NNPC GAS INFRASTRUCTURE COMPANY LIMITED ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC) OF PIPELINE INFRASTRUCTURE FOR ESCRAVOS ENVIRONS POWER SUPPLY PROJECT WORK METHOD STATEMENT FOR CROSSING USING THRUST BORING METHOD DOCUMENT NO: R01 16/04/2023 Issued for Review REV. DATE DESCRIPTION I. Mathew BY Client Project Contractor Discipline NGC EEPSP O. Charles CHECKED A. Abiodun APPROVED Doc. Type Sequence- Rev. Sheet Doc. Control No. YNL PIP WMS 0002 R01 This document contains information, which is for company use only. This information is to be held in confidence. Disclosure, reproduction, or other use of this document is prohibited without the prior written consent of CLIENT ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD Revision Date Description Remarks REVISION HISTORY Work Method Statement Civil Works Page 2 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD TABLE OF CONTENTS 1.0 PROJECT OVERVIEW 4 2.0 1.1 Project Objective 1.2 Scope DEFINITIONS / ABBREVIATIONS 4 4 4 3.0 2.1 REFERENCE DOCUMENTS ROLES AND RESPONSIBILITIES 5 5 4.0 MATERIAL REQUIRED FOR CIVIL AND STRUCTURAL WORKS Error! Bookmark not defined. 5.0 EQUIPMENT’S AND TOOLS AS PER SITE REQUIREMENT Error! Bookmark not defined. 6.0 WORK PROCEDURE 5 6.1 7.0 SURVEYING, WORK SEQUENCE FOR EXCAVATION. Error! Bookmark not defined. 6.2 SETTING OUT. Error! Bookmark not defined. 6.3 FORM WORKS Error! Bookmark not defined. 6.4 BLINDING WORKS. Error! Bookmark not defined. 6.5 CONCRETE PROCESS Error! Bookmark not defined. 6.6 CURING CONCRETE. Error! Bookmark not defined. 6.7 SITE CLEARANCE Error! Bookmark not defined. 6.8 SEQUENCE OF WORKS Error! Bookmark not defined. DEVIATIONS Error! Bookmark not defined. 8.0 QUALITY CONTROL 10 9.0 SAFETY 10 Work Method Statement Civil Works Page 3 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD 1.0 PROJECT OVERVIEW Nigerian National Petroleum Corporation NNPC through its Subsidiary Nigerian Gas Company (NGC) Limited intends to construct 6" x 5km and 4”X 2km gas pipelines that will transport lean gas from Chevron Escravos Gas Plant (CNL-EGP) and NPSC Utility pipelines respectively to EEPSP Plant within PPMC tank farm at Escravos. To this end invited competent contractors to bids for the EPC works for gas supply to the power generation plant at NPSC tank farm. 1.1 Project Objective The primary objective of the project is to supply gas by tie in at the 16” pipeline using the valve connection and 24” pipeline via hot tapping and construct a 6” spur line from the tiein point and also 4” at the 8” utility pipeline at NPSC Tank farm via hot tapping for the early gas phase, provide facility for filtering/separating any liquid and debris, heat and reduce the gas pressure ((PRMS) to (2- 4)bar that will be further reduced by the regulator to be provided for the gas driven generator. 1.2 Scope This Work Methods Statement (WMS) details the general requirements, applicable to sitespecific tasks, necessary to perform the thrust boring necessary for the crossing which is part of EEPSP LOT III project (pipeline). 2.0 DEFINITIONS / ABBREVIATIONS FATC…………………. First Aid Treatment Cases SM…………………. Site Manager PM…………………. Project Manager ITP…………………...Inspection & Test Plan QC…………………...Quality Control PQP…………………Project Quality Plan PPE…………………Personnel Protective Equipment Work Method Statement Civil Works Page 4 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD HSE…………………Health & Safety Environment 2.1 3.0 REFERENCE DOCUMENTS • Client’s Project Specifications • Relevant Project Drawings • Contractor/Company’s Project Quality Plan • Contractor/Company’s Field HSE Plan ROLES AND RESPONSIBILITIES Crossing using thrust boring method will be performed with all appropriate and certified equipment that will be managed under the supervision of an experienced and qualified Superintendent, according to this WMS. The qualified supervisor will coordinate and control the works during it realization. The following list include the personnel will be present during the activity, but not limited to this: • • • • • • • Supervisor Welders Grinders QC inspector (when necessary) HSSE supervisor Operators Helpers 4.0 WORK PROCEDURE 4.1 Preliminary works All necessary permissions and authorization shall be obtained from the relevant Authorities concerned before starting any work, including Permits to Work. All restrictions and provisions accompanying this approval shall be respected. The necessary traffic control measures for excavations left open during day and night, shall be implemented as required by the Risk Assessment and in conjunction with local Authority regulations. Work Method Statement Civil Works Page 5 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD Surveyor shall fix the center line of crossing prior to actual construction. 4.2 Pits construction The area for the Launching pit and receiving pit (if necessary) will be marked out, as per equipment dimensions or pipe installation. Ground levels may be reduced, stepped or battered to reduce pit depths. Temporary fences to limit the pits area will be placed by CONTRACTOR. 