GE Renewable Energy – Original – Technical Documentation Wind Turbine Generator Systems 3MW Platform - 50 & 60 Hz Bolt Torque Specification 2018 - Revision 11 3MW Platform: 2.X Gen 0 (PMG): 2.3- (94) & 2.5- (88) 2.X Gen 1 (PMG): 2.5- (100,103) & 2.75- (100,103) 2.X Gen 2 (DFIG): 2.5- (100,103,120); 2.75- (100,103,120); 2.85- (100,103) 3.x DFIG: 3.x- (103,120,130,137) imagination at work © 2017 General Electric Company. All rights reserved. GE Renewable Energy – Original– Visit us at www.gerenewableenergy.com All technical data is subject to change in line with ongoing technical development! Copyright and patent rights This document is to be treated confidentially. It may only be made accessible to authorized persons. It may only be made available to third parties with the expressed written consent of General Electric Company. All documents are copyrighted within the meaning of the Copyright Act. The transmission and reproduction of the documents, also in extracts, as well as the exploitation and communication of the contents are not allowed without express written consent. Contraventions are liable to prosecution and compensation for damage. We reserve all rights for the exercise of commercial patent rights. 2018 General Electric Company. All rights reserved. GE and the GE Monogram are trademarks and service marks of General Electric Company. Other company or product names mentioned in this document may be trademarks or registered trademarks of their respective companies. imagination at work Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification Table of Contents 1 General ............................................................................................................................................................................................................... 5 1.1 Purpose .................................................................................................................................................................................................... 5 1.2 Restrictions ............................................................................................................................................................................................. 5 1.3 Lubrication ............................................................................................................................................................................................. 7 1.3.1 Restrictions ........................................................................................................................................................................................ 7 1.3.2 Application ........................................................................................................................................................................................ 7 1.3.3 Preferred Lubricants ..................................................................................................................................................................... 7 1.4 Tools .......................................................................................................................................................................................................... 7 1.5 Bolt Torque Requirements ............................................................................................................................................................... 8 1.5.1 Preparation........................................................................................................................................................................................ 8 1.5.2 Generic Process .............................................................................................................................................................................. 8 1.5.3 Marking Fasteners ......................................................................................................................................................................... 9 1.5.4 Visual Inspections of Torqued/Tensioned Fasteners ..................................................................................................... 9 1.5.5 Inspection of Fasteners with Thread Locking Compound ...................................................................................... 10 2 Testing and Torque Instructions for Bolted Connections .......................................................................................................... 11 2.1 Instructions for the 10 % Installation Inspection for Bolted Connections (excluding blade bolts) – Installation Inspection, BIM & Maintenance ....................................................................................................................................... 11 2.2 Instructions for Manual and Hydraulic/Electronic Torque-Controlled Tightening for the Annual Maintenance (other than Blade Connections) ................................................................................................................................... 12 2.3 Axial Hydraulic Tensioning of Foundation Anchor Bolts.................................................................................................. 13 2.3.1 Instructions for the Hydraulic Tightening of Anchor Bolts During Assembly or Refurbishment (Only if foundations are within GE´s scope) ................................................................................................................................................... 14 2.3.2 Instructions for the Hydraulic Testing of Anchor Bolts During Maintenance ................................................... 16 2.4 Typical Tower and Tower to Yaw Bearing Bolt Requirements...................................................................................... 19 2.4.1 Tower Flange Torque – Installation ..................................................................................................................................... 19 2.4.2 Tower Flange Torque – BIM and Maintenance ............................................................................................................... 20 2.5 Typical Nacelle Connection Requirements .......................................................................................................................... 21 2.5.1 Modular Nacelle ........................................................................................................................................................................... 21 2.5.2 BTP Nacelle ..................................................................................................................................................................................... 22 2.6 Typical Rotor Shaft/Hub Bolt Requirements......................................................................................................................... 24 2.7 Blade to Pitch Bearing Bolts Tightening Procedure .......................................................................................................... 27 2.7.1 Blade to Pitch Bearing Bolts Tightening Procedure – Only Down-Tower ........................................................ 27 2.7.2 Blade to Pitch Bearing Bolts Tightening Procedure for Single Blade Installation - ONLY Up-Tower .. 28 2.7.3 Instructions for Bolt Installation Inspection (10 % of Blade Bolts) ....................................................................... 29 2.7.4 Maintenance of Blade to Pitch Bearing Connection .................................................................................................. 30 2.8 Electrical Connections .................................................................................................................................................................... 35 2.8.1 Transformer Cable Terminals ................................................................................................................................................ 35 2.9 Tightening of the Tensioning Nuts for the Generator Elastic Mounts ....................................................................... 36 2.10 How to Determine Torque Associated with Pre-Loads.................................................................................................... 38 3 Torque Values............................................................................................................................................................................................... 39 3.1 Safety-Relevant Bolt Connections (Component Torque Chart) ................................................................................. 39 3.2 Electrical Connections – Tightening Torque ........................................................................................................................ 46 3.2.1 Standard Connections - Electrical ...................................................................................................................................... 46 3.2.2 Terminal Bolt Torque for Battery Connections (in Hub) ............................................................................................ 46 3.2.3 Transformer Cable Terminals ................................................................................................................................................ 47 3.2.4 Permanent Magnet Generator (PMG) Cabinets ............................................................................................................ 