Process Control Systems. Design & engineering, material supplies,
equipment installation, panel integration, commissioning and facility maintenance services. Operational safety, IT
networking & security solutions and water treatment for industrial facilities.”
While determining the Scope of work, Flowtronix Arabia Ltd. has considered the following;






External & Internal issues associated with Flowtronix Arabia Ltd. business (refer to clause 4.1).
The requirements of relevant interested parties (refer to clause 4.2), and
The scope of the organization (refer to clause 01),
Other interested parties, in addition to workers, that are relevant to the integrated management system;
(refer to clause 4.2)
Relevant needs and expectations (i.e. requirements) of workers and other interested parties;
Which of these needs and expectations are or could become legal requirements and other requirements.
Page 7 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
All the requirements of ISO 45001:2018, ISO 14001:2015 & ISO 9001:2015 standards are applicable to the Flowtronix
Arabia Ltd. scope of work. Flowtronix Arabia Ltd. is also involved in design and development activities so 8.3 clause is
applicable. The scope of work is effectively reviewed and maintained whenever required. This scope has stated the
types of services being delivered to the customers. Flowtronix Arabia Ltd. has addressed the requirements (clauses) of
ISO 45001:2018, ISO 14001:2015 & ISO 9001:2015 in this Integrated Manual and has focused on their effective
implementation in order to ensure no effect on Flowtronix Arabia Ltd. ability or responsibility to provide conformity of
its services, to enhance Customer Satisfaction, eliminate hazards and prevent pollution.
Integrated Management System and its Processes
Flowtronix Arabia Ltd. has established, implemented, maintained and continually improved its Integrated
Management System in accordance with the requirements of ISO 45001:2018, ISO 14001:2015 & ISO 9001:2015. For
this purpose, Flowtronix Arabia Ltd. has determined the following;
a) Processes required for the Integrated Management System and their application throughout the
Flowtronix Arabia Ltd.,
b) Inputs required and the output expected from these processes,
c) Sequence and interaction between these processes,
d) Criteria and Methods needed to ensure the effective operation and control of these processes,
e) Resources needed for these processes and ensuring their availability,
f)
Assigning the responsibilities and authorities for these processes,
g) Address the Risk and opportunities associated with the processes,
h) Evaluating these processes through a defined mechanism of monitoring, measurement and analysis of
processes performances and evaluating any changes needed to ensure that these processes achieve
their intended or planned results.
i)
Improving the process of the Integrated Management System.
Flowtronix Arabia Ltd. Integrated Management System is structured to achieve a good internal management system
and to get the results of customer satisfaction and effective continual improvement.
Flowtronix Arabia Ltd. has maintained documented information wherever there is a need or requirement to have
documented information, either by this international standard “ISO 45001:2018, ISO 14001:2015 & ISO 9001:2015” or
by organization for its effective planning, control and operation. Clause 7.5 of this Integrated Manual has addressed
requirements of Documented Information.
As mentioned in clause 01, Flowtronix Arabia Ltd. has maintained Process Sequence and interaction in Master Process
Map (Process Interaction), Appendix-B of this Integrated Manual.
Flowtronix Arabia Ltd. has maintained the list of Procedures in Appendix-A of this Manual. Organization hierarchy is
established and maintained in Organization Chart, Appendix-D of this manual.
Page 8 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
LEADERSHIP AND WORKER PARTICIPATION
Leadership and Commitment
General
Flowtronix Arabia Ltd. Top Management has demonstrated effective leadership and commitment with respect to its
Integrated Management System by ensuring the following;
a) Taking overall responsibility and accountability for the prevention of pollution, work-related injury and ill
health as well as the provision of safe and healthy workplaces and activities;
b) Top Management has undertaken whole accountability for the effectiveness of the Integrated Management
System.
c) Top Management has ensured that Integrated Policy and Integrated Objectives (documented in Appendix – C
of this manual) are documented, implemented and maintained. The documented policy and objectives are
made compatible with the context and strategic direction of the organization.
d) Top Management has ensured integration of the Integrated Management System requirements in to its
Business process through establishment of effective documentation structure (detailed in clause 7.5 of this
manual).
e) Top Management has ensured the use of “Risk base approach” and “Process approach” through effectively
defining and promoting the Flowtronix Arabia Ltd. documentation structure.
f)
Top Management is committed for continual improvement. Where training, new equipment, additional
support or personnel is needed, the management shall exert all efforts to acquire or hire all essential
resources.
g) Top Management has ensured that effective communication processes are established for communicating
the importance of effective Integrated Management System and importance of conformity to the Integrated
Management System requirements.
h) Top Management has ensured, via process for Quality Assurance, including Management Review and Internal
Audit, that its Integrated Management System achieve its intended result.
i)
Top Management has ensured that personnel at each level are effectively engaged, directed or supported in
order to demonstrate their contribution for the effectiveness of the Integrated Management System. This is
ensured for example, via implementation of defined organization hierarchy, assigned responsibilities and
authorities and other monitoring parameters.
j)
Top Management has emphasized on the promotion of continual improvement of its Integrated
Management System through defined mechanism of monitoring and / or measurement.
k) Top Management has always encouraged and supported personnel on Management Roles for demonstration
of their leadership skills, within their area of responsibility.
Page 9 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Customer Focus
Top Management has ensured and committed that Customer requirements are determined and fulfilled with the aim
of attaining customer’s satisfaction. This includes company’s commitment to comply with the requirements of work
order contract / service suitability and conformity.


Risk and opportunities that can affect conformity of services and the ability to enhance customer
Satisfaction are determined and addressed.
The focus on enhancing Customer Satisfaction is maintained via defined mechanism of evaluating Customer
Satisfaction, as documented in Clause 9.1.2 of this Integrated Manual.
Integrated Policy
Establishing the Integrated Policy
Flowtronix Arabia Ltd. Top Management, as evidence of its commitment, has established, documented, implemented
and maintained via continuous review, an Integrated Policy. The Integrated Policy is documented in this Manual.
Communicating the Integrated Policy
Top Management has ensured that this Integrated Policy is communicated, understood, applied within the
organization and made available to interested parties via different defined means of communication. This Policy is
effectively reviewed at defined interval, within Management Review in order to ensure its continuing suitability with
respect to Flowtronix Arabia Ltd. Management System and its business needs.
Organizational Roles, Responsibilities and Authorities
Top Management has ensured that responsibilities and authorities for relevant roles are assigned, communicated and
understood within the organization. Flowtronix Arabia Ltd. Organizational Chart (documented in Appendix-D of this
Integrated Manual) pictorially represents the designations of personnel and their inter-relationships. Functional roles
of each division/department/unit, duties and responsibilities of personnel are clearly defined to them, which is part of
Flowtronix Arabia Ltd. IMS.
The responsibilities of Top Management of Flowtronix Arabia Ltd. are given below:
General Manager
As vested to him by the Shareholders, the General Manager is responsible for providing resources for establishment
of Integrated Management System, for customer satisfaction and improvement of internal system, and shall pursuit
and implements continual improvement in order to ensure effectiveness and efficiency of Integrated Management
System.
He is also responsible for following;



Final confirm and approve major annual plans and work.
Establish Integrated Policy and approve Integrated Management System Manual.
Heads overall management review.
Page 10 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL

ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Delegate Management Representative to implement and maintain Integrated Management System.
Management Representative
The Top Management of Flowtronix Arabia Ltd. has appointed Management Representative (MR), assigned for
effective implementation of Integrated Management System (ISO 45001:2018, ISO 14001:2015 & ISO 9001:2015)
Requirements. The technical administration of this Integrated Management System is delegated who is vested on him
the responsibility, authority and accountability for all Quality Control and Assurance functions.
The MR on the performance of the Integrated System including the needs for improvement. He shall also
communicate with the customers and other interested parties on the promotion of Quality, Health & Safety
awareness and matters pertaining to the Quality, Environment, Health & Safety Programs.
The responsibilities of the MR are given below:

Ensuring that processes, needed for the Integrated Management System, are established, implemented and
maintained and delivering their intended output.

