INSPECTIONEERING JOURNAL Challenging Baseline Inspection Paradigms for Oil & Gas Upstream Equipment By George C. Williamson, VP of Integrity, Risk Management & Litigation Support at Integrity & Emission Reduction Partners, LLC, and Dr. Bill Hedges, Independent Consultant. This article appears in the July/August 2022 issue of Inspectioneering Journal. Introduction Conventional wisdom holds that baseline inspections must be done for all piping and other static mechanical pressure equipment [1-3]. An investigation was conducted to challenge this paradigm and the potential risk of changes to it. This article introduces a new approach to baselining practices that were developed for and implemented by one upstream operator. One substantial change was the elimination of baseline inspections for production and facility piping. Alterations were also made in baselining practices for pressure vessels with the objective of enhancing non-intrusive inspection (NII) programs. Baseline Inspection Overview Determining the purpose of performing baseline inspections is the principal consideration for a practitioner. Baselining is done for different purposes and can be classified in the three following categories: 1. Quality Control (QC) 2. Quality Assurance (QA) 3. Determination of future in-service corrosion rates by adding condition monitoring locations (CMLs) (API 570 Piping Inspection Code definition designates areas on piping systems where periodic examinations are conducted. API 510 Pressure Vessel Inspection Code definition designates areas on pressure vessels where periodic external examinations are conducted in order to directly assess the condition of the vessel.) What is necessary and fit for purpose for each of the objectives can vary significantly. Another factor to consider is when to perform baseline inspections and depending on the objective, the optimal time will vary. The scope of baseline inspection activities can include any of the following: Verification of materials of construction Visual testing (VT) or inspection to verify installations and evaluate general equipment condition (e.g., material quality, coatings, insulation, absence of mechanical or other forms of damage) Verification of installed wall thickness versus design requirements Although the definitions of QC and QA are different, the activities are interrelated and often overlap. Given the context of this article, QC is the implementation of procedures used to ensure that facilities are constructed to meet the design specifications. QC typically works best when done early-on during the construction phase with the intent of correcting problems proactively and to ensure mistakes are not repeated. QA is a larger part of the overall quality management system that is applied throughout different project stages and sometimes on into the operational phase. This article questions what baseline inspections are needed for determining inservice corrosion rates on upstream equipment. It also assesses when and how they should be done. Background and Investigation The operator’s general baselining practice was to perform wall thickness measurements on all static mechanical pressure equipment along with visual inspections prior to placing the equipment in service. The approach was to perform all these activities as part of an integrated program, (i.e., QC, QA, and wall thickness measurement for in-service corrosion rate determination) during the construction to pre-commissioning phases. Several issues arose from this practice which drove a reevaluation of the approach. One problem was that the requirements for adding CMLs were more arduous than needed for QC and QA wall thickness verifications. The result was a delay of construction activities. Additionally, the qualifications of personnel needed to implement the CML program exceeded what was necessary for the basic wall thickness verification work. Both factors were driving cost overruns and affecting optimal resource allocation. The investigation pivoted to what was needed for determining in-service corrosion rates. The primary focus was on ultrasonic testing (UT) and wall thickness measurement. The objective was to optimize the approach and ensure a fit for purpose program. The investigation utilized information collected over many years from the following three data sources: Damage mechanism reviews (DMRs) Equipment degradation patterns Failure analyses The effort was multidisciplinary and included a broad range of subject matter experts (SMEs): Inspection engineers Corrosion engineers Materials engineers Mechanical engineers Operations and maintenance Projects After analyzing the data, it was concluded that, for upstream equipment, no credible thinning damage mechanism would be defined as general corrosion. The Association for Materials Protection and Performance (AMPP) describes “general corrosion" or "uniform corrosion" as proceeding more or less uniformly over an exposed surface without appreciable localization [7]. The specific credible damage mechanisms for thinning, of course, vary with specific service conditions (e.g., deadlegs, high flow areas, production composition, etc.), but some of the more prevalent upstream damage mechanisms are as follows: CO2 corrosion H2S corrosion Erosion Microbiologically influenced corrosion (MIC) Preferential weld corrosion (PWC) Oxygen corrosion (often downstream of tank batteries or in some parts of seawater handling systems) The reviews confirmed that damage ranged from highly isolated (pitting) to areas of relatively large wastage. However, it was determined that damage did not result fully over a component or entire portion of equipment. This included production piping, facility process piping, pressure vessels, and pipelines. In all cases, it was determined that undamaged areas on a component (fitting, pipe joint, shell plate, etc.) were always available to measure wall thickness for comparative purposes and corrosion rate determination. A few examples of Upstream equipment damage are illustrated in Figures 1-3. Figure 1. Radiograph of carbon dioxide (CO2) corrosion on well site piping. Some areas of deeper isolated damage are illustrated by the red notations. Photograph