ACC 202 CONSTRUCTION (Questions) QUESTION 1 Mac Construction entered a contract to build a new multi-purpose sports centre on 1 January 2016. The construction is expected to take three years to complete at a cost of RM10.5 million. Costs were budgeted at 2016 2017 2018 30% 45% 25% The contract required 3 equal payments of RM4 million at 31 December 2016 and 31 December 2017 and on completion (expected 31 December 2018). Accumulated Progress billings for the year ended 31 December 2016, 2017 and 2018 are expected to be RM3 million, RM9.5 million and RM12 million respectively. Required: (a) Calculate the percentage of completion for 2016, 2017 and 2018. (b) Prepare extracts of statements of profit and loss, showing complete calculation of revenues recognised, costs recognised and gross profits for each of the three years. (c) Prepare extracts of statements of financial position for each of the three years, showing the contract asset or contract liability . 1 ACC 202 Cost to date Cost to complete Total estimated cost % of completion 2016 2017 2018 RM’000 RM’000 RM’000 3,150 7,875 10,500 7,350 2,625 10,500 10,500 10,500 30% 75% 100% Contract price SOPL Revenue to date Revenue recognised Revenue for year Cost to date Recognised previous years Cost for year Profit/(loss) SOFP Contract asset Contract liability Working Contract costs recognised Recognised profits Progress billing Contract asset/liability 2016 2017 2018 RM’000 RM’000 RM’000 3,600 9,000 12,000 3,600 9,000 3600 5,400 3,000 3,150 3,150 7,875 3,150 4,725 10,500 7,875 2625 450 675 375 2016 RM’000 600 - 2017 RM’000 2018 RM’000 500 - 3,150 7,875 10,500 ____450__ ______1,125 ______1,500 3,600 9,000 12,000 ______3,000 ______9,500 ______12,000 ______600 ______(500) ______- 2 ACC 202 Question 2 Elegent Construction Sdn Bhd has a contract to construct a twin-building in Kuala Lumpur. The contract price is RM40 million. The construction started in July 2016 and was completed in November 2018. The following table shows the position of the contract at the end of the year 2016, 2017 and 2018. 2016 2017 2018 RM’000 RM’000 RM’000 Variation to the contract price - increase 1,000 Cumulative costs incurred to date 8,750 25,830 32,000 Estimated cost to complete 26,250 11,070 Progress billings to date 8,000 29,500 41,000 Elegent Construction accrued profit on the contract using the percentage of completion method measured by cost to date to total estimated cost. Required: (a) Calculate the percentage of completion for 2016, 2017 and 2018. (b) Prepare extracts of statements of profit and loss, showing complete calculation of revenues recognised, costs recognised and gross profits for each of the three years. (c) Prepare extracts of statements of financial position for each of the three years, showing the contract asset or contract liability. Cost to date Cost to complete Total estimated cost % of completion Contract price 2016 2017 2018 RM’000 RM’000 RM’000 8,750 25,830 32,000 26,250 11,070 35,000 36,900 32,000 25% 70% 100% 40m 40m 41m 3 ACC 202 SOCI Revenue to date Revenue recognised Revenue for year Cost to date Recognised previous years Cost for year Profit/(loss) SOFP Contract asset Contract liability Working Contract costs recognised Recognised profits Progress billing Contract asset/liability 2016 2017 2018 RM’000 RM’000 RM’000 10,000 28,000 41,000 10,000 28,000 10,000 18,000 13,000 8,750 8750 1,250 2016 RM’000 2000 25,830 32,000 8,750 25830 17,080 6,170 920 2017 RM’000 6,830 2018 RM’000 1500 8750 25830 32,000 ______1250 ______2170 ______9,000 10,000 28000 41,000 ______8000 ______29500 ______41,000 ______2000 ______(1500) ______- Question 3 ABC Sdn Bhd has a contract to construct a RM4,500,000 bridge at an estimated cost of RM4,000,000. The construction started in July 2019, and the bridge is to be completed in October 2021. The following data pertain to the construction period. (Note that by the end of 2020 ABC has revised the estimated total cost from RM4,000,000 to RM4,050,000. The following table shows the position of the contract at the end of the year 2019, 2020 and 2021. 