VISIT KANGPING SUPPLIER REPORT MOTOR KANGPING VN: 742307004 Date: May.18.2023 Prepare: Felix GENERAL CONTENT OVERALL INFORMATION 1 4 5/23/2023 2 PRODUCT OVERVIEW 3 PROCESS OVERVIEW IMPROVEMENT POINT FOR BUILD EB SAMPLE NPI @ Techtronic Industries Vietnam 2 1. OVERALL INFORMATION SUPPLIER’S INFORMATION SUPPLIER NAME: KANGPING VN ADRESS: 28 Dan Chu Street, VSIP 2 Industrial Park, Hoa Phu Ward, TDM, Binh Duong COUNTRY: Vietnam SUPPLIER PERSONEL PARTICIPATING Ms. Carina Mr. Henry Email: carina@chinahighspeed.net Email: mc-sale@vnkangping.com VISITORS PERSONEL Mr. Felix-NPI Email: synam.ho@ttigroup.com.vn Mr. Peter Email: CongHieu.Tran@ttigroup.com.vn MOTOR INFORMATION EB Sample Motor 742307004 (Lot May.18th 2023) © Techtronic Industries Co. Ltd. All rights reserved. 3 2. PRODUCT OVERVIEW Rotor 5/23/2023 Stator NPI @ Techtronic Industries Vietnam Motor 4 3. PROCESS OVERVIEW Winding coil Rotor Assembly A01 A02 Coating Glue, Press commutator A01 A04 Spot Welding A06 A07 A09 A08 Griding Comutator Coating glue of commutator A03 Cleaning copple chips R04 Insert ball bearing Insert carbon brush Insert the oil plate M02 M01 Insert Rotor into stator NOTE: A: Rotor processes R : Stator processes M: Motor assembly Process 5/23/2023 A05 Balancing Magnetization A02 Insert V Shape & Magnets Motor Assembly A03 Coating Glue & drying Stator Assembly Coating glue & Insert cooling Fan Functions check 1 M03 Pre-running motor Insert magnetic ring M04 Reviting at back cover M05 M06 M07 Cheking dim’s output shaft NPI @ Techtronic Industries Vietnam Engraving output shaft Load test M08 No Load Test M09 M10 M11 Engraving date code 5 A01- Insert commutator Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 Coating glue of commutator A05 Press commutator Add glue commutator Items Check Process product Spec Actual Result The commutator angle 14 ~ 16° 15.64° Pass Temperature dry glue 145±10°C 143 °C Pass 45~60 minutes 60 minutes Pass Coating glue & Insert cooling Fan A06 Griding Comutator A07 Time dry A08 Pull out force of commutator 30Kgf Min 110, 120kgf Pass Twist torque of commutator 1N.m Min 2.93 N.m Pass 68.2±0.1 mm 68.26 mm Pass Rotor Balancing Cleaning copple chips A09 commutator inserting dimension © Techtronic Industries Co. Ltd. All rights reserved. 6 A02- Winding Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Tensile winding Functions check 1 A04 Coating glue of commutator A05 Coating glue & Insert cooling Fan A06 Items Check Griding Comutator A07 Rotor Balancing A08 Cleaning copple chips A09 Winding Process product Spec Actual Result Ø0.65*16T Ø0.65*16T Pass Winding tensile 25~30N 21 N FAIL Wire deformed 5% max. 4.1, 4.2 % Pass Spray test 24V/60S/10mA 24V/60S/10mA Pass Resistance bar-bar 0.065~0.076 Ω 0.0660, 0.0688 Ω Winding Pass Spray test © Techtronic Industries Co. Ltd. All rights reserved. 7 A03- Welding Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 welding Coating glue of commutator A05 Coating glue & Insert cooling Fan A06 Griding Comutator A07 Rotor Balancing A08 Cleaning copple chips A09 Process product Items Check Spec Actual Result Size of welding rod 0.24~0.30mm 0.28 mm Pass Wire diameter change single coil 20~40% 33% Pass Wire diameter change double coil 20~50% 36 % Pass © Techtronic Industries Co. Ltd. All rights reserved. 8 A04- Rotor integration testing Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 Coating glue of commutator A05 Coating glue & Insert cooling Fan A06 Griding Comutator A07 NG master sample Rotor test Rotor Balancing A08 Cleaning copple chips A09 Items Check Spec Actual Result Resistance bar-bar 0.0508~0.0687Ω 0.0627 Ω Pass High voltage test AC600V/1s/1mA AC600V/1s/1mA Max Wave deformed Welding resistance OK test result Pass 15% Max/AC600V 8.3 % Pass 0.05Ω Max 0.015 Pass © Techtronic Industries Co. Ltd. All rights reserved. Master sample 9 A05- Coating glue of commutator Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 Coating glue of commutator A05 Coating glue & Insert cooling Fan Items Check Spec Actual Result Weight of varnish 1.5~2.0g 1.682 g Pass Weight