courtesy of Integrity Emission Reduction Partners (IERP) LLC. Figure 2. Radiograph of erosion-corrosion on piping in produced water service with entrained solids. Photograph courtesy of Integrity Emission Reduction Partners (IERP) LLC. Figure 3. Gathering line failure caused by to top-of-line (TOL) corrosion. Although a relatively large area of corrosion damage was observed there were several locations on the pipe joint with no damage. These locations were used to calculate a long-term corrosion rate. Photograph courtesy of Integrity Emission Reduction Partners (IERP) LLC. Before deciding to change baselining practices, it was essential to further analyze the ramifications of a potential change and align the organization. A critical discipline to get agreement from was corrosion engineering, where it was a strongly held cultural view, that baselining must always be done. However, after reviewing data and the collective body of experience across the organization, it was agreed that a change might be acceptable. The accuracy of manual UT wall measurement and the potential effects on corrosion rates were included as part of the investigation. Publications cite that there are several variables and significant errors or variations in UT wall thickness measurements [4, 5]. Minimum thicknesses reported in UT qualification testing showed differences from the “true” thickness of +/- 25.0 mils (0.025 inches) within two standard deviations [4]. Another study illustrated that depending on the specific instrument and transducer type that the measurement error at mean thickness varied from +/- 19.0 to 44.0 mils (0.019 to 0.044 inches) from the true material thickness [5]. The operators’ inspection programs required a threshold value of greater than or equal to 0.020 inches of change before trusting a real reduction in thickness. We are aware of one other operator similarly using a threshold value as high as 0.030 inches. It was decided to do a corrosion rate sensitivity analysis on potential measurement errors of 0.020, 0.030, and 0.040 inches. Table 1 shows the maximum variability in corrosion rates that could result from the different wall thickness measurement errors. Table 1. Potential Maximum Deviation in Corrosion Rate Due to Wall Thickness Measurement Error (mils per year). Inspection Frequency (Months) Measurement Error (Inches) 0.020 0.030 0.040 24 10.0 15.0 20.0 36 6.7 10.0 13.3 48 5.0 7.5 10.0 60 4.0 6.0 8.0 72 3.3 5.0 6.7 (Corrosion rates were calculated and converted to mils per year using the maximum potential measurement errors for each of the inspection frequencies listed in the table.) In every scenario, there is a possibility that the actual corrosion rate could be zero. The potential errors in corrosion rate for the different scenarios ranged from 3.3 up to 20 mils per year. The impact of these potential errors on corrosion control mitigation decisions and recurring inspection frequencies can be significant. In consideration of most corrosion control programs, corrosion rates above 2.0 mils per year (mpy) would be considered non-optimal and typically drive mitigation actions. The sensitivity analysis demonstrated that there was a considerable amount of uncertainty in actual corrosion rates even when applying past practices that included pre-operational baseline inspections. This challenged the paradigm that reliable and highly accurate corrosion rates were always applied. While these errors are significant, they are not as high as if a program were to simply use nominal wall thicknesses for the baseline wall thickness. Nominal pipe wall thickness varies significantly - commonly up to 12.5%. Specific values depend upon manufacturing method, size, and material standard [6]. It was concluded that using nominal wall thickness would not be acceptable for determining corrosion rates. Elevated risk or critical piping that could also be subject to high corrosion rates was a past justification or mandatory driver of baselining. After considering measurement errors, practicable inspection frequencies, and existing technologies; subject matter experts agreed that real-time permanently installed monitoring sensors (PIMS) and mitigation were more appropriate integrity management tactics in these situations. The overall view was that reliance on the historical practice was no longer necessary or adequate in these situations. Baselining Approach Following this work, it was concluded that the old paradigm should be shifted to a default position of no baselining for piping unless there was a valid technical justification (e.g., using and leaving poor quality hydrotest water in the equipment). The view was that there would be either no cases or extremely limited cases that the exception might apply. As previously discussed, if piping was so critical due to consequence of failure or extremely high corrosion or erosion rates; the solution would likely be PIMS and not the application of periodic manual UT. Read Related Articles 11 Primary Elements to Ensure Asset Integrity in the Lifecycle of Oil and Gas Facilities MI Inspection During Capital Projects Promotes PSM Compliance, Corrosion Rate Accuracy and Improved Budgeting The Role of Record-keeping and Data Management in Achieving Excellence in Pressure Equipment Integrity and Reliability Improving Confidence in On-Stream Inspections of Pressure Equipment The Piping Integrity Management Challenge It was recommended to stop the approach of performing all the baselining activities as part of one program. The decision was made to only perform QC and QA baselining during construction and through pre-commissioning. The practices were simplified in general along with different personnel requirements for these activities. The operator put a well-documented and robust control process in place. They also made a firm decision to rely on this information and not repeat any such activities afterwards (e.g., in commissioning or operational life cycle phases). The view was that new facilities should not be started up unless these activities were reliably done in the first place. A summary of the key principles of the innovative approach for baselining are the following: Activities for