ARC FLASH ASSESSMENT GUIDE Author CLASSIFIED SR 11.13122 25/09/2011 P Freeman PTE/EELE Confidential SR.11.13122 Arc Flash Assessment Guide by Peter Freeman (PTE/EELE) This document is Confidential. Distribution is restricted to the named individuals and organisations contained in the distribution list maintained by the copyright owners. Further distribution may only be made with the consent of the copyright owners and must be logged and recorded in the distribution list for this document. Neither the whole nor any part of this document may be disclosed to any third party without the prior written consent of the copyright owners. Copyright SIEP B.V. 2011. Shell International Exploration and Production B.V., Rijswijk Further electronic copies can be obtained from the Global Information Centre. SR.11.13122 0. - II - Confidential Executive summary Exposure of workers to the energy associated with arcing faults can and has caused serious injuries and even deaths within the Shell group of companies. Since the mid 1990s, there has been increasing attention within the electrical community in North America to quantify and reduce the hazards associated with electrical arc flashes. Review of older non-internal arc protected IEC switchgear has identified the potential of similar arc flash-overs in such equipment. Purpose of this guide is to provide not only a description of the recommended arc flash assessment processes to be followed, but also practical advice as to difficulties that may be encountered and possible methods of resolving them. The arc flash assessment process described in this document is intended to fully satisfy the Shell HSEE guidelines in the use of PPE. Apply the following Hierarchy Of Control to manage Personal Protective Equipment use. First: Eliminate the Hazard or exposure. Second: Substitute materials or equipment to reduce the Hazard or exposure. Third: Use engineering Control of the Hazard or exposure. Fourth: Use procedural Control of the Hazard or exposure. Fifth: Use Personal Protective Equipment The output of an arc flash risk assessment produced following this guide includes Identification of where arc flash risk can be eliminated by only working on isolated equipment Identification of where arc flash risk can be reduced by using alternative techniques or measurement points Identification of mitigating actions that can be taken to reduce the probability of an arc flash event occurring, looking at both the current practices and what additional mitigations are feasible to introduce Assessment of the residual levels of risk with no mitigation in place, with current mitigations in place and after additional measures are implemented. This gives an appreciation of the effectiveness of mitigation actions and basis for an objective assessment of the level of actions needed to achieve ALARP. Identification of any additional procedures and controls needed to reduce the probability of an arc flash event occurring and to ensure that the correct levels of site management at the location are involved depending on the level of the risk being managed. Identification of when and where wearing of additional PPE is required to achieve ALARP Identification of improvements needed to reduce the maximum arc flash level a person may be exposed to at a location to below the target maximum level of 13 cal/cm 2. These improvements can be prioritised in terms of the level of risk reduction achieved so as to provide a basis for a location improvement plan. This review process is recommended to be followed at all locations. Actions additional to those given in this document may be required in some jurisdictions, where legislation or local regulatory authorities have proscribed the actions to be undertaken. In such cases these mandated actions must be completed in addition to those recommended in this document. SR.11.13122 - III - Confidential Table of contents 0. Executive summary II 1. Introduction 5 1.1. Why is arc flash now seen as an issue? 5 1.2. Business implications of an arc flash incident 6 1.3. Differences in regulatory requirements 6 1.4. Arc Flash energy units 7 General approach to management of Arc Flash Risks 8 2.1. Bowtie representation 8 2.2. General approach 9 2. 3. 4. Arc Flash Risk Assessment procedure 13 3.1. Information required 14 3.2. Process steps to be followed 14 3.2.1. Generic switchgear actions 15 3.2.2. Step 1 – Eliminate the risk 16 3.2.3. Step 2 – Evaluate the switchgear 16 3.2.4. Step 3 – Calculate arc flash energy levels (where required) 17 3.2.5. Step 4 – Review of the outcome of energy level calculations 18 Example Switchboard Assessment Summary Tables 19 4.1. Example LV Switchboards assessment form 19 4.2. Example HV switchboard assessment form 25 4.3. Example comparison table of overall clearance times vs tested IAC clearance times 31 4.4. Example record of assessment for Switchboards operated remotely or de-energised 31 5. Conclusions 32 6. Bibliographic information 33 7. Report distribution 34 Appendix A. Commentry & advice on Arc flash assessment Procedures 35 A.1 Comments on Step 1 Elimination of the risk 35 A.2 Comments on Step 2 Evaluate the switchgear 36 A.3 Comments on Step 3 Calculate arc flash energy levels 36 A.4 Comments on Step 4 – Review of the outcome of energy level calculations 37 A.4.1 HV Circuits 38 A.4.2 LV Circuits 38 A.5 Use of temporary changes to protection settings Appendix B. Withstand times of Internal Arc Tested switchgear 39 40 B.1 IEC and US standards 40 B.2 Effect of reduced fault currents 40 Appendix C. Comparison of clearance times and energy levels 41 C.1 HV switchgear (>1kV) 41 C.2 LV switchgear (400/415v & 690v) 42 SR.11.13122 - IV - Appendix D. Confidential Calculation of arc flash energy levels using IEEE 1584 spreadsheet 43 D.1 Calculation from “fixed” fault level sources 43 D.2 Calculation from “variable” sources of fault current. 45 D.3 Determining operating conditions for arc flash calculations 47 D.4 Entering values in the IEEE spreadsheet data input sheet 49 Appendix E. E.1 E.2 2 Additional busbar insulation 2 E.1.1 LV switchboards 3 E.1.2 HV switchboards 3 Cable terminations Appendix F. F.1 Additional insulation and Cable Terminations Scope for protection to minimise arc flash energy levels 4 5 HV switchboards 6 F.1.1 Non IAC tested switchboards Voltage range up to 15kV 6 F.1.2 Non IAC tested switchboards - Voltage range above 15kV 7 F.1.3 IAC tested HV switchboards 8 F.2 LV Switchboards 10 F.3 Summary of practical solutions 13 F.3.1 Non IAC-tested HV switchboards up to 15kV 13 F.3.2 Non IAC-tested switchboards above 15kV 13 F.4 Summary of solutions for LV switchboards 14 F.4.1 IAC tested switchboards 14 F.4.2 Non IAC-tested switchboards 14 SR.11.13122 1. 1.1. -V- Confidential Introduction Why is arc flash now seen as an issue? Since the mid 1990s, there has been increasing attention within the electrical community in North America to quantify and manage the hazards associated with electrical arc flashes. This issue came to the fore in the United States when there was recognition in late 1990’s that there are a large number of incidents where persons were being seriously hurt or killed, not by the widely acknowledged risk of electrocution, but by the effects of blast and heat following a flash over. A report compiled in 1990’s estimated that five to 10 arc flash explosions happened in the USA every day, resulting in 1 to 2 deaths per day. In considering these figures it should be seen in context of relating to a continent with more than 240 million people and the highest energy use per person in the world, hence there are a very large number of electrical installations and relatively large numbers of persons operating or working on them. Sufficient evidence was collected that the US Occupational Safety & Health Administration (OSHA) was persuaded to act. OSHA dictated that all sites should perform energy calculations, label switchgear with the potential energy level, provide additional PPE to match the potential energy release, identify closest approach without wearing additional PPE that would not result in 2nd degree burns provide training to staff regarding arc flash hazards in their workplace. Review of older non-internal arc protected IEC switchgear has identified the potential exists of similar arc flash-overs with consequent severe effects. However within European countries concerns about reducing the effect of internal short circuits were being considered from 1970’s onwards and there have been attempts within individual countries to develop national or industry standards to address this issue e.g. PELHA in Germany. However it was not until a common approach was adopted by the IEC that testing regimes applicable to all countries were developed. Reflecting this international common approach, the requirement for internal arc protected switchgear has been included in the DEP 33.67.51.31-Gen for HV switchgear since 1985 and the DEP 33.67.01.31-Gen. for LV switchgear since 1998 (Testing requirements for “arc resistant” switchgear built to North American standards are given in IEEE C37.20.7-2001). IEC switchgear manufactured before those dates and North American switchgear not tested in accordance with IEEE C37.20.7 are to be regarded as non-Internal Arc Controlled (IAC) switchgear. The above statement regarding existing equipment may be modified only if the manufacturer can confirm that the design of switchgear prior to the adoption of the IEC standards met the requirements for the subsequent IAC tests without modification. This reflects the fact that some manufacturers had already put on the market IEC designs which were IAC compliant before the tests were adopted by the IEC. Note IEC test for LV switchgear (IEC/TR 61641) is not accepted within all jurisdictions therefore it remains a technical report and is not a full standard. SR.11.13122 - VI - Confidential Within the Shell group we have not separately categorised electrical incidents as arc flash incidents. Such incidents have occurred at many locations, not only in US but in other countries as well. Recent frequency rate of such incidents within the group has been one or two per year and in every instance those involved in the incidents were hospitalised at best or died immediately or soon thereafter. Since our experiences mirror to a degree those experienced in the US, it follows that the issue of arc flash is not restricted to US locations or locations using equipment built or operated to US standards, it applies to all group locations. Nevertheless the differences in standards used in specifying equipment and/or operating practices between Europe and US do affect both the probability of such events occurring and their potential consequences. 1.2. Business implications of an arc flash incident Not only can an arc flash incident affect people but there are also usually significant implications in terms of cost and lost revenue or margin. Even if the equipment is designed to control an arc (i.e. is to an IAC design), it can be seriously damaged and need substantial repairs and extensive cleaning. Often the contamination of conductive carbon or metal spreads to other equipment in the substation / switchroom and the cleaning programme can be very extensive. In many cases complete replacement of part or all of the equipment is required. There will be a loss of function for periods typically ranging from weeks to many months. Not only the direct repair costs but also the consequential losses to the business can be very high. From a purely business perspective therefore, actions which prevent arc flash over’s from occurring generate maximum benefit in terms of avoiding additional costs or loss of margin. Where an arc flash does occur then rapid extinction of the arc not only limits the energy a person may be exposed to, but also reduces the extent of damage to equipment and therefore potentially cost of repairs and / or lost production. This extinction can come from design of the equipment or operation of protective devices. 1.3. Differences in regulatory requirements As mentioned in section 1.1 in the US there are proscribed actions to be taken with regard to arc flash hazards. These are the actions most regularly mentioned in literature about arc flash. However these actions should not be taken in isolation. There is a general hierarchy of controls which the US regulator requires to be in place that matches almost exactly those referred to in the Shell HSSE & SP Control Framework, namely: Apply the following Hierarchy Of Control to manage Personal Protective Equipment use. First: Eliminate the Hazard or exposure. Second: Substitute materials or equipment to reduce the Hazard or exposure. Third: Use engineering Control of the Hazard or exposure. Fourth: Use procedural Control of the Hazard or exposure. Fifth: Use Personal Protective Equipment For Shell sites within US jurisdiction, actions taken must comply with their national requirements. In jurisdictions other than the US/Canada, the direction provided by regulators is less explicit. Typically a target or goal setting approach is taken rather than setting prescriptive actions. SR.11.13122 - VII - Confidential The direction given by other regulators is that if the site feels that the equipment is unsafe to operate, or the actions to be taken are felt to be unsafe, then the work should not proceed until these concerns are adequately addressed. Arc flash hazards are not separately addressed and are treated in similar manner to electrocution or other electrical hazards. The interpretation taken by regulators is that, if reliance is placed mainly on additional PPE to ensure safety, then inherently the proposed actions or work scope does not meet the advice given since PPE does not prevent an incident from occurring. Strong preference is given to being able to demonstrate adequate measures to prevent an arc flash incident occurring in the first instance. Regulators do not wish to see efforts aimed at mitigating the effects of an incident reducing attention given to the primary focus of reducing the probability of an incident occurring. A further consideration is the requirement to be able to demonstrate we are compliant with As Low As Reasonably Practical (ALARP). This means in some instances taking precautions which may be in excess of that required purely from a conventional risk assessment. Essentially the above means that 1. The equipment, through a combination of correct selection, installation, maintenance and operation, should be safe to operate at all times provided that the previously mentioned barriers are in place and are followed. 2. In some (but not all) cases, PPE can help mitigate the consequences to an individual should the above barriers be inadvertently breached. 1.4. Arc Flash energy units There are two methods of expressing the energy released in arc flash calculations, Joules/cm2 or cal/cm2. Values expressed in cal/cm2 are used in this report for convenience since these currently are far in wider use than their SI equivalents (even though in principal J/cm2 is the “correct” S.I. unit). These values can be compared using the equation: 5.0 J/cm2 = 1.2 cal/cm2 Hence for values commonly used in this report the equivalent J/cm2 values are 1.2 cal/cm2 = 5 J/cm2 13 cal/cm2 = 55 J/cm2 40 cal/cm2 = 167 J/cm2 SR.11.13122 2. - VIII - Confidential General approach to management of Arc Flash Risks 2.1. Bowtie representation The bowtie relating to arc flash hazard can be represented as Top Event Loss of Control - Arc Flash T h r e a t s 1. Controls Recovery Measures - Design for incident energy (limit fault current or duration) - PPE - Control of Personnel (distance from Arc Flash) - Physical Barrier Critical Activities - Inspection and Maintenance Threats – Operating and Maintaining Switchgear - Competency development (training) Consequence – Major injury or Fatality C o n s e q u e n c e - Work practices The Shell approach to risk management is to 1. Ensure the barriers to the incident on the left hand side of the bowtie are as robust and effective as possible. 2. After these barriers are in place then consider how to reduce the effect on the incident. In arc flash terms this means either reducing the amount of energy released and/or relocating people away from the possible incident location. 