UAP DOCUMENTS 5 days - immediately 7 days - from receipt of NOTICE TO PROCEED 10 days -notice to stop, resume before beginning or suspending, resuming - request on drwn & matrls from date needed 15 days - request for payment by contractor - change of order - certificate of payment by the architect - for owner to pay the contractor from issuance of certificate of payment - reqst of extension frm occurrence of delay - notice of termination upon written notice - contract sum & breakdown UAP DOCUMENTS Sole power of interpreting the provisions of the code: National Board of Directors of the United Architects of the Philippines Board of Professional Regulation Commission Doc 201 Pre- design Services Doc 202 Design services Doc 203 Specialized Allied Services Doc 204 Construction Services Doc 205 Post- Construction Services Doc 206 Comprehensive Architectural Services Design- Build Services Doc 207 30 days - arbitration - certificate of occupancy Doc 208 Selection of Architects & Methods of Compensation 60 days - to make good of known defects after issuance of certificate of completion (expiration of performance & payment bond) Doc 209 Competition Code ArchitecturalPlumbingElectrical- Building Code National Plumbing Code Philippine Electrical Engineering Law RA185 Philippine Mechanical Engineering Law CW294 Phil Structural Code for Buildings 90 days - work stoppage ordered by the court - retention (3 months after acceptance of work) 120 days - building permit validity 365 days - guarantee bond effectivity - building permit validity if there was no Construction MechanicalStructural LAWS Performance Bond- 15 % of contract amount Payment Bond- 15% of Contract amount valid until replacement of Guarantee Bond Guarantee Bond- 30% of contract amount valid up to 1 yr from date of acceptance After 65% completion of work, the contractor should present certificate of non financial obligation After 98% substantial completion of contract work, the architect shall inspect the project & issue certificate of completion after certification, the contractor will finish outstanding work during period of making good of all known defects of 60 days. SUSPENSION OF WORK Contractor can suspend work: 1. non- payment after 15 days request 2. order of government to stop work for 90 days Owner can suspend work: 1. bankruptcy- declared by BIR 2. insubordination 3. non payment of contractors debt 4. non superintendence of contractor PD 1185 PD 1096 PD 957 PD 23 PD 49 Fire Code Building Code Condominium & Subdivision, Bridges Protective Law Law that Created the PRC Intellectual Property Law RA 545 The Architects Law BP 344 The Law Enhancing the Mobility of Disabled The Socialized Housing Law BP 220 ARCHITECTS FEE Simple Moderate Exceptional Residential Monumental Repetitive Housing Extensive Detailing Alteration and Renovation Consultation 6% 7% 8% 10% MBF + 50% 80%, 60%, 40% 60%, 30% 15% 150% P200