2019 2020 2021 RM’000 RM’000 RM’000 Cumulative cost to date 1,000 2,916 4,050 Estimated cost to complete 3,000 1,134 Progress billings for the year 900 2,400 1,200 Cash collected during the year 750 1,750 2,000 4 ACC 202 ABC accrued profit on the contract using the percentage of completion method measured by cost to date to total estimated cost. Required: (a) Calculate the percentage of completion for 2019, 2020 and 2021. (b) Prepare extracts of statements of profit and loss, showing complete calculation of revenues recognised, costs recognised and gross profits for each of the three years. (c) Prepare extracts of statements of financial position for each of the three years, showing the contract asset or contract liability and accounts receivable. 5 ACC 202 Solution Cost to date Cost to complete Total estimated cost % of completion Contract price SOCI Revenue to date Revenue recognised Revenue for year Cost to date Recognised previous years Cost for year Profit/(loss) SOFP Contract asset Contract liability Accounts receivable Working Contract costs recognised Recognised profits Progress billing (accumulated) Contract asset/liability 2019 2020 2021 RM’000 RM’000 RM’000 1,000 2,916 4,050 3,000 1,134 4,000 4,050 4,050 25% 72% 100% 4,500 4,500 4,500 2016 2017 2018 RM’000 RM’000 RM’000 1,125 3,240 4,500 1,125 3,240 1,125 2,115 1,260 1,000 1,000 2,916 1,000 1,916 4,050 2,916 1,134 125 199 126 2016 RM’000 225 2017 RM’000 2018 RM’000 60 150 800 - 1.000 125324 1,125 900 225 2,916 450 3,240 3,300 (60) 4,050 4,500 4,500 - 6 ACC 202 Question 4 The following data relate to contract XZ for the years ended 31 December X4 and 31 December X5 Date contract started 1.4.X4(Contract Price) – Year X4 Year X5 RM million RM million 200 200 Variation to price (increase) 20 Cost to date 75 147 Cost to complete 145 63 Accumulated Progress billing 70 140 Required: (a) Calculate the percentage of completion for X4 and X5. (b) Prepare extracts of statements of profit and loss, showing complete calculation of revenues recognised, costs recognised and gross profits for each of the two years. (c)Prepare extracts of statements of financial position for each of the two years, showing the contract asset or contract liability 7 ACC 202 Solution Year X4 RM Million Contract price 200 Total estimated contract cost 220 Estimated loss (20) The percentage of completion was: Cost to date/ Cost to date plus estimated costs to complete x 100 75,000,000/(75,000,000 + 145,000,000) x 100 = 34% Statement of profit or loss for the year ended 31 December X4 RM Million Revenue (RM200 million x 34%) 68 Costs (34% of RM220 million) (75) Future loss on contract (13) Loss (20) Statement of Financial Position as at 31 December X4 RM million Contract liability 15 8 ACC 202 Working: RM Million Contract costs to date 75 Recognised profit (less recognized losses) (20) 55 Progress billing (70) Contract liability 15 Year 5 The percentage of completion was: Cost to date/ Cost to date plus estimated costs to complete x 100 147,000,000/(147,000,000 + 63,000,000) x 100 = 70% RM Million Contract price 200 Variation 20 Total estimated contract price 220 Total estimated cost 210 Estimated profit 10 Statement of profit or loss for the year ended 31 December X5 9 ACC 202 RM Million Revenue (RM220 million x 70%) 154 Less: Revenue recognized in prior period 68 RM Million 86 Costs (70% of RM210 million ) 147 Less: Cost recognized in prior period 88 59 Profit 27 Statement of Financial Position as at 31 December X5 RM million Contract asset 14 Working: RM Million Contract costs to date Recognised profits (27-20 million) 147 7 154 Progress billing (140) Contract asset 14 10