3. The final action is to wear additional PPE, but this is seen as a method of last resort and only applied after all other actions are taken. In this context, provided prevention and mitigation are sufficient in extent and robustness, the wearing of PPE may be beyond what is required by assessment of risk level by the business. Wearing of additional PPE could therefore be seen as demonstrating ALARP rather than significantly reducing the level of risk to the business or individual. From a business and personnel safety perspective it is logical to focus on prevention since it provides the maximum financial benefit as well as providing the maximum protection for the individual. The other aspect of Shell approach to risk management is that when barriers are identified, they are “actively managed”. “Actively Managed” means their profile is kept high so people remain aware of the requirements and there are audits or checks to ensure the barriers remain sound and are in place i.e. what happens in practice matches what should happen theoretically. SR.11.13122 2.2. - IX - Confidential General approach Where there are no mandated requirements from national regulator or local legislation the following is recommended as the hierarchy of actions to be taken. 1. Educate and train staff to understand and recognise where arc flash hazards may exist. Ensure their role is fully understood in providing effective barriers to arc flash events by following procedures, completing QA checks and similar activities. Highlight that, wherever there doubt exists, advice should be sort rather than continuing with any action. 2. All work which involves switching or working on live equipment is challenged to determine if there is no practical alternative to live working. Where working dead can be implemented, then practices and procedures should be to be changed to suit. Example Racking in/out of voltage transformers can nearly always be planned to be done when deenergised. 3. If working live is required e.g. to isolate a circuit to allow subsequent maintenance or inspection then, where possible, choice of live working point should be such as to minimize risk either to the business or to the individual. Examples A single transformer feeder fed switchboard where isolation of board could be by operating the LV incomer or by tripping HV feed to transformer. If energy levels are lower at HV board or if the HV board is an IAC design and the LV board is not, then isolation could be best performed at HV switchboard. Use remote switching of circuits where such features exist rather than operating from directly in front of the switchgear Use points which are protected by fault limiting devices for phasing out or voltage checks 4. The existing barriers on site to an arc flash incident occurring are to be reviewed and where necessary reinforced. Note should be taken that current rules will almost certainly have been written with risks of electrocution as the foremost hazard and may not consider prevention of arc flash events as a specific hazard. Reinforcement should take the form not only of improving the barriers but also considering how they can be made robust through audits and additional checks which assist in the correct execution of the task. Example Before issuing clearance for electrical work, the clearance signatory requires the technician to confirm he has the correct test equipment against a check list of the equipment required against common electrical tasks. In this way the technician will not be tempted to short cut procedures due to not having correct equipment when he arrives at the substation (which is often remote from workshops). 5. The installation is reviewed to establish if the energy released in an arc flash incident could be reduced and what are the resultant energy levels. Effectively this constitutes a review of a significant part of the protection schemes for the site and experience elsewhere has shown that some improvement can nearly always be made. The same experience shows that there is a high probability that some addition or alteration to existing schemes may be required to reduce potential energy release levels to acceptable levels. 6. Establish if, and if so where and when, additional PPE can be used or additional controls are required, to reduce risk to individuals and demonstrate ALARP. Amend practices and procedures to match these requirements. Note Use of PPE as the only mitigating action against risk from arc flash is not ALARP SR.11.13122 -X- Confidential The controls required can be summarized by this flow diagram and its associated notes. 1 1 2a 1 2b SR.11.13122 - XI - Confidential FLOW CHART COMMENTS (Refer to numbers in boxes in flow chart) 1. If switchgear/switchboard is replaced, it should be designed such that the incident energy that the operator is exposed to during an arc flash is limited to less than 1.2 cal/cm2 **. If the equipment is modified, the modification should lower the incident energy that the operator is exposed to less than the rating of the standard PPE used by the facility (typically this is between 1.2 cal/cm2 and 13 cal/cm2, but no greater than 13 cal/cm2). ** NFPA 70E – Standard for Electrical Safety in the Workplace states that maintaining arc flash incident energies below 1.2 cal/cm2 to the head and torso improves the chances of survivability to persons exposed to electric arc flash events. Common ways that the switchgear can be modified to achieve ALARP are shown below. The location or project should evaluate both replacement and modification options to determine which method is most appropriate and to verify modifications are consistent with accepted company and industry practices and standards. A. Reduce the Energy released during an arc flash by - Limiting fault duration i. Use instantaneous circuit breaker protection (i.e., bus differential protection, zone selective interlocking, maintenance switches, etc.) ii. Minimize time overcurrent settings (without sacrificing selective coordination) iii. Use current limiting fuses - Limiting fault current (keep in mind that limiting fault current may have an overall effective of increasing incident energy because of the impact on fault clearing times) i. Increase transformer impedance ii. Utilize current limiting fuses iii. Operate parallel secondary systems as normal open iv. Utilize current-limiting reactors B. Reduce Exposure - Change distance person is from gear i. Utilize remote operation/control panels ii. Utilize remote racking mechanisms for circuit breakers - Install an internal physical barrier (Internal Arc Controls) 2. (a & b) To operate and maintain energized switchgear/switchboards having Arc Flash energy exposure levels between 13 cal/cm2 and 100 cal/cm2, Arc Rated PPE shall be worn and formal work authorization should be obtained and documented (existing work process, such as Permit To Work, may be used to do this or the location may decide to develop their own authorization form ) The Senior Electrical Authority is responsible for reviewing and verifying the requirements for authorization have been completed. 2. (a) Operations and maintenance of the energized switchgear between 40-100 cal/cm2 will be allowed on an interim basis until the switchgear/switchboard can be modified or replaced. Additionally, the process unit manager is required to approve the work authorization. The work authorization process for performing operation and maintenance on switchgear/switchboard shall include the following: 1. 2. 3. 4. 5. 6. Approval by Senior Electrical Authority for 13-40 cal/cm2. Approval by Senior Electrical Authority and process unit manager for 40-100 cal/cm2 Verification of PMs on time and none overdue Completed Job Hazards Analysis (JHA) Emergency Response Plan – including CPR trained watch at job site Verification of electrical and HSE Competencies of person performing work SR.11.13122 - XII - Confidential General Note 1: The Arc Flash Consequence during operation and maintenance of the switchgear will only occur if the switchgear is energized. It is an option not to undertake modifications or replacement and instead only operate and maintain the switchgear when it is de-energized. General Note 2: Emphasis should be placed on preventing arc flash events from occurring in the first place by properly maintaining electrical equipment in accordance with Shell and industry standards and by using special precautionary techniques when operating or maintaining the equipment. General Note 3: PPE is the last line of defence and should be selected based on the incident energy exposure potential. The following table provides guidance for selecting the appropriate PPE to demonstrate ALARP. It is important to note that PPE only protects against the burn consequence and not the impact or arc blast, burning shrapnel, pressure waves and percussion consequence associated with the arc flash. For these reasons PPE is regarded as being ineffective at protecting an individual at energy levels above 40 cal/cm2, even if the thermal effects can be managed by heavier or thicker suit materials. Required PPE for Switchgear / Switchboard Arc Flash Energy Exposure Level Exposure Level < 1.2 Calories / cm2 1.2 to 13 Calories / cm2 Required PP E No special PPE required, however standard level of PPE assumed Standard PPE and face shield (Nomex or equivalent clothing, gloves, hearing and eye protection, etc.). Depending on Location specifications, standard PPE will be typically rated for incident energy exposure between 5 to 13 cal/cm2. Supplemental PPE per location requirements should be used for exposure levels greater than the standard PPE rating and up to 13 calories/cm2. 13- 40 Calories / cm2 Special PPE – Arc Rated Flash Suit with hood SR.11.13122 3. - XIII - Confidential Arc Flash Risk Assessment procedure Following the hierarchy of controls mandated by the Shell HSEE guidance of: First: Eliminate the Hazard or exposure. Second: Substitute materials or equipment to reduce the Hazard or exposure. Third: Use engineering Control of the Hazard or exposure. Fourth: Use procedural Control of the Hazard or exposure. Fifth: Use Personal Protective Equipment The outcome of an arc flash assessment must be able to answer five questions What measures have been implemented to eliminate the risk of an arc flash event? What measures have been implemented to reduce the consequences of an arc flash event? What changes have been made to control of activities to reduce the probability of an arc flash event occurring? What changes have been made to procedures to reduce the probability or consequences of an arc flash event? What measures have been implemented to reduce the effect of the consequences of an arc flash event on individuals? An assessment which fails to provide substantive answers to all these questions would be inadequate. An example of such an inadequate assessment would be one which comprises only of a listing of energy levels at each switchboard and identification of the corresponding level of supplementary PPE to be worn. Where the assessment is part of a sequence of assessments of different facilities it may be that answers to some of the questions are “have the recommendations from initial assessments been implemented?” rather than developing or identifying new measures in every case. The procedure to be followed therefore should seek to ensure each of the hierarchy of controls is satisfactorily covered. It should also be recognised that protection schemes and their associated trip times at arc flash current levels have a significant impact on resultant potential arc flash energy levels. Existing protection schemes would have been originally developed without consideration of arc flash energy levels. Therefore existing schemes are highly unlikely to have been optimised so as to minimise arc flash energy levels. Typically this means settings may need changing and potentially additional protection elements added. The implication is that an arc flash assessment study will almost inevitably result in changes being recommended to protection schemes. This, as a minimum, will mean the associated documentation will require updating to reflect proposed changes and in many cases additional expenditure to implement additional protection functions. Depending on how the documentation is created e.g. manually or by computer, the costs and difficulty of updating documentation will vary significantly. Similarly, existing protection schemes not using multi-function relays will require either upgrading or additional protection relays fitted, if additional protection elements are seen as being necessary. SR.11.13122 - XIV - Confidential The costs and resources to validate any changes proposed to changed protection schemes are recommended to form part of the arc flash risk assessment budget. This work is needed to be able to provide firm recommendations as to remedial actions required. If it is not included as part of the risk assessment the quality and clarity of any recommendations that can be made will be significantly lower. 3.1. Information required To allow the assessment to be completed it is necessary to assemble information about the facility to be assessed. As a minimum the following information will be required 3.2. The electrical safety rules and common practices / procedures followed at the facility. This should explicitly cover any instances of “live” working. Make, model and age of the switchgear to be assessed including operating times of circuit breakers and the arc withstand time of any IAC switchgear. Understanding of the routine actions undertaken on the switchgear e.g. how switching, earthing, racking in / out and testing is carried out Knowledge of test equipment used with the equipment to prove dead or phasing out Single line diagrams for the overall system and for individual segments of the system (depending on size of the system being assessed) and clear definition of modes of “normal” modes of operation to be assessed. Maximum and minimum fault levels at the switchgear to be assessed for “normal” modes of operation. Information to allow protection operation times at predicted arcing currents to be determined. This can be either through knowledge of the protection types, setting values, ct ratios etc or more conveniently the output of the protection co-ordination study with protection curves drawn for schemes in use. Checks should be made that drawings or records accurately reflect actual settings on the switchgear. Process steps to be followed To provide a framework for the process a list shall be prepared of the switchboards in the location to be assessed and visits should be made to review actual operations done on equipment. This has been found to act as an excellent prompt, even when personnel are familiar with the equipment. It has been suggested that videoing the operations being performed provides a very useful reference when these actions are being reviewed in meetings away from the workplace The generic actions given in the following table should be compared against the actual equipment operation and the review outcomes recorded. Note that if additional actions for particular types of switchgear are identified then these should also be recorded and if required, such additional actions can be added to the generic list. Links are provided in this section betaeen the body of main text and the Commentary and Advice held in Appendix 1. This is done to make the main document text and the required actions easier to understand. SR.11.13122 3.2.1. - XV - Confidential Generic switchgear actions Task Description Typically applicable to 1. Inspection of substation, short visit typically < 4hr LV & HV substations 2. Work in substation but not on switchgear (re-lamping, painting etc) typically taking from 4hrs to 1-2 weeks LV & HV substations 3. Testing or modification of protection relay settings 4. Test IR (megger) of a motor cable or feeder LV & HV 5. Rack In/Out feeder circuit breaker, starter or vacuum contactor LV & HV 6. Rack In/Out voltage transformer 7. Open / Close fuse protected motor contactors or feeder switches 8. Open / Close outgoing circuit breaker fed feeders or motors 9. Open / Close Incoming switches or circuit breakers HV HV LV & HV HV LV & HV 10. Open / Close Bus Section switches or circuit breakers LV & HV 11. Proving a circuit is dead LV & HV 12. Application of earth to