Permanent Secant Pile Cut-Off Wall for UIHC Children’s Hospital (CH) & Parking Ramp No. 2 (HPR2) Iowa City, IA Schnabel Foundation Company By: Mark Goudschaal, P.E. Presentation Overview Owner/Project Team & Summary of Work – Overall Plan and Facts. 2. Secant Pile Section and Soil Profile 3. Secant Pile Wall Procedures and Installation. 4. Perm. Wall Const. 5. Conclusion 1. Project Team Owner: University of Iowa Hospitals and Clinics (UIHC) Construction Manager: Gilbane Construction Company (GCC) Excavation/Sitework Contractor: Peterson Contracting, Inc. (PCI) SPW Contractor: Schnabel Foundation Company (SFC) DP Contractor: Veit Companies Architect/Engineer: Carl Walker, Inc. (HPR2) & Heery Design (CH) & Shive Hattery Geotechnical Engineer: Terracon Existing Site – Prior to Construction Bid Package Plan/Work Sequencing Children’s Hospital & HPR2 Plan CH Temporary ERS – HPR2 S. SPW Children’s Hospital & Parking Ramp Soil Boring Locations UIHC CH & HPR2 Soil Borings SPW & ERS PLAN Existing Caissons Typical Section Typical SPW Section Ex. Parking Ramp Caisson Obstruction Secant Pile Walls (SPW) Definition: SPW are formed by installing overlapping piles to form a water cut-off. 1. First install primary piles. 2. Then install secondary piles within the gaps and set reinforcing steel. 3. The difference in pile diameter and spacing determines the actual overlap. Secant Piles: Hydraulic Piling Rig – Bauer BG28 Secant Pile Wall (SPW) - Plan and Verticality Tolerances are critical. BG28 Install SPW Templates Installed Circular Foam Template South SPW & Cap – Children’s SPW Drill Primary (Unreinforced) First Concrete, f’c=3,000psi for Primary & Secondary Piles. Secant Piles Hard-Hard Shafts HPR2 Drill More Primary Holes Secondary Holes – Pile Installation I I I I I Finish Secondary Piles I I I I I I I I I Casing Shoes and Tooling Repairs New Casing teeth High Torque Rotary Casing Thick walled sections of temporary flush-joint steel casings (2 – 5 meter lengths) with cutting teeth on starter casing shoe. Used with high torque rotary piling equipment and/or casing oscillator. Oscillator Pulling Casing Flush-Joint Casing – Conical Bolts Placing Concrete & Pile Drilling and Setting Pile Crane Mat Access Road SPW Tie Connections Drilling 2nd Tier Permanent Tiebacks Drilling Tiebacks – Using Uncoiler Automated Grout Plant Automated High Volume Grout Station Finished SPW - October 2013 Current HPR2 & Childrens Hospital CH- April 2014 – Looking North ANY QUESTIONS/COMMENTS?