48 3.2.5 Doubly Fed Induction Generator (DFIG) Cabinets ....................................................................................................... 49 3.3 Standard Connections – Mechanical ...................................................................................................................................... 50 4 Tightening Torque Conversion Charts ............................................................................................................................................... 51 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx x GE Power & Water 5 – Original – Bolt Torque Specification 4.1 Tightening Torques Mentioned in Section 3 ......................................................................................................................... 51 Appendix(es) .................................................................................................................................................................................................. 51 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. x Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 1 General 1.1 Purpose This document defines the torque or tensioning requirements for all bolts used within the assembly, erection, and maintenance of a 3MW Platform Wind Turbine Generator System (WTGS). This does not apply for customer provided components. 1.2 Restrictions Specifications/requirements may change at any time, check for updates prior to performing operations. It is NOT acceptable to re-use previously torqued or tensioned hardware for components listed in table 3.1 “Safety-Relevant Bolt Connections (Component Torque Chart)“unless specified within the re-use column or otherwise approved by GE Engineering. Unauthorized re-use of fasteners may cause them to fail. Unless otherwise indicated by a Non-GE design requirement, Non-GE manufacturer requirement, or an update from within GE, all hardware must be torqued to values indicated in the component torque chart in section 3. Torque values defined on assembly drawings or assembly specifications from other vendors may supersede the values indicated in this document. If in doubt consult GE Energy. ATTENTION For all level 1 components connections: Base Flange-To-Anchor bolt, Tower Flange-to-Tower Flange, Top Tower Flange-To-Yaw Bearing, Rotor-To-Hub Adaptor, & Rotor Blade-To-Pitch Bearing. 1) Mixing of fastener hardware (bolt, washer & nuts) between manufacturer's is not authorized on each fastener location. 2) Two different manufacturer's fasteners may be used on one joint with no more than 10 % of the fasteners being from the second manufacturer. Requirements for re-use of fasteners: If any condition is not met the hardware must be replaced. A) Joint must not be loose and no more than 10 % of fasteners fail maintenance torque check. B) No indication of prior re-use (punch mark or paint). No cracks, deformation (bending or stretching), and no galling/deformation/damage on threads/washer. C) Nut must be able to be run by hand over the threads above/through/below the engaged area. Fasteners listed as single re-use have the following additional requirements: A) No indication of prior re-use (as documented below) B) Required documentation: i. Entry made in turbine log and written message on joint indicating re-use. If fasteners are replaced at later time, then line out message on joint with date and make entry into turbine log. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 5/51 GE Renewable Energy ii. – Original – Bolt Torque Specification Stud ends are colored in with paint pen and if studs are exposed to weather the end must additionally be marked by hitting it with a punch to indicate re-use. Figure 1: Proper installation of a chamfered washer Figure 2: Wedge locking washer (e.g. Nordlock) and installation CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 6/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 1.3 Lubrication 1.3.1 Restrictions Lubrication must not be used when the fasteners are attached to or near electronic equipment unless specified by the specific drawing or assembly procedure. Lubrication must only be used in cases where indicated on the torque specification table. 1.3.2 Application Remove any debris or contaminant and ensure that the threads are clean prior to applying. Use an appropriate cleaner on all threads of the threaded holes to remove contaminants. When lubrication is used, ensure that the lubricant completely covers the bolt threads and that there is 360 ° coverage. Do not apply lubricant underneath the bolt head, on the washer faces, or on the nut faces. 1.3.3 Preferred Lubricants The lubricant must demonstrate and allow for uniform application and even distribution on threads. Use of lubricants not provided here may create significant risks. Only use lubricants identified within the Lubricant List. 1.4 Tools CAUTION Prevent Personnel Injury! Hydraulic or electronic torque tools must react off other turbine components. It is vital to keep hands and body parts in appropriate locations away from these reaction points to prevent crush and pinch injuries. ATTENTION Only calibrated tool systems with a maximum torque tolerance of ± 6 % must be used! The contractor for projects & installation, will have additional requirements that outlined in the installation manual which include, but are not limited to, daily tool calibration checks. To check measuring and test equipment for damage and accuracy prior to each use. This is to ensure the measuring equipment has not suffered deterioration in accuracy, prior to its next calibration expiration date. Consult the installation manual for additional information. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 7/51 – Original – GE Renewable Energy Bolt Torque Specification ATTENTION Prevent damage to the WTGS! Pressure, force, resistance, torque, distance, voltage, amperage and measuring tools shall be calibrated against standards traceable to the National Institute of Standards and Technology (NIST) measurement standards or ISO/IEC 17025 in accordance with ISO 10012 or ANSI and all applicable local and national standards. 1.5 Bolt Torque Requirements 1.5.1 Preparation 1. Ensure threads are clean and free of debris or burrs. 2. Check the flange surfaces for burrs and high spots or any foreign debris and correct as needed. 3. Where required, apply lubrication to the following areas: z All threads of a bolt for complete coverage. z Do not apply lubrication underneath the bolt head. NOTE This does not apply to tower bolts as the nuts are lubricated by the supplier nor does it apply to torque controlled blind holes. There you must lubricate the bolt head underneath, except for the underside pitch bearing stud bolt heads which should not be lubricated. 4. Thread bolts/nuts by hand for the first 4 threads to ensure proper thread engagement. 1.5.2 Generic Process 1. If 18 or more bolts are arranged in a circular pattern, use the following tightening sequence. Number all bolt sequentially per Figure 11 or sequentially in three groups (e.g. 1-22, 1-21, 1-21). 2. Unless otherwise indicated on the appropriate drawing, hardware must be torqued to values indicated in section 3. 3. Torque values defined on the face of other vendor assembly drawings or assembly specifications may supersede the values indicated in this document (cf. component torque chart in section 3). If in doubt, please consult with GE Engineering. 4. During initial installation and major component exchange, torque bolts according to star-cross-pattern unless otherwise described. 5. Do not perform torque check on same bolt until all bolts have been inspected. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 8/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 1.5.3 Marking Fasteners 1. All torqued bolts must be marked with a single straight unbroken line running down the side of the bolt head, across the washer and onto the clamped part, with a permanent or oil-based marker. 2. For installation, blue is preferable for a first torque and always use red for torque inspections. Figure 3: Example tower flange bolt markings 1st final torque final torque + 60 ° Figure 4: Proper torque marking of fastener final torque + 90 ° final torque + 120 ° final torque + 150 ° final torque + 180 ° Figure 5: Example bolt marking for torque + angle fasteners Note: Under certain circumstances, the stud or bolt may rotate slightly while being tensioned. This is not necessarily a problem unless spelled out with a specific limit in this document. The final marking will look slightly different than those images above. 3. If threadlock is applied to fastener (outside of manufacturing), make circular mark on fastener head in addition to standard marking. 1.5.4 Visual Inspections of Torqued/Tensioned Fasteners Inspect each fastener for the following conditions: Corrosion – note and report to GE Representative Defects – unusual or unexpected wear Movement: Inspect existing mark on torqued fastener If no visual movement, no further action is required If indication of movement or the mark is illegible/missing, it is necessary to perform physical torque check on individual fastener to maintenance values stated in sections 3 and 4. If there was excess movement (> 20°) when performing this torque check, it is necessary to torque check 100 % of the fasteners on the flange. If more than 10 % of the total count of the connections nut/bolt can be turned more than 20° the angle needs to be recorded and contact your GE representative so Engineering/Product Service Engineering can be informed. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 9/51 GE Renewable Energy – Original – Bolt Torque Specification Figure 6: Torque marking – acceptable movement <20 ° 1.5.5 Inspection of Fasteners with Thread Locking Compound Note: This process does not apply to any fastener larger than M24. Any critical joint covered in section 3 of this document does not apply either (unless specifically identified). 1. Perform visual inspection of fastener per section 1.5.4. (Note: All glued (thread locker – i.e. LOCTITE) fasteners should have torque marks applied during manufacture or commissioning.) 2. Check hand tight (or small hand wrench far below fastening torque) to ensure that bolt has not sheared in place. 3. If fastener shows no indications of movement from steps 1 and 2, no further actions are required. 4. Corrective actions if fastener has moved: Remove existing fastener. Re-use or replace fastener depending on criticality or condition of fastener. Apply adequate thread lock compound (if not pre-applied on new fastener). Reinstall fastener and apply proper torque per section 3 of BTS or assembly drawings. Mark newly applied fastener per section 1.5.3. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 10/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 2 Testing and Torque Instructions for Bolted Connections 2.1 Instructions for the 10 % Installation Inspection for Bolted Connections (excluding blade bolts) – Installation Inspection, BIM & Maintenance 1. A sample of 10 % of the bolts evenly distributed over the bolt reference circle is required on all connections after the rotor has been installed and the complete compression load is on the tower. The same bolts should not be checked during consecutive inspection cycles. 2. Do not loosen the bolts and, using a hydraulic or torque wrench/spanner, pre-tighten to the referenced maintenance torque values as required. 3. If the nut/bolt can be turned beyond the original marked position by more than 20 ° (see Figure 7) using the maintenance torque value, all bolts in the circle must be inspected and torqued to specification as identified in the Maintenance torque values without unscrewing the bolts. If during an Installation Inspection any bolt is found loose or not torque marked, all bolts in the circle must be inspected and torqued as required. 4. This is only required for Projects Installation: Note the date and name of the inspector on the flange that was inspected and mark a line on the bolt to indicate the 10 % inspection was completed. 5. If more than 10 % of the total count of the connections nut/bolt can be turned more than 20° the angle need to be recorded and contact your GE representative so Engineering/Product Service Engineering can be informed. Figure 7: Torque marking – acceptable movement < 20 ° CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 11/51 GE Renewable Energy – Original – Bolt Torque Specification 2.2 Instructions for Manual and Hydraulic/Electronic Torque-Controlled Tightening for the Annual Maintenance (other than Blade Connections) ATTENTION All bolts have to be tightened in greaseless condition. Don’t use any lubricant. 1. If no specific instructions, choose 10 % of the bolts at random and mark (see Figure 8). Do not perform torque check on same bolt until all bolts have been inspected. 2. Do not loosen bolts and, using a hydraulic screwdriver or torque spanner, pre-tighten to the reference maintenance torque (see section 3). 3. If a nut/bolt can be turned by more than 20 ° (see Figure 9) beyond its original position, all bolts must be pre-tightened again with the required maintenance torque without unscrewing the bolts. 4. If more than 10 % of the total count of the connections nut/bolt can be turned more than 20° the angle need to be recorded and contact your GE representative so Engineering/Product Service Engineering can be informed. Figure 8: Torque marking Figure 9: Acceptable movement < 20 ° CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 12/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx – Original – GE Renewable Energy Bolt Torque Specification 2.3 Axial Hydraulic Tensioning of Foundation Anchor Bolts NOTE Follow the foundation designer’s maintenance recommendations. NOTE This section also applies to the anchor bolts installed. The tightening/check is carried out around the circumference in a clockwise direction. Bolt no. 1 is located at the bottom longitudinal weld and must be permanently marked, so that it can be identified as no. 1 in subsequent measurements. This procedure applies to both the inner and outer anchor bolts. Figure 10: Axial hydraulic tightening of foundation anchor bolts CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 13/51 GE Renewable Energy – Original – Bolt Torque Specification 2.3.1 Instructions for the Hydraulic Tightening of Anchor Bolts During Assembly or Refurbishment (Only if foundations are within GE´s scope) (Initial Tightening or Re-tightening) The required pretension force can be found in the respective foundation design specification. 1. Apply the required pretension force to the bolts. 2. Mark the tightened bolts. 3. Note the applied pretension force on the tower flange at bolt no. 1 (using a waterproof pen). The following data must be documented for the initial or re-tightening of the anchor bolts: Project name Pad/WTGs Number Date performed GIB number Identification of the tool used (pump, cylinder) with serial number and calibration date Bolt designation and information Design tensioning force (kN/KIPS) Operator (e.g. personnel number) Final pretension force or elongation CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 14/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx – Original – GE Renewable Energy Bolt Torque Specification The specimen report "Anchor Bolt Tension Record" provided below shows the scope of the documentation. Anchor Bolt Tension Record Site Name: WTG: Maintenance cycle: Tool type/model: Design tension (KIPS): Serial number: Target Nut Displacement: Calibration Date: kN: Bar: Inside Flange Outside Flange Date Performed: Date Performed: Wind Speed: Temperature: Wind Speed: Temperature: Bolt # Movement Bolt # Movement Bolt # Movement Bolt # Movement Bolt # Movement Bolt # Movement 1 36 71 1 36 71 2 37 72 2 37 72 3 38 73 3 38 73 4 39 74 4 39 74 5 40 75 5 40 75 6 41 76 6 41 76 7 42 77 7 42 77 8 43 78 8 43 78 9 44 79 9 44 79 10 45 80 10 45 80 11 46 11 46 12 47 12 47 13 48 13 48 14 49 14 49 15 50 15 50 16 51 16 51 17 52 17 52 18 53 18 53 19 54 19 54 20 55 20 55 21 56 21 56 22 57 22 57 23 58 23 58 24 59 24 59 25 60 25 60 26 61 26 61 27 62 27 62 28 63 28 63 29 64 29 64 30 65 30 65 31 66 31 66 32 67 32 67 33 68 33 68 34 69 34 69 35 70 35 70 Technician Signature: Date: CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 15/51 GE Renewable Energy – Original – Bolt Torque Specification 2.3.2 Instructions for the Hydraulic Testing of Anchor Bolts During Maintenance NOTE These instructions provide an example of testing and reporting instructions. Depending on contractual requirements and local/national requirements, this inspection may be different. Refer to your maintenance contract to determine what elements are included in the scope of supply. Please obtain the required pretension force from the specific foundation design specification. The following data must be documented for the anchor bolt maintenance: z Site name z Date z Tower/pad # z Maintenance cycle z Wind speed z Temperature z Tool type/model, serial number, and calibration date z Design tension (kN/KIPS) z Bolt designation z Names of technicians performing check z Nut movement NOTE Do not release the pre-tension of the bolts beforehand! NOTE Maintenance pre-tension load values and inspection requirements are based on 95 % of the site-specific installation value. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 16/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification NOTE Pre-tension load values and inspection requirements are solely dependent on the foundation design criteria. Do not deviate from the foundation design criteria found in the foundation design documentation. NOTE Intervals may be superseded by the specific foundation design documentation. If design documents deviate from this cycle, it is required to follow those designs. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 17/51 GE Renewable Energy – Original – Bolt Torque Specification 2.3.2.1 Generic Tension Requirement – Non-GE Foundations Maintenance on Non-GE designed foundations may vary in scope, tension value and frequency. The detailed inspection and verification process will be obtained from the foundation design engineer, whether already recorded in the design drawing or via a letter from the engineering firm. The customer may be required to provide this information prior to scoping, quoting and performing the maintenance checks. 