circuit for motor contactor HV 13. Application of earth to circuit for outgoing feeder HV 14. Application of earth to circuit for incomer HV 15. Application of earth to bus bars LV & HV 16. Fault finding work in the circuit breaker or contactor compartment (withdrawable component jammed or circuit breaker/contactor will not open to allow the truck or starter tray to be withdrawn) 17. Fault finding in LV circuit compartment LV & HV 18. Inspection of bus bars LV & HV 19. Modification to wiring or components in non-withdrawable starters 20. Phasing out 21. Removal of fuse or fuse carrier when circuit is still live and is not protected by upstream fuse or current limiting circuit breaker i.e. where there is a high fault level LV & HV LV LV & HV LV SR.11.13122 3.2.2. - XVI - Confidential Step 1 – Eliminate the risk Action Review operating practices and identify where arc flash risk can be eliminated by only working on equipment when it is de-energised. Review operating practices and ensure that they include requirement for all persons not required to be inside switchroom or substation leave when an activity with potential to create an arc flash event is being undertaken. Link to Commentary 3.2.3. Step 2 – Evaluate the switchgear This step combines consideration of substitution or alternative methods of working and engineering / procedural controls. It also includes identification of whether switchgear is designed to contain or manage the consequences of an internal arc for a period of time. Actions The practical checks to be made are; a) Evaluate what tasks are undertaken with switchgear energised b) Evaluate if, and exactly how, an arc flash can occur during these tasks. Then For switchgear which has no internal arc control features i. Evaluate possible mitigating actions (excluding additional PPE) that can be taken which reduce the probability and consequences of a flash over. ii. Evaluate the residual risk to personnel after mitigation is applied and if further mitigation is necessary e.g. additional PPE. iii. Evaluate which protection element will operate in event of a phase to phase fault and the time before the current is interrupted in event of a bus bar fault or fault in an outgoing circuit which can develop into a bus bar fault. iv. Evaluate the distance of individual (face/torso) from the possible flash over point. Or For switchgear which has internal arc control features i. Identify the time for which the switchboard has been tested to withstand or manage the effects on an internal arc. ii. Evaluate if the design features to control the consequences of an internal arc are effective for the identified tasks. If they are not covered then complete assessment as above for a switchboard without internal arc control features. An example of this could be that the internal arc tests do not cover racking in / out with doors open. The example tables are provided in Appendix B show how the information in this step can be collected and collated. The use of tables also allows checks that there is consistency in assessment. The risks levels are expressed in terms of the standard Shell Risk Assessment Matrix. The assessment is based upon the types of switchgear rather than switchboard identification or location so only one example need be assessed which can then be applied to all similar installations. Link to Commentary SR.11.13122 3.2.4. - XVII - Confidential Step 3 – Calculate arc flash energy levels (where required) Before undertaking this step, refer to Appendix D for guidance on entering data into the IEEE spreadsheet Action Following the previous two steps and using the information thereby gained, a) For switchboards which are claimed to be of internal arc control (IAC) design, Check operating times of protective elements using the reduced current levels suggested by IEEE spreadsheet (i.e. enter fault levels and voltage values and note the arcing current calculated by the spreadsheet) Provided the manufacturers arc withstand test time is not exceeded at these reduced arcing current levels then board may be regarded as interally arc controlled and there is no requirement to calculate arc flash energy levels. This is subject to any restrictions the manufacturer may place regarding when its IAC status is impaired. For example IAC conditions may not be met if doors are opened to allow racking in/out of circuits. An “IAC” board may therefore still have some actions where it creates an arc flash hazard and hence require arc flash energy levels to be calculated. A nominally “IAC” board, where clearance times are not within tested time, must be treated as though it is a non-IAC board, at least for those sections of the switchboard where the arc flash containment tests rely upon the upstream protection to operate. Link to Commentary b) For switchboards which have not been tested for internal arc containment (non-IAC) Evaluate (using IEEE 1584 spreadsheet) the potential arc flash energy level an individual may be exposed to. This applies where an arc flash risk has been identified during the switchgear review for particular actions. It also applies to actions where there is insufficient other mitigation available or if the wearing of PPE is seen as being required to be ALARP. Link to Commentary SR.11.13122 3.2.5. - XVIII - Confidential Step 4 – Review of the outcome of energy level calculations As indicated in section 2 on Arc Flash Risk management, two arc flash energy levels are identified namely 13 cal/cm2 and 40 cal/cm2 as being boundaries where changes to PPE and the management of activities should take place. It is recommended to restrict arc flash PPE used to maximum of two types, one suitable for use up to 13 cal/cm2 and another suitable for use up to 40 cal/cm2. It follows therefore that outcomes from calculated energy levels can be grouped into three categories, namely 1. >40 cal/cm2., 2. >13cal/cm2 < 40cal/cm2 3. < 13 cal/cm2, In the absence of any other factors this provides a prioritisation for remedial actions i.e. tackle higher arc flash energy levels first. Actions a) Establish if there is scope for reducing energy levels by protection (i.e. reducing protection operating times) – either through changes to existing settings or design ,or by adding fast acting protection elements such as blocking schemes, bus zone protection or differential protection. Link to Commentary and advice on HV & LV switchgear protection An alternative solution is to reduce clearance times only when racking in/out or other higher risk actions are taking place through a temporary decrease of setting values. If such a scheme is implemented then there must have rigorous safeguards to ensure that it is impossible for incorrect settings to be left in place after the work is completed. Link to Commentary Further advice Refer to Appendix F for discussion on the options available to improve clearance times and reduce arc energy levels b) Depending on the residual energy levels after any improvements in protection clearance times have been implemented, refer to flow chart in section 2.2 and implement the necessary engineering and procedural controls to comply with flow chart requirements. This can be expected to include the wearing of additional arc flash resistant PPE for certain tasks. The implementation of engineering and procedural controls should follow the guidance given in the flow chart and associated notes. However, as far as is possible, they should use existing documentation and procedures at a location. This means that they should be integrated into the existing safety systems at a location rather than being a completely new set of controls, documentation and procedures. The new practices and controls shall be applied to all switchboards reflecting the current arc flash energy levels i.e. relaxation is only permitted after any improvement is implemented and not before. SR.11.13122 4. - XIX - Confidential Example Switchboard Assessment Summary Tables Mitigation Actionss and risk levels are shown as example only. Grey text should be deleted when using forms for an actual assessment 1. Wear PPE appropriate to incident energy level B4 A4 A2 Work in substation but not on switchgear (relamping, painting etc) typically taking from 4hrs to 1-2 weeks Insulation failure in bus bar or incoming compartment Entry to substations and switchrooms is restricted to competent people who have undergone periodical refresher training. Regular maintenance inspection of switchboards includes busbars 2. Wear PPE appropriate to incident energy level B4 A4 A2 Test IR (megger) of a feeder or motor cable Contact with droppers through openings at rear of cubicle Test before applying meggar and use instruments with insulated probes and suitable internal fuse or short circuit protection for fault level. Training and experience of staff 3. B4 A0 Inspection of substation, short visit typically < 4hr Reason Standard Mitigation Actions Switchboard 2 Make and model No Risk level with additional mitigation Insulation failure in bus bar or incoming compartment Entry to substations and switchrooms is restricted to competent people who have undergone periodical refresher training. Regular maintenance inspection of switchboards includes busbars Task Description Switchboard 1 Make and model No Possible additional actions Risk Level with standard mitigation Example LV Switchboards assessment form Risk level with no mitigation 4.1. 7. A4 A2 B4 A0 – if procedures are followed A2 (for case where mistakes are made) Wear PPE appropriate to incident energy level B4 A4 A2 Wear PPE appropriate to incident energy level B4 A4 A2 Possible additional actions Rack In/Out feeder circuit breaker, starter Short inside starter tray + misalignment Training and experience of staff. Test with 500v Megger that starter bus bar stabs are clear to earth and between phases before racking in. Wear PPE appropriate to incident energy level Open / Close withdrawable circuit breaker/switches fed feeders after maintenance Internal fault in C/B or switch due to incorrect maintenance Last checks before completion of maintenance are functional check, continuity check and insulation checks Wear PPE appropriate to incident energy level Open / Close withdrawable circuit breaker/switches fed feeders (normal operation) Internal fault in C/B or switch Check operation during routine maintenance. Open / Close fixed switches or circuit breakers Internal fault in C/B or switch Checks on operation during routine maintenance. Switchboard 2 Make and model No B4 Standard Mitigation Actions Switchboard 1 Make and model No Risk level with additional mitigation 6. Risk Level with standard mitigation 5. Confidential Reason Task Description 4. - XX - Risk level with no mitigation SR.11.13122 9. Proving a circuit is dead Application of loose earth leads to circuit for incomer or bus bars Possible additional actions Contact with droppers for work in outgoing compartments or wrong side of bus section switch connections. Training of staff to always check labelling and compare circuit identification against work scope before starting work. Use instruments with insulated probes and suitable internal fuse or short circuit protection for fault level to prove dead Use low fault level source to test instrument before use B4 A4 A0 Training of staff to always check labelling and compare circuit identification against switching programme and work scope before starting work. Use instruments with insulated probes and suitable internal fuse or short circuit protection for fault level to prove dead before attaching earths Wear PPE appropriate to incident energy level B4 A0 Wrong compartment Switchboard 2 Make and model No Standard Mitigation Actions Switchboard 1 Make and model No Reason Risk level with additional mitigation 8. Confidential Risk Level with standard mitigation Task Description - XXI - Risk level with no mitigation SR.11.13122 . 11 . Fault finding in LV circuit compartment (fixed equipment) Flash over due to reduced clearances Contact with live dropper connections Do not work on equipment in this state with busbars or circuits energised Training and experience of staff. Minimum level of IP20 as design standard for circuit connections in fixed compartments and IP41 for connections which are live when compartment is isolated Include check of shrouding and possible gaps to live connections as part of work site inspection. Do not proceed with the work if excessive gaps identified C4 A0 A0 C4 B4 A0 Switchboard 2 Make and model No Possible additional actions Switchboard 1 Make and model No Standard Mitigation Actions Risk level with additional mitigation 10 Fault finding work in the circuit breaker or contactor compartment (withdrawable component jammed or circuit breaker/contactor will not open to allow the truck or starter tray to be withdrawn) Reason Confidential Risk Level with standard mitigation Task Description - XXII - Risk level with no mitigation SR.11.13122 12 . 13 . Wrong compartment Start inspection and removal of covers from compartment where loose earth leads are applied Modification to wiring or components in fixed starters Accidental contact with dropper connections, typically through inadequate shrouding, incorrect removal of covers, mechanical failure of supports or shrouding of live connections due to work being undertaken exerting forces on these components Training and experience of staff. Minimum level of IP20 as design standard for circuit connections in fixed compartments and IP41 for connections which are live when compartment is isolated None – working on dead system B4 A0 Only undertake modifications with boards isolated. C4 C4 A0 Switchboard 2 Make and model No Inspection of bus bars Possible additional actions Switchboard 1 Make and model No Standard Mitigation Actions Risk level with additional mitigation Reason Confidential Risk Level with standard mitigation Task Description - XXIII - Risk level with no mitigation SR.11.13122 . 15 . Phasing out/prove dead Removal of fuse or fuse carrier when circuit is still live and is not protected by upstream fuse or current limiting circuit breaker i.e. where there is possible high fault level Fault with leads or test equipment Use instruments with insulated probes and suitable internal fuse or short circuit protection for fault level to prove dead before attaching earths. Failure of fuse base while fuse is removed / inserted Do not insert or remove fuses where there is no upstream fault level limiting device (fuse or fault limiting circuit breaker or if circuit is not switched off I.e. off load. Or wear PPE suitable for incident energy level. Use low fault level source to test instrument before use B4 A2 A0 C4 A2 A2 Switchboard 2 Make and model No Possible additional actions Switchboard 1 Make and model No Standard Mitigation Actions Risk level with additional mitigation 14 Reason Confidential Risk Level with standard mitigation Task Description - XXIV - Risk level with no mitigation SR.11.13122 SR.11.13122 3. Work in substation but not on switchgear (relamping, painting etc) typically taking from 4hrs to 1-2 weeks Testing or modification of protection relay settings or Fault finding in LV circuit compartment Insulation failure in bus bar or cable compartment Entry to substations and switchrooms should be restricted to competent person who have undergone periodical refresher training. Regular maintenance inspection of switchboards including busbars and cable compartments No evidence from PD monitoring of imminent insulation failure. Insulation failure in bus bar or cable compartment Entry to substations and switchrooms should be restricted to competent person who have undergone periodical refresher training. Regular maintenance inspection of switchboards including busbars and cable compartments PD measurements to be taken immediately before work starts and repeated every 2 weeks thereafter Insulation failure on bus bars Entry to substations and switchrooms should be restricted to competent person who have undergone periodical refresher training. Regular maintenance inspection of switchboards including busbars and cable compartments PD measurements to be taken immediately before work starts B4 B4 B4 A4 A0 (business case may be stronger than HSE) A4 A0 (business case may be stronger than HSE) A4 A0 (business case may be stronger than HSE) Switchboard 2 Make and model No Possible additional actions Switchboard 1 Make and model No Standard Mitigation Actions Risk level with additional mitigation 2. Inspection of substation, short visit typically < 4hr Reason Risk Level with standard mitigation Example HV switchboard assessment form Task Description 1. Confidential Risk level with no mitigation 4.2. - XXV - 4. Test IR (megger) of a motor cable Being on wrong panel and contacts live Correct and visible labelling at front and rear on non-moveable panels. Training of staff to always check front and rear labelling and compare circuit identification read against switching programme or work scope before removing covers. B4 A0 B4 A0 Check circuit is dead before applying megger. 