Reporting to Top Management on the performance of the Integrated Management System and any need for
improvement.

Ensuring the promotion of awareness of customer requirements throughout the organization

Ensuring the integrity of the Integrated Management System is maintained when changes to the Integrated
Management System are planned and implemented.
Project Manager/Project Lead
Project Manager/Project Lead shall be responsible for:
 Overall supervision and implementation of all the contract activities in an efficient and controlled manner.
 Ensure implementation of Quality System at the project.
 Preparation of project budget and recommendation for cash flow.
 Ensure availability of T&P at site.
 Coordinate with customer and manage resources.
 Represent FTA in all meetings held at site with the customer.
 Communication/correspondence with FTA office.
 Liaise with the sub-contractors on all aspect of the project activities and resolve any differences that may
arise.
 Effective and efficient utilizations of company resources
 Ensuring that the work is being carried out as per the Project schedule, quality inspection plan & QMS
system
 Ensuring that all staff is adequately trained and experienced to perform its duties in accordance with
requirements of the project quality plan.
 Ensuring all necessary safety measures are taken during execution of jobs.
Page 11 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL


ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Implementing appropriate corrective action where deficiencies are detected.
Determining and reporting the root causes of non-conformances identified at site.
Site In-charge
Site In-charge shall be responsible for:
 The supervision of field construction activities.
 Efficient and effective deployment and utilization of manpower and other resources as per work front
 Verifying that the quality policy of the company is being fully implemented and maintained
 Checking and verifying that construction work is being carried out as per the latest approved drawings.
 Ensuring that the work is performed in accordance with the specifications.
 Ensuring that the work is being carried out as per the project quality plan.
 Ensuring that all staff are adequately trained and experienced in their discipline, to perform their duties in
accordance with the project quality plan.
 Determining and reporting the root causes of non-conformances
 Implementing appropriate corrective action where non-conformances are identified
 Ensure that all necessary safety measures are taken during execution of jobs.
 Ensure implementation of HSE policies and procedures
 Ensure valid calibrated test equipment is used at site
 Ensure all T&P is safe and in proper working condition.
Planning & Control Engineer
Planning & Control Engineer is responsible for:
 Project planning and progress monitoring of the work
 Preparation of site planning team before start of the project.
 Preparation of master schedule of the project.
 Calculate cost to complete the project.
 Prepare the monitoring module which covers the progress of works, resources utilization and financial
status reports.
 Generate the weekly/ monthly progress reports.
 Generation of analytical reports to update project progress/status.
 Invoices are generated on the basis of progress of work done.
 Liaise with the sub-contractors regarding the materials, progress of works and invoices verification.
 Identifying any delays through project analytical reports, which are highlighted in Project Schedule
 Reasons of delay of projects are recorded on project delay report by suitable means
 Issuance of revision in Project Schedule.
Page 12 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Purchasing Lead
Purchasing Lead is responsible:
 For procurement of all contractor-supplied materials, consumables, tools and plant, safety gear and
temporary supplies as per procedure of Quality Management System.
 Request for quotations from pre-qualified suppliers / vendors and evaluate the quotations received on the
basis of commercial and technical comparisons
 Coordinate with QC representative for inspection.
 Issue Purchase Order to the finalized supplier / vendor as per authorized limit
 Coordinate with finance department for release of payment to the suppliers / vendors.
 Take necessary actions to achieve smooth, timely and efficient flow of materials to the projects.
 Acquire information on all Government policies regarding, Custom Duties, Sales Tax and all other levies
affecting the “Landed Cost”.
 Advise right procedures and methods for the efficient opening / establishment of the Letter of Credit (L/C).
 Ensure efficient and effective custom clearance for goods to be imported.
 Ensure safe & timely delivery of goods from port to projects / warehouse to port / from supplier’s premises
to projects.
 Ensure the release of Indemnity Bonds / Bank Guarantee / Post Dated Cheques deposited with Customs in
order to avail the all-possible benefits.
QA&QC Lead
QA & QC Lead is responsible
 To ensure implementation of Quality Management System at site.
 To prepare the Project Quality Plan as per Project’s specifications and drawings received from Customer.
 To prepare the inspection procedures/protocols/formats for site execution as per specifications provided by
customer.
 To arrange/depute the QA/QC manpower for sites on the requirements of project manager/project lead.
 To arrange the raw material inspection at market as per Purchase requisition.
 Ensures that adequate corrective actions are taken for any NCR raised at sites.
 Liaise with site QC Teams to resolves the QC matters.
 Co-ordination with Third party Inspection/calibration Team.
 Coordinates with store staff and site QC for calibration of inspection, measuring and test equipment being
used at site.
 Ensure Quality Dossiers of completed jobs are complied by the site QC.
HSE Lead
HSE Lead is responsible for:
 Keeping close liaison with the client safety department.
Page 13 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL









ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Establish and implementation of safety procedures during construction (at site) and also at the residential
area (camp).
Arranging training of staff/workers for all safety discipline and assess the adequacy of such training by
monitoring the personnel at site.
Advising the management for measures required for pollution free, healthy and hygienic atmosphere for
site workers/ staff.
Making arrangements for fire prevention and emergency evacuation.
Arranging first aid kits for all busy locations of site/ works/ camp.
Making audits of records of lifting equipment tools and tackles and advise management for safety
improvement.
Introduction/ installation of safety signs/ warnings and arrangement of safety tool box meetings with site
staff, as per requirement.
Reporting of site accident and ensure timely investigation for root cause and submit reports with
recommendations to avoid recurrence
Issue agreed weekly/ monthly performance reports regarding HSE parameters to top management.
Project Engineers
Responsibilities of area engineers include:
 Prepare the job plans according to work front
 Review design docs and carry out activities accordingly.
 Assign required resources including manpower, T&P and material in efficient ways
 Supervise the job activities and provide guidance to crew where and when required for effective delivery of
the job plan
 Assist the planning department for actual measurements of work done required in the preparation of
running bills
 Co-ordinate and liaise with other disciplines and interfaces
 Compile daily progress reports and analyze against targets and highlight any delay/problem
 Assist Planning department for reports generation for head office and client
 Assist in preparing the final consolidated plan
 Ensure that all necessary safety measures are taken during execution of job
 Report to the project lead regarding any technical problems, work front issue or modifications required
 Maintain a good teamwork spirit and cordial relationship with staff.
Consultation and Participation of Workers
The Flowtronix Arabia Ltd. has established, implemented and maintained a process for consultation and participation
of workers at all applicable levels and functions, and, where they exist, workers’ representatives, in the development,
Page 14 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
planning, implementation, performance evaluation and actions for improvement of the Integrated Management
System.
The organization shall:
a) Provides mechanisms, time, training and resources necessary for consultation and participation;
b) Provides timely access to clear, understandable and relevant information about the Integrated Management
System;
c) Determines and remove obstacles or barriers to participation and minimize those that cannot be removed;
d) Emphasizes the consultation of non-managerial workers on the following:









Determining the needs and expectations of interested parties (Clause 4.2);
Establishing the policy (Clause 5.2);
Assigning organizational roles, responsibilities and authorities as applicable (Clause 5.3);
Determining how to fulfil legal requirements and other requirements (Clause 6.1.3);
Establishing integrated objectives and planning to achieve them (Clause 6.2);
Determining applicable controls for outsourcing, procurement and contractors (Clause 8.1.4);
Determining what needs to be monitored, measured and evaluated (Clause 9.1);
Planning, establishing, implementing and maintaining an audit program (Clause 9.2);
Ensuring continual improvement (Clause 10.3);
e) Emphasizes the participation of non-managerial workers in the following:

Determining the mechanisms for their consultation and participation;

Identifying hazards and assessing risks and opportunities (Clause 6.1.1, and 6.1.2);

Determining actions to eliminate hazards and reduce OH&S risks (Clause 6.1.4);

Determining competence requirements, training needs, training and evaluating training (Clause
7.2);

Determining what needs to be communicated and how this will be done (Clause 7.4);

Determining control measures and their effective implementation and use (Clause 8.1, 8.1.3 and
8.2);

Investigating incidents and nonconformities and determining corrective actions (Clause 10.2).
PLANNING
Actions to Address Risks and Opportunities
General
Flowtronix Arabia Ltd. has established, documented, implemented and maintained the information, in procedure #
MR-ISP-005 for determining the Risk and Opportunities associated with;
a) Determined External and Internal issues (Clause 4.1).
Page 15 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
b) Determined External and Internal interested parties and their needs and expectations (Clause 4.2).
c) Scope of the Integrated Management System.
When determining the risks and opportunities risks and opportunities related to integrated management system and
its intended outcomes, Flowtronix Arabia Ltd. has addressed and shall take into account:
a)
b)
c)
d)
e)
Risk and Opportunities related to environmental aspects,
Issues with works or relevant interested parties,
hazards Identification
OH&S Risks and Opportunities
Compliance obligations, Legal and other requirements
The purpose of this procedure is to ensure provision of assurance that Flowtronix Arabia Ltd. Integrated Management
System can achieve its intended results, enhance desirable affects, prevent or reduce undesirable affects and achieve
improvements.
Environmental Aspect/Impact, Hazard Identification and Assessment of Risks & Opportunities
6.1.2.1 Environmental Aspect / Impact Assessment
The established procedure aims to identify and document in a register its environmental aspects and the resulting
impacts of its activities and services that it can control or influence, taking into account planned or new
developments or new or modified activities and services.
The procedure determines the criteria of defining aspects that have significant environmental impacts.
Related documents:
MR-ISP-011 - Environmental Aspects / Impacts identification and Evaluation Procedure
6.1.2.2 OH&S Hazard Identification
The established procedure identifies ongoing hazards, risk assessments and the necessary control measures for:






Routine and non-routine activities (emergency, breakdown, etc.)
All activities of all personnel in the company including visitors and subcontractors.
All the company facilities and work places.
The procedure defines the methodology for hazard identification and risk assessment.
All the assessment results are considered in setting the objectives and program.
The assessment and risk control is updated.
6.1.2.3 Assessment of OH&S Risks and Other Risks
The Flowtronix Arabia Ltd. has established, implemented and maintained a process to:
a) Assess OH&S risks from the identified hazards, while taking into account the effectiveness of existing
controls;
Page 16 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
b) Determine and assess the other risks related to the establishment, implementation, operation and
maintenance of the Integrated Management System.
6.1.2.4 Assessment of OH&S Opportunities and Other Opportunities
The Flowtronix Arabia Ltd. establish, implement and maintain a process to assess:
a) OH&S opportunities to enhance OH&S performance, while taking into account planned changes to the
organization, its policies, its processes or its activities and:


Opportunities to adapt work, work organization and work environment to workers;
Opportunities to eliminate hazards and reduce OH&S risks;
b) Other opportunities for improving the Integrated Management System.
Related documents:
Hazard Identification, Risk Assessment & Risk Control Procedure – MR-ISP-016
Determination of legal requirements and other requirements and Compliance Obligation
Legal and other HSE requirements applicable to Integrated Management System of Flowtronix Arabia Ltd. are
identified, accessed and updated periodically in legal Requirements Identification and Compliance Evaluation
Register. The applicable legal and other a requirement with which subscribes to have been taken into account while
establishing, implementing and maintaining the Integrated Management System. The Management Representative is
responsible for ensuring the updating, communication and compliance of the applicable legal requirements.
Relevant information about applicable legal and other requirements is communicated to employees through various
means of communication. Same is also communicated to customers and interested parties, upon request, through
company profile, company manual, policy and meetings. Records of compliance with the applicable legal and other
requirements including compliance evaluation are also maintained.
Relevant Procedure legal and other Requirements Identification, Compliance and Evaluation Procedure (ISP-017) has
been established for the purpose of identifying legal and other requirements applicable to the OH&S hazards and
evaluating compliance to such requirements on a periodic (yearly) basis.
Related documents:
ISP-017 – legal and other Requirements Identification, Compliance and Evaluation Procedure.
ISF-017/1 – legal Requirements Identification and Compliance Evaluation Register.
Planning action
Flowtronix Arabia Ltd. has planned actions to address significant environmental aspects, compliance obligations, risks
and opportunities, address legal requirements and other requirements and prepare for and respond to emergency
situations. We have planned to integrate and implement the actions into its integrated management system
processes or other business processes and evaluate the effectiveness of these actions;
Flowtronix Arabia Ltd. has taken into account the hierarchy of controls and outputs from the integrated management
system when planning to take action. When planning these actions, Flowtronix Arabia Ltd. consider its technological
options and its financial, operational and business requirements.
Page 17 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Integrated Objectives and Planning
Flowtronix Arabia Ltd. has established and documented Integrated Objectives at relevant functions, levels and
processes needed of the Integrated Management System, in Appendix – C of this Integrated Manual. Documented
Integrated Objectives are;
a)
b)
c)
d)
e)
f)
Consistent with the Integrated Policy,
Made Measurable,
Taking in to account applicable legal requirements,
Relevant to conformity of services and to enhancement of Customer Satisfaction,
Communicated and Monitored,
Reviewed (in Management Review at defined planned interval) and updated as necessary.
Flowtronix Arabia Ltd. has also established achievement plan for documented objectives, with in Appendix – C of this
Integrated Manual. This achievement plan covers the following;
a) Actions to be taken for achievement of the objectives or the means by which objectives are to be
achieved.
b) Required resources.
c) Target time.
d) Responsible department / person.
e) Monitoring mechanism including frequency.
Related document:
Integrated Objectives – Appendix-C
Planning Objectives – ISP-008
Planning of Changes
When the organization determines the need for changes, Flowtronix Arabia Ltd. ensures that integrity of the
Integrated Management System is maintained while planning and implementation of changes. This shall be carried out
in accordance with the planned arrangements, as mentioned in clause 9.3.2.
SUPPORT
Resources
General
The Top Management of Flowtronix Arabia Ltd. along with the concern Department Managers has determined and
provided the resources needed to implement and maintain the Integrated Management System and continually
Page 18 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
improve its effectiveness, preventing pollution eliminating hazards and ill health and to enhance customer
satisfaction by meeting customer requirements.
While determining the required resources, the organization has also considered risk associated with this process,
including;


