MS PROJECT ASSIGNMENT APRIL 2023

advertisement
MS PROJECT ASSIGNMENT
Refer to the attached Bills of Quantities case study comprising the construction of a residential
house. Execute the following tasks:
•
•
Price the Bills of Quantities using your best estimates of prevailing market rates.
Prepare a work programme for the following elements, each to be completed within a
maximum period of 8 weeks. Your proposed work programme should cover the
following parameters:
1.
2.
3.
4.
5.
6.
7.
Project Summary and other Summary Tasks
WBS (with Outline Numbers)
Resources (cost resources; work resources and materials resources)
Milestones
Critical Path(s)
Project costs, including the overall cost of the selected element.
Project status date (in dashed red line) is 10/04/2023. Assume the project/element
start date is 1st March 2023, and the work must be completed within a maximum
period of 8 weeks/ 56 calendar days.
8. Assume the first 4 activities of the project are 100% complete, the next 3 activities are
75% complete and all other activities are 0% complete. Set the start date to
01/03/2023 and the status date to 10/04/2023. Based on the information provided,
determine if the project is behind schedule, on schedule or ahead of schedule.
9. Set the project calendar to work throughout the weekends (7 days a week).
10. Submit both pdf and MS Project files.
TASK ALLOCATION
1. Substructure
2. Superstructure: R.C. Frame; Stairs & Ramps; Walling & Partitioning
3. Roofing & Rainwater Disposal; Windows & Doors; Internal & External Finishes
4. External Works
NB: proposed
work programme should be done on each
task above.
END OF ASSIGNMENT