Retrofit Presentation Tanmay

advertisement
Date: 11/28/2022
RETROFIT OF MARY
COLLEGE AT ASU
Submitted To: Dr. Kristen Parrish
6.53
Submitted By:
Anuradha Jambhulkar
Nikitha Saraboju
Shiva Arabi
Sushma Sirikonda
Tanmay Musale
TEAM INTRODUCTION
Tanmay Musale
Project Manager
7/1/20XX
Sushma Sirikonda
Anuradha
Jambhulkar
Cost
Engineer
Project Engineer
Shiva Arabi
Nikitha Saraboju
Planning Engineer
Structural Engineer
Pitch deck title
2
WHY RETROFITTING IS REQUIRED
• Building is not designed according to codes
• Deterioration of Strength and aging
• Modification in existing structure
• Damages in structural members
• Poor quality of construction
• To achieve maximum sustainability
3
Group 8
Mary College At ASU
Group 8
4
Name of structure: Mary College at
ASU
Location: 230 E University Dr,
Tempe, AZ 85281
Area of structure: 8165 S.F
Use: Educational institute for
Catholic studies
Group 8
5
Built in 1903
Originally built as St. Mary Mission
Church
Rev. Severin Westhoff, OFM –
Builder of the old church
Oldest Catholic structure in the valley
Currently serving as an institute for
Catholic studies and is in partnership
between the University of Mary and
Arizona State University
Group 8
6
PROBLEMS ENCOUNTERED / PROJECT GOALS
1. Cracks on outer walls and on the ceiling
2. Poor Lighting
3. Old fashioned windows
4. Cracked window frames
5. Squeaky floor
Group 8
7
OPTION 1
Lighting Upgrade
Windows
Upgrade
Repairs of
Structural Cracks
8
LIGHTING UPGRADE
• Existing Condition – Only 4 lights in upper
level
• We proposed to use new LED lights to
improve brightness in the hall
9
Group 8
WINDOWS UPGRADE
1. Replace existing wood frames with new metal
frames
2. Replace the old window glass with new stainedglass panels.
Group 8
10
REPAIRS OF STRUCTURAL CRACKS
1. Major structural cracks on
brick wall will be repaired
using Epoxy Resin Mortar.
2. Minor cracks be repaired by
using cement mortar
Group 8
11
OPTION 2
Lighting
Upgrade
Windows
Upgrade
Repairs of
Structural
Cracks
Squeaky Floor
Upgrade
Bell tower
repair
12
LIGHTING UPGRADE
• Use of motion sensing lights
It functions similarly to a regular light except that it is
connected to a sensor that activates the light when the
sensor detects movement.
• Antique, luxurious light fixtures
Group 8
13
WINDOWS UPGRADE
1. Installation of modern window frames
2. Installation of window glass film to upgrade the efficiency of
glass pane which can also reflects infrared radiations.
3. Install solar shaders
Group 8
14
WALL CRACKS
1. Wall cracks can be repaired by using drywall compound
2. New reinforcement wall can be constructed to retrofit
external wall cracks
Group 8
15
BELL TOWER REPAIR
This bell tower will be repaired for aesthetic purpose.
The old metallic mesh and the corroded wood from
inside and outside will be removed. New window frame
and glass will be installed to give a better look to the bell
tower.
Group 8
16
OPTION 3
(RECOMMENDATION)
Lighting
Upgrade
Windows
Upgrade
Repairs of
External Wall
Cracks
Squeaky Floor
Upgrade
Addition of New
Restroom
17
OPTION 3 UPGRADES
1. Installation of LED lights
2. New window frames with new stained glass
3. Cracks will be repaired with cement mortar or use of FRP
4. Squeaky floor can be repaired by using brand new carpet tile
Group 8
18
ADDITION OF
NEW RESTROOM
• There is not a single restroom in this
building. We proposed to build a new
restroom at the ground floor as there is
some empty space in there and it is
currently used for pantry. So, we can
utilize this space to build a new
restroom.
DURATION SCHEDULE
Type of Retrofit
Activity
LIGHTING
ENVELOPE
Lighting Upgrade
Window Upgrade
Repairs of External Wall Cracks
Repairs of Ceiling Cracks
Squeaky Floor Upgrade
Addition of New Restroom
STRUCTURAL
Start
End
Aug-23
Sep-23
Jul-23
Jan-24
Mar-24
Dec-23
Oct-23
Dec-23
Aug-23
Mar-24
Apr-24
Mar-24
Months
2
3
1
2
1
3
Status
% Done
u
Not Started
u
Not Started
u
Not Started
u
Not Started
u
Not Started
u
Not Started
Group 8
20
Jun-24
May-24
Apr-24
Mar-24
Feb-24
Jan-24
Dec-23
Nov-23
Oct-23
Sep-23
2024
Aug-23
Jul-23
Jun-23
May-23
Month Starting
Apr-23
Mary College at ASU
Retrofit Project
Mar-23
Project Name
2023
Feb-23
Expected Completion: Apr-24
Jan-23
Project Start Date: May-23
COST SCHEDULE
Type of retrofit
LIGHTING
ENVELOPE
STRUCTURAL
Activity
Unit
Qty
Material
Labor
New LED Lights
Antique Light Fixtures
Metal frames
Stained glass for window
Bell tower window frame
Bell tower stained glass
Repairs of External Wall Cracks
Repairs of Ceiling Cracks
Installing new carpet Tiles
Addition of New Restroom
Ea
Ea
Ea
Ea
Ea
Ea
L. S.
L. S.
Sf
Sf
32
4
10
10
4
4
640
800
4500
15000
1600
6400
6400
8000
18000
30000
3200
12800
8165
45.5
65320
6825
130640
4550
SUB-TOTAL
Total
$
$
$
$
$
$
$
$
$
$
$
Contractor profit margin
TOTAL
$
Group 8
7,040.00
8,800.00
22,500.00
45,000.00
4,800.00
19,200.00
7,000.00
5,000.00
195,960.00
11,375.00
326,675.00
8%
352,809.00
21
COST CONSIDERATIONS
•
Labor Cost
•
Cost changes due to schedule delays
•
Equipment Cost
•
Cost increase due to site conditions
•
Material Cost
•
Resource availability
•
Repairing and Maintenance Cost
•
Cultural Issues
•
Contingencies
•
Freight Mobility
•
Taxes and Insurances
•
Productivity
•
Design changes/Change orders
•
Financial Resources (Rate of interest, dividends, profit
margin, etc.)
22
Team 8
THANK YOU!
QUESTIONS?
Team 8