The capabilities of, and constrain on, existing internal resources
And the requirements for outsourcing of resources from external providers.
People
Flowtronix Arabia Ltd. has determined and provided the persons necessary for the effective implementation of its
Integrated Management System and for the operation and control of its processes.
Man power requirements for each activity are determined and provided by the assigned Manager which is further
then further evaluated for adequacy.
To achieve its performance improvement objectives, Flowtronix Arabia Ltd. has encouraged the involvement of its
personnel by:





Having continual training and awareness,
Defining responsibilities and authorities,
Ensuring effective & efficient teamwork,
Communicating suggestions and opinions,
Recognizing and rewarding.
Infrastructure
Flowtronix Arabia Ltd. has determined, provided and maintained the infrastructure necessary for the operations of its
processes and to achieve conformity of its related services.
Environment for the Operation of Processes
Flowtronix Arabia Ltd. has determined, provided and maintained the environment necessary for the operation of its
processes and to achieve conformity of services. The determined work environment covers Social, Psychological and
Physical factors, as addressed in Risk Assessment relevant to the working environment process.
Flowtronix Arabia Ltd. personnel work, allocated by the customer. Prior to deployment of personnel, each one is
briefed thoroughly about the requirements of customers and applicable statutory and regulatory requirements
includes but not limited, to quality, health and safety and general workmanship safety orientation.
Page 19 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Monitoring and Measurement Resources
7.1.5.1 General
Flowtronix Arabia Ltd. has determined and provided the resources needed to ensure the valid and reliable results
when monitoring or measurement is used to verify the conformity of service to requirements. These resources
include;
a) Methods or 2nd / 3rd party reference standards used for monitoring of product to requirements.
b) Reference equipment used for monitoring or measurement purpose during inspection, testing or any sort
of verification.
c) Personnel with their specific competency relevant to the monitoring or measurement of any specific
process or service. For example, like Welder qualification requirements in Welding process.
d) Any other resource related to Infra structure or Work Environment, needed to ensure valid and reliable
results.
Flowtronix Arabia Ltd. shall maintain appropriate documented information as evidence of fitness for the purpose of
monitoring or measurement resources.
7.1.5.2 Measurement Traceability
Where Measurement traceability is the requirement, Flowtronix Arabia Ltd. observes proper control of measuring
and test equipment, determines the monitoring and measurement to be undertaken and the monitoring and
measuring equipment needed to provide evidence of conformity of service to determined requirements. It
established processes to ensure that monitoring and measurement can be carried out and are carried out in a
manner that is consistent with the monitoring and measurement requirements. To ensure valid results, measuring
equipment;
a) are calibrated or verified, or both, at specified intervals, or prior to use, against measurement
standards traceable to international or national measurement standards; where no such
standards exist, the basis used for calibration or verification shall be retained as documented
information;
b) adjusted or re-adjusted as necessary;
c) have identification in order to determine its calibration status;
d) safeguarded from adjustments that would invalidate the measurement result;
e) Protected from damage and deterioration during handling, maintenance and storage.
Company’s Specialist Technicians or Third Party Calibration Lab is responsible for the calibration of all test
equipment. The QA/QC personnel shall ensure that only calibrated equipment is used in inspection and testing
operations.
List of measuring and test equipment shall be identified suitable to the need of the job specification.
Calibration shall be done against a certified reference standard whose accuracy is traceable to national standard or
obtained from independent reproducible standard. Calibrated test equipment shall be provided with calibration
Page 20 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
status identification sticker or Tag. Defective equipment or those calibration date had expired should be
immediately segregated for appropriate action.
A list of Calibrated Measuring and Test Equipment shall be maintained showing the equipment identification, serial
number, the calibration dates and due dates.
Organization Knowledge
Flowtronix Arabia Ltd. has determined and maintained the necessary knowledge specific to processes & competence
for personnel performing work requirements. The knowledge is determined in terms of evaluation of personnel work
experience for specified process, at the time of hiring or at the time of transfer from one process to another. This is
covered as part of competency parameter itself which include other parameter like education, training, skill and
experience.
Competence
Flowtronix Arabia Ltd. provides training or take other actions to achieve the necessary competence, evaluate the
effectiveness of the actions taken. Ensures that its personnel are aware of the Integrated Policy and relevant
Integrated Objectives, their contribution to the effectiveness of the Integrated Management System including the
benefits of improved performance, the implications of not conforming to the Integrated Management System
requirements. Maintains appropriate document information of education, training, skills and experience.
Awareness
All new employees of are required to undergo Induction training program to familiarize their job requirements and the
Management System. This program defined in such a way that new employee clearly understands the channels of
internal communications and System requirements. Through immediate superior or department head, the
Management conducts performance evaluation to each employee as their basis for giving increment and
regularization. The new employee will be evaluated on the basis of their performance by their immediate superior or
the department head prior to the completion of their probationary period of 3 months or prior to their regularization.
Communication
The Procedure for Communication (ISP-018) is implemented to have effective arrangements for communicating the
hazards, Aspects and management system internally and externally. Employees are involved in hazard and risk
analysis, incident investigation and are consulted on matters that may affect their health & safety in the workplace.
The means of communication are via internal memos, posters, notice boards, letters, website, trainings and internet.
Consultations with employees are done during safety meetings, tool box talks, interviews, discussions and
investigation process. Contractors and suppliers who work for or on behalf of are consulted on changes in the
workplace or activities that could affect their Integrated Management System. Decision to communicate externally
Page 21 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
about significant environmental aspects and the required methodology is documented in the procedure
Communication (ISP-018).
For External communication, Flowtronix Arabia Ltd. has defined or designated the responsibility for each relevant
department.
External communication included communication to and or from external interested parties, such as;



Communication to and / or from customer relevant to the contracted services, its feedback including
resolution of complains.
Communication to and / or from external providers relevant to the purchased product.
Communication to and / or from Regulatory bodies
Where ever required, organization shall retain documented information for internal and external communications.
Related document:
Communication Procedure – ISP-018
Page 22 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Documented Information
General
Flowtronix Arabia Ltd. has established Integrated Management System which includes documented information for
Integrated Policy & Integrated Objectives and the structure of its documentation is in Four (4) levels to ensure that
the services provided By Flowtronix Arabia Ltd. conform to specified requirements and continually improves its
effectiveness.
The structure of the IMS documented information is illustrated below and elaborated in the succeeding paragraphs:
IMS DOCUMENTATION STRUCTURE
Level 1:
Integrated Manual
Level 2:
Integrated System Procedures
Level 3:
Process Flows / Work Instructions
Level 4:
Records / Formats
Creating & Updating
Level 1 – Integrated Management System Manual (This manual), as documented information, is introductory
describing Flowtronix Arabia Ltd.’s Integrated Policy and objectives and broadly stating what are to be done to assure
expected quality of services. The manual has covered all the requirements of the International Standard ISO
45001:2018, ISO 14001:2015 & ISO 9001:2015. The Integrated Manual also makes reference of the applicable
procedures.
Level 2 – Quality Procedures are the documented information which describe the overall procedures and
responsibilities for operating the Integrated Management System (IMS) by all divisions/departments/units of
Flowtronix Arabia Ltd. to effectively implement each requirement of ISO 45001:2018, ISO 14001:2015 & ISO
9001:2015 standards. It covers the documented procedures and records required by ISO 9001, ISO 14001 & ISO
Page 23 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
45001 and to include those other documents and records that may be needed by Flowtronix Arabia Ltd. to ensure the
effective planning, operation and control of its process.
Level 3 – Quality Process Flows/Work Instructions are documented information, which describes the specific quality
process. Contain individual process flow documents, work instructions, internal specifications operational processes
& instructions and plans pertaining to the business operations.
Level 4 – Quality Records/Forms: These comprise the fourth level of the Integrated System documentation. They are
generated and maintained as per the system requirements. They provide evidence that the Integrated System has
been implemented and maintained effectively. The particular record to be generated and the standard formats to be
used are detailed under the relevant functional procedures.
Control of Documented Information
As part of documented information, Flowtronix Arabia Ltd. maintains a documented procedure for control of
documented information. The details of the process of documentation including review, approval, changes and
distribution of document are found in the Procedures –Level ‘2’.
Flowtronix Arabia Ltd. adheres to the adequate control of documented information, is an essential requirement in
the pursuit of an efficient operation.
The IMS Manual distribution is divided into two (2) categories, i.e.:
a. Controlled Copies:
Controlled copies of the IMS Manual shall be stamped “Controlled Copy” in red and issued to the authorized holders.
Any changes in the IMS Manual affected by any revisions shall be incorporated to the controlled copies issued.
The originals of the IMS documents are under the custody of QA / QC Head.
List of Controlled Copy holders are the following;
1. General Manager – Copy # 01
2. Management Representative – Copy # 02
3. Library Copy – Copy # 03
b. Uncontrolled Copies:
Any photocopy of Flowtronix Arabia Ltd. IMS document is considered an “Uncontrolled Copy”.
A soft copy of the original Integrated Management System Manual (in PDF format) is available at Flowtronix Arabia
Ltd. Portal.
7.5.3.1 Documented Information Control Coverage
Documented information subject to control can be in the form of hard copy or electronic media. Flowtronix Arabia
Ltd. ensure that documented information of external origin determined by the organization to be necessary for the
planning and operation of Integrated Management System.
Page 24 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
7.5.3.2 Documented Distribution Control
Management System are identified and their distribution controlled. Documents cover but not limited to the
following:











Department Functional Procedures
Quality / Safety Programs/ Plans
Specific Work Process Procedure.
Maintenance/ Procedure.
Industry Codes and Standards
Engineering Standards and Specifications.
Client Specifications.
Materials Specifications.
Change Orders / Contract Amendments
Third Party Test and Inspection Reports
External Audit Reports
a) Flowtronix Arabia Ltd. prevents the unintended use of obsolete documented information, and to apply
suitable identification to them if they are retained for any purpose.
b) While creating or updating any documented information, Flowtronix Arabia Ltd. ensures; proper
identification and description on the documented information, to have it in proper format and media and to
have proper review and approval for adequacy.
c) Flowtronix Arabia Ltd. has established a documented information in form of Procedure to define the controls
needed for the identification, storage, protection, retrieval, retention and disposition of documented
information. The Company’s documented information to be retained (Quality Records) is described in Doc.
No. MR-ISP-001, to include Final QA/QC documented information comprising all Test and Inspection
Certificates/Reports for a particular contract shall be treated as documented information (quality records), a
special type of documented information to provide evidence of conformity to the requirements and effective
operation of the Integrated Management System.
d) All documented information to be retained (quality records) shall be maintained and filed in an orderly
manner for a retention period as specified in contract agreement with customers.
e) Documented information (Quality record) retention shall be identified and marked with “Date of Destroy.”
Expiry of the retention period is described in Documented Information; Document no. MR-ISP-001 (Clause
7.5). Periodical audits shall be conducted to ensure safety storage of the documented information.
f)
All company’s computers are protected with anti-virus program (i.e., MacAfee Virus Scan Enterprise).
Documented information in computer shall be retained or provided with backups.
Related document:
Control of Documents – MR-ISP-001
Page 25 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
OPERATIONS
Operations Planning and Control
General
Flowtronix Arabia Ltd.’s business starts with the identification/selection of prospective activity & preparation of prequalification within the framework of its Integrated Objectives.
Flowtronix Arabia Ltd.’s Business Development arm has a full knowledge of the company’s line of businesses and it has
established and maintains processes required for management and execution. Each processes are identified,
evaluated, planned, documented and controlled.
Inter-dependent Related documented information (such as Technical Services, Manpower, QA/QC, Purchasing, etc.)
shall maintain with proper coordination to achieve an effective and efficient operation to satisfy the customers and
other interested parties.
To outline Flowtronix Arabia Ltd. operations, the following shall be considered:






Determine and communicate significant features of the processes
Define training requirements in the operation of processes
Share skill and experience to every work group/section
Measure and audit processes
Analyze, review and improve the processes
Ensure safety for all employees
Flowtronix Arabia Ltd. shall maintain and retain the documented information in order to have confidence that
processes have been carried out in planned manner and to demonstrate the conformity and relevant service to the
defined requirements.
When any change is required to be planned, Flowtronix Arabia Ltd. shall control such planned changes via reevaluation of the addressed risk associated with such changes and shall ensure that all the action are effectively
planned and implemented in order to mitigate any adverse effects.
Flowtronix Arabia Ltd. shall strive for continual improvement to provide satisfactory activity, to improve customer
satisfaction and confidence, to improve utilization of resources, to improve safety program and reduction of waste to
achieve more effectiveness and efficiency of processes.
To ensure continual improvement on activity realization, the company shall retain evaluation of existing processes,
revising Procedures and Work Instruction (as required) and providing appropriate resources.
Established Procedure as Hazard Identification, Risk Assessment & Risk Control (ISP-016) is established for defining
and managing required Operational Control to ensure that operations and activities associated with specified OH&S
Risks are controlled and related responsibilities and accountability are determined and defined.
Page 26 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Controls related to all OH&S hazards and risks are identified in, Hazard Identification, Risk Assessment & Observations
Register where resultant risks are rated and adequacy of controls is determined.
Flowtronix Arabia Ltd. has established Operational Controls Procedure for defining and managing required Operational
Control to ensure that operations and activities associated with specified EMS Risks and Significant Environmental
Aspects are controlled and related responsibilities and accountability are determined and defined.
Controls related to all Significant Environmental Aspects and their impacts are identified in, Environmental Aspects &
Impacts procedure, where resultant impacts of the Environmental Aspects are rated and adequacy of controls is
determined.
Controls include:
a) Operational controls in the form of method statements, work instructions, safe systems of work and
effective supervision;
b) Controls related to purchased goods, equipment and services (i.e. obtaining approval for raw material &
consumable material purchase, supplier evaluation, availability of product information, documents for
preventive maintenance, etc.).
c) Controls pertaining to supplier and other visitors to the workplace (i.e. IMS induction, operating
procedures, work supervision and monitoring).
Eliminating hazards and reducing OH&S risks
Controls related to all OH&S hazards and reducing OH&S risks are defined Hazard Identification, Risk Assessment &
Operational Control Procedure (ISP-016). OH&S Hazards and OH&S Risks are identified in, Hazard Identification, Risk
Assessment & Operational Control Register where resultant risks are rated and adequacy of controls is determined.
Controls include:


Operational controls in the form of method statements, work instructions, safe systems of work and
effective supervision;
Controls pertaining to supplier and other visitors to the workplace (i.e. induction, procedures, work
supervision and monitoring).
Related document:
Hazard Identification, Risk Assessment & Risk Control Procedure – ISP-016
Management of change
The Flowtronix Arabia Ltd. has established a process for the implementation and control of planned temporary and
permanent changes that impact Integrated Management System performance, including:
a) New services and processes, or changes to existing services and processes, including:


workplace locations and surroundings;
work organization;
Page 27 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL



ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
working conditions;
equipment;
work force;
b) Changes to legal requirements and other requirements;
c) Changes in knowledge or information about OH&S hazards and OH&S risks;
d) Developments in knowledge and technology.
The organization shall review the consequences of unintended changes, taking action to mitigate any adverse effects,
as necessary.
Procurement
8.1.4.1 General
The Flowtronix Arabia Ltd. has established, implemented and maintained a process to control the procurement of
products and services in order to ensure their conformity to its IMS.
8.1.4.2 Contractors
The Flowtronix Arabia Ltd. coordinate its procurement process with its contractors, in order to identify hazards and
to assess and control the OH&S risks arising from:
a) contractors’ activities and operations that impact the organization;
b) organization’s activities and operations that impact the contractors’ workers;
8.1.4.3 Outsourcing
The Flowtronix Arabia Ltd. ensures that outsourced functions and processes are controlled. Its outsourcing
arrangements are consistent with legal requirements and other requirements and with achieving the intended
outcomes of the Integrated Management System.
Requirements for Services
Customer Communication
To ensure effective arrangements of communication with the customers, Flowtronix Arabia Ltd. has implemented
effective communication with customers in relation to:
 Providing information relating to services.
 Client Information.
 Enquiries, contracts, amendments and change order.
 Customer’s feedback including complaints.
 Handling or Controlling Customer Property.
 Specific requirements of contingency action, when relevant.
Page 28 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Determining the Requirements for Services
As a fundamental business practice, viability of a certain contract undertaking depends on the full understanding and
acceptance on the contents of the Contract Agreement with the customers. From bidding and negotiating stage, the
company exercise proper assessment of documents and any changes identified shall be incorporated in the Final
Contract Agreement.
Flowtronix Arabia Ltd. determines and implement procedures to ensure adequate understanding of the needs and
expectation of the customers, including the classification and review of all relevant information.
Relevant information related to the activities:





Contract Agreement and Specification
Job completion requirement
Inspection and Test requirements and other requirements necessary for specified or intended use
Statutory and Regulatory requirements applicable to the Activity
Any additional requirements as needed
Review of the Requirements
Flowtronix Arabia Ltd. shall ensure that services requirement are properly defined, any differing contract or order
requirements are resolved and its ability to meet the defined requirements.
If required, sales and marketing department will be formed to evaluate the requirements of the activity. This review
shall be conducted prior to Flowtronix Arabia Ltd. commitment to supply services to the customer such as submission
of bids, acceptance of contracts or orders, acceptance of changes to contract or orders.
Prior to quotation submission, thorough review shall be made by the Review Committee member/s decided by the
Head Service & Operations Manager on cost estimates to ensure all contract requirements is achievable.
Once the quotation is approved, the Estimate & Proposal Unit of the Technical Services Department shall review the
contents of the Contract Agreement and cross-check the Pre-bid documents for any possible changes or addendum.
It is then endorsed to the General Manager for Contract Acceptance and signing. Pre-bid documents are recorded in a
Control Log Book, maintaining the date of receipt and subsequent changes or revisions.
Flowtronix Arabia Ltd. shall retain the documented information on the results of review and on any new
requirements for the contract / service.
Changes to Requirements for Services
Flowtronix Arabia Ltd. shall ensure that relevant documented information is amended, and the relevant persons are
made aware of the changed requirements, when any of the service requirements are changed.
Page 29 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Design and Development
FTA has a system to carryout design and development of product or process as required by customer. The design &
development includes detailed engineering of a project on basis of inputs from the customer and deliverable like the
preparing bill of quantities and detailed drawings etc.
Control of Externally Provided Products and Services
General
Flowtronix Arabia Ltd. ensures that externally provided products and service confirms to the requirements. The type
and extent of control applied to the external provider and the purchased product, shall be dependent upon the effect
of the purchased products on organization’s ability to consistently deliver confirming services to its customers.
Flowtronix Arabia Ltd. shall retain documented information of selection, evaluation, re-evaluation and performance
monitoring of external providers and any necessary action arising from such evaluations.
Type and Extent of Control
Flowtronix Arabia Ltd. ensures that such out sourced activities do not adversely affect its ability to consistently
deliver confirming services to its customers, by ensuring the following;



Such outsourced activities remains within organization’s control.
Controls related to the external providers and to the resulting output from the outsourced activities are
defined and effectively applied.
Effectiveness of the application of control and potential impacts of the outsourced activities on Flowtronix
Arabia Ltd. ability to fulfill customer requirements is ensured.
Information for External Providers
Flowtronix Arabia Ltd. ensures the adequacy of the requirements prior to their communication to external providers.
The Procurement Department is responsible for the purchase of materials / products in compliance with the products
standards and specifications set forth by the customer.
Purchase Orders are prepared from the Purchase Requisitions, containing all relevant technical and quality
information.
Purchasing information, communicated to external provider, shall describe the requirements for purchasing,
including, where appropriate;
a)
b)
c)
d)
e)
requirements for approval of product, procedures, processes, methods and equipment,
requirements for qualification of personnel,
Flowtronix Arabia Ltd. IMS requirements,
External provider interaction with the organization,
Controls and monitoring of the external providers’ performance to be applied by the Company,
Page 30 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
f)
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Verification or validation activities that Flowtronix Arabia Ltd., or its Customer, intends to perform at the
external providers’ premises.
Aside from Flowtronix Arabia Ltd. Inspectors and if stipulated in customer’s requirement/s, Flowtronix Arabia Ltd.
allows customer’s representative to have access to the supplier’s facilities to conduct verification to ensure that the
products conform to the specifications.
This however will not relieve Flowtronix Arabia Ltd. and the external providers of its obligations for any subsequent
rejection that may be found during inspection.
As an Integral part of the overall inspection and testing processes, the Material Management Plan shall detail the
requirement of receipt inspection, storage, preservation, traceability identification and inventory control before it is
released for service.
Documented information relevant to the Purchase Order shall be retained.
Service Provision
Control of Service Provision
Flowtronix Arabia Ltd. has established and maintained procedures, and plan actions to execute specific contract
treated as a whole activity works that requires documentation and pre-qualified program aimed to ensure controlled
conditions, preventing deviation during the stages of services and completion of the activity.
Controlled conditions shall include, as applicable,
a) The availability of documented information that describes the characteristics of the services or the activities
to be performed, and the results to be achieved.
b) the use of suitable infrastructure and environment for operation of its processes,
c) the availability and use of monitoring and measuring resources,
d) the implementation of monitoring and measurement activities at appropriate stages,
e) the appointment of competent persons, including any required qualification,
f)
the validation, and periodic re-validation, of the ability to achieve planned results of the processes for
services provision, where the resulting output cannot be verified by subsequent monitoring and
measurement,
g) The implementation of actions to prevent human error.
Flowtronix Arabia Ltd. maintain the documented information required to justify the effective implementation of
above defined controlled conditions.
Identification and Traceability
Flowtronix Arabia Ltd. maintains proper identification and documented information to every materials and products
for any specific contract job to ensure traceability and identification during the stages of installation.
Page 31 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
The system of identification, marking and traceability shall be established and incorporated in the Purchase Order (as
appropriate) to form part of the specification attachment. This covers bulk materials, fabricated items or finished
products coming from the suppliers and subcontractors.
Property Belonging to Customers or External Providers
Flowtronix Arabia Ltd. shall exercise care with property belonging to Customers or External Providers (including,
where applicable, materials, components, tools and equipment, premises, intellectual property and personal data)
while it is under the Company’s control or being used by the organization.
Flowtronix Arabia Ltd. shall identify, verify, protect and safeguard customers’ or external providers’ property
provided for use or incorporation into the product.
If any customers’ or external providers’ property is lost, damaged or otherwise found to be unsuitable for use,
documented information shall be retained and reported to the customer or external provider on what has occurred.
Preservation
Flowtronix Arabia Ltd. properly identifies the product and adheres with the necessary handling procedure, storage,
packaging, protection and delivery of materials/products to its intended destination in order to maintain conformity
to the requirements as per the Material Management Plan. At every stage of process, materials are handled
according to company regulation to protect from damage and maintain its quality.
Post – Delivery Activities
Flowtronix Arabia Ltd. ensures fulfillment of all requirements relevant to post-delivery activities agreed contractually
with the customer. While determining the extent of post-delivery activities that are required, Flowtronix Arabia Ltd.
considers;
a) Statutory and regulatory requirements,
b) The potential undesirable consequences associated with its service,
c) The nature, use and intended life time of its product,
d) Customer requirements and
e) Customer feedback
Control of Changes during Services
When any change is addressed, Flowtronix Arabia Ltd. shall review and control such changes, to the extent necessary
to ensure continuing conformity with the requirements.
Flowtronix Arabia Ltd. shall maintain documented information of such changes, including the results of the review of
changes, the person authorizing the changes and any necessary actions arising from the review of such changes.
Page 32 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Release of Products and Services
Evidence of conformity, as documented information, shall be affirmed and retained through test and inspection during
receipt of the materials, services processing and once completed. Result of inspection and acceptance shall be
retained as documented information in the QA/QC Department.
The product and services shall be monitored and measured based on:
 Client issued Non-Conformance Report (Client’s Standard NCR Form) and Internal Non-Conformance Report.
 Weekly coordination meeting report.
 Complaints raised during regular coordination or special meetings with client recorded in the minutes of
meetings.
The release of services and products and delivery to the customer shall not proceed until the planned arrangements
have been satisfactorily completed, unless otherwise approved by a relevant authority and, where applicable, by the
customer.
Control of Non-Conforming Outputs
Flowtronix Arabia Ltd. maintains documented information in handling non-conformance to contract specification
and/or purchase order as observed during the course of QC inspection and after delivery or use has started. It deals
with non-conforming outputs in one or more of the following ways:
a) By taking action to eliminate the detected non-conformity;
b) By informing to customer where applicable and required;
c) By authorizing its use, release or acceptance under concession by a relevant authority and, where
applicable, by the customer;
d) By segregation, containment, return or suspension of provision of services.
e) By taking action appropriate to the effects, or potential effects, of the non-conformity when nonconforming product is detected after delivery or use has started.
When non-conforming product is corrected it shall be subject to re-verification to demonstrate conformity to the
requirements.
Documented information shall be retained, covering following information;