5. Test IR (megger) of a feeder cable Being on wrong panel and contacts live Correct and visible labelling at rear on non-moveable panels. Training of staff to always check front and rear labelling and compare circuit identification read against switching programme or work scope before removing covers. Prove circuit dead before touching terminals Switchboard 2 Make and model No Possible additional actions Switchboard 1 Make and model No Standard Mitigation Actions Risk level with additional mitigation Reason Confidential Risk Level with standard mitigation Task Description - XXVI - Risk level with no mitigation SR.11.13122 B4 A4 A0 Rack In/Out voltage transformer Flash over at spouts due to misalignment or flash over due to internal insulation failure inside transformer Only rack in/out with circuit or bus bar de-energised . B4 A0 8. Open / Close fuse protected contactors Fault inside starter downstream of contactor Fuse operates quickly enough to prevent arc flash event Open / Close withdrawable circuit breaker/contactors after maintenance Internal fault in C/B or switch due to incorrect maintenance. Insulation failure of ct's / circuit conductors / cable terminations Operate from "remote" panel where possible. Routine inspection of ct's etc. include in maintenance routines Last checks before completion of maintenance are functional check, continuity check and insulation checks. 9. Rack In/Out feeder circuit breaker, starter or vacuum contactor Flash over at spouts due to misalignment or flash over due to internal insulation failure inside switching device. Pole stays closed when there is individual phase switching None Wear PPE appropriate to incident energy level A2 B4 A0 – remote operation A0 - if procedures are followed A2 (for case where mistakes are made) Switchboard 2 Make and model No Risk level with additional mitigation Training, experience and authorisation of staff. Maintenance checks specifically include checks of mechanical interlocks IR check on breaker spouts for earth/phase faults with 5000v megger and then confirm breaker or contactor is open Reason Switchboard 1 Make and model No Possible additional actions Risk Level with standard mitigation 7. Confidential Standard Mitigation Actions Task Description 6. - XXVII - Risk level with no mitigation SR.11.13122 12. A2 Proving a circuit is dead Being on wrong panel, contacts live and flash over when cover is removed Correct and visible labelling at front and rear on non-moveable panels. Training of staff to always check front and rear labelling and compare circuit identification read against switching programme or work scope before removing covers. B4 A0 Application of earth to circuits or busbars using temporary leads Circuit energised from another source Test circuit is dead immediately before applying earths. Backfeed isolation part of switching programme B4 A0 Reason Standard Mitigation Actions Open / Close withdrawable circuit breaker/switches (normal operation) Internal fault in C/B or switch. Insulation failure of ct's / circuit conductors / cable terminations Operate from "remote" panel. Investigate and determine reasons for trips before re-closing. (O/H lines one remote reclose permitted) Routine inspection of ct's etc during maintenance Possible additional actions Wear PPE appropriate to incident energy level Switchboard 2 Make and model No B4 A0 – remote operation A4 otherwise Task Description Switchboard 1 Make and model No Risk level with additional mitigation 11. Confidential Risk Level with standard mitigation 10 - XXVIII - Risk level with no mitigation SR.11.13122 14. Fault finding work in the circuit breaker or contactor compartment (withdrawable component jammed or circuit breaker/contactor will not open to allow the truck or starter tray to be withdrawn) Flash over due to reduced clearances Do not work on equipment in this state with busbars or circuits energised Being on wrong panel, contacts live and flash over when cover is removed Correct and visible labelling on bus bar covers. Training of staff to always check labelling and compare circuit identification against switching programme or work scope before removing covers. Prove circuit dead before touching terminals Inspection of bus bars Possible additional actions None – working on dead system C4 A0 B4 A0 Switchboard 2 Make and model No Standard Mitigation Actions Switchboard 1 Make and model No Reason Risk level with additional mitigation Task Description Confidential Risk Level with standard mitigation 13 - XXIX - Risk level with no mitigation SR.11.13122 15. Phasing out/Proving dead Use of incorrect voltage measurement stick or failure of the stick in service Training, experience and authorisation of staff. Check stick using test device before and after use. Test sticks visually checked before use for damage and sent for more extensive testing according to maintenance schedule Use voltage indication on front (if fitted) after proving they are phase correct. Earthing sticks and voltage test sticks are marked such that differences are immediately apparent e.g. colour coding and are kept in separate bags or transport boxes or wear PPE appropriate to incident energy level B4 A0 Switchboard 2 Make and model No Possible additional actions Switchboard 1 Make and model No Standard Mitigation Actions Risk level with additional mitigation Reason Confidential Risk Level with standard mitigation Task Description - XXX - Risk level with no mitigation SR.11.13122 SR.11.13122 4.3. - XXXI - Confidential Example comparison table of overall clearance times vs tested IAC clearance times Make and model of switchgear Switchboard number / location Comments Allowed IAC time Actual clearance time Low Voltage Holec Capitole 40 IAC type relies on upstream protection to clear faults in incomers and bus section areas 300ms 650ms ABB MNS Version 1 of MNS - relies on upstream protection to clear faults in incomers and bus section areas 300ms 300ms 0.5s 300ms 0.5s 900ms 1.0s 4s 0.5s To be confirmed High Voltage 20kV Siemens model 8BC1 / 8BD1 Pressure switch added when normal protection takes longer than 0.5s. Tested IAC conditions met 20 kV Holec Unitole 20 kV Schneider Megrini Clearance times for generation less than 1s but backfeeds from 66kV take much longer than 1s to operate 6.6 kV Hazemyer Unitole 6.6 kV Schneider Mergrini Check operating time less than 1.0s so IAC conditions are met (some checked) 1.0s <1.0s 3.3kV ABB Type BA (HB07) IAC status to be checked with site documentation otherwise treat as non- IAC 0.5 350ms 3.3 kV Schneider Megrini IAC board 1.0s < 1.0s 4.4. Example record of assessment for Switchboards operated remotely or de-energised Switchgear identification Summary of conclusions Switchboard A Substation XYZ Single end fed and can be isolated at supply end using remotely operated switchgear. No arc flash risk therefore and no calculation required Switchboard B Substation ABC All external switchgear in switchyards operated remotely from control room. Access not permitted in switchyards when switching being undertaken. No arc flash risk therefore and no calculation required SR.11.13122 5. - XXXII - Confidential Conclusions The arc flash assessment process described in this document is intended to fully satisfy the Shell HSEE guidelines in the use of PPE. Apply the following Hierarchy Of Control to manage Personal Protective Equipment use. First: Eliminate the Hazard or exposure. Second: Substitute materials or equipment to reduce the Hazard or exposure. Third: Use engineering Control of the Hazard or exposure. Fourth: Use procedural Control of the Hazard or exposure. Fifth: Use Personal Protective Equipment The output of an arc flash risk assessment produced following this guide includes Identification of where arc flash risk can be eliminated by only working on isolated equipment Identification of where arc flash risk can be reduced by using alternative techniques or measurement points Identification of mitigating actions that can be taken to reduce the probability of an arc flash event occurring, looking at both the current practices and what additional mitigations are feasible to introduce Measurement of the residual levels of risk with no mitigation in place, with current mitigations in place and after additional measures is implemented. This gives an appreciation of the effectiveness of mitigation actions and basis for an objective assessment of the level of actions needed to achieve ALARP. Identification of any additional procedures and controls needed to reduce the probability of an arc flash event occurring and to ensure that the correct levels of management at the location are involved depending on the level of the risk being managed Identification of when and where wearing of additional PPE is required to achieve ALARP Identification of possible improvements to reduce the maximum arc flash level a person may be exposed to at a location to below the target maximum level of 13 cal/cm 2. These improvements can be prioritised in terms of the level of risk reduction achieved so as to provide a basis for a location improvement plan. This review process is recommended to be followed at all Shell operated locations. Note - Additional actions may be required to those given in this document in some jurisdictions. National regulations or directives shall always take precedence over the recommendations in this document unless they are less onerous than this document’s recommendations. SR.11.13122 6. - XXXIII - Bibliographic information Classification Confidential Report Number SR.11.13122 Title Arc Flash Assessment Guide Author(s) Peter Freeman (PTE/EELE) Keywords Arc flash Date of Issue August 2011 US Export Control Not subject to EAR-No disclosure of technology Approved by Wim de Wilt (PTE/EELE) Sponsoring Company / Customer SHELL GLOBAL SOLUTIONS B. V. Spons./Cust. Address Carel van Bylandtlaan 30, 2596 HR, The Hague, the Netherlands Issuing Company Shell International Exploration and Production P.O. Box 60 2280 AB Rijswijk The Netherlands Confidential SR.11.13122 7. - XXXIV - Confidential Report distribution Paper copy distribution OU Recipient Ref.ind. No. of copies Recipient Ref.ind. No. of copies Electronic distribution (PDF) OU N/A – distribution via SIGN forum SR.11.13122 Appendix A. A.1 - XXXV - Confidential Commentry & advice on Arc flash assessment Procedures Comments on Step 1 Elimination of the risk This action will involve challenging the need for all actions traditionally carried out with equipment live. Often the outcome of such reviews on non-IAC switchgear is that the flexibility in operating equipment will be restricted compared to that previously enjoyed. Examples of eliminating the risk could be to state that: Withdrawable voltage transformers in non-IAC switchboards will not be withdrawn or inserted with the main circuit live Fuses fed from high fault level sources shall not be withdrawn if the fuse is live. It should be noted that almost inevitably isolating equipment before allowing work to proceed requires switching - which itself exposes the operator to an arc flash risk if the switching device fails. However the evidence from past failures is that switching devices are unlikely to give rise to arc flash events provided that they are properly maintained and inspected. Preference should normally be given to working on equipment when isolated and accept the risks of performing switching to create that condition. This assumes that the appropriate maintenance and inspection is correctly carried out on switches and circuit breakers used for isolation. The second method of eliminating the risk is to use fault level limiting devices such as fuses, or certain types of moulded case circuit breakers (mccb’s). These devices can interrupt high fault currents in less than ¼ of a cycle and limit both the peak magnitude of the fault current. By this means the amount of energy released is reduced such that an arc flash event can be prevented from occurring. There can still be release of energy sufficient to cause burns or other injury but this will not normally be life threatening. There will remain a risk of death from electrocution if there are exposed accessible live connections. Note There must be sufficient current to cause the protective devices to operate quickly (say <10ms), typically 10 – 20 times the nominal full load rating of the device. As an example a gG 10A fuse requires minimum of 100A to operate within 10ms whereas a gG 400A fuse requires 7500 amps. This means that for larger fuses or supplies with low fault levels the assumption cannot be made that fuses or fault limiting mccb’s will automatically provide sufficiently fast protection that resultant arc flash energy levels will be below the 1.2 cal/cm2 level. Examples of this type of risk elimination are: Phasing out MV circuits by using fixed capacitive voltage devices rather than test sticks Phasing out LV circuits by using test points protected by fuses rather than measurement points directly on main bus bars or incoming terminals. (click here to return to main document) SR.11.13122 A.2 - XXXVI - Confidential Comments on Step 2 Evaluate the switchgear The mitigation actions must specifically address the potential cause of a flash over identified in step 2 otherwise they cannot be classed as a mitigating action. With reference to operating distances to switchgear - these may vary depending on the action being performed. In considering the effectiveness of mitigations which are dependent on actions by personnel, assessor should be aware that the majority of arc flash incidents that have occurred in industry have occurred during, or just after, human intervention in form of maintenance, modifications or commissioning and often with experienced staff involved. This leads to the conclusion that mitigation actions based upon actions of personnel must be reinforced, for example by having independent checks made of each step. This almost inevitably means that single person working will become much less common, at least until isolation is established. For Shell approved vendor DEP compliant IAC tested LV switchboards the evaluation should include examination of the detail of the IAC tests. This will reveal that there are only a limited number of locations where the tests required the upstream protection to operate i.e. where there is a time limitation to the internal arc resistance. At other locations arcs may have been impossible to creare, self extinguish or are cleared by the protective device of the outgoing circuit. Therefore the actions which could give rise to an arc flash event will be limited. Typically these will be racking in/out of air circuit breakers, flash over in incoming cable compartments or at copperwork terminations onto air circuit breakers or large switches. For such boards with non-withdrawable switches for incomers/bus section switches (or limitation placed that air circuit breakers are not racked in/out with connections live) and where the additional insulation has been extended to cover terminations at switches there may be no locations where an internal arc can be sustained hence no arc flash risk. (click here to return to main document) A.3 Comments on Step 3 Calculate arc flash energy levels a) For switchboards which are claimed to be of internal arc control (IAC) design, The fault clearance time is the combination of the protection operating time and the breaker opening time. Use fault current through protective device (i.e. without motor contribution to fault level) to establish tripping time. If no specific information is available, assume motor contribution is the same as the sum of