of glue commutator 1.0~1.4g 1.210 g Pass Time bake glue 60 minutes 60 minutes Pass Temperature add varnish 75~95° 82 Pass 100~110° 103 Pass 130~150° 145 Pass OK test result A06 Griding Comutator A07 Rotor Balancing A08 Cleaning copple chips NG master sample Rotor test A09 Temperature freeze glue Temperature dry glue © Techtronic Industries Co. Ltd. All rights reserved. Rotor cut check glue inside -> OK 10 A06- Coating glue & Insert cooling Fan Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 Coating glue of commutator A05 Add glue slot Items Check Spec Actual Result 0.4~0.8g 0.68 g Pass Pull out force fan 15Kgf Min 90 Kgf Pass Time bake glue 60 minutes 60 minutes Pass Length of slot glue 10~14mm 12 mm Pass Temperature dry glue 145±10°C 145 Pass Weight of slot glue Coating glue & Insert cooling Fan Add fan Add protect fan A06 Griding Comutator A07 Rotor Balancing A08 Cleaning copple chips A09 © Techtronic Industries Co. Ltd. All rights reserved. Process sample 11 A07- Grinding commutator Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 Coating glue of commutator A05 Coating glue & Insert cooling Fan Turning commutator Process sample Items Check Spec Actual Result Roughness of commutator Ra 0.6~1.0um 0.73 um Pass Flatness of commutator 5um Max 2.75 um Pass Bar to bar 3um Max 1.18 um Pass Length of turning 7.0 mm Min 7.32 mm Pass Diameter commutator turning 7.4 mm Min 7.52 mm Pass A06 Griding Comutator A07 Rotor Balancing A08 Cleaning copple chips A09 © Techtronic Industries Co. Ltd. All rights reserved. 12 A08/A09- Rotor balancing/ Visual check Rotor Assembly Coating Glue, Press commutator A01 Winding coil A02 Spot Welding A03 Functions check 1 A04 Coating glue of commutator A05 Coating glue & Insert cooling Fan Griding Comutator Rotor Balancing Rotor balance Items Check Spec Actual Result 30mg max 9.1 mm Pass Deep cut 0.9mm Max 0.78 mm Pass Length of cut 9.6 mm Max 8.6 mm Pass By CCD camera CCD camera Pass Unbalance spec A06 A07 A08 Check visual of rotor Cleaning copple chips Process sample Visual check A09 © Techtronic Industries Co. Ltd. All rights reserved. 13 R01- Insert magnet Stator Assembly Insert V Shape & Magnets A01 Coating Glue & drying A02 Insert ball bearing A03 Magnetization R04 Insert magnet Items Check The deep of magnet Inner diameter of magnet Stator sample Spec Actual Result 17.1±0.5mm 16.96 mm Pass Ø25.8mm Min check 100% by gauge Pass © Techtronic Industries Co. Ltd. All rights reserved. inner diameter of magnet 14 R02- Add glue magnet Stator Assembly Insert V Shape & Magnets A01 Coating Glue & drying A02 Insert ball bearing A03 Magnetization R04 Add magnet glue Items Check Weight of magnet glue Push force magnet Temperature dry glue Time dry glue Stator sample Spec Actual Result 0.1 ~0.2g 0.134 g Pass 150Kgf Min 225 Kgf Pass 145±10°C 143 °C Pass 45~60 minutes 60 minutes Pass © Techtronic Industries Co. Ltd. All rights reserved. 15 R03- Ball bearing press Stator Assembly Insert V Shape & Magnets A01 Coating Glue & drying A02 Stator sample Add magnet glue & press ball bearing Insert ball bearing A03 Items Check Magnetization R04 Spec Actual Result Weight of magnet glue 0.003~0.01g Coating by hand Fail Push force bearing 70Kgf Min 132 Kgf Pass 55.4±0.1 mm 55.40 mm Pass Dimension press bearing © Techtronic Industries Co. Ltd. All rights reserved. 16 R04- Magnetic flux loading Stator Assembly Insert V Shape & Magnets A01 Coating Glue & drying A02 Insert ball bearing Magnetization stator A03 Items Check Magnetization The voltage magnetic R04 The voltage of magnetization Center force of magnet Flux of stator Spec Actual Result 1800V±50V 1850 V Pass 115±5mT 112 mT Pass 10.8±0.2 mWb 10.69 mWb Pass © Techtronic Industries Co. Ltd. All rights reserved. 