4.3 Boring operation 4.3.1 Installation of Boring Equipment The Thrust Boring equipment consists of a Thrust / Auger Boring Machine, base frame with rails, steel jacking shield, rotating cutting head, augers, jacking frame and hydraulic power pack. Once the excavation base is completed and the rails for the boring machine will be installed, a surveyor will check the exact alignment before the installation of the boring machine. The boring machine elements will be rigged up, lifted, and set up in the thrust pit. Suitable mobile crane or excavator with adequate lifting capacity to be utilized for the works. The boring machine and supporting structure including jacking frame are to be installed on the correct level under supervision of boring subcontractor. All the certificates of the Trust Boring equipment shall be provided to Company for approval prior to start the boring activity. 4.3.2 Thrust Boring Operation The Cutting head is installed at the front of the pilot pipe and the boring operation proceeds by rotating the augers and cutting head, and simultaneously moving the boring machine forward via hydraulically operated jacks. Pilot pipe, with an open face, with the same diameter of the casing pipe, will be progressively loaded into the boring machine The boring operation will start pushing the first pilot pipe gently forward and once the first section of the pipe has been installed, the next section is lowered into the pit, using a crane or excavator with adequate lifting capacity, allocated inside the thrust machine, levelled, aligned with the first pipe welded and painted securely together. The operation then begins again, boring and pushing the casing pipe forward. The activity will continue until all sections Work Method Statement Civil Works Page 6 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD of pilot pipe have been installed and all the sacrificial string has protruded from the launch pit at the other side of the crossing. The excavated spoil from the cutting face is carried through the augers inside the pilot pipe and is extracted from the side of the boring machine, (see figure 1). During the boring operation, elevation and alignment of the pipe shall be regularly monitored to ensure the correct level and alignment is maintained throughout the entire boring operation. When the bore has been completed, the cutting head and the shield will be removed from the front of the pipe and the augers are continuously rotated clockwise until all the spoil has been removed from inside of the pipes. Before the start of the pull-in activity, the receiving pit will be enlarged to a sufficient size to provide ample working space for the equipment and prepared with a gentle slope on the external side to receive with elastic bend the carrier pipe string. The String will be sustained during the pulling operation by a sufficient number of side-booms or manually by labor depending on the length of the crossing Excavator will be utilized to remove the spoil from the thrust pit to an approved temporary stockpile area, outside of the property easements. The stockpile locations will be chosen inside the RoW, without using additional areas. 4.4 Cased pipeline 4.4.1 General All construction work shall be carried out in accordance with the Contract Documents. Due care and consideration will be given to any overhead power lines and property in the vicinity. Pit launcher and receiving shall be excavated to the depth in accordance with the relevant drawing of the particular crossings and also the cover that is the height from the crown of pipe to the surface, a minimum of 2,00 m shall be maintained. Excavated materials shall be preserved beside the trench. 4.4.2 Crossing string preparation Work Method Statement Civil Works Page 7 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD The adequate pipe string length, shall be prefabricated and welded by using COMPANY approved welding procedures with qualified welders. All these carrier pipe welded joints, shall be tested with the adequate NDT method, if any defect detected, same shall be repaired and radiographed. Prior to lowering-in of prefabricated string, a holiday test shall be carried out on the full string. If any defective coating noted, it shall be repaired and re-tested. While carrier pipe inserting in casing, adequate safety precautions shall be implemented to ensure that the pipe section doesn't hit or drop over the existing utilities. This is ensured by the following: Providing adequate room for insertion of the pipe section; Guiding the pipe section carefully under or over the utility; Use of trained rigging personnel. The carrier pipe to insert in casing section shall be properly centered and positioned. After completion of carrier pipe string insertion, a tie-in will be realized in order to assure the pipeline continuity. 