corrosion rate determination would be separated from other baselining activities for QC and QA purposes. The default position was that baselining wall thickness measurements would not be done on any equipment before in-service operation for corrosion rate determination purposes. A damage mechanism review and risk assessment would determine if any exceptions to the default position were necessary. The frequency and timing for initial inspections would be set based upon risk-based inspection (RBI) methodology. Corrosion rates would be calculated after the initial in-service inspection by comparing wall thickness measurements at CMLs and undamaged wall on the component. Results from QC and QA baselining activities (verification of materials of construction, installation requirements, and general conditions) performed during construction and precommissioning will be relied upon and not repeated as a separate baseline activities in the operations life cycle. Note that baselining is not to be confused with on-going visual inspections / surveillance done during operational rounds or as part of regular inservice inspection programs. These ongoing activities will continue as part of the overall in-service integrity programs.) The investigation did identify activities in current practices done during QC or QA baselining that should be continued or even expanded. Specifically, some of the baselining activities done on pressure vessels. As an example, during the operational phase, the operator was using non-intrusive inspection (NII) to endorse the integrity of pressure vessels without vessel entry. The NII program was delivering huge value and reducing health, safety, and environmental (HSE) risk. Information from the pre-service baselines on pressure vessels was an important enabler of the NII program. Challenges with implementing NII programs can arise when damage is present on vessel components from fabrication or construction. Internal surface anomalies or irregularities on vessel shell plates and head components caused by grinding or formation (e.g., rolling or forging) can be misidentified as inservice deterioration. Misinterpretation of these anomalies as in-service damage can drive unnecessary inspections and other spurious activities. Having a good understanding of the pre-service internal surface condition of the components is essential for optimizing the NII program. The standard approach for pre-service baseline inspection of pressure vessels included the following: Visual inspection and photographic documentation of the internal shell surface conditions, other internal equipment, and coating if applicable. Spot wall thickness measurements at select locations on shell plates and heads. The visual inspections and photographic documentation from pre-service baselining was viewed as value adding and an enabler of NII. The collection of spot UT wall thickness data was not. It was considered whether there would be a benefit of applying automated UT for wall thickness mapping over large surface areas to expand baselining data collection. It was decided that there were better and lower cost alternatives. The optimal baselining practice to support the NII program was determined to be the following: Continue the internal visual inspections and photographic documentation of internal surface conditions and other internals. Adding 3D laser scanning of internal surface anomalies that are identified by visual inspections. Specific criteria regarding surface anomaly patterns and depth thresholds were included in the operator’s new baselining practice to determine when to apply the 3D laser scanning. Benefits Several benefits have come out of the operator’s modification of their practices. Separation of the programs has clarified roles and responsibilities. It has allowed a focus on specific program objectives with better allocation of resources. For example, after eliminating the corrosion rate determination baselining activities on major projects, reducing redundancies, and aligning competency requirements with job tasks, costs were reduced by over 50%. The technical subject matter experts (SMEs) agreed that the clarifications and additions made to pre-service baseline requirements for pressure vessels would deliver value. Specifically, by reducing uncertainty from vessel inspection results as part of the in-service NII program. Data from the enhanced baselining practices will help eliminate the need for supplemental inspections and spurious mitigation actions. Potential Challenges and Limitations Given that pre-service UT baselines will not be done, corrosion rates will be calculated using wall thickness comparisons between measurements at a CML and a different location on a component. All measurements will be taken at the time of first in-service inspection. There are factors that must be considered when selecting the comparative locations. Production conditions, component type, manufacturing method, damage mechanism, and damage morphology must all be considered. In most cases, it is optimal to select undamaged wall adjacent to the CML as the comparative location. Ideally the closer the comparative location to the CML, the less likely there will be any variation in wall thickness from manufacturing processes. However, depending upon specific CML patterns and damage mechanisms, there is a possibility that damage might extend beyond the CML. This could result in an error that underestimates corrosion rates. Upstream inspection programs sometimes use radiographic testing (RT) on piping for screening using the double wall single image (DWSI) technique (Figure 4). This is done to detect damage, identify corrosion patterns, and the extent of damage. The RT is followed up by UT for quantitative wall thickness determinations. Typically, the RT inspections cover the entire CML pattern designated for UT measurement and extend well beyond it. This procedure can be used to ensure an appropriate comparative location with undamaged wall is selected. Another way to provide assurance is to require UT scanning patterns that extend beyond the CML to find undamaged areas. Figure 4. Illustration of Double Wall Single Image (DWSI) RT technique with