17 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test Load test M07 M08 M01 - Insert the oil plate Insert washer intor rotor shaft Items Check Commutator site Visual check Actual Result OK Pass 1 pcs temple 0.5mm OK Pass 55.2mm REF 55.38 Pass 1 pcs oil shield long 4 pcs 0.4mm Copper ring site M09 Copper ring site Engraving date code Spec Commutator site M10 M11 Length of rotor after insert washer © Techtronic Industries Co. Ltd. All rights reserved. Fixture check 18 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 M02- Insert rotor to stator Insert sample to fixture Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor M07 No Load Test M08 Load test M09 Engraving date code Press machine Process sample Items Check Spec Actual Result The leght of output shaft 13.2 ±0.5 mm 13.30 mm Pass M10 Check out shaft dimension Visual check M11 © Techtronic Industries Co. Ltd. All rights reserved. 19 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor M03- Insert Carbon brush Add base ass’y to motor M07 No Load Test M08 Load test M09 Engraving date code M10 Visual check M11 Add cover Station’s requirement: ❖ Insert base ass’y correct position on motor → Actual: OK ❖ Insert cover correct position on motor → Actual: OK ❖ Check visual of motor → Actual: OK © Techtronic Industries Co. Ltd. All rights reserved. 20 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test Load test Engraving date code Engraving output shaft M07 M08 M04 - Reviting at back cover Finish goods Press Machine Items Check Number point reviting Push force Spec Actual Result 8 points OK Pass 50 kfg Min 108 kgf Pass 42 ±0.15 mm 41.98 mm Pass M09 Out side diameter of motor M10 Finish goods M11 © Techtronic Industries Co. Ltd. All rights reserved. 21 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test Load test M07 M08 M05 - Insert magnetic ring Process product Insert Magnetic Ring Items Check Spec Actual Result The leghth of magnetic ring insert 3.5 mm Min 4.72 Pass 0.5 ±0.1 Mpa Not shown Fail Air Pressure M09 Engraving date code M10 Visual check M11 © Techtronic Industries Co. Ltd. All rights reserved. 22 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test Load test M06 – Cheking dim’s output shaft Checking;s Fixture M07 M08 Items Check Spec Actual Result The height of ouput shaft 13.2±0.5 mm 13.45 mm Pass M09 Engraving date code M10 Visual check M11 © Techtronic Industries Co. Ltd. All rights reserved. 23 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M07 – Pre-running motor Time setting Fixture put Motor Voltage setup M06 Items Check Pre-running motor M07 No Load Test M08 Load test M09 Voltage running Engraving date code M10 Visual check M11 Time setting Direction Spec Actual Result 18.0±0.1V DC 18.09 V Pass 60s 60s Pass CCW Check by hand Pass © Techtronic Industries Co. Ltd. All rights reserved. 24 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test Load test Engraving date code M08 – No load test Fixture Items Check Spec Actual Result Current running 1.70A MAX 1.29 A Pass Voltage running 18±0.1V DC 18.0 V Pass 17550~21450 rpm 19765 rpm Pass 10s 10s Pass CCW CCW Pass Machine testing M07 M08 M09 Speed Time check M10 Direction Visaul check Check direction by hand M11 © Techtronic Industries Co. Ltd. All rights reserved. 25 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test M09 – Load test Items Check Spec Actual Result Current running 12.5A MAX 8.9 A Pass Voltage running 18±0.1V DC 18.0 V Pass 17000±10%RPM 19165 rpm Pass 6s 6s Pass CCW CCW Pass M07 M08 Load test M09 Engraving date code M10 Speed Time check Direction Visaul check Machine testing Check direction by hand M11 © Techtronic Industries Co. Ltd. All rights reserved. 26 Motor Assembly Insert the oil plate M01 Insert Rotor into stator M02 Insert carbon brush M03 Reviting at back cover M04 Insert magnetic ring M05 Cheking dim’s output shaft M06 Pre-running motor No Load Test Load test M07 M10/ M11 - Motor engraving, Visual check Station’s requirement: ❖ Part no for engraving M08 M09 Engraving date code M10 Visual check M11 Motor sample engraving Motor engraving 742307004 01 RS655PM6516F 18VDC KPVN xxxxxx → Actual: OK ❖ Check visual of motor → Actual: OK © Techtronic Industries Co. Ltd. All rights reserved. 27 4. IMPROVEMENT POINT FOR BUILD EB SAMPLE © Techtronic Industries Co. Ltd. All rights reserved. 28 5/23/2023 NPI @ Techtronic Industries Vietnam 29