the starting currents of the normally continuously running motors connected to the board. As an alternative to calculation via the spreadsheet, the following conservative reductions in potential bolted symmetrical phase to phase fault current can be used to calculate protection operating times for comparison with switchboard IAC test times. HV circuits For all fault levels – assume 94% of potential fault current LV Circuits Fault levels up to 10kA – assume 55% of potential fault current Fault levels up to 30kA – assume 43% of potential fault current Fault levels up to 50kA –assume 40% of potential fault current Fault levels up to 80kA –assume 35% of potential fault current Fault levels up to 100kA –assume 30% of potential fault current For example for 10kA assume 5.5kA, for 45kA assume 10kA etc. (click here to return to main document) SR.11.13122 - XXXVII - Confidential b) For switchboards which have not been tested for internal arc containment (non-IAC) An alternative approach is to compare the fault levels, voltages and clearance times with the tables given in Appendix C. The tables are based upon the following assumptions and shall not be used if these are not valid for the particular equipment / action: Distance between the torso of the operator and the switchgear when carrying out an action is 900mm for HV and 610mm for LV. Equipment is a switchboard or MCC LV systems are solidly earthed and HV systems resistance earthed For LV applications tripping times are substantially unchanged if the assumed arc current is reduced by 15% Voltages covered are 400V, 690V, 1kV to 15kV and 33kV. Similar tables can be readily drawn up using alternative values if a location wishes to use different voltages or distances. Note that there are limitations in use of tables for voltages above 15kV. Use of the table allows assignation of boards to categories corresponding to the arc flash levels of 1. >40 cal/cm2., 2. >13cal/cm2 < 40cal/cm2 3. < 13 cal/cm2, This classification is needed in review of the outcomes which is the next step in the process (click here to return to main document) A.4 Comments on Step 4 – Review of the outcome of energy level calculations Reduction in clearance times by changes to protection schemes Since original protection design schemes did not consider arc flash energy levels, the design of such schemes will not necessarily have been set to minimise prospective arc flash energy levels. It can be anticipated therefore that many of the arc flash energy levels will exceed the target value of 13 cal/cm2 and, especially for circuit voltages above 15kV, will exceed the upper limit of PPE of 40 cal/cm2. This limit is also likely to be exceeded for boards at the upper levels in a distribution system where the need for discrimination with downstream protective devices will increase time delay settings, thereby increasing clearance times. Of particular concern are Main generation switchboards where the symmetrical fault currents do not decay as rapidly as in other locations on the network i.e. fault levels are high and the clearance times can be relatively long due to location in network Boards which can be fed from a lower fault level sources as well as a relatively high level source e.g. board fed via a transformer and also from an emergency generator. Transformer fed LV switchboards with secondary side protected by IDMT elements on the primary side or primary side fuses. (click here to return to main document) SR.11.13122 A.4.1 - XXXVIII - Confidential HV Circuits For HV circuits the reduction in arcing current compared to the symmetrical fault level suggested by the IEEE spreadsheet is relatively small and hence the operating time of the protection functions will be very close to that expected in original protection design for a short circuit condition. For IAC design switchboards with a short circuit withstand capability of 1 sec and an internal arc withstand time of 1 second this means faults on such boards should be cleared within the internal arc withstand time. Care needs to be taken where boards with an short circuit withstand time of 3 seconds have been specified, that the protection still operates within the tested internal arc withstand time for internal short circuits, otherwise the board will have to be classed as non-IAC. For non-IAC HV boards it is probable that scope of changing settings and reducing operating times to reduce arc flash energy levels is limited, unless the protection scheme is changed. Effectively in most cases the options to reduce exposure to less than 13 cal/cm2 arc flash energy levels are restricted to either remote operation of both open/close and racking in/out (i.e. remove personnel from being near the switchgear) or by changing the protection schemes to include bus zone protection or blocking schemes based upon directional over current relays. The latter solution will normally require replacement of existing relays and installation of new numeric relays to provide the required functionality together with a limited amount of bus wiring between cubicles. It should be noted that use of an improved protection scheme not only reduces risk to the individual but also reduces the consequences to the business in event of a fault, as the extent of damage will be significantly reduced. Therefore there is a business justification to support expenditure as well as a safety justification. (click here to return to main document) A.4.2 LV Circuits For LV circuits the reduction in arcing current suggested by the IEEE spreadsheet as compared to the symmetrical fault level is much greater than for HV circuits and suggested arcing currents will vary from 55% to 30% of the nominal symmetrical fault current value. The standard Shell design for protection of LV switchboards downstream of transformers is to use an extremely inverse IDMT over-current element and an instantaneous element fitted to the HV circuit breaker feeding the transformer and a standby earth fault relay fed from a c.t. on the neutral to earth link. The secondary side phase to phase protection (via HV IDMT element) will normally have been chosen to protect against overload and to trip rapidly (<1s) in event of a primary side short circuit (based upon minimum short circuit current levels). The only specific advice given is that the earth fault relay should trip within 1 sec for 50% of maximum earth fault current and that the HV instantaneous element should be pick up at 130% of the maximum secondary side fault current reflected into HV windings i.e. the instantaneous element should only respond to faults in HV cable and windings. For fuse contactor fed transformers the fuse effectively adopts the role of the instantaneous element. SR.11.13122 - XXXIX - Confidential The reduction in fault current to be considered for internal arc condition (55-30% of possible short circuit value) will mean the protection operating time of the IDMT element will increase significantly compared to clearance time at the full prospective fault current. It is highly probable that the arc withstand time of any IAC LV switchboards (300ms) will be exceeded with the standard Shell protection scheme set up as described above. In fuse protected HV/LV transformers the combination of large fuses and low fault levels can give rise to long clearance times (hence high arc flash levels) . Whereas fault levels on switchboards mounted close to transformers will normally be high enough to ensure fast operation of fuses for faults close to the switchboard, long feeder cables to remote switchboards can result in significantly reduced fault levels at such sub-distribution boards due to the effects of cable or overhead line impedances. As a consequence there can be increased clearance times at the reduced fault levels (bearing in mind the additional 55-30% reduction still has to be applied to determine clearance times). This can lead to the counter intuitive result that arc energy levels at the termination of the supply cable at feeder switchboard are lower than those at the termination of the cable at the sub-distribution board. (click here to return to main document) A.5 Use of temporary changes to protection settings There are many past examples within the Company of unnecessary trips occurring when protection settings have been altered, e.g. during commissioning or maintenance tests, and not restored to correct values. Effectively this means such changes should be automatically corrected if accidently left in more sensitive position i.e. overrides can only exist for a limited period before timing out and reverting to normal settings. Although such temporary setting changes are strictly not maintenance overrides as used in instrumentated protective systems (i.e. they do not override safety systems) it is possible that the same type of management control system can be used to manage application and removal of such temporary changes to protection settings. Alternatively the site management of change process could be used, provided such a system can accommodate the numbers of times such setting changes will be implemented. (click here to return to main document) SR.11.13122 Appendix B. B.1 - XL - Confidential Withstand times of Internal Arc Tested switchgear IEC and US standards Internal Arc testing of HV switchgear, whether to US or IEC standards, has very similar approaches. Both require that the tests show an individual will not be harmed by deliberately introducing an arc inside the equipment and showing that cotton indicators mounted around the board are not significantly damaged or scorched, provided the arc is interrupted within a certain period of time. Regrettably however the tests are not inter-changeable and it is necessary for staff to understand the specific standards relating to the equipment they are responsible for. One difference between the standards is that the suggested arc withstand time in US HV standards is 0.5s and there is a strong recommendation to detect the arc condition (e.g. by light, pressure rise etc) and initiate a trip of the beaker(s) feeding the fault. It should be appreciated that a 0.5s withstand time with an arc detection system / upstream trip will effectively co-ordinate with downstream outgoing feeders, even if their short circuit clearance times are greater than 0.5s. This is because the arc detection trip is dependent on combination of high currents and triggering of the arc detection system i.e. the zone of protection is limited to inside the switchboard; hence it should not react for external faults. The IEC standard allows 0.1, 0.5 or 1s arc withstand times and makes no such recommendations as to additional equipment to trip the supply breaker. Provided the protection on the board’s supplying breaker is set to clear within IAC test time then the board will control the consequences of an internal arc. If the clearance time of the upstream breaker is longer than the IAC test time then the board will not control the consequences Some manufacturers of IEC standard switchgear have adopted a similar approach to that described for American equipment in the past, and examples of this type of protection maybe found in some IEC based switchboards. Care is needed in such circumstances that the upstream trip command has actually been connected to the breaker(s) supplying the board since its role may not have been fully appreciated by the system designers. Refer also to Appendix A.2 Commentry on Swithgear evaluation for additional information re Shell approved vendor DEP compliant IAC tested LV switchboards. B.2 Effect of reduced fault currents If the boards being considered have been internal arc tested, then the longest clearance time must be within the test time for the board to be classified as IAC. This is irrespective of whether there is a reduction in arc current during the tripping sequence (for situations with multiple sources) or if the arc current is less than that used in the IAC test (see extract below from IEC 62271 Annex A). Extract from IEC 62271 Annex A A.4.5 Duration of the test NOTE: It is in general not possible to calculate the permissible arc duration for a current which differs from that used in the test ....... there is no universal rule according to which the permissible arc duration may be increased with a lower test current. SR.11.13122 Appendix C. - XLI - Confidential Comparison of clearance times and energy levels Tables are only valid for systems and equipment complying with assumptions stated as to voltage, equipment type, earthing arrangements and distances of torso to equipment C.1 HV switchgear (>1kV) Working Distance in mm Equipment Class: Grounding Type: Protective Device Type: 900 3 or 4 2 0 Switchboard or MCC Resistance Earthed Other Protective device Applicable voltage range 33kV 15kV < V < 5kV 5kV < V < 1kV Potential fault current (kA) Arc current (kA) Maximum clearance times in seconds (protection trip time + breaker operating time) 40 40.00 0.05 <0.050 30 30.00 0.06 <0.050 20 20.00 0.1 <0.050 10 10.00 0.2 0.6 5 5.00 0.4 0.13 40 37.92 0.55 0.18 30 28.58 0.75 0.24 20 19.18 1.15 0.37 10 9.71 2.4 0.78 5 4.91 5 1.63 40 37.92 0.63 0.20 30 28.58 0.85 0.28 20 19.18 1.3 0.42 10 9.71 2.75 0.89 5 4.91 5.8 1.89 To meet 40 cal/cm2 limit To meet 13 cal/cm2 limit Notes Values provided by IEEE spreadsheet for 33kV are for information only. These values should be used with caution since they are considered to very conservative compared to values for voltages up to 15kV. Nevertheless it illustrates that non-IAC tested 33kV indoor switchgear without fast operating protection for internal faults is likely to have arc flash energy levels above 40 cal/cm 2. SR.11.13122 C.2 - XLII - Confidential LV switchgear (400/415v & 690v) Working Distance in mm Equipment Class: Grounding Type: Protective Device Type: 610 3 or 4 1 0 Switchboard or MCC Solidly Earthed Other Protective device Applicable voltage range 400/415V 690V Potential fault current (kA) Arc current (kA) Maximum clearance times in seconds (protection trip time + breaker operating time) To meet 40 cal/cm2 limit To meet 13 cal/cm2 limit 40 16.64 1.1 0.35 30 13.27 1.4 0.45 20 9.64 1.95 0.64 10 5.58 3.5 1.16 5 3.23 6.5 2.1 40 32.28 0.53 0.175 30 24.56 0.72 0.23 20 16.70 1.1 0.35 10 8.65 2.2 0.72 5 4.47 4.5 1.45 Notes These values illustrate that the reduction in system voltage from 690 to 400/415 has a dramatic effect on the arc current to be assumed. This actually means in most cases it is easier to set protection to operate within the required time for 690v boards since the higher currents will mean faster operating times of the IDMT curves SR.11.13122 Appendix D. D.1 - XLIII - Confidential Calculation of arc flash energy levels using IEEE 1584 spreadsheet Calculation from “fixed” fault level sources In calculating arc flash energy levels it is necessary to determine what the fault level will be and which protection devices will operate, to determine how long the arc will exist. As a general rule arc flash energy levels will be reduced if the fault levels are reduced and fault clearance times remain unchanged or are also reduced. Based upon experience it is also recognized that probability of arc flash events occurring are greatest when racking equipment in or out of housings and when re-energising circuits which have been de-energised and have been previously worked on. The latter includes the initial energisation of new installations. Faults in the actual switching devices which are energised on both sides of the device are much less common – provided that the switching devices are properly operated, maintained and inspected. Therefore, wherever possible, those activities which carry the highest probability of an arc flash should be done when fault levels are lowest provided clearance times remain, at worst, unchanged. Actions should be limited to switching only when fault levels will be unavoidably highest e.g. when paralleling or de-coupling parallel supplies. Racking in/out should therefore be done when fed from minimum number of sources. Implication is that two arc flash energy calculations may be required, one covering worst case when switching is taking place and a second when switching has been completed and racking in/out or similar activities are being carried out. For existing installation ideally the protection should be such that the energy levels are less