Uploaded by MOHD RAFE ABDUL MAJID

3C45 CEDP 3 EW and ESCP design practice

advertisement
WORKSHOP ON
CIVIL ENGINEERING DESIGN AND
PRACTICE
Ir. Dr. Abdul Naser Abdul Ghani, P.Eng, MIEM, MASCE, MACEM
Associate Professor
School of Housing, Building and Planning, USM
Consulting Engineer
ABADINI INTEGRAS ENGINEERS SDN BHD
PERUNDING PINANG SDN BHD
USAINS HOLDING SDN BHD
Earthwork and ESCP Design Practice
Ir. Dr. Abdul Naser Abdul Ghani, P.Eng, MIEM, MASCE, MACEM
Associate Professor
School of Housing, Building and Planning, USM
Consulting Engineer
ABADINI INTEGRAS ENGINEERS SDN BHD
PERUNDING PINANG SDN BHD
USAINS HOLDING SDN BHD
EARTHWORK CONSTRUCTION DRAWINGS
EXISTING LAND SURVEY /DTM
EW LAYOUT PLAN
Drawings
X-SECTION DRAWINGS
DETAIL DRAWINGS
EARTHWORK CONSTRUCTION DRAWINGS
Land survey plan indicates existing
ground level and details such as
existing stream and structures.
Depending on whether there is
significant variation in ground level,
contour lines indicating major and
minor interval will be shown in this
drawing. The land survey drawing will
also show or indicate the location of
bench mark (BM) or temporary
benchmark (TBM). Reference to a BM
is important during earthwork
operation activities to ensure correct
design and construction of platform
level.
LAND SURVEY PLAN
Graphic courtesy of : Perunding Pinang SB
DTM
Graphic courtesy of: ABADINI Integras Engineers SB
EARTHWORK LAYOUT DRAWINGS
The earthwork layout plan will show and
describe the earthwork components
within a project. Information such as cut
and fill area, temporary works, cross
section alignment, various earth
retaining structures and earthwork
operation notes will be shown in this
drawing.
EARTHWORK LAYOUT
EARTHWORK X-SECTION DRAWINGS
Cross section drawing is usually drawn to
an exaggerated scale especially the vertical
scale. Usually the vertical scale is 10 times
the horizontal scale. This will give clear
indication of changes in level or level
variation along the section. Cross section
drawing can also be used estimate volume
of earthworks.
EARTHWORK DETAIL DRAWINGS
Detail drawing for earthwork is the
type of drawing that is prepared or
made to ensure all the details can be
seen clearly. The number of detail
drawings depends on the components
shown in the earthwork layout. An
example could be the detail of a
sedimentation pond, silt trap, silt
fence, temporary earth drain, and the
various earth retaining structures.
EARTHWORK CALCULATIONS
In the absence of a pre-computed earthwork volume by
design engineers, a contractor or a builder will need to
carry out the computation to ensure the earthwork
operation can be carefully planned and executed. This
demands basic knowledge of plan reading including using
scales, calculation of area on plan, determination of cut
and fill area and finally earthwork volume computation
using suitable methods.
EARTHWORK AREA CALCULATION
Area for cut and fill or for other construction component such as open space, pond or
slope can be calculated using several techniques. Other reasons why there will be the
needs to determine area are: ·
To check the acreage or area within your boundary, project or property
To determine the area of sections of interest, for example
Open space
lakes or water pond
watersheds / catchment area
Pavement / parking space
To estimate materials for:
area to be paved
area to be seeded
area to be resurfaced
AREA CALCULATIONS
There are three common
methods that can be used to
determined or calculate an
area. They are :
1) Division of the area into
simple figures (triangles,
rectangles, and
trapezoids),
2) Triangulation, and
3) Rectangular coordinates.