2.3.2.2 Generic Tension Requirement – GE Foundations If any anchor bolt does not pass the directed maintenance checks the appropriate corrective action must be followed as defined in section 2.3.2.3. Break-in Maintenance Pre-tensioning of 100 % of the anchor bolts to 100 % of the site-specific installation value is required during break in maintenance unless specified differently per foundation design. Subsequent Maintenance Cycles Check the pre-tensioning value of the anchor bolts on the inner and outer flange and mark (at 95 % tension value). Pre-tensioning is performed annually for the first 5 years, and once every 3 years thereafter unless specified differently per foundation design. 2.3.2.3 Corrective actions for failed checks – GE Foundations If any anchor bolt does not pass the check (indication of any movement), then 100 % of the anchor bolts on that flange (inner or outer) must be checked (at 95 % tension value). If 10 % of the anchor bolts on either flange (inner or outer) do not pass, then 100 % of the anchor bolts on the opposite flange must be checked (at 95 % tension value). Any anchor bolt that does not pass the check must be tensioned to 100 % of the site-specific installation value. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 18/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 2.4 Typical Tower and Tower to Yaw Bearing Bolt Requirements 2.4.1 Tower Flange Torque – Installation Typical Bolt (Star/Crossover Pattern) First round installation torque: Start with 3 groups evenly distributed over the flange. Each group with 5 bolts in a row (Blue pattern in Figure 11). Following bolts may be installed in sequence. Second round installation step (torque or angle, as applicable) can be applied in sequence. ATTENTION Different tower flanges require different torque values! Ensure correct torque values are selected from the component torque chart in section 3. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 19/51 GE Renewable Energy – Original – Bolt Torque Specification 2.4.2 Tower Flange Torque – BIM and Maintenance Start at one location and continue evenly spaced around the flange until all selected nuts have been torqued. Figure 11: Example for typical tower flange numbering scheme (green) and sequence for first round installation torque (blue). Applicable for tower-to-tower L-flanges and to yaw bearing. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 20/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 2.5 Typical Nacelle Connection Requirements 2.5.1 Modular Nacelle Connections for the roof panels: Figure 12: Connections for the roof panels (modular nacelle) In all connections except for 5A, B and C all M12 bolts connecting the roof panels to the steel structure have to be checked with 7.5 Nm. In connections 5A and 5C the M12 rods are also to be torqued with 7.5 Nm. In connections 5B all threaded rods with one nut on top and one nut below bracket have to be checked with 25 Nm. First check lower nut, then check upper nut! All four threaded rods should be checked for correct installation and correct hardware: CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 21/51 GE Renewable Energy – Original – Bolt Torque Specification Latches on the cable hatch on the third roof panel: For torque tightening specifications, please refer to the component torque chart in section 3. Figure 13: Latches on cable hatch 2.5.2 BTP Nacelle The locations identified in Figure 14 and Figure 15 must be torqued according to the values in the component torque chart in section 3. Connections for the nacelle enclosure: Figure 14: Connections for the nacelle enclosure (BTP nacelle) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 22/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification Connections for the roof panels: Figure 15: Connections for the roof panels (BTP nacelle) Latches on the cable hatch: For torque tightening specifications, please refer to the component torque chart in section 3. Figure 16: Latches on cable hatch CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 23/51 GE Renewable Energy – Original – Bolt Torque Specification 2.6 Typical Rotor Shaft/Hub Bolt Requirements Figure 17: Typical hub adapter (sequential circular/pattern) – 48 & 52 fasteners hubs (2500 & 2570RE) Figure 18: Hub adapter (double row sequential circular/pattern) – 90 fastener hubs (2900) Installation of 48 Stud Hub (2500 hub, 88, 94, 100, 103): 1. Maintain a minimum of 90 % of the rotor weight on the crane. 2. Align the main shaft and rotor/hub with the crane and impact all nuts to ensure there is no gap between the flanges prior to tightening the nuts. 3. Install between 18 and 24 nuts to the initial torque value. 4. Release the crane. 5. Engage the hydraulic disc brake and rotor lock when installing washers and nuts. 6. Torque-check the first 6 nuts to the initial torque value. If no movement (< 1/3 of a flat) move on to step 7, otherwise recheck all the installed nuts. 7. Roll the rotor either CW or CCW to access the next set of nuts. 8. Engage the hydraulic disc brake and rotor lock when installing washers and nuts. 9. Once 24 nuts are installed the rotor may be rolled to access the next 8 nuts. Tighten the nuts in a sequential pattern by starting immediately after the last one tightened in the previous set. 10. Continue rolling the rotor to access 8 nuts at a time and tighten to the initial torque value, continue the sequential pattern. 11. Repeat step 9 as necessary until you reach the first set of nuts installed. Torque-check all accessible nuts to the initial torque value and then apply the angle, continue the sequential pattern. 12. Roll the rotor to access the next set of accessible nuts installed. Torque-check these nuts to the initial torque value and then apply the angle, continue the sequential pattern. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 24/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 13. Roll the rotor to access any remaining nuts. Torque-check these nuts to the initial torque value and then apply the angle, continue the sequential pattern. 14. Perform 10 % torque check to the maintenance torque value. Installation of 48/52 Stud Hub (2570/2570RE (rear entry) Hub, 2.0 MW ~ 107, 116, 127, 132): 1. Maintain a minimum of 90 % of the rotor weight on the crane. 2. Align the main shaft and rotor/hub with the crane and impact all nuts to ensure there is no gap between the flanges prior to tightening the nuts. 3. Install and tighten at least 32 nuts to the initial torque value. 4. Release the crane. 5. Engage the hydraulic disc brake and rotor lock when installing washers and nuts. 6. Torque check the nuts installed to the initial torque value. 7. Roll the rotor/hub either CW or CCW to access the remaining nuts. 8. Engage the hydraulic disc brake and rotor lock when installing washers and nuts. 9. Install and tighten remaining nuts to the initial torque value. 10. Torque-check the remaining nuts to the initial torque value. 11. Roll the rotor back to the original position. 12. Torque check first 6 nuts installed to the initial torque. If any move, torque-check all 32. 13. Apply the angle to all 32 nuts. 14. Roll the rotor/hub to access the remaining nuts installed. 15. Apply the angle to the remaining nuts. 16. Perform 10 % torque check to the maintenance torque value. For Installation and Re-assembly for 2900RE, Rotor shaft – Hub (Adaptor) Refer to 3.1 Component Torque Chart Section, for torque values & degree turns) 1. Maintain a minimum of 90 % of the rotor weight on the crane. 2. Align the main shaft and rotor/hub with the crane and ensure there is no gap between the flanges prior to tightening the nuts. 3. Install at least 50 nuts for the 2900 to the installation value given in torque chart – pen mark the nut positions starting with 1st nut tightened on the flange. 4. Release the crane. 5. Torque-check all accessible nuts to the installation value given in torque chart. 6. Roll the rotor either CW or CCW (~105 °) to access the next set of nuts (while ensuring adequate fastening at the top of the joint). 7. Install all remaining nuts to the installation value given in torque chart (alternate between rolling rotor and securing nuts). 8. Roll the rotor to access the first 50 nuts for the 2900 installed and torque check these first nuts in sequential pattern. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 25/51 GE Renewable Energy – Original – Bolt Torque Specification 9. Roll the rotor/hub to access the remaining nuts, torque checking these nuts. 10. Apply the additional degree nut turn given in torque chart to the initial 50 nuts for the 2900 fasteners in a sequential pattern starting at one end. 11. Roll the rotor in the same direction to access the remaining nuts installed and apply the additional degree nut turn to these fasteners continuing immediately after the last one tightened in the previous set. 12. Perform 10 % torque check to maintenance value; refer to 3.1 Component Torque Chart section. NOTE The installation process was designed for the 48/52 fastener hubs (2500, 2570 & 2570RE) on 2.5-100/103 and 2.5-120 units respectively. For the 90-fastener hub (2900) on the 3.2-130, the process remains the same except for the ability to access additional fasteners at any one time. When installing the 2900 hub, access to the initial ~50 fasteners will take the place of the 32 (referenced in the work steps above). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 26/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx – Original – GE Renewable Energy Bolt Torque Specification 2.7 Blade to Pitch Bearing Bolts Tightening Procedure 2.7.1 Blade to Pitch Bearing Bolts Tightening Procedure – Only Down-Tower Follow approximate pattern as illustrated in groups of three: z 10 o’clock three bolts z 2 o’clock three bolts z 8 o’clock three bolts z 4 o’clock three bolts z 9 o’clock three bolts z 3 o’clock three bolts Figure 19: Torque the bolts as illustrated in groups of three and in between the pattern NOTE For installation and major component exchange: All bolts must be lubricated per the Lubricant List. Prior to applying pre-torque value, all nuts must be installed and impacted in the specified pattern on all three blades. 1. Apply pre-torque (check table in section 3.1) to these bolts and to the remaining bolts in between the pattern. Continue pattern until all bolts are pre-torqued. 2. Pitch the blades to expose remaining studs and install washers and nuts. 3. Continue pattern and pre-torque all remaining hardware. 4. After all bolts have been pre-torqued proceed with degree nut turn, refer to 3.1 Component Torque Chart section for the correct degree turn value. 5. Continue pattern to torque the exposed bolts between the 7 to 9 and 2 to 4 o’clock positions. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 27/51 GE Renewable Energy – Original – Bolt Torque Specification 2.7.2 Blade to Pitch Bearing Bolts Tightening Procedure for Single Blade Installation - ONLY Up-Tower The procedure below must be followed to tighten the bolts of the blade to pitch bearing joint: 1. Install all exposed blade nuts on blade 1 using impact gun in 3 o’clock position, achieving a torque between 50-95 % of the final pre-torque value specified in the Work Instructions for the bolted connections. (Pitch and yaw movement not allowed) 2. Release the tool from blade (Pitch and yaw movement not allowed) 3. Turn blade 1 to 6 o’clock position using turn drive tool. (Pitch and yaw movement not allowed) 4. With Blade 1 at 6 o´clock put all remaining bolts with impact gun using pitch to get to the remaining bolts. When all bolts are torqued achieving a torque between 50-95 % of the final pre-torque value specified in the Work Instructions for the bolted connections, park the blade in idling position (90 deg pitch) Pitch and yaw movement are allowed again when torque is applied to all bolts. 5. Apply final torque and nut turn to each bolt with blade pointing down (6 o’clock position) as described in the following: Mark the first bolt to be tightened. Loose each nut and apply the specified pre-torque (check table in section 3.1) to all the bolts in the circle following a sequential order (one by one, per the sequence in Figure 20 left). Once the whole circle is completed, continue to re-apply the specified pre-torque to the bolts in the initial half of the circle (one by one, per the sequence in Figure 20 right). Mark all pre-torqued bolts (white), to ensure that 1.5 circles are torqued. 6. 7. Apply the specified nut turn to all the bolts in the circle (one by one, per the sequence in Figure 20 left), mark all bolts as usual. 8. Turn Hub, lifting blade 2, repeat sequence step 1-7 9. Turn Hub, lifting blade 3, repeat sequence step 1-7 10. When 100% of 3 blades bolts are torqued and degree turn is applied, crane can be de-commissioned Figure 20: Blade to pitch bearing bolts tightening sequence: circular torqueing or nut turn of all the bolts in the circle (left) and only half the bolts in the circle (right). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 28/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification BIM and Maintenance In case one or more bolts are found loose, the following repair procedure must be followed. z z z If one nut is loose, the two adjacent bolts -the one on the left and the one on the right- must be replaced If two nuts in a row are loose, the four adjacent bolts -two on the left and two on the right- must be replaced If five nuts in a row are loose, ten adjacent bolts -five on the left and five on the right- must be replaced In case loose nuts and bolts are being detected during BIM (break-in maintenance) or thereafter, note the bolt position and open a PAC case. Loose bolts must be reinstalled using thread locker as specified. NOTE For installation and major component exchange: All bolts must be lubricated per the Lubricant List. 2.7.3 Instructions for Bolt Installation Inspection (10 % of Blade Bolts) 1. After completion of the rotor assembly, proceed to bolt installation inspection. Complete the 10 % inspection of the bolts, evenly distributed over the bolted circle of the blades following the 3 Torque Chart value. This should be performed with approved tooling or with a manual torque wrench to ensure that no bolts are drastically under-tensioned. This inspection must be performed on the three blades. ATTENTION This torque value is never used for final torque. Mark these 10 % of the bolts with a red paint pen. 2. If any nut moves more than 3 mm measured tangent to the washer edge (allowing for some flex of the bolt shank), an error has occurred during installation. In this case, the nut must be fully loosened and all installation, pre-torque and nut turn steps must be repeated on the affected nut. Then repeat step 1 but inspecting 100 % of the bolts and repeat this step as applicable. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 29/51 – Original – GE Renewable Energy Bolt Torque Specification 2.7.4 Maintenance of Blade to Pitch Bearing Connection NOTE After loosening blade nuts but prior to re-tensioning, ensure blade bolts have not backed out from blade assembly. ATTENTION A maximum of three non-sequential nuts per blade may be loosened at any given time with rotor blades in any position (one if using an electronic torque tool). ATTENTION Perform the hub entry procedure. Apply necessary LOTO to axis cabinets to prevent movement of the blades. 2.7.4.1 Break-in Maintenance Blade bolts break-in maintenance procedure is described below: 1. Visually inspect all hardware. If any nuts have misaligned paint marks document the position and estimated degree of movement of affected bolts. NOTE Under normal conditions, the bolt tension may decrease through seating of the bolt, but it is not normal for nuts to actually rotate on the bolt due to operation. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 30/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification Figure 21: Example of nut markings at installation (A), 1 month (B), and annual maintenance (C) (Stickers are a local practice - verify local and national regulations) 2. Loosen up to three nuts at a time in any position of the joint. 3. Ensure blade bolts have not backed out from blade assembly. If the bolt / T-bolt moves when removing a nut, follow instructions in section 2.7.4.3. 4. Apply 100 % of the pre-torque value specified in Component Torque Chart section 3.1 to every nut in one operation. Nuts may be torqued in any order but ensure that no steps are missed on any nuts. NOTE It is common for the nuts to rotate 0 to 20 degrees beyond the earlier torque mark. 5. Apply the corresponding nut turn angle to all of the loosened nuts with an accuracy of +/- 5 degrees or approximately 4 mm at the nut corner. Right after, perform alignment marks across bolt end, nut, and surrounding bearing surface before proceeding to the next nut to avoid losing track of the nuts that have been torqued as the blade is pitched for access to all bolts. NOTE Steps 4-5 above are performed in one operation when using an electronic torque tool and require that nuts are re-torqued one at a time. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 31/51 GE Renewable Energy – Original – Bolt Torque Specification Once all accessible bolts have been re-torqued it will be necessary to pitch the blades to gain access to the bolts behind the axis boxes. 6. Repeat steps 1-4 until all bolts on all blades have been properly torqued. 7. Document position and estimated degree of movement of any nuts that have a final position more than 30 degrees or half a flat away from the previous position. Contact the GE representative with details. 2.7.4.2 Annual Maintenance 1. Visually inspect 100 % of hardware. If any nuts have misaligned paint marks document the position and estimated degree of movement of affected bolts. 2. Check 10 % of the nuts evenly distributed along the bolt circle. Position the blades to be re-tensioned at the 6:00, 10:00 and 2:00 o’clock rotor position (rabbit eared position). NOTE Under normal conditions, the bolt tension may decrease through seating of the stud, but it is not normal for nuts to actually rotate on the bolt due to operation. Figure 22: Example of nut markings at installation (A), 1 month (B), and annual maintenance (C) (stickers are a local practice - verify local and national regulations) 3. Loosen one to three nuts evenly spaced around the bolt circle. The nuts should be taken off, the threads relubricated and the nuts re-applied until they are finger tight. 4. Ensure blade bolts have not backed out from blade assembly. If movement occurs, follow instructions in section 2.7.4.3. 