than the target maximum (13 cal/cm2) for worst case switching and during subsequent racking in/out. However that will not always be practical. A more pragmatic approach in such cases would be that it is less than13 cal/cm2 during racking in/out and less than 40 cal/cm2 during switching. Switching as a means to reduce fault levels before racking in/out is only effective if the fault levels are affected by the switching operation. A Switchboard No 1 Feeder Tx No 1 N/C Feeder Tx No 2 Tx No 2 Tx No 1 C Incomer No 1 Incomer No 2 Switchboard No 3 N/O B N/O Switchboard No 2 SR.11.13122 - XLIV - Confidential In example given above the fault levels at B and C are at maximum when the downstream switchboards are fed by parallel supplies and at a minimum when the boards are fed by a single supply. However the reduction is dependent on the impedances of the feeders between the supply board A and the downstream boards. Where there are transformers the fault level will always be higher in the parallel supply case. Where there are plain feeders such as for switchboard B, if the interconnection has relatively short cable connections, the fault level will be essentially unchanged. However if they are long overhead lines the fault level in parallel case will be much higher than single feed case. In order to be able to able to take advantage of reduced fault levels by switching before racking in/out it is necessary to follow a specific sequence of actions. As an example, if it is wished to take transformer No 1 out of service, then the following switching scheme should be followed. (In this it assumed any other bus section switches further up in the system are closed and other steps, such as checking for voltage indication, applying padlocks etc. are not mentioned for sake of clarity) Close bus section A Switchboard 1 Close bus section C Switchboard 3 Open Incomer No 1 on board C Switchboard 3 Open bus section A Switchboard 1 Open Transformer No 1 Feeder on board A and rack out Switchboard 1 Rack out Incomer No 1. Switchboard 3 The difference is that normal practice would be to Open Incomer No 1 and rack out before leaving Switchboard No 3 to minimize journeys between substations. This may not be an issue in plant areas but can be significant if substations are some distance apart. To restore supplies the sequence is essentially reversed Rack in Incomer No 1. Switchboard 3 Rack in Transformer No 1 Feeder on board A Switchboard 1 Close bus section A Switchboard 1 Close Transformer No 1 Feeder on board A Switchboard 1 Close Incomer No 1 on board C Switchboard 3 Open bus section C Switchboard 3 Open bus section A Switchboard 1 SR.11.13122 - XLV - Confidential Difference again is that racking in of Incomer No 1 is done early in sequence and again this implies an additional journey between substations. Given the wide variation found in circuit configurations it is not possible to provide examples which cover all cases. However as a guiding rule it is recommended to always develop switching schedules where racking in / out breakers only takes place after parallel supplies have been restored to single feed status. Additionally always ensure that the schedule will not result in “back feeding” i.e. the system is being energised from the reverse of its normal operation, unless the protection schemes have been designed for this condition. For example closing Incomer No 1 on board C before closing Feeder No1 Transformer on board A would result in energisation of the primary winding of Transformer No 1 with no earth reference and it being inadequately protected. From an arc flash calculation standpoint then there are two values; one when board C is fed by two transformers and one when it is fed by single transformer. Typically the feeders will operate in the same time as each other in both cases and there is no doubt as to the time to be assumed until the arc will be extinguished D.2 Calculation from “variable” sources of fault current. Equal clearance times will not be found where there are dissimilar sources e.g. when there is distributed generation or interconnection to the local grid with local generation. G B Fault condition power flow G Substation No 1 33kV (fed from grid) Normal power flow Normal power flow Fault condition power flow A Substation No 2 11 kV EG Substation No 3 0.4 kV C SR.11.13122 - XLVI - Confidential In example above the generation at Substation 2 is normally run in parallel with the grid substation No 1 and power flows are normally from the grid towards substation No 2 with the local generation running part loaded. In event of loss of grid then loads on substation No 2 can be supported by running both generators at close to full load. There is an islanding scheme which trips the 33/11kV transformer feeders if power flows are from Substation No 2 towards Substation No 1 i.e. preventing back feeding of substation No 1 and hence the grid. During monthly testing the emergency generator is run in parallel with main generation. How can switchboards 2 and 3 be assessed for arc fault energy levels? Substation 2 The natural presumption is that worst case will be when fault levels are at their highest i.e. with all bus section switches closed, maximum potential fault level at Substation 1 from the grid and with all generation in operation. The fault current values for this condition will typically be calculated in any system study to allow the required short circuit withstand current capability of the switchboards to be established. In practice the generation and transformer protection will almost inevitably take different times to trip so the fault current at switchboard No 2 will start at a high figure and then reduce in steps as the supplying breakers open. It is also necessary to look at case of minimum grid fault level if this reduction has the effect of significantly increasing transformer trip times for faults at Substation No 2. The IEEE spreadsheet assumes single fault levels and single trip times and is not designed to deal with fault currents varying with time. Recommendation is to take following approach If trip times are close (<100ms difference) then assume highest value of fault current will flow for the longest clearance time of a supplying breaker. If trip times differ significantly (>100ms difference) use tool such as SKM Power Tools to model the system and calculate energy levels. This will provide most accurate figures currently available. If it is wished to make a manual calculation and it is accepted that this will not be as accurate as a computer programme solution then assume worst case fault current and a trip time equating to when first significant drop in fault current occurs (in example above this will be when either the generation or the transformers trip). Enter these values into spreadsheet and note arc flash energy predicted. Then assume the lower fault current that will flow after one set of sources have tripped and the clearance time for the remaining supply points. Enter these lower current / longer time values in spreadsheet and note arc flash energy predicted. Take whichever is the higher value as being the arc flash energy level but Substation No 3 At 400v level it is necessary to calculate energy levels when fed by transformers and generation and also when fed by the generator alone. Assuming the transformer and generator are of equal capacity then it may be assumed that the same protection settings may be used at feeder breakers on Switchboard 2 and at generator. This SR.11.13122 - XLVII - Confidential however ignores the fact that typically the maximum generator fault current will be between one third and one quarter that provided by a single transformer. When running on emergency generator alone, the combination of longer clearance time and a lower fault current will result in higher arc flash energies than when fed by transformers. This issue can be resolved by using a faster acting element at the generation circuit breaker relay than for the transformers, but this will almost certainly be at the expense of discrimination with the larger outgoing circuits fed from Substation 3. Recommendation is to ensure (if possible) that setting of generation protection should clear faults on associated busbar such that arc flash energy level does not exceed 13 cal/cm2. In determining tripping time account should be taken of the arc current suggested by the IEEE spreadsheet, which will be around 55% of bolted short circuit value for generation up to 1250 kVA. Note however this recommendation is dependent on still being able to start or energise the necessary loads fed under emergency conditions. Alternatively expressed, the constraint on tripping time at reduced fault current may limit the maximum permitted size of emergency loads having a significant inrush or starting current. A mitigation will be to fit additional measures to detect a start condition and prevent the generation protection from operating prematurely during a large motor start. This will add significant complexity to the protection design and ideally should be avoided unless there are no other options available. D.3 Determining operating conditions for arc flash calculations A further distinction needs to be made in determining which operating mode or conditions the arc flash levels will be calculated for. In example given previously there are many possible operating modes. For example 1. 2. 3. 4. 5. Grid supply available and both main generators. Grid supply available and only one main generator running. Grid supply available and no generation running Only one grid transformer available and both main generation running Only one grid transformer available and only one main generator running To each of these can be added the options of minimum and maximum grid fault levels and whether or not the emergency generator is running. Calculation for all possible modes of operation would be a very extensive task and most of the calculations will not provide useful additional information. The simplest approach for the HV switchboard is to consider the scenario with maximum fault levels and calculate the arc flash energy level. Then look at minimum fault level conditions to see if the tripping times are significantly extended. In this instance are tripping times of the transformers extended when there are minimum grid fault levels? If so worst case could be when grid fault levels are at minimum not maximum value. For the LV board, as mentioned previously, both the condition when fault levels are at a maximum and when they are at a minimum (emergency generator only) should be considered. SR.11.13122 - XLVIII - Confidential This may require a comparison of different conditions to arrive at an indicative figure for the arc flash energy where there are differences in clearance times of the supplying circuits. In more complex circuits there may be even greater numbers of potential operating modes and a decision may be required to only consider “normal” modes which exist for extended periods of time i.e. accept that under abnormal operating conditions arc flash calculations may not be correct. The implication of such a decision to manage size of arc flash study is that works during abnormal system arrangements should be limited to those needed to put the system in a safe condition e.g. isolate faulty circuits or to return the system to a normal (hence studied) condition. If works (other than switching) which have a risk of creating an arc flash event have to be completed during abnormal conditions then a specific assessment for the particular configuration should be carried out to confirm the arc flash energy levels and/or if IAC test times are not exceeded. SR.11.13122 D.4 - XLIX - Confidential Entering values in the IEEE spreadsheet data input sheet Motor Contribution Factor: 0.03 Enter typical portion of bolted fault from motor contribution. Example: 0.03 Enter zero if no motor contribution kV of bus Bolted fault current of bus in kA (from study) Portion of Bolted fault current that flows through protective device in kA (from study) Protective device fault current without motor contrib. in kA (B21) Switchboard XYZ – single feeder 3.3 6.75 6.75 6.75 Switchboard XYZ – single feeder 3.3 6.75 Switchboard XYZ – twin feeder 3.3 13.5 6.75 6.75 Switchboard ABC – single feeder 0.4 25 25 25 Name of bus 6.55 Free choice of text which is repeated on summary page This is always the Voltage of the Busbar being considered Fault level at the busbar being considered at the voltage level in previous column Cells coloured yellow are available for data or text entry. White boxes have calculation formula in them and should not have any data entered in them All currents should be entered at the voltage of the busbar being considered. This is the current flowing through protective device. If there are twin sources of supply it will be half the Bolted Fault current less any motor contribution This is the current flowing through protective device. If no entry in previous column it will insert the value of the study Bolted Fault current reduced by the fraction shown in Motor contribution factor box above the table – see red text 6.75*97% = 6.55 If an entry is made in previous column, that value will be used SR.11.11111 -1- Trip time of protective device at arcing current. For LV circuits only, the calculation requires the tripping time at 85% of the arcing fault current to also be entered. Note If the protective device is at a different voltage level to the busbar voltage being considered, then the arcing current will have to be converted to match the voltage level at which the protective device is operating to be able to establish the trip time. Arcing fault current in protective device, in kA (Calculated) Confidential As before this may have to be converted to the fault current at the voltage level on which the protective device is operating If an entry is required the cells remain blue Trip Time Opening Time Reduced arcing fault current in protective device, in kA 6.52 0.1 0.25 6.40 0.12 6.52 12.2 Trip Time at Reduced Current Opening Time at reduced current Grounding Type: Working distance is the distance to the torso of the person from the front of the switchboard 1 - Solid Grounded 2 - Ungrounded, Resistance Grounding, Other Impedance Grounding Working Distance in mm Equipment Class Grounding Type Protective Device Type Not required 1000 3 2 0 0.25 Not required 1000 3 2 0 0.1 0.25 Not required 1000 3 2 0 0.8 0.2 10.37 610 4 1 0 1.0 0.2 Operating time of the circuit breaker or contactor Equipment Class: 1 - Open Air 2 - Cable Calculation of the current value to be used in assessing the trip time of the protection device. 