Description of Non-Conformity;
Description of the actions taken;
Describes any concession obtained;
Identifies the authority deciding the action in respect of the Non-Conformity.
Page 33 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Emergency Preparedness and Response
The procedure for Emergency Response (MR-ISP-006) supported by Emergency Response Plans (ERPs) have been
developed and relevant personnel have been identified in order to effectively communicate and take any necessary
actions. The Management Representative and safety personnel ensure that drills and other emergency practices are
conducted regularly and recorded, wherever applicable, in order to create awareness of the OH&S consequences,
actual or potential, of their work activities and the benefits of improved personnel performance. Review of response
plans is mandatory at defined interval and specifically, immediately after the occurrence of any incident or emergency.
Related document:
Emergency Preparedness & Response Procedure – MR-ISP-006
PERFORMANCE EVALUATION
Monitoring Measurement Analysis and Performance Evaluation
General
Flowtronix Arabia Ltd. has established and maintains documented systems in monitoring, measurement, analysis and
improvement processes to prove that conformity of the activity is in relation to the Integrated System and customer’s
requirements.
a) Service Conformity
Flowtronix Arabia Ltd. ensures effective and efficient measurement; collection and validation of data to ensure the
finished service conform to the requirements.
All completed services are subject for test and inspection at appropriate stages of processes, as specified in the
Quality Plan or required by customer specification.
Flowtronix Arabia Ltd. continually monitors its performance improvement actions and retains documented
information of its result. These data results from improvement activities shall be used as added input during the
Management Review Meeting. These provide information for improving the quality of the activity and operational
sequence.
b) Integrated Management System Conformity
To ensure effective continual improvement, Flowtronix Arabia Ltd. has established and maintained documented
information for planning and implementing Audits, to verify quality activities and relates results comply with
planned arrangements, and to determine the effectiveness of company’s Integrated System.
Flowtronix Arabia Ltd. shall identify the need for statistical techniques required for establishing, controlling or
verifying process capability and product characteristics, including the establishing and maintaining documented
information to implement and control the application of the statistical techniques.
Page 34 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
c) Integrated Management System Effectiveness
Satisfactory results from past services shall be the basis of analyzing the effectiveness of the Integrated System
continual improvement.
Technical reports which features advance technology for effective processes shall be another source of identifying
the need of improvements.
Customer’s feedbacks and non-conforming reports shall be statistically analyzed to attain appropriate information
to implement corrective actions.
Test and Inspection results can be analyzed statistically to provide data suitable to the customer’s requirement.
Statistical analysis generated by the company will be released to the customer (if required).
Customer Satisfaction
Flowtronix Arabia Ltd. shall determine Customer Satisfaction through survey by providing questionnaire to the
customer at least once in a year to ensure service requirement is achieved.
Customer feedback (as indicator of Company’s performance) such as complaints, non-conformities, performance
indices, deficiencies including commendation for excellent performance are normally issued to Flowtronix Arabia Ltd.
in documented forms of communication / documented information i.e.:
a. Client issued Non-Conformance Report (Client’s Standard NCR Form)
b. Complaints raised during regular coordination or special meetings with client recorded in the minutes of
meetings.
c. Performance Indices report issued by Customer on monthly basis to Flowtronix Arabia Ltd. serves the basis
of knowing the degree of satisfaction of customer on Company’s performance.
d. Excellent Performance Rating included in the Customer’s website re: “Posting of Contractors Name with Best
Performance in completing the ahead of schedule, high quality and well administered” (if available).
Where customer complaint is received, the Management Representative and work services heads shall conduct a
thorough investigation to provide appropriate corrective actions to satisfy the conformity of the services.
Analysis and Evaluation
Flowtronix Arabia Ltd. determines, collects and analyzed appropriate data to demonstrate the suitability and
effectiveness of the quality management system and to evaluate where continual improvement of the
effectiveness of the Integrated Management System can be made. This shall include data generated as a result of
monitoring and measurement and from other relevant sources.
The results of data analysis shall be retained as documented information and shall be used to evaluate;
a)
b)
c)
d)
The degree of customer satisfaction,
Conformity of service,
The performance and effectiveness of the Integrated Management System’
If planning has been effectively implemented,
Page 35 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
e) The effectiveness of the actions taken to address risk and opportunities,
f) The performance of external providers,
g) The need for improvements to the Integrated Management System.
Evaluation of Compliance
Compliance with legal (statutory and regulatory) and other requirements applicable to the operations and activities is
evaluated periodically for conformance to established Integrated Management System as per documented Procedure
for Legal Requirements identification and Compliance Evaluation Procedure (ISP-017) where the results of periodic
evaluation are recorded in Legal Requirements identification and Compliance Evaluation register.
Related document:
Legal & Other Requirements Identification, Compliance and Evaluation Procedure – ISP-017
Internal Audit
Flowtronix Arabia Ltd. planned and conducted Internal Audits for each functional area of the company at least once
per year in order to determine the compliance of the Integrated Management System to the requirements of ISO
45001:2018, ISO 14001:2015 & ISO 9001:2015 standards established by the organization, and is effectively
implemented and maintained.
The Flowtronix Arabia Ltd. shall ensure all corrective actions and recommended improvements are effectively
implemented. Quality Planning shall also be flexible in order to allow changes in emphasis based on the results and
objectives evidence during the audit.
The audits and follow-up actions shall be carried out in accordance with documented procedures and deficiencies
found by the Auditor shall be notified to the relevant function. The Auditor will review the deficiency; assess the
corrective action suggested by an auditee and sign off the audit if satisfactory. The Auditors shall be independent or
impartial during the conduct of audit to the area they are assigned to audit. Auditors shall not audit the area of his
work assignment. The criteria and scope of the audit shall be defined while managing the audit process.
Department/sections audited must ensure corrective actions are implemented within the specified time frame.
Internal Audit Process shall be managed in accordance with the documented information for internal audit process,
maintained in ISP-002. Documented information of the audits and its result shall be retained.
Related document:
Internal Audit / Control of Non-Conformity / Correction & Corrective Action Procedure – ISP-002
Management Review
General
Flowtronix Arabia Ltd. Management reviews its Integrated Management System at least once in a year, as per
maintained documented Information # ISP-003, to ensure its continuing suitability, adequacy and effectiveness. This
Page 36 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
review meeting includes the opportunities for improvement and the need for the changes to the Integrated
Management System. It also includes the review of Integrated Policy and Integrated Objectives.
This review being conducted by the Management Committee chaired either by the General Manager or by
department heads, process owners for the purpose of reviewing and ensuring the continuing suitability and
effectiveness of the Integrated Management System.
Management Review Inputs
Review inputs shall evaluate efficiency as well as effectiveness of the Flowtronix Arabia Ltd. Integrated Management
System to sustain and maintain a continual improvement program of the Integrated Management System. All
approved decisions or actions are programmed for implementation including but not limited to:
a) Results of the audits, (Internal & External),
b) Changes in External and Internal issues that are relevant to the Integrated Management System,
c) Customer feedback, (Complaints & Satisfaction Survey),
d) Process performance and service conformity,
e) Status of correction and corrective actions,
f)
Follow-up actions from previous management reviews,
g) The performance of external providers,
h) The extent of which Integrated Objectives have been met,
i)
The adequacy of the resources,
j)
The effectiveness of the actions taken to address risks and opportunities,
k) Changes that could affect the Integrated Management System including any change in relevant
applicable regulatory and statutory requirements, and
l)
Opportunities for improvement.
Management Review Outputs
The output from the management review shall include any decisions and actions related to:
a) Improvement of the effectiveness of the Integrated Management System and its processes,
b) Improvement of services related to customer requirements, and
c) Resource needs
Documented information, as evidence of the results of Management Review, shall be retained.
Related document:
Management Review Procedure – ISP-003
Page 37 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
IMPROVEMENT
General
Flowtronix Arabia Ltd., in consideration to commitment for continual improvement, demonstrated in the Integrated
Policy, continually improves the system in order to meet customer requirements and to enhance customer
satisfaction. This shall be carried out through the use of the Integrated Policy, Integrated Objectives, audit results,
analysis of data, corrective actions and management reviews.
Flowtronix Arabia Ltd. considers the results of the analysis and evaluation, and the outputs from the Management
review, to determine if there are needs or opportunities, which shall be addressed as part of the continual
improvement.
Incident Investigation, Non-Conformity and Corrective Action
Incident Investigation
The procedure established for Incident Investigation (ISP-019) demonstrates the method of how the carries out an
incident investigation (accident, near miss or emergency) as well as the specific responsibilities and authorities of
personnel. Incident investigation log forms part of reactive measures of performance as stated in Section 9.1
Monitoring Measurement Analysis and Performance Evaluation of this Manual. Incident facts are entered initially
either in form Incident /Accident Report or in form NCR / CA Report after which a full investigation report is finalized
and submitted to the General Manager. The procedure for Incident Investigation (ISP-019) delineates how the
following processes are carried out and by whom:



Incident scene preservation;
Incident investigation documentation;
Investigation process.
Related document:
Incident Reporting & Investigation Procedure – ISP-019
Non-Conformity and Corrective Action
The need for corrective and preventive action is determined on the basis of identified actual and potential nonconformities. Corrective Action Requests are normally generated in response to non-conformities such as a deviation
in Quality planning, safe working systems, procedures or work instructions, unsafe acts and conditions as a result of
inspections and surveys, deviation in emergency response, or an audit finding while Corrective actions result from
identification of any problems requiring corrections or the use of appropriate sources of information such as trend
analyses of incidents, audit reports, records, risk analyses updates, new information on hazardous materials, safety
inspections, and consultation and advice from employees. Reference can be made to the established procedure
Internal Audit, Control of Non-conformities, Correction & Corrective Action (ISP-002) on how non-conformities are
handled.
Page 38 of 39
Issued date: 20/Jun/2018
Rev: 00
ISM-001
INTEGRATED MANAGEMENT SYSTEM MANUAL
ISM-001
Revision 00
Issue Date: 20/Jun/2018
PREPARED BY:
MR
REVIEWED BY:
MANAGER SALES
APPROVED BY:
GENERAL MANAGER
Requirement for corrective actions are documented in a Non-Conformance Report where the nature of the nonconformity is recorded. The process owner identifies the proposed corrective action and sets reasonable time frames
for implementation. After the due date, Management Representative reviews the action taken and evaluates the
effectiveness of the corrective action.
This Corrective Action Procedure defines the requirements for:
a) Identify a non-conformity, correct it and take action to mitigate its consequences;
b) reviewing non-conformities (including customer complaints)
c) Investigate a nonconformity, determine its root cause and take action to prevent its recurrence;
d) evaluating the need for corrective actions to ensure that non-conformities do not recur
e) updating the risks and opportunities determined during planning, if necessary
f) determining and implementing the action needed
g) records of the results of action taken
h) Review the effectiveness of corrective action taken
i) Addressing changes to the Management System if necessary or required as part of addressed corrective
action
The Management Representative maintains records of all the corrective actions initiated analyses and reports
trends periodically and during management review meetings. A procedure for Internal Audit, Control of Nonconformities, Correction and Corrective Action (ISP-002) is established to describe the method for taking corrective
actions in order to avoid recurrence and prevent occurrence of non-conformities.
Risk is carried out prior to implementation of corrective actions that identify new or changed hazards or necessitate
new or changed controls. Changes arising from corrective actions are then incorporated to the integrated
management system documentation.
Related document:
Internal Audit / Control of Non-Conformity / Correction & Corrective Action Procedure – ISP-002
Continual Improvement
Flowtronix Arabia Ltd. in consideration to commitment for continual improvement, demonstrated in the Integrated
Policy, continually improves the system in order to meet customer requirements and to enhance customer
satisfaction, eliminating Hazards and preventing pollution. This shall be carried out through the use of the Integrated
Policy, Integrated Objectives, audit results, analysis of data, corrective actions, opportunities for improvements and
management reviews.
The Flowtronix Arabia Ltd. continually improves the suitability, adequacy and effectiveness of the Integrated
Management System, by promoting the participation of workers in implementing actions for the continual
improvement of the Integrated Management System.
Flowtronix Arabia Ltd. considers the results of the analysis and evaluation, and the outputs from the Management
review, to determine if there are needs or opportunities, which shall be addressed as part of the continual
improvement.
 THE END 