5. Apply 100 % of the pre-torque value specified in the Component Torque Chart section 3.1 to every nut in one operation. Nuts may be torqued in any order but ensure that no steps are missed on any nuts. 6. Apply the corresponding nut turn angle to all of the loosened nuts with an accuracy of +/- 5 degrees or approximately 4 mm at the nut corner. Right after perform alignment marks across each bolt end, nut, and CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 32/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification surrounding bearing surface before proceeding to the next nut to avoid losing track of the nuts that have been torqued as the blade is pitched for access to all bolts. NOTE It is common for the nuts to rotate 0 to 20 degrees beyond the earlier torque mark. NOTE Steps 5-6 above are performed in one operation when using an electronic torque tool and require that nuts are re-torqued one at a time. Figure 23: Applying 120-degree nut turn Figure 24: Non-permissible deviation (>20) 7. Once all accessible bolts have been re-torqued it will be necessary to pitch blades to gain access to bolts behind the axis boxes. 8. Repeat steps 2-6 until all bolts on all blades have been properly torqued. 9. If any of the nuts checked during the annual 10 % bolt check presents a rotation larger than 30 degrees beyond their initial position (nut to flange mark), 100 % of the bolts in the joint will be checked. 10. Document the bolt position and estimated degree of rotation of those nuts having a final rotation larger than 30 degrees, or half a flat away, from the previous position. Contact a GE representative with details. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 33/51 – Original – GE Renewable Energy Bolt Torque Specification 2.7.4.3 Blade Bolt Movement Correction This procedure is to be performed if a blade bolt / T-bolt is found loose or loosens during the nut removal. Ensure that the bolt is seated in the barrel nut or bushing. 1. Remove bolt from blade assembly. NOTE If the hole in the blade and the hole in the bearing no longer align preventing the removal of the bolt: f Position the blade in the 6 o’clock rotor position, then try to adjust blade position to bearing to align the holes and allow for removal of the bolt. f If the blade to bearing adjustment cannot be made, once the bolt has been loosened from the barrel nut, the barrel nut may be moved/removed from the blade (depending on blade design). 2. Inspect bolt and barrel nut or bushing threads for damage. NOTE f If the barrel nut was removed, inspect the threads of the bolt as it travels through the barrel nut hole. 3. Clean the bolt threads with degreaser. 4. Apply adequate permanent thread locking compound (i.e. LOCTITE 277) to the blade end of the bolt and then assemble. NOTE Ensure that the bolt is seated in the barrel nut or bushing: f Bolt should be screwed in to match the stud protrusion of bolts of neighboring bolts. Studs on LM inserts do not bottom out. f Apply adequate torque values (range) per table in section 3.1 to obtain proper bolt seating. 5. Inspect the threads of the bearing end of the bolt and nut. 6. Clean the exposed bolt threads with degreaser. 7. Apply appropriate lubricant as described in section 1.3 Lubrication. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 34/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification ATTENTION Ensure no lubricant gets applied to the bearing surface. This can impact the clamping force applied to the bearing and blade structure 8. Reinstall bolts at appropriate torque values per table in section 3.1. 9. Apply circular mark on the bolt end face using permanent mark to indicate that thread locker has been applied to the bolt. NOTE Reinstalling blade bolt removes original torque mark reference and does not allow for the 30deg reference for torque marking check. NOTE If a blade bolt moves during nut removal, it is not necessary to check all the bolts in the flange. 2.8 Electrical Connections NOTE For fasteners not specified in section 3.2.4 ‘Electrical Connections,’ use standardized torque values from 3.2.1 2.8.1 Transformer Cable Terminals ATTENTION All electrical connections are to be torqued without lubricant! NOTE For Non-GE supplied transformers follow the manufacturer’s maintenance recommendations. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 35/51 GE Renewable Energy – Original – Bolt Torque Specification 2.9 Tightening of the Tensioning Nuts for the Generator Elastic Mounts Figure 26: Functional principle of the tensioning nut Figure 25: Assembly situation The complete tensioning nut consists of a nut (pos. 1), washer (pos. 2) and pressure bolts (pos. 3). The pressure bolts (Figure 25, pos. 3) in the tensioning nut may not protrude from the nut on the pressure side (see Figure 27). 1. Slip on the washer (Figure 25, pos. 2) and then screw on the nut (Figure 25, pos. 1) and fasten finger tight. Figure 27: Screwing out the nut ATTENTION All components must rest against each other without a gap. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 36/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx – Original – GE Renewable Energy Bolt Torque Specification 2. Next screw out the nut (Figure 25, pos. 1) by approx. a quarter turn. (this results in a gap of approx. 1 mm). 3. First, fasten the M 10 pressure bolts marked in Figure 28 (pos. 1, 2, 3, 4) finger tight. 4. Then, tighten the M 10 pressure bolts to 13 Nm. 5. In the next pass tighten the M 10 pressure bolts to 26 Nm. 6. Next, tighten all eight pressure bolts one after another in several passes, until all bolts have been tightened to the requisite torque of 26 Nm. Figure 28: Tightening the pressure bolts 7. Apply torque marking on the individual pressure bolts and the entire assembly to the clamped flange per section 1.5.3. Figure 29: Completely assembled tensioning nut NOTE The pressure bolts may not abut with the bearing face after the assembly (Figure 29). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 37/51 GE Renewable Energy – Original – Bolt Torque Specification 2.10 How to Determine Torque Associated with Pre-Loads Depending on regional installation and major component exchange requirements, use this procedure to determine torque associated with pre-loads (if applicable). Field adjustable, calibrated torque wrenches must be used to tighten all tower flange bolts. Steps 1 through 9 must be performed at a minimum daily for each bolt size and grade. 1. A calibrated preload device, capable of use with the installation hardware shall be used. (I.E. Skidmore test) 2. Follow all guidelines specified by the manufacturer of the device. 3. Select at random, three-bolts, washer, and nut (bolt set-up). 4. Use a steel spacer that matches the thickness of bolted tower flange for use with the tensioning pre-load device. 5. Determine the torque value required for each of the bolt, washer, and nut sets selected to obtain the pretension value specified in the Component Torque Chart. 6. Average the resulting three torque values and use this average for all tensioning for that day unless the restrictions imposed in step 8 occur. 7. Torque associated with preload results values must be recorded by installer in 3 locations: Daily Log, ICL and Tower wall next to the flange bolts for future reference with date to indicate proper torque was completed. 8. This procedure will be repeated if the temperature changes by more than 20 degrees or weather conditions change (rain stop and start, etc.). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 38/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 3 Torque Values 3.1 Safety-Relevant Bolt Connections (Component Torque Chart) Connection Tower anchor bolts Hybrid tower concrete – steel (see Appendixes) Mat. -No./Type Per foundation designer specification Bolt Size Number - - - Per foundation designer specification Instruction Re-use Allowed Yes Identification the hybrid tower type, Reference the vendor specific documents (designer spec) in PLM for Installation & maintenance of Hybrid-tower anchor. Yes 104W5057 M64 444W4984 100 M56 444W4984 90 M48 444W4984 80 M42 444W4984 70 M36 444W4984 105W1931P010 standard washers 60 60 Max 9000 Nm See footnote 2 1st round 1400 Nm 2nd round 2800 Nm See footnote 1 1st round 1920 Nm 2nd round +90° (± 10°) - M36 Max 13000 Nm See footnote 2 1st round 2250 Nm 2nd round 4500 Nm See footnote 1 1st round 3100 Nm 2nd round +90° (± 10°) - 104W5057 Max 20000 Nm See footnote 2 1st round 3250 Nm 2nd round 6500 Nm See footnote 1 1st round 4450 Nm 2nd round +90° (± 10°) - 104W5057 Max 30000 Nm See footnote 2 1st round 5000 Nm 2nd round 10000 Nm See footnote 1 1st round 6850 Nm 2nd round +90° (± 10°) - 104W5057 1st round 7500 Nm 2nd round 15000 Nm See footnote 1 1st round 10300 Nm 2nd round +90° (± 10°) - 104W5057 st First Installation Per foundation designer specification Tower flanges (see Figure 11) Tower head – yaw bearing Maintenance Nut Size 55 Max 5600 Nm See footnote 2 1500 Nm + 60° (± 5°) See footnote 1 15000 Nm No BIM: +15° (+5°) See footnote 2a No BRM: 15000 Nm 10000 Nm No BIM: + 15° (+5°) See footnote 2a No BRM: 10000 Nm 6500 Nm No BIM: + 15° (+5°) See footnote 2a No BRM: 6500 Nm 4500 Nm No BIM: + 15° (+5°) See footnote 2a No BRM: 4500 Nm 2800 Nm No BIM: + 15° (+5°) See footnote 2a No BRM: 2800 Nm 2500 Nm No nd 1 round 50 % of final torque; 2 round 100 % of final torque. 2 In case the target angle of 90° is not reached within max torque value; contact GE representative for Engineering/Product Service resolution 1 2a Target angle of 15° might not be reached within max torque value specified for installation. Acceptable angles between 0° and 15° (+5°). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 39/51 GE Renewable Energy – Original – First Installation 60 55 1500 Nm + 150° (± 5°) See footnote 1 2500 Nm No M36 60 55/60 1500 Nm + 90° (± 5°) 2500 Nm No M36 60 55/60 2400 Nm + 120° (± 5°) 3800 Nm No M36 70 55/60 2400 Nm + 120° (± 5°) 3800 Nm No M36 5 x 12 55 2800 Nm Tectyl conservation 2800 Nm Yes M36 5 x 12 55 3500 Nm Tectyl 3500 Nm Yes M24 4 x 24 19 1000 Nm 1000 Nm Yes 444W5078P001 M24 4 x 28 19 1000 Nm 1000 Nm Yes - - - - - Visual Check Yes Upper part main frame – Bottom part main frame 105W1931P020 M39 119 60 2500 Nm + 90° (± 5°) 3300 Nm No Bearing cover 1 – Main frame (rotor side) L14EP33100M11 L14EP33110M11 M24 20 36 See footnote 3 See footnote 4 Yes 1500 Nm + 90° (± 5°) 2500 Nm 2400 Nm + 120° (± 5°) 3800 Nm 2400 Nm + 120° (± 5°) 3800 Nm (see Figure 11) Yaw bearing –main frame Hydraulic yaw brake caliper – main frame Yaw drive – bed plate Yaw motor –gearbox Rotor shaft – Hub (Adaptor) (see Figure 17) Low-speed rotor lock mounting Number 105W1931P010 Wedge locking (Nordlock) washers M36 444W3498P001 Standard washers Maintenance Nut Size Connection Bolt Size Bolt Torque Specification Mat. -No./Type 115W2238P015 Wedge locking (Nordlock) washers 444W3498P001 Wedge locking (Nordlock) washers 105W1931P011 standard washers 105W1931P011 Wedge locking (Nordlock) washers ISO 4762 M24 x 120 - 10.9 2.x – 100, 103 2500 Standard Washers 2.x – 100, 103 2500 Wedge Locking 2.x – 103, 120 2570 Wedge Locking 2.x – 120 2570RE Wedge Locking 3.x – 130, 137 2900RE Fine Thread & Thick Washers 3.X-130, 137 2900RE Coarse Thread Wedge Locking M16 x 90 – 8.8 48 M36 48 55 48 Instruction Re-use Allowed See note below See note below See note below See note below M39 52 60 3500 Nm + 120° (± 5°) 4700 Nm M36 90 55 2400 Nm + 240° (± 5°) 2800 Nm See note below M36 90 55 2400 Nm + 120° (± 5°) 3800Nm See note below M16 8 24 210 Nm 210 Nm Yes 1st round: vertical position, 500 Nm; 2nd round: horizontal position, 1000 Nm. In any case, the assembly must be done by slow relative rotation between main shaft and main frame. 3 The torque support gearbox nuts, studs and spacers may be re-used 3 times after the initial tightening. The studs shall be clearly marked to identify the number of times they have been re-torqued and shall be replaced after a total of 4 torque sequences. 4 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 40/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy Bolt Size Number N/A N/A Flange – Main shaft 105W1932P001 Flange – Gearbox Bolt Torque Specification Maintenance Nut Size First Installation 1 19 200 Nm 200 Nm Yes M36 20 - 1500 Nm + 90° (± 5°) - No 105W1932P001 M36 24 - 1500 Nm + 90° (± 5°) - No Flange main shaft Flange gearbox 105W1931P004 M36 58 55 1500 Nm + 90° (± 5°) 2500 Nm See note below Shrink disc shaft – Gearbox N/A M33 32 N/A installation process to obtain flush face 2210 Nm Yes 114W2773P001 M36 16 55/60 1500 Nm + 270° (± 15°) see footnote 4 & 5 2500 Nm Yes M20 x 55 DIN 6912 M20 2x4 17 464 Nm ± 23 Nm 464 Nm ± 23 Nm Yes M16 x 55 DIN 6912 M16 2x4 14 150 Nm ± 15 Nm 150 Nm ± 15 Nm Yes 105W1931P010 M36 2 55 2800 Nm 2800 Nm Yes - M24 4 36 730 Nm 730 Nm Yes All - - - per supplier document per supplier document Yes L217P37B normal nut M30 4 46 1200 Nm 1200 Nm Yes 107W6497P001 tensioning nut M10 4x8 I6 See section 2.9 26 Nm Yes - M20 16 30 450 Nm with thread lock compound Visual Check with thread lock compound No - - 3x4 - 15 Nm Visual - 105W1931P016 M36 20 55 1500 Nm + 90° (± 5°) 2500 Nm No L114AP21060M11 M12 - 19 86 Nm 86 Nm No L114AP29040M11 M20 - 30 410 Nm 410 Nm No Connection Manual low - Speed rotor lock operation Torque support Gearbox – Main frame Main bearing groove nut – Lock screw Brake – Gearbox Mat. -No./Type High-speed rotor lock mounting bolts High speed coupler Generator damper Damper generator Generator frame DFIG generator Pfisterer plug Generator frame – Main frame Spinner – Hub (N/A 3.2-130 + design) 5 – Original – Instruction Re-use Allowed The torque support gearbox studs need to be installed properly in order to ensure proper fitment. To do so please follow these steps: • Hand tighten each torque support gearbox stud to the end of the thread. • Turn each torque support gearbox stud 360° back. • Start with tighten procedure. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 41/51 GE Renewable Energy Connection Nose cone step assembly – Hub (N/A 3.2-130 + design) Pitch bearing Hub Mat. -No./Type Grade 10.9 w/Nordlock Table 3.3 for others Pitch drive - Hub Pitch motor Gearbox Rotor Blade – Pitch bearing: 10 % inspection Rotor blade - Pitch bearing GE blade designs First Installation 3 30 410 Nm 3 x 70 55 1500 Nm + 120° (± 5°) Instruction 410 Nm 2500 Nm M36 3 x 91 55/60 3 x 104 1500 Nm + 150° (± 5°) 2500 Nm + 180° (± 5°) 3.3 Standard Connections Mechanical 3.3 Standard Connections Mechanical Re-use Allowed Yes See note below No 2800 Nm No See note below See note below 3 x 32 17 3.2-130 M16 3 x 28 24 All others - ISO 4762 M16 x 120 M16 3 x 18 14 295 Nm 295 Nm Yes 3.2-130 L15DP25070 M16 3 x 18 14 295 Nm 295 Nm Yes All others - ISO 4014 M12 x 35 - 8.8 VZ M12 3x4 18/19 84 Nm + Loctite 243 Visual Check Yes 3.2-130 L114AP25050 M16 3x4 24 210 Nm + Loctite 243 Visual Check Yes All configurations - - - 10 % @ 1000 Nm 1000 Nm Yes M36 3 x 68 60 500 Nm + 120° (± 5°) 500 Nm + 120° (± 5°) Yes 550 Nm + 120° (± 5°) 550 Nm + 120° (± 5°) 200 Nm 210 Nm GE 43 GE 46 (see Figure 19) (Apply spray lubricant per Lubricant List) GE 50.2 Without stiffener M20 Maintenance Nut Size M12 GE 48.7 LM blade designs Number Bolt Torque Specification All other configuration Without stiffener Rotor blade – Pitch bearing Bolt Size All others (2500) 102W1404P001 2.5-120 (2570) 115W2238P011 and P014 3.2-130 (2900) 444W0229P00 Axis cabinets Hub – Original – LM 45.7p 3 x 68 LM 48.7p LM 58.7p 550 Nm + 120° (± 5°) M36 3 x 92 60 500 Nm + 120° (± 5°) LM 63.7p (see Figure 19) (Apply spray lubricant per Lubricant List) LM 67.2p/p2/p3 Rotor blade – Pitch bearing (0.1m stiffener) All GE blades 3 x 104 M36 LM design 48.7 3 x 68 60 550 Nm + 120° (± 5°) 500 Nm + 120° (± 5°) Yes 550 Nm + 180° (± 5°) 550 Nm + 180° (± 5°) 500 Nm + 150° (± 5°) 500 Nm + 150° (± 5°) Yes 550 Nm 550 Nm Yes CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 42/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy Connection Rotor blade – Pitch bearing (0.3m stiffener) Blade studs to blade/barrel nut assembly Mat. -No./Type All blade designs – Original – Bolt Size M36 Number 3 x 68 Bolt Torque Specification Nut Size 60 GE Design M36 - N/A LM Design Maintenance First Installation Instruction + 150° (± 5°) + 150° (± 5°) 750 Nm + 180° (± 5°) 750 Nm + 180° (± 5°) 250 Nm + Loctite 277 See footnote 6&7 See footnote 6, 7 & 8 If applicable + Loctite 277 See footnote 6&8 See footnote 6, 7 & 8 108W5114P001 M30 3 46 60 Nm + Loctite 243 See footnote 9 Visual Check See footnote 9 (see Figure 12, Pos. 1) Ejot self-drilling screw JT3 6.0 x 36 6 48 - 5 Nm 5 Nm (see Figure 12 Pos. 2a, 2b, 4a, 4b) Ejot self-drilling screw JT3 5,5 x 2 5.5 112 - 5 Nm 5 Nm M12 4 19 7.5 Nm 7.5 Nm M12 7 19 7.5 Nm 7.5 Nm Nose cone safety tie- off eyebolt Re-use Allowed Yes Yes Yes No Modular Nacelle (see Figure 12, Pos. 1) (see Figure 12, Pos. 3a) DIN 931 M12 x 160 - 8.8 hot dip galvanized DIN 931 M12 x 140 - 8.8 (see Figure 12, Pos. 2a, 2b) DIN 931 M12 x 100 – 8.8 M12 16 19 7.5 Nm 7.5 Nm (see Figure 12, Pos. 4a, 4b) DIN 931 M12 x 100 – 8.8 M12 2 19 7.5 Nm 7.5 Nm (see Figure 12, Pos. 6a, 6b) DIN 931 M12 x 90 - 8.8 M12 2 19 7.5 Nm 7.5 Nm (see Figure 12, Pos. 5a, 5c) DIN 931 M12 x 50 - 8.8 M12 2 19 7.5 Nm 7.5 Nm (see Figure 12, Pos. 2a, 2b) DIN 931 M10 x 150 - 8.8 M10 12 17 49 Nm 49 Nm (see Figure 12, Pos. 2a, 2b, 4a, 4b, 6a, 6b) DIN 931 M10 x 140 - 8.8 M10 12 17 49 Nm 49 Nm (see Figure 12, Pos. 3a, 3b) DIN 931 M10 x 50 - 8.8 M10 16 17 49 Nm 49 Nm (see Figure 12, Pos. 5b) Threaded rod M10 - 8.8 M10 4 17 49 Nm 49 Nm See note below In cases of reinstalling LM designed blade studs, contact GE Representative. All blade studs when reinstalled will require LOCTITE 277 or equivalent permanent thread lock compound. 6 Installation of blade stud may require higher torque application to ensure adequate seating and thread engagement – maximum values up to 500 Nm may be applied. 7 8 Bolt should be screwed in to match the stud protrusion of bolts of neighboring bolts. Studs on LM inserts do not bottom out. 9 Thread-locker applied to all joints – checks to be performed per section 1.5.5 of this document. For installation, adapter placed hand tight on bolt. Initial nut on bolt torqued to 120 Nm, locking nut bound to first nut and eye bolt attached to other end of adapter at 60 Nm. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 43/51 GE Renewable Energy Connection Mat. -No./Type – Original – Bolt Size Number Bolt Torque Specification Maintenance Nut Size First Installation Instruction (see Figure 12, Pos. 3a, 3b) DIN 931 M8 x 150 - 8.8 M8 8 13 hand tighten hand tighten (see Figure 12, Pos. 5b) DIN 931 M8 x 35 - 8.8 M8 8 13 hand tighten hand tighten - M16 24 24 210 Nm visual - 72 - 5 Nm 5 Nm M16 48 24 140 Nm 140 Nm M12 24 19 86 Nm 86 Nm M12 33 19 86 Nm 86 Nm M10 M10 17 49 Nm 49 Nm M10 M10 17 49 Nm 49 Nm M10 M10 17 49 Nm 49 Nm Nacelle crane rail mount Re-use Allowed BTP nacelle Ejot self-drilling screw JT3 5.5 x 25 See Figure 14, Pos. 2) (see Figure 14, Pos. 1) (see Figure 14, Pos. 1) (see Figure 14, Pos. 1) screw, hex cap, M16 x 60, hot dip zinc screw, hex cap, M12 x 1.75 x 65, hot dip zinc screw, hex cap, M12 x 1.75 x 55, hot dip zinc screw, hex cap, M10 x 1.5 x 60, hot dip zinc screw, hex cap, M10 x 1.5 x 50, hot dip zinc screw, hex cap, M10 x 1.5 x 30 (see Figure 14, Pos. 3 and 4) screw, hex cap, M8 x 1.25 x 35 M8 M8 13 25 Nm 25 Nm (see Figure 15, Pos. 5 and 6) screw, hex cap, M6 x 1.0 x 30 M6 M6 10 hand tighten hand tighten - M16 24 24 140 Nm visual Nacelle Crane Rail Mount See note below CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 44/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification Re-use Allowed NOTE A single re-use of these fasteners is approved if all of the following conditions are met. If any condition is not met the hardware must be replaced. A) Joint must not be loose and no more than 10 % of fasteners fail maintenance torque check. B) No indication of prior re-use (punch mark or paint). No cracks, deformation (bending or stretching), and no galling/deformation/damage on threads/washer. C) Nut must be able to be run by hand over the threads above/through/below the engaged area. Required documentation: Entry made in turbine log and written message on joint indicating re-use; if studs replaced at later time then line out. Stud ends are colored in with paint pen and if studs are exposed to weather the end must additionally be marked by hitting it with a punch to indicate re-use. Break-In-Maintenance NOTE For all fasteners for any connection that becomes loose or replaced due to maintenance, repair & component upgrade, one must follow all Break-InMaintenance requirements listed in the Bolt Torque Specifications. Any connection effected by such work should begin a new set of BIM intervals and be recorded In the WTG log. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 45/51 GE Renewable Energy – Original – Bolt Torque Specification 3.2 Electrical Connections – Tightening Torque 3.2.1 Standard Connections - Electrical Size Grade 5.8 8.8 10.9 12.9 IN lbs Ncm IN lbs Ncm IN lbs Ncm IN lbs Ncm M1.6 1 11.3 1 11.3 1 11.3 2 22.6 M1.9 1 11.3 1 11.3 2 22.6 2 22.6 M2 1 11.3 2 22.6 3 33.9 4 45.2 M2.2 2 22.6 3 33.9 4 45.2 5 56.5 M2.5 2 22.6 4 45.2 6 67.8 8 90.4 M3 4 45.2 8 90.4 11 124.3 13 146.9 M3.5 7 79.1 12 135.6 17 192.1 20 226 M4 10 113 18 203.4 25 282.5 30 339 M5 20 226 35 395.4 50 564.9 59 666.6 Ft lbs Nm Ft lbs Nm Ft lbs Nm Ft lbs Nm M6 3 4.1 6 8.1 9 12.2 10 14 M7 6 8.1 10 14 14 19 17 23 M8 8 10.8 15 20.3 21 29 25 34 M10 17 23 29 39 41 56 50 68 M12 29 39 51 69 72 98 86 117 M16 - -- 126 170 185 250 - - Note: Torque values are for lubricated bolts. 3.2.2 Terminal Bolt Torque for Battery Connections (in Hub) Tightening Torque Battery Model in-lbs Nm 3EP & XE13 50 5.6 16EP & XE16 50 5.6 26EP & XE30 60 6.8 42EP & XE40 60 6.8 70EP & XE70 60 6.8 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 46/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 3.2.3 Transformer Cable Terminals Application Bolted joints at the bus Size M12 or M16 Torque 35 Nm +/- 5 or 80 Nm +/- 10 Notes Do not torque unless a major fault was detected or the bolt was loosened for another reason. Tap link and line lead connection M12 or M16 35 Nm +/- 5 or 80 Nm +/- 10 Do not strip the threads in the inserts that are cast in the winding. Core clamping hardware M16 120 Nm +/- 20 Torque core through bolts and external clamping bolts. Bolting core and coil assembly M24 or M20 or M16 to the base 230 Nm +/- 30 or 180 Nm +/- 30 or 90 Nm +/- 10 Do not over-tighten. Do not overcompress the vibration pads. Do not loosen or remove hardware after installation. Bolting the core clamp to the transformer base M24 or M20 or M16 Bolting the transformer base to the enclosure base M24 or M20 230 Nm +/- 30 or 180 Nm +/- 30 or 90 Nm +/- 10 230 Nm +/- 30 or 180 Nm +/- 30 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 47/51 GE Renewable Energy – Original – Bolt Torque Specification 3.2.4 Permanent Magnet Generator (PMG) Cabinets 3.2.4.1 Converter Cable Terminals Connection Name Asm. Torque Value in-lb (Nm) X1: L1, L2, L3 (line cable lugs) X3: L1, L2, L3 (generator cable lugs) 40 lbf-ft (54 Nm) @ M12 nut side (per UL486A-B; Table 24) X1: L1, L2, L3 (internal cables) 168 in-lb (19 Nm) @ M10 nut side LC: 1, 2, 3, 4, 5, 6 common mode reactor 168 in-lb (19 Nm) @ M10 nut side LL: 1, 2, 3, 4, 5, 6 line reactor 168 in-lb (19 Nm) @ M10 nut side SHA1_2_BUS, SHB1_2_BUS, SHC1_2_BUS converter line bus 168 in-lb (19 Nm) @ M10 nut side SHA2_2_BUS, SHB2_2_BUS, SHC2_2_BUS converter generator bus 168 in-lb (19 Nm) @ M10 nut side LG: 1, 2, 3, 4, 5, 6 generator reactor 168 in-lb (19 Nm) @ M10 nut side FUA, FUB, FUC generator fuse cable connections fuse connection at BUS 168 in-lb (19 Nm) @ M10 nut side 96 in-lb (11 Nm) @ M8 nut side X3: L1, L2, L3 (internal cables) 168 in-lb (19 Nm) @ M10 nut side E1, E2, E3, EGND 300 in 300 in-lb (34 Nm) @ ball stud 3.2.4.2 PDP Cable Terminals Connection Name Asm. Torque Value in-lb (Nm) entry cable lugs L1, L2, L3 55 lbf-ft (75 Nm) @ M16 nut side (per UL486A-B; Table 24) INTERNAL CONNECTIONS BUS & cable lug 420 in-lb (47 Nm) @ M12 nut side 504 in-lb (57 Nm) @ M12 bolt side 168 in-lb (19 Nm) @ M10 nut side 202 in-lb (23 Nm) M10 bolt side FUA, FUB, FUC line fuse BUS connections 168 in-lb (19 Nm) @ M10 nut side 96 in-lb (11 Nm) @ M8 nut side Thread 1,2,3,4; L1, L2, L3 line cable lugs 40 lbf-ft (54 Nm) @ M12 nut side (per UL486A-B; Table 24) 43Q1, 33Q1 NH 1 fuse holder lug connections 168 in-lb (19 Nm) @ M10 nut side CCFU1, CCFU2, 33Q2, 35F1,2,3 NH 0, 00 fuse holder lug connections 96 in-lb (11 Nm) @ M8 nut side 43Q1 distortion filter contactor 96 in-lb (11 Nm) @ M8 nut side DFR1, 2, 3 distortion filter resistor 168 in-lb (19 Nm) @ M10 nut side 420 in-lb (47 Nm) @ M12 nut side DFC distortion filter capacitor 180 in-lb (20 Nm) @ brass terminal stud CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 48/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 3.2.5 Doubly Fed Induction Generator (DFIG) Cabinets 3.2.5.1 Converter Cable Terminals Connection Name Asm. Torque Value in-lb (Nm) X2: LA, LB, LC (MV Transformer cable lugs) 54 Nm (480 in-lb) X2: RA, RB, RC (Rotor cable lugs) 54 Nm (480 in-lb) X2: AUXA, AUXB, AUXC (Aux Transformer cable lugs) 54 Nm (480 in-lb) PEN Connections (Gen Rotor, MV Transformer, Aux Transformer, Converter Frame, Walking Platform) 54 Nm (480 in-lb) AC Line Fuse Terminals (ACLFU1A-ACLFUC2) 47 Nm (420 in-lb) Distortion Filter Fuse Terminals (DFFUA/DFFUB/DFFUC) 47 Nm (420 in-lb) Auxiliary Feed Fuse Terminals (AUXFUA/AUXFUB/AUXFUC) 19 Nm (168 in-lb) Distortion Filter Capacitor Terminals (DFC1/DFC2: 1-3) 17 Nm (150 in-lb) 3.2.5.2 Low Voltage Distribution Panel Connection Name Asm. Torque Value in-lb (Nm) Ground Cables (XPE.2, XPE.3, XPE.6) 112 in-lb (16Nm) @M8 nut side 3.2.5.3 Stator Switch Cabinet Connection Name Asm. Torque Value in-lb (Nm) Line Connections: (L1, L2, L3) 442 in-lb (50 Nm) @ M12 nut side Load Connections: (L1, L2, L3) 442 in-lb (50 Nm) @ M12 nut side 3.2.5.4 Auxiliary Transformer Connection Name Asm. Torque Value in-lb (Nm) Mechanical Mounting points 86 Nm 690VAC Connections (H1, H2, H3) 54.0 Nm 400VAC Connections (X1, X2, X3) 27.12 Nm CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 49/51 GE Renewable Energy – Original – Bolt Torque Specification 3.3 Standard Connections – Mechanical 8.8 10.9 V4A stainless steel AISI 316 12.9 HV – (10.9) Nm ft lbf Nm ft lbf Nm ft lbf Nm ft lbf Nm ft lbf M5 6 4 9 6 10 7 -- -- -- -- M6 10 7 15 11 17 13 -- -- -- -- M8 25 18 36 27 41 30 -- -- -- -- M10 50 37 71 52 83 61 27 20 -- -- M12 87 64 124 91 145 107 50 37 100 74 M16 220 160 310 230 355 262 115 85 250 185 M20 420 310 600 440 690 509 -- -- 450 332 M24 730 540 1030 760 1200 886 -- -- -- -- M27 1050 775 1500 1107 1800 1328 -- -- -- -- M30 1450 1070 2000 1476 2400 1771 -- -- -- -- M36 2450 1808 3450 2546 4150 3063 -- -- -- -- CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. 50/51 Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx GE Renewable Energy – Original – Bolt Torque Specification 4 Tightening Torque Conversion Charts 1 Nm = 0.7376 ft lbf 1.356 Nm = 1 ft lbf 4.1 Tightening Torques Mentioned in Section 3 Nm ft lbf Nm ft lbf Nm ft lbf Nm ft lbf Nm ft lbf 84 62 295 218 620 457 2500 1844 10000 7376 105 78 315 232 720 531 2800 2065 15000 11064 200 148 450 332 800 590 3300 2434 210 155 500 369 1000 738 4500 3319 215 159 550 406 1500 1106 6500 4794 5 Appendix(es) Anchorbolt_Tensioning_ConcreteHybrid_G04 + G99: https://plm-wind.energy.ge.com/windplm/common/emxNavigator.jsp?targetLocation=content&objectId=15488.20533.53176.5424 Anchorbolt_Tensioning_ConcreteHybrid_G05: https://plm-wind.energy.ge.com/windplm/common/emxNavigator.jsp?targetLocation=content&objectId=15488.20533.60991.59783 Anchorbolt_Tensioning_ConcreteHybrid_G07: https://plm-wind.energy.ge.com/windplm/common/emxNavigator.jsp?targetLocation=content&objectId=15488.20533.36294.4073 Anchorbolt_Tensioning_ConcreteHybrid_G98: https://plm-wind.energy.ge.com/windplm/common/emxNavigator.jsp?targetLocation=content&objectId=15488.20533.53934.53108 Note: You may need to copy & paste link to address bar. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company and/or its affiliates. UNCONTROLLED when printed or transmitted electronically. © 2018 General Electric Company and/or its affiliates. All rights reserved. Bolt_Torque_Specification_3MW_xxHz_EN_r11.docx 51/51