3 - Switchgear 4 - MCCs, Panels For HV circuits this reduction is only a few % of the protective device fault current in previous column The spreadsheet reports only one energy level in the summary sheet For LV circuits the reduced value will be between 55 and 30% of the potential fault current. The % reduction is greater as the LV bolted fault current value increases This is the higher of the two arc flash energy levels calculated using the trip time / arcing fault current and the trip time / 85% of arcing fault current (where entered) Protective device type refers to US standard MCB’s and should be left with zero entered SR.11.11111 Appendix E. E.1 -2- Confidential Additional insulation and Cable Terminations Additional busbar insulation Switchgear uses air, or an insulating gas such as SF6, together with supports made from insulating materials to meet the normal and over voltage requirements of the relevant IEC standards. In some cases this is supplemented by insulating phase barriers especially where the same equipment is used for a range of voltages e.g. 400 & 690v or 11kV and 13.8kV. Phase barriers are often added where air insulation values will not meet peak over-voltages applied during testing. All such insulation and phase barriers can be described as being the functional insulation of the switchboard. There has been a requirement for additional insulation called for in the relevant DEP’s which predates any requirement for formal tests for arc flash containment. This insulation is additional to that required to meet IEC standards and is to be applied to busbars and droppers of a switchboard for both LV and HV Air Insulated switchgear. The purpose of this insulation is not to be able to meet any of the IEC tests, but to reduce the probability of a flash over occurring and to reduce the consequences should one occur. This can be described as additional insulation since it is not required to meet the IEC functional requirements. The advice provided with the IEEE spreadsheet recommends using a tripping time based upon phase protection only and takes no account of earth fault protective devices. The assumption is that a three phase fault represents the worst case in terms of energy released and the phase protection elements will be the slowest acting protection element. This is approach is sensible if the majority of equipment being considered has little or no additional insulation to minimise the opportunity for a flash over between phases and little or no segregation of different segments of the switchgear. Typically this situation will be found in most switchgear not built to IEC based DEP standards. Uncontrolled arcs will naturally tend to expand their path length and the driving voltage / current will pass through zero, potentially creating a condition which will naturally extinguish the arc. This can occur because the products of the arc (ionised gasses and vapourised metal) tend to be moved away from original source of the arc, effectively increasing the arc length hence its impendence. In equipment without additional insulation the roots of the arc can move so as to keep the arc length short negating this natural arc impedance increase and allowing a restrike after current/voltage zero i.e. the arc will be sustained once it is established. It is the existence of a sustained arc which gives rise to highest energy levels. If the arc is extinguished quickly this significantly limits the amount of energy released. Note however Pressure development in the vicinity of the arc is within the first 15 ms after ignition The temperature increase within the first 20 ms will be up to 20 000 °C Equipment therefore still has to be able to withstand initial pressurization event and there will be significant damage to equipment unless the arc extinguishes very quickly (say < 15ms). SR.11.11111 E.1.1 -3- Confidential LV switchboards During testing to demonstrate internal arc control, a shorting wire is placed at various points in a low voltage switchboard where there are exposed connections permitting such wires to be attached. Results of such tests between boards with un-insulated bars and those with insulated bars and segregation of compartments show a marked difference. Those with insulated bars obviously limit the possibility of an arc occurring by virtue of the insulation preventing an arc from being created in the first place. Even if the insulation is damaged sufficiently to allow a shorting wire to be installed then, provided such damage is limited in extent, the arc will self extinguish i.e. there is no reliance on upstream devices to operate in order to extinguish the arc. Arc duration is short, typically between 7 and 15ms. However most test reports do not show tests results from these “arc free zones” since it is not called for in the IEC TR test standard. By comparison, an un-insulated bus bar design with large areas of exposed copper work does not prevent an arc from being established initially and it will continue to support the arc until the test supply is interrupted i.e. self extinguishing will not occur because arc impendence is not increased. In practice the arc impendence is likely to be reduced by allowing multiple arcs to be established. Such a system is wholly dependent on the upstream protective device operating to extinguish the arc. Experience and test results allow that if a board has a fully insulated bus bar system (including droppers) in accordance with DEP requirements, then the system can be treated as an arc free zone and assumed not to be a possible source of arc flash. This applies irrespective of whether the board has been subject to an IAC test. Note It may be necessary to examine the board to ensure the manufacturer has continued the insulation up to and including connection points to major components such as bus bar or down dropper couplers, incoming switches or circuit breakers. If significant exposed areas of copper are identified then these shall be treated as potential arc locations (or insulation applied to eliminate them from this consideration). Refer also to Appendix A.2 Commentry on Evalauation of switchboards for observations on Shell approved DEP compliant IAC tested LV switchboards. E.1.2 HV switchboards Testing for HV boards also use similar shorting wires where there are exposed connections. The test results show no self extinguishing capability and arcs only extinguish when the test supply is disconnected. All IAC tested HV switchboards therefore have an arc withstand time. However tests have not been completed with insulated bus bar systems so no conclusions can be drawn as to whether arc flash containment performance of such boards differs from un-insulated bus bar systems. Practical experience indicates however that the extent of damage is much reduced if insulated systems are used; but that any flash over will readily find any exposed copper work or other weaknesses in the additional insulation. SR.11.11111 -4- Confidential Implication for HV switchboards is that a benefit in terms of reduction in arc flash energy due to the additional insulation called for in the DEP exists, but cannot be readily quantified. Fot this reason no allowance can be made for any reduction in risk due to additional insulation. E.2 Cable terminations For HV three core cables there can be phase to phase faults especially within the crotch of the cable where cores are split out for termination or where crosses are made to maintain correct phase sequence. In such instances electric stress levels can be high, especially if termination has not been completed exactly in accordance with termination kit manufacturers’ recommendations. Often there are differential schemes across cables which are sensitive enough to react before such faults can fully develop. For such installations the arc flash hazard is therefore also significantly reduced since such systems have very fast tripping times. There are instances e.g. motors and feeders to LV transformers which do not have such differential protection and faults can develop into phase to phase faults before protection can react. This is especially true of outdoor terminal boxes where water may gain ingress. There have been many examples of such terminals boxes literally shattering under such fault conditions when fed by circuit breakers. The introduction of fuse protection to most motor and HV/LV transformer circuits has eliminated such consequences since the fuse limits the amount of energy released in the HV circuits. Note however that fuses chosen to provide short circuit protection of the HV circuits (as found in vacuum contactor circuits) provide no protection for the LV windings or LV secondary cables / terminations. Refer to Appendix F for discussion on HV/LV transformers protection. Cable terminations to be considered as possible arc flash locations are therefore those which are not within a differential tripping scheme (or similar instantaneous protection) or are not protected by an upstream fuse at the same voltage level as the cable termination. SR.11.11111 Appendix F. -5- Confidential Scope for protection to minimise arc flash energy levels For a given type and make of switchgear there is little that can be done to alter the level of protection afforded by equipment design i.e. convert to IAC design, nor is there great scope for altering the position of the individual with respect to the location of a potential arc flash point. The only realistic methods of changing the energy levels an individual is exposed to, is either by remote operation or by reducing the arc duration. The practicality of remote operation will depend on the action needed to be carried out and the availability of suitable equipment. The availability or practicality of such equipment cannot be guaranteed for all equipment types. However reducing the arc duration is possible in every case by altering the protection settings to reduce tripping times. Downside of such a change is that it will reduce discrimination between upstream and downstream devices. If differentiation is reduced below the recommended limits (typically 0.4s for traditional HV relays and air or oil circuit breakers reducing to 0.3s for modern relays and vacuum or SF6 breakers), false trips may occur and larger parts of the network may be lost as a result of a downstream fault. Since unexpected trips of part of the network may of themselves create other potential hazards, loss of discrimination in order to reduce arc flash energy levels is not a satisfactory long term option. Therefore there will be a limit as to the extent arc flash energy levels can be reduced by changes to protection settings unless the protection scheme is changed to one with a restricted zone of protection. A further complication is that the recommended arc flash current (from IEEE spreadsheet) for calculating clearance times is less than the maximum fault current. The original designers of existing protection schemes will not have considered these reduced values since these limits were not available to be considered at the time of the original design. In considering what improvements can be made using protection the target values we are looking for are: For non-IAC tested switchboards Maximum arc flash energy of 13 cal/cm2 (long term) and 40 cal/cm2 (in short to medium term) at all voltage levels For IAC tested switchboards Total clearance time 300ms (L V)* Total clearance time 1s or 0.5s (HV) *300ms is normal IAC test time but must check actual test time for switchgear being considered as some can be as low as 100ms SR.11.11111 F.1 F.1.1 -6- Confidential HV switchboards Non IAC tested switchboards Voltage range up to 15kV For HV equipment and voltages in range up to 15kV the reduction in fault current to be used in calculation of arc flash energy is relatively small (6% max) and the clearance time will be little changed from that calculated for maximum fault current. Properly designed protection schemes with fast acting elements for short circuit conditions should already result in almost the lowest practical arc flash energy levels for the fault level at that point in the system while providing adequate discrimination. Difficulties will be found in achieving fast operating times when there are multiple levels of substations fed at same voltage level unless there is bus zone or blocking scheme protection installed. Traditionally such systems have not been installed at lower voltage levels (3-15kV) within the Shell Group, since their complexity and cost were seen as outweighing the benefits. This balance has now changed with introduction of numeric relays and implementation of such schemes is now much simpler and requires no additional ct’s and little additional wiring. For new installations this type of protection is still not preferred since it is possible to purchase IAC switchgear which has been tested to control internal arc faults. Such protection solutions are acceptable however as a retrofit solution to allow continued use of an otherwise acceptable older installation. Clearance times to meet 13 Cal/cm2 limit Time in seconds Proportion of fault current to calculate tripping times (based upon resistance earthed 6 kV board and 900mm distance) 1.1 1 0.9 0.8 Total Clearance time to meet 13 cal/cm2 limit 0.7 0.6 Protection operating time assuming a 80ms breaker operating time Proportion of potential fault current through protective device 0.5 0.4 0.3 0.2 0.1 0 10 20 30 40 50 60 Prospective Fault level in kA In above illustrative graph it can be seen that, for the example 6kV switchboard being considered, the allowable clearance times to meet a 13 cal/cm2 arc flash energy restriction will only permit discrimination with downstream devices (tripping time > 0.4s) once fault levels are SR.11.11111 -7- Confidential below 10-15kA, which is relatively low level for most locations. Also shown (green line) is the relatively small change in proportion of prospective fault current to be used to deterimine tripping times It can also be seen that for any fault level up to around 40kA, protection which operates within 100ms will keep energy levels below 13 cal/cm2. If this protection operating time is adopted as a standard then inherently the objective of restricting arc flash energy levels will be achieved provided that care is taken that protection pick up values are consistent with available fault levels. Therefore control of energy levels to maximum of 13 cal/cm2 by fast protection operation for voltage levels up to 15kV is possible, provided discrimination can be achieved by some means. In practice this implies using a blocking scheme when making protection changes to existing boards since this does not require additional c.t.’s. to be fitted F.1.2 Non IAC tested switchboards - Voltage range above 15kV Once the voltage rises above 15kV a different calculation method is used in the IEEE spreadsheet and the energy levels thereby calculated undergoes a step change and uses the original Lee equations. These give results which are very conservative and for this reason the IEEE recommendation is to restrict use of the spreadsheet to voltage below 15kV. Unfortunately we do not yet have an alternative more accurate method available to quantify arc flash energies at these higher voltages. If the IEEE spreadsheet is followed as the method for determining arc flash energy levels, then, even with total clearance time of 100ms, the calculated energy levels for a metal clad switchboard with impedance earthing and at a typical 900mm distance a from the switchgear are always in excess of 13cal/cm2 unless fault levels are below 10kA for 24kV and 6kA at 33kV. These are relatively low fault levels compared to those normally seen at petrochemical facilities for these voltage levels. Exception to the above will be applications where higher voltages have been selected to reduce voltage drop rather than as a consequence of higher power ratings. In these circumstances boards at remote locations fed by overhead lines may have relatively low fault levels at the receiving end. This means that the corresponding arc flash energy level will also be low and may be kept below 13 cal/cm2 if “normal” fast acting protection is fitted and set up to reflect the lower fault currents. Note however in such circumstances it is still likely that the board at the sending end will have a much higher fault level and be subject to higher potential arc flash energy levels. Therefore for majority of applications using the IEE spreadsheet to calculate realistic protection settings to control arc flash energy levels to less than 40 cal/cm2 at voltages above 15kV is not possible with spreadsheet version currently available. In conducting risk assessment we are forced to rely on a more subjective and less analytical approach. Specifically to use our experiences with consequences seen when such flashovers have occurred and the design features stipulated in our DEP’s which limit the creation of phase to phase faults. SR.11.11111 -8- Confidential Design features which assist in control of arc flash energy levels at voltages above 15kV can be Fixed switchgear with cast resin insulation and cable terminations insulated to functional insulation standards Fast acting zone protection or blocking schemes, Insulated bus bars System impedance earthing to limit size of earth fault currents coupled with sensitive fast acting earth fault protection. Such systems designed such that an earth fault will always develop initially (limited by the earth neutral impedance) and be detected & acted upon quickly before or while a phase to phase fault is being fully established. Although the possibility of a phase to phase fault developing cannot be eliminated, such a system is already reacting and responding to the fault condition and hence the time during which a phase to phase fault exists will be less than the clearance time of the phase to phase protection and associated circuit breaker. It is not possible to make a firm prediction as to the resultant time a full phase to phase fault exists. However evidence from locations where such failures have occurred, is that the consequences are not as severe as predicted by the IEEE spreadsheet in its current form. As a further restriction and to make the assumption conservative, such reduced effects can only be assumed to be effective in limiting arc flash energy if all covers and doors are closed and secured. Due to the difficulty in being precise in the arc flash energy levels present, for non IAC tested switchboards operating above 15kV preference shall be given to operating remotely wherever possible. This should include both switching and isolation actions. For boards which are in compliance with DEP requirements and incorporate fast (typically trip initiation within 100ms) acting protection i.e. differential, bus zone or blocking schemes, then wearing of 40 cal/cm2 PPE when undertaking racking in/out operations is deemed to be ALARP. F.1.3 IAC tested HV switchboards The manufacturers IAC test report will define the test time which will typically be 0.1, 0.5 or 1s duration. There are no boards with a 3s IAC test time. Boards with a 0.1s IAC test time should be effectively assumed to be non-IAC tested since it is almost impossible to detect and interrupt the supply within such a short timescale. To maintain their IAC status it would be necessary to fit arc detection and very fast acting (6-10ms) switches which apply a solid earth to all phases to quench the arc. The use of such switches and deliberate application of a solid earth to the system is not recommended, both because of the stress of the high fault currents on other components in the system and the depression of system voltage that will occur. 