Iridium 192 source and digital detector array. Given situations where components are not expected to have significant wall thickness variations due to manufacturing methods (e.g., rolled pipe) and depending upon damage mechanisms and production conditions, it may be preferred to select comparative locations that are not close to CMLs. An example of this would be a situation where corrosion is only credible at water wet locations and not in the gas phase. In this case, the comparative readings for the first corrosion rate calculation could be selected on a component in the gas phase. It should be noted that the practice of using the comparative location is only used for the first corrosion rate determination. Subsequently, all corrosion rate calculations will be made as in conventional programs by comparing previous readings at a CML. Conclusion After completion of a review of the approach and long-held paradigms regarding baseline inspection practices for upstream equipment, a decision was made to make some significant changes. The operator’s prior practice was to combine baselining activities with multiple objectives all into one program done during construction and precommissioning. Several problems resulted such as redundancy, misalignment of needs and personnel competency requirements, project delays, and excessive costs. In order to improve overall effectiveness and reduce costs, a decision was made to segment programs by only performing baselining activities needed to support quality control and quality assurance objectives prior to operations. It was also decided to trust, rely on, and not repeat these activities in the operation’s life cycle. A review of UT wall thickness measurement errors and the expected accuracy of subsequent corrosion rate calculations showed potential variability in predicated corrosion rates. This exposed gaps in past assumptions about the effectiveness of conventional practices. It made clear that the risks associated with change might be tolerable or within current limits. Furthermore, after considering measurement errors, practicable inspection frequencies, and existing technologies, it was decided that real-time permanently installed monitoring sensors (PIMS) and mitigation were more appropriate integrity management tactics in situations requiring highly accurate corrosion rates. As part of the in-service integrity management program, significant changes were made to baselining practices associated with how and when to take wall thickness measurements for the purpose of corrosion rate determinations. One substantial change in baselining inspection practices was the elimination of preservice UT wall thickness measurements for production and facility piping. This conclusion was enabled by analysis of damage mechanism reviews (DMRs) and operating experience with equipment degradation patterns. The findings demonstrated that upstream damage mechanisms are not general and that comparative locations on a component could be selected for corrosion rate determination. Moreover, wall thickness measurements at CMLs and comparative locations could be done at the same time during the first in-service inspection interval. It should be noted that several considerations were identified with the selection of comparative locations. The operator made changes to the pre-service baselining activities for pressure vessels. This was done to enhance the NII programs. Optimal baselining was determined to continue with internal visual inspections and photographic documentation of internal surface conditions and internals with the addition of 3D laser scanning of some internal surface anomalies. Specific criteria regarding surface anomaly patterns and depth variation thresholds were included in the operator’s new baselining practice. The operator decided to discontinue wall thickness measurements during the construction phase unless information was provided to change this. Although modifications to baselining practices were predicated on a solid foundation of experience and analysis, they do incorporate major changes and so these programs are carefully monitored. References 1. Anwer, A., 2018, “The Importance of Baseline Inspections,” Inspectioneering Journal, 24(5), pp. 46-47. 2. API 510, 2014, “Pressure Vessel Inspection Code: In-Service Inspection, Rating, Repair, and Alteration,” Tenth Edition, American Petroleum Institute. 3. API 570, 2016, “Piping Inspection Code: In-Service Inspection, Rating, Repair, and Alteration of Piping Systems,” Fourth Edition, American Petroleum Institute. 4. Weire, D.R., Pardini, A.F., 2007, “Evaluation of UT Wall Thickness Measurements and Measurement Methodology,” Prepared for U.S. Department of Energy. 5. Lebowitz, C. A., Brown, L. M., 1993, “Ultrasonic Measurement of Pipe Thickness,” Review of Progress in Quantitative Nondestructive Evaluation, Vol. 12, Plenum Press, New York. 6. API RP 574, 2016, “Inspection Practices for Piping System Components,” Fourth Edition, American Petroleum Institute. 7. AMPP, “What is Corrosion?” Association for Materials Protection and Performance, https://www.ampp.org/resources/what-is-corrosion Did you find this article helpful? About the Authors George C. Williamson, VP of Integrity, Risk Management & Litigation Support at Integrity & Emission Reduction Partners, LLC George Williamson, P.E. is VP of Integrity, Risk Management & Litigation Support at Integrity Emission Reduction Partners (IERP), LLC in Houston, Texas. George has over 30 years of integrity management, operations, and maintenance experience as a major asset owner with ARCO and BP. His roles have included managing global oil and gas production facilities, pipelines, and subsea systems in... Read more » Dr. Bill Hedges, Independent Consultant Bill is an independent consultant with over 35 years experience in integrity management in the oil and gas industry working for international oil companies. He has led large integrity teams in operational assets as well as central engineering teams. His specialist area is developing risk-based corrosion management programs and troubleshooting operational integrity problems. ... Read more » Comments and Discussion There are no comments yet.