7.4.3 Casing Pipe – inspection of pipe Before welding, CONTRACTOR shall inspect the casing pipe in order to detect any possible out of roundness or dents. Such defects shall be eliminated by suitable methods. 7.4.4 Casing Pipe - Vent and Drain Pipes Vent and drain pipes, shall be welded to casing pipe. Vent / drain pipes shall be coated, including a length of 400 mm above grade. The remaining section shall be painted. A final check shall be made to verify the air is free to circulate on the vent / drain pipes. The welding operations of vents and drains can be arranged after the lowering-in of the prefabricated arrangement of carriers pipes already inserted in casing pipe. 7.4.5 Carrier pipe - Installation of Collar spacers / Insulator Rings Collars spacers / insulator rings, shall be fastened and secured to the carrier pipe with fixtures and according the procedure provided by collars spacers / insulator rings, manufacturer. Collars spacers / insulator rings shall be fixed by spacing of 1,00 m while, at both ends of casing a double set of collars spacers / insulator rings shall be installed, as per typical drawing checked and approved by COMPANY. Materials used for the manufacturer of collars spacers / insulator rings shall ensure electrical insulation between the carrier pipe and the casing pipe and which ensures permanent resistance to chemical corrosion. No metal Work Method Statement Civil Works Page 8 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD bolts or attachments are required. Collars spacers / insulator rings guarantee an easy insertion of the carrier into the casing pipe preventing damage of carrier pipe coating. Collars spacers / insulator rings will permit to be tightly fastened onto carrier pipes in order to avoid horizontal movements during insertion and are resistant to mechanical and thermal shocks and stresses, particularly those that occur during both the installation and the inserting operation. 7.4.6 Sealing of Cased Pipe The casing end seal can be arranged after the tie-in operation with pipeline. 7.4.7 Carrier Pipe - Installation into the casing Prior to installation of carrier pipe in the casing pipe, the casing shall be cleaned and inspected. Carrier pipe shall be pushed / pulled into the casing pipe with constant force and maximum care shall be taken to not damage the collars spacers / insulator rings during this operation. 7.5 Backfilling At the conclusion of thrust / auger boring operation, both receiving pit, launching pit and slip trench will be backfilled with an acceptable original sub soil. Padding and backfilling operation will be realized according project documents WMS for bedding, padding and backfilling”. The pipe shall be backfilled across the extent of the road in accordance with the requirements and specifications stated on the Approved for Construction (AFC) Drawings. A casing for FOC shall be laid alongside the carrier pipe. FOC will be installed by CONTRACTOR during FOC installation. Surveyor engineer shall collect all data pertaining the preparation of “as built” drawings. QA/QC Engineer shall carry out all inspection activities and record all parameters in the inspection formats. Care shall be taken at all times when backfilling around existing foreign services in order to ensure that they are fully supported by the backfill material prior to the removal of any temporary supporting structures. 7.6 Crossing restoration and pipeline signage All repair works necessary to restore facilities to the original condition, cut or damaged by crossing activities, will be carry out. All restoration work shall be to the requirements, in order to restore the area within the crossing to its previous condition and shape. Area of construction shall be cleared off Work Method Statement Civil Works Page 9 of 10 ENG I NEERI NG , PRO CUREMENT AND CO NST RUCT IO N (EPC) OF PI PEL I NE I NF RAST RUCT URE FO R ESCRAVO S ENVI RO NS PO WER SUPPL Y PRO JECT WORK MET HOD ST AT EMENT FOR CROSSING USI NG T HRUST BORING MET HOD all materials including obstruction and rubbish disposed to a suitable place as per project specifications and COMPANY instruction. The shoulders, ditches, banks, and slopes of all roads and railroads crossed will be restored to their former condition. Construction debris, surplus material and left-over pipe pup pieces shall be collected and disposed of as appropriate. Existing facilities and installation shall be restored to original condition. Pipeline warning signs will need to be installed after the crossing is completely restored. 5.0 LIST OF EQUIPMENT AND MATERIALS The equipment defined herein shall be considered as standard and could be substituted by equipment with equivalent function, characteristics and skills. The following equipment and tools will be used for relevant operations: - Excavator or backhoe - Truck - Thrust Auger machine (TAM) Work Method Statement Civil Works Page 10 of 10