AREA CALCULATIONS
Using simple division as shown , the area of each triangle can be calculate by using
simple trigonometric equation such as:
Where:
C is the angle between ‘a’ and ‘b’
In the case of when lengths of all the three sides are known, the following formula
can be used to calculate the area within the triangle:
Where,
AREA – COORDINATE METHOD
the area concerned is plotted into a coordinate systems with which each corner
of the site is identified with reference coordinate based on suitable X and Y axis.
COORDINATE METHOD
The steps to calculate the shaded area
shown is as follows:
•List X and Y coordinate in two
columns.
•Repeat coordinates of starting point
at the end
•Sum the products designated by the
arrows as shown in Figure xx
•Difference between the two sums =
twice the area
PRACTICAL APPLICATION
PRACTICAL APPLICATION
Example 1: The site plan shows several existing boundary marker in circles. The
rectangular grid shown in the plan is actually 200 meter x 200 meter on site.
1) Identify the scale of this plan and:
2) Determine the distance between marker “D” and marker “17”
3) Calculate the area in between “16-13-14-D-17-16”
PRACTICAL APPLICATION - SOLUTION
Step 1: Use suitable ruler or scale to measure the rectangular 200 m x 200 m grid
on the plan.
Step 2: Find the ratio between measurement on the plan (in cm or mm) to the 200
meter ( use similar unit e.g. cm)
Step 3: Measure the distance between “D” and “17” in cm or mm, and use the
scale found in step 2 to determine actual distance on site between the two points.
(Answer: 177 meter)
In order to calculate the area within “16-13-14-D-17-16” using triangulation, the
boundary length and diagonal distances between the marks may be needed.
Alternatively, plot suitable X, Y axis and determine the coordinate at each corner
then use coordinate method to find the area. In both situations, use the scale
found in solution 1 to measure the distance for the boundaries and the
coordinates. (Answer: 31307 m2)
EARTHWORK OPERATION AREA – CUT/FIL
Earthwork plan prepared by the engineers usually indicates the layout of the cut and fill
area. However, in the absence of such information, it is the responsibility of the builder to
correctly identify the boundary. Laws regarding the boundary of earthworks especially
when there will be deep cut or fill must be referred before the start of work. Platform
level for the proposed building or structure will usually determine the extent of cut and
fill required. Existing survey plan showing the present ground level will help one decide a
suitable platform level for the building site. Once the platform level is decided, the cut
and fill area and boundary can be determined. This will also identify the needs for any
retaining structure to contain the slope within certain perimeter. For example, retaining
wall is required to prevent cut or fill slope encroaching into neighboring land.
EW Bylaw
OK
?????
TROUBLE
EARTH FILL
TROUBLE
EARTHWORK VOLUME COMPUTATION
Earthworks involve cutting down of hills and filling in of valleys to create building
platform or road sub-grade.
Other related earthworks include excavation for drains and channels. Average end area
or sometimes called double end areas method is usually used for calculating the
earthwork quantities along a road, drain or channel projects. This method calculates the
average end areas of cross sections times the distances between the cross sections. The
volumes are then added together along the route to yield the total volume.
Another method called grid method is more suitable for site development although the
average end area is also suitable in most situations including site development.
Therefore, two primary methods usually used in earthwork volume computations are:
1) Average end area of cross sections
2) Average cut/fill depth using grid
EARTHWORK –AVE. END AREA
Average end area from cross section method, as discussed earlier is particularly more
suitable for road, highways, drain, irrigation canal and other linear structures. For site
specific project such as housing development, school and building platform, this method
will give quick estimation of earthwork volumes required within the site.
VOLUME – AVE END AREA
VOLUME – SHRINKAGE FACTOR
VOLUME – X-SECTION INFO
VOLUME – BASED ON X-SECTION AND ‘AEM’
VOLUME – GRID METHOD
Grid method of earthwork volume
computation utilizes imaginary
gridline spread onto the site. Existing
and propose elevation at grid
intersections are abstracted and used
to calculate average elevation for the
known grid area. Smaller grid space
will require more data abstraction but
will improve the accuracy of
calculation.
VOLUME – GRID METHOD
VOLUME – GRID
Download