0.5s IAC tested boards can only be assumed to be IAC compliant if their upstream supply feeder protection operates within 0.5s. This implies all outgoing feeders must have instantaneous protection which will then permit adequate discrimination (0.4s) between the upstream feeder and outgoing feeder protection. However existing protection schemes may not have been set up with this constraint and changes may be necessary. If such a board has a feeder supplying a SR.11.11111 -9- Confidential subsidiary board at the same voltage then it will be impossible to maintain discrimination between the incomer of the main board, the outgoing feeder from the main board and the outgoing feeders of the subsidiary board without some form of blocking or differential scheme being employed. Note that comments previously made about cable terminations in Appendix E will apply to the incoming cable connections, the outgoing cables will be protected by the instantaneous protection on feeder circuits. 1.0s IAC tested switchboards will allow conventional protection schemes to be used since they will have normally been designed to match the short circuit withstand time of the board (typically 1s). Such boards therefore do not require modification to protection schemes for board to remain IAC with possible exception of incoming cable compartments. Where a 3s short circuit withstand time for a 1s IAC board has been specified there should have been measures applied to interrupt bus bar faults within 1s since a 3s fault would effectively destroy the switchboard. 3s short circuit withstand time boards are normally specified where greater than 1s is required to provide discrimination with outgoing feeders and sub distribution boards at the same voltage level. If no measures have been implemented to ensure bus bar fault clearance within 1s then these boards should be treated as non-IAC boards. To achieve compliance with IAC test timeanad still retain discrimination between incoming and outgoing supplies it will be necessary to use blocking or bus zone protection scheme. SR.11.11111 F.2 - 10 - Confidential LV Switchboards For LV switchboards the reduction in potential fault current to be used to calculate protection operating times is much larger, typically value to be used lies between 55% and 30% of maximum fault current. This severe reduction is applied as a result of tests done in the US to verify the size of fault currents seen in practical applications. The reduction in fault level is due to the fact that LV faults seen in practice always have impedance which limits the maximum current to significantly less than that of a solidly bolted fault. A solidly bolted fault is typically calculated in system studies and used to determine the required short circuit withstand current of the busbar system. If original scheme designers followed the rules and advice given in DEP or other sources of good protection practice, then the protection will have been designed as described in Appendix A Section 4.2 Commentary on LV switchgear assessment. Experience has shown these guidelines have not been universally observed and relatively long clearance times can have been allowed, especially where there are several levels of distribution with air circuit breakers as protection elements rather than fuses. This may arise because original protection design may have assumed it was sufficient for faults to be cleared within the short circuit withstand time of the LV busbars (typically 1 or 3 seconds) or even longer if the fault currents are less than the busbar rating. Such assumptions are not valid if fault clearance time exceeds the arc flash tested value (nominally 300ms for LV boards). There is no extension permitted to the clearance time because the fault current is less than that used in the IAC test. Clearance times to meet 13 cal/cm2 limit (based on 400v board, solidly earthed and at a 610mm Time in seconds Proportion of fault current to calculate tripping times distance) 1.3 1.2 1.1 1 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0 10 30 50 70 90 Prospective Fault level in kA Total Clearance time to meet 13 cal/cm2 limit Protection operating time assuming a 80ms breaker operating time SR.11.11111 - 11 - Confidential From the above illustrative graph it can be seen that, to stay with a 13 cal/cm2 limit, for a 80kA fault level the protection operating time must be around 100ms and that it must respond to 35% of available fault current so around 28kA. Similarly for 50kA and 30 kA fault levels the time and trigger current levels are 200ms / 20kA and 360ms / 13kA. It is only when fault levels are less than 15kA that sufficient time delay can be allowed to permit discrimination with a second level of distribution and still stay with a 13cal/cm 2 limit if a minimum discrimination time between devices of 300-400ms is assumed. For typical transfomer fed LV board this means limiting the supply transformer to having a rating of 500kVA or lower and not being operated in parallel with another supply. Such installations are only normally found in electrified production fields with a limited number of ESP’s installated. A typical potential 50kA short circuit level installation is where two 1 MVA transformers are paralleled by closing a bus section, say to allow one transformer and its switchgear to be taken out of service for maintenance. It should be noted that when operating alone the fault level is say 25kA and the corresponding fault current for assessment of operating time is 11.5kA but when operating in parallel at 50kA the tripping time calculation fault current is 9.9kA. The difference is explained by the reduction in proportion of available fault current from 45% at 25 kA down to 40% at 50kA. Hence parallel operation is likely to be the most onerous limit to be met. For an installation with more than one level of low voltage distribution which is not fed by a fault limiting device e.g. a fuse, then to restrain the energy levels below the 13 cal/cm2 target where fault levels are greater than 15kA at the supplying board it will be necessary to have devices which allow much shorter discrimination times than default 300-400ms. Vendors of modern air circuit breakers suggest that discrimination will still be achieved even with timing differences as low as 100ms. 1600A Incomer air circuit breaker 2 1 1 Main switchboard 400A Feeder air circuit breaker 3 Incoming switch 2 Subsidiary switchboard 160A Moulded case circuit breaker 160A 3 SR.11.11111 - 12 - Confidential In this example the vendor is suggesting 100ms is sufficient to allow discrimination between the incoming air circuit breaker and the feeder to the subsidiary board while still co-ordinating with loads on subsidiary board. This example gives an operating time of 200ms from 3000A upwards for main board which would mean for 2*1MVA fed switchboard the criteria for keeping energy levels below 13 cal/cm2 would be met. Whilst this reduced time discrimination may be possible for modern numerical microprocessor based protection it is not recommended to use such close settings for older devices with conventional thermal or magnetic trips. It is also recommended that, irrespective of circuit breaker age or protection type, whenever use is made of lower discrimination times than default values, the application is discussed with vendors of the circuit breakers to obtain confirmation system will operate as expected. A protection operating time of 100ms will restrain energy levels below 13 cal/cm 2 for up to 90kA. So control of energy levels to below 13 cal/cm2 by fast protection operation is theorectically possible, provided discrimination can be achieved by some means. SR.11.11111 F.3 F.3.1 - 13 - Confidential Summary of practical solutions Non IAC-tested HV switchboards up to 15kV Ideal solution is to fit protection which will operate within 100ms. This will limit energy levels to 13 cal/cm2 or less for all fault levels up to 40kA, allowing use of lower rated PPE when undertaking tasks with a significant risk of an arc flash event. For retro fit permanent solutions this can most economically be achieved by replacing existing relays with numeric devices and implementing a blocking scheme between the outgoing feeders and the incoming sources of supply. Note that standing load of new relays will mean the associated substation DC power supply units and batteries will also need to be replaced. An alternative solution is to fit new relays to incoming sources of supply and a have means of temporarily applying definite time elements with 100ms trip time while activities with highest risk of an arc flash event e.g. racking in / out are being undertaken. As an example a switch could be provided to change the setting group to one which has a definite time element included. To prevent sensitive setting being left on by accident then use a timer in the relay logic to force reversion to original setting group after a set period has elapsed from activation e.g. 5 minutes. As an additional safeguard local indication and/or alarm could be raised while the more sensitive settings are enabled. Even with an automatic cancellation of protection settings change, the latter solution carries a residual risk i.e.a fault occurring downstream of the switchboard while the more sensitive setting is applied could cause whole board to trip rather than just affected circuit. For either solution fitting of fast acting elements to incomer circuit breakers will not limit arc flash energy at the incoming cable compartments or the incomer circuit breakers themselves. Hence additionally it is recommended to adopt procedure that racking in/out is only performed when incoming supply is isolated such that the breaker being moved is then protected by fast acting protection on the remaining incomer (refer to switching sequences mentioned in Appendix D section1) F.3.2 Non IAC-tested switchboards above 15kV Preferred solution is to use remote racking in / out open / close equipment where personnel can undertake these operations either in a control room or while standing outside the substation and away from the entrance doors to the substation. While it is normally relatively straightforward to implement a remote electrically operated open/close function it is less easy to make racking in/out a remote operation. There are motorised devices available to drive the racking lead screw, either from the switchgear vendor or from specialist companies. Alternatively (although this is not supported by a formal calculation) for boards compliant with DEP (insulated busbars, higher IP ratings etc) where all potentially arc flash creating actions can be undertaken with doors or covers closed then use fast acting protection (as described for switchgear up to 15kV) set to operate at maximum of 100ms together with PPE rated to 40 cal/cm2. As with lower voltage boards the fast protection setting can be permanent or temporary in nature SR.11.11111 F.4 F.4.1 - 14 - Confidential Summary of solutions for LV switchboards IAC tested switchboards Assuming the installation follows DEP std drawings and recommended protection scheme then simplest modification is to introduce a fast acting definite time element to the upstream protection set to pick up and start to time out at 85% of the calculated arcing fault current with a delay of 300ms (assumes IAC test time of board is 300ms). In almost every case this will require a check made with the largest outgoing feeder protection to ensure adequate discrimination at the proposed pick up current. If fault levels are such that the fault level is determined principally by the transformer impedance (i.e. transformer impedance >> supply system impedance) and if the largest outgoing fuse is no greater than ¼ of the transformer FLC then adequate discrimination should be possible. Where larger fuses are fitted than this ratio there is a greater possibility that discrimination time will be less than recommended value given by 4*fuse operating time + 150ms. A further limitation is that in most instances the pick up value of this element will be within the value of the inrush current of the transformer (10-12 times FLC). To prevent tripping on energisation it is recommended that the fast acting element is inhibited from operation before and for first 10 seconds after transformer energisation. As with HV protection there is an opton to make this additional element a temporary change such that it is only activated when undertaking higher risk activities. Especially if the board is of DEP compliant type with limited locations / actions which give rise to an arc flash risk, then use of a temporary setting reduction may be preferable to a permanent application of an additional fast acting element if discrimination margins with outgoing circuits are close to recommended minimum margins. Note For Delta-Star connected transformers to ensure discrimination under all possible fault conditions the discrimination must be valid when primary side currents are calculated at a value of approx 15% higher than use of simple transformer voltage ratio indicates. F.4.2 Non IAC-tested switchboards The same protection as referred to for IAC tested boards can be applied as suggested for IACswitchboards but with time delay limited to 100ms to reduce arc flash level to below 13 cal/cm2 for all fault levels up to 80kA. This will mean discrimination with outgoing circuits cannot be maintained in many instances therefore can only be used as a temporary change while higher risk activities are carried out. Depending on type of switchgear this can mean such a reduction is being routinely applied which increases risk of an unwanted trip due to co-incident downstream fault elsewhere while lower settings are being applied. In such cases it may be decided that business risks of lost production justify the cost and difficulty of making the switchgear fully remotely operable at least for high risk activities such as racking in/out. If the lack of discrimination affects only larger circuit breaker protected outgoing circuits it may be possible to add an inhbit function to such circuits such that the incoming supply fast acting element is inhibited in event of a downstream fault on one of the circuit breaker fed circuits. SR.11.11111 - 15 - Confidential The copyright of this document is vested in Shell International Exploration and Production, B.V. The Hague, The Netherlands. All rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval system or transmitted in any form or by any means (electronic, mechanical, reprographic, recording or otherwise) without the prior written consent of the copyright owner.