Date: 11/28/2022 RETROFIT OF MARY COLLEGE AT ASU Submitted To: Dr. Kristen Parrish 6.53 Submitted By: Anuradha Jambhulkar Nikitha Saraboju Shiva Arabi Sushma Sirikonda Tanmay Musale TEAM INTRODUCTION Tanmay Musale Project Manager 7/1/20XX Sushma Sirikonda Anuradha Jambhulkar Cost Engineer Project Engineer Shiva Arabi Nikitha Saraboju Planning Engineer Structural Engineer Pitch deck title 2 WHY RETROFITTING IS REQUIRED • Building is not designed according to codes • Deterioration of Strength and aging • Modification in existing structure • Damages in structural members • Poor quality of construction • To achieve maximum sustainability 3 Group 8 Mary College At ASU Group 8 4 Name of structure: Mary College at ASU Location: 230 E University Dr, Tempe, AZ 85281 Area of structure: 8165 S.F Use: Educational institute for Catholic studies Group 8 5 Built in 1903 Originally built as St. Mary Mission Church Rev. Severin Westhoff, OFM – Builder of the old church Oldest Catholic structure in the valley Currently serving as an institute for Catholic studies and is in partnership between the University of Mary and Arizona State University Group 8 6 PROBLEMS ENCOUNTERED / PROJECT GOALS 1. Cracks on outer walls and on the ceiling 2. Poor Lighting 3. Old fashioned windows 4. Cracked window frames 5. Squeaky floor Group 8 7 OPTION 1 Lighting Upgrade Windows Upgrade Repairs of Structural Cracks 8 LIGHTING UPGRADE • Existing Condition – Only 4 lights in upper level • We proposed to use new LED lights to improve brightness in the hall 9 Group 8 WINDOWS UPGRADE 1. Replace existing wood frames with new metal frames 2. Replace the old window glass with new stainedglass panels. Group 8 10 REPAIRS OF STRUCTURAL CRACKS 1. Major structural cracks on brick wall will be repaired using Epoxy Resin Mortar. 2. Minor cracks be repaired by using cement mortar Group 8 11 OPTION 2 Lighting Upgrade Windows Upgrade Repairs of Structural Cracks Squeaky Floor Upgrade Bell tower repair 12 LIGHTING UPGRADE • Use of motion sensing lights It functions similarly to a regular light except that it is connected to a sensor that activates the light when the sensor detects movement. • Antique, luxurious light fixtures Group 8 13 WINDOWS UPGRADE 1. Installation of modern window frames 2. Installation of window glass film to upgrade the efficiency of glass pane which can also reflects infrared radiations. 3. Install solar shaders Group 8 14 WALL CRACKS 1. Wall cracks can be repaired by using drywall compound 2. New reinforcement wall can be constructed to retrofit external wall cracks Group 8 15 BELL TOWER REPAIR This bell tower will be repaired for aesthetic purpose. The old metallic mesh and the corroded wood from inside and outside will be removed. New window frame and glass will be installed to give a better look to the bell tower. Group 8 16 OPTION 3 (RECOMMENDATION) Lighting Upgrade Windows Upgrade Repairs of External Wall Cracks Squeaky Floor Upgrade Addition of New Restroom 17 OPTION 3 UPGRADES 1. Installation of LED lights 2. New window frames with new stained glass 3. Cracks will be repaired with cement mortar or use of FRP 4. Squeaky floor can be repaired by using brand new carpet tile Group 8 18 ADDITION OF NEW RESTROOM • There is not a single restroom in this building. We proposed to build a new restroom at the ground floor as there is some empty space in there and it is currently used for pantry. So, we can utilize this space to build a new restroom. DURATION SCHEDULE Type of Retrofit Activity LIGHTING ENVELOPE Lighting Upgrade Window Upgrade Repairs of External Wall Cracks Repairs of Ceiling Cracks Squeaky Floor Upgrade Addition of New Restroom STRUCTURAL Start End Aug-23 Sep-23 Jul-23 Jan-24 Mar-24 Dec-23 Oct-23 Dec-23 Aug-23 Mar-24 Apr-24 Mar-24 Months 2 3 1 2 1 3 Status % Done u Not Started u Not Started u Not Started u Not Started u Not Started u Not Started Group 8 20 Jun-24 May-24 Apr-24 Mar-24 Feb-24 Jan-24 Dec-23 Nov-23 Oct-23 Sep-23 2024 Aug-23 Jul-23 Jun-23 May-23 Month Starting Apr-23 Mary College at ASU Retrofit Project Mar-23 Project Name 2023 Feb-23 Expected Completion: Apr-24 Jan-23 Project Start Date: May-23 COST SCHEDULE Type of retrofit LIGHTING ENVELOPE STRUCTURAL Activity Unit Qty Material Labor New LED Lights Antique Light Fixtures Metal frames Stained glass for window Bell tower window frame Bell tower stained glass Repairs of External Wall Cracks Repairs of Ceiling Cracks Installing new carpet Tiles Addition of New Restroom Ea Ea Ea Ea Ea Ea L. S. L. S. Sf Sf 32 4 10 10 4 4 640 800 4500 15000 1600 6400 6400 8000 18000 30000 3200 12800 8165 45.5 65320 6825 130640 4550 SUB-TOTAL Total $ $ $ $ $ $ $ $ $ $ $ Contractor profit margin TOTAL $ Group 8 7,040.00 8,800.00 22,500.00 45,000.00 4,800.00 19,200.00 7,000.00 5,000.00 195,960.00 11,375.00 326,675.00 8% 352,809.00 21 COST CONSIDERATIONS • Labor Cost • Cost changes due to schedule delays • Equipment Cost • Cost increase due to site conditions • Material Cost • Resource availability • Repairing and Maintenance Cost • Cultural Issues • Contingencies • Freight Mobility • Taxes and Insurances • Productivity • Design changes/Change orders • Financial Resources (Rate of interest, dividends, profit margin, etc.) 22 Team 8 THANK YOU! QUESTIONS? Team 8 23