UAP DOCUMENTS
5 days
- immediately
7 days
- from receipt of NOTICE TO PROCEED
10 days -notice to stop, resume before beginning or
suspending, resuming
- request on drwn & matrls from date needed
15 days - request for payment by contractor
- change of order
- certificate of payment by the architect
- for owner to pay the contractor from
issuance of certificate of payment
- reqst of extension frm occurrence of delay
- notice of termination upon written notice
- contract sum & breakdown
UAP DOCUMENTS
Sole power of interpreting the provisions of the code:
National Board of Directors of the United Architects of
the Philippines Board of Professional Regulation
Commission
Doc 201
Pre- design Services
Doc 202
Design services
Doc 203
Specialized Allied Services
Doc 204
Construction Services
Doc 205
Post- Construction Services
Doc 206
Comprehensive Architectural
Services
Design- Build Services
Doc 207
30 days - arbitration
- certificate of occupancy
Doc 208
Selection of Architects & Methods
of Compensation
60 days - to make good of known defects after
issuance of certificate of completion
(expiration of performance & payment bond)
Doc 209
Competition Code
ArchitecturalPlumbingElectrical-
Building Code
National Plumbing Code
Philippine Electrical Engineering
Law RA185
Philippine Mechanical Engineering
Law CW294
Phil Structural Code for Buildings
90 days - work stoppage ordered by the court
- retention (3 months after acceptance of
work)
120 days - building permit validity
365 days - guarantee bond effectivity
- building permit validity if there was no
Construction
MechanicalStructural
LAWS
Performance Bond- 15 % of contract amount
Payment Bond- 15% of Contract amount
valid until replacement of Guarantee
Bond
Guarantee Bond- 30% of contract amount
valid up to 1 yr from date of acceptance
After 65% completion of work, the contractor should
present certificate of non financial
obligation
After 98% substantial completion of contract work, the
architect shall inspect the project & issue
certificate of completion after certification,
the contractor will finish outstanding work
during period of making good of all known
defects of 60 days.
SUSPENSION OF WORK
Contractor can suspend work:
1. non- payment after 15 days request
2. order of government to stop work for 90 days
Owner can suspend work:
1. bankruptcy- declared by BIR
2. insubordination
3. non payment of contractors debt
4. non superintendence of contractor
PD 1185
PD 1096
PD 957
PD 23
PD 49
Fire Code
Building Code
Condominium & Subdivision,
Bridges Protective Law
Law that Created the PRC
Intellectual Property Law
RA 545
The Architects Law
BP 344
The Law Enhancing the Mobility of
Disabled
The Socialized Housing Law
BP 220
ARCHITECTS FEE
Simple
Moderate
Exceptional
Residential
Monumental
Repetitive
Housing
Extensive Detailing
Alteration and Renovation
Consultation
6%
7%
8%
10%
MBF + 50%
80%, 60%, 40%
60%, 30%
15%
150%
P200