Uploaded by adeolowoo

construction information

advertisement
Unit 6
Construction Information
(Drawing, Detailing, Specification)
LOl Evaluate different types of construction information in the
context of diverse project types - Schedules & Specifications
Schedules
Within a construction project, many types of item may be used
numerous times - they all fit within a general category but may have
different types depending on their location and use.
For example, there may be many different types of window in a
project; some will be the same and others will be different, depending
on their location, etc. Similarly, there will be different types of door,
door handle, plumbing fixture, etc. In most cases, the individual items
will be purchased (rather than made or built for the project) and we
need a simple way to indicate where each specific type of item is to be
used.
Schedules
A schedule is a table or list of the different items. Depending on the
complexity of the project, we may need to identify different
characteristics (height, width, thickness, colour, material, etc.) to
differentiate the items.
Alternatively, where the list includes pre-made items (from a single
manufacturer or group of manufacturers), we may just need to give the
manufacturer code and some basic information (type, finish).
This information is coded in the list and the codes can then be cross•
referenced with the drawings. When we need to install an item (a door,
for example), we can find the code on the plan, look this up in the
schedule, and know the specific type of door that is to be used.
Schedules
Some common types of schedule, used in coordinating with drawings, are:
►
►
►
►
►
►
►
►
►
door schedules
window schedules
hardware schedules (e.g. door handles, window handles, etc.)
finish schedules (types of paint, colour, ti ling, etc.)
plumbing schedules (for large projects with many different plumbing fixtures).
Individual activity
What is the purpose of schedules?
Why don't we just include all the information in the drawings?
How does a bill of quantities differ from a schedule of works?
What type of information are included in schedules?
Schedules
There are also other forms of schedule that may comprise part of the
construction information. These may be used when quantifying materials
and costs, for example:
► a schedule of rates shows the costs associated with specific types of
construction work
► a schedule of works is a table listing the different types of work to be
undertaken in a project (this is more commonly used in smaller
projects)
► a bill of quantities (BoQ) lists the measured quantities required for the
`different works identified in a project
► a schedule of services lists the specific services to be provided
contractor or consultant.
by a
Specifications
The specification is a written document (or, for large projects, a series of
documents) describing in detail the scope of work, materials to be used,
methods of installation, and quantity of workmanship with reference to
established standards in the construction industry.for a parcel of work to
be placed under contract.
It is usually utilized in conjunction with working (contract) drawings in
building construction.
Specifications do not include information about cost or quantities; this
information will be compiled in related schedules, drawings and contract
documents.
In some cases, the specification will include information about specific
products and suppliers, or it may describe items in relation to their
expected characteristics (performance).
Specification vary considerably depending on the stage to which the design has been
developed, ranging from performance specifications (open specification) that
required further design work to be carried out, to prescriptive specifications (closed
specifications) where the design is already complete.
Who uses Specifications?
Pre contract:
•Part of the design brief process
•Cost control team
•Contractors estimating team
During contract:
•Site agent and operatives
•Clerk of the works
Post contract:
•Design record
•Evidence in disputes
+FM
Specifications – Content
Design requirements - what needs doing
Details of the materials to be used
Performance specification - how it is to be done
The extent of works to be carried out
•The quality and type of materials to be used
•The standards of workmanship that will be acceptable
•The specification does not instruct the contractor how the work is to be
done rather describes what must be achieved in terms of quality.
Characteristics of a Specification
•
have a logical layout
The layout of the Specification should follow a logical order and be
simple to use. The order of the clauses should follow the 'Standard
Method of Measurement'.
•
be complete
There should be no missing items and the descriptions given should
need no further clarification. (When read in conjunction with the drawings)
•
be concise
There should be no redundant
information should be avoided.
material.
In
particular,
repetition
•
be clear and precise
The clauses should be written in clear, unambiguous language that is
not open to misinterpretation. This is a very difficult task. Historically.
Architects I Engineers will interpret clauses differently from building
contractors. This has led to much dispute and litigation.
•
be cross checked with the other contract documents
The Specification must not contain any information that conflicts with
information shown on the contract drawings or schedules. Any conflicts
can lead to costly disputes.
of
Types of Specification
There are different types of specification that may be used:
The first stage in the development of a specification is the preparation of an
outline specification. An outline specification is a brief description of the
main components to be used in construction. They should be described in
sufficient detail to allow the cost consultant to prepare some approximate
quantities.
An outline specification is a description of the main elements to be used in
the construction. Each element will be described at a level of detail that
allows the cost consultant to provide approximate quantities and costs.
Types of Specification
►
Performance specifications are commonly used in projects that are relatively
standard or straightforward. This type of specification describes what the
various elements must do (their performance) and allows the contractor to
determine what materials and systems may be used to provide the expected
performance need.
Performance specification - don't identify a brand, just the performance
characteristics.
■
This gives greater freedom to the contractor and can reduce the cost as a
cheaper alternative is found.
■
The designer must check that the material used complies with the
specification.
 It gives contractor flexibility in his construction approach and limits how
much authority an architect maintains once construction is underway.
 The nature of the performance required may be defined by the desired
outcome or reference to standards such as NBS.
Specifications
►
Prescriptive specifications (or full/Close specifications) are the most detailed.
They are commonly used on projects which have very specific requirements,
either from the client or due to the nature of the project.
For example, a high-level containment laboratory (for working with very
contagious diseases) will have very strict requirements for nearly every aspect of
the project. In this case, the specification will prescribe many of the materials,
systems and processes to be used to construct the facility. Similarly, a high-end
apartment building (which will have very expensive apartments) may have very
particular requirements from the designer and client, in terms of materials and
finishes.
Prescriptive specification - gives clear details about the exact product required.
■ This will link to the performance criteria of the product.
■ Often the words 'or equal approved' & 'or equal' are used.
Specifications
Prescriptive specifications typically provide detailed description of what specific
materials must be used as well as the installation instructions. This type of specification
usually involves three key components:
• General provisions: requirements surrounding codes and standards which may
include information about specific types of material, suppliers, finishes,
etc.
• Required products: the types of products required based on performance and
structural stipulations, provisions may include door hardware, kitchen
equipment, furniture, lighting, etc.
• E x e c u t i o n p r o c e d u r e s / construction/installation methods - the
client team (client/ architects/designers) may specify how custom-
designed items are to be manufactured and installed, to ensure the
quality of the final outcome.
Prescriptive specifications put a greater burden on the architect (as opposed
to the contractor) to ensure proper installation.
Proprietary Specifications demand that only one specific product be used for a
given installation. It is commonly utilized if the portion of a project requires a
certain performance that only one product can achieve. This could ultimately
drive up project costs.
Specification clauses
All Specifications are made up of many clauses. Each clause should be written in a
standard way starting with a general description of the work item followed by more
detailed information.
Simple descriptions should be used using everyday language. Certain types of
description should be avoided altogether, such as:
"finest quality"
" 4
. nm
to th
us·f;ac·v+o
:he A\r, cn·Aiir4ecst4,s sa·#
¢
Specification clauses
Specifications can be written in various ways, for example:
1. The Specification is divided into
two parts:
•
The' Materials Section' - giving exact descriptions of all the materials to be
used, with reference to the relevant British Standards
•
The 'Workmanship Section' - describing exactly how the materials should
be handled and used, with reference to any applicable BS Codes of
Practice.
This method is commonly used for Civil Engineering Works
2.
The Specification is divided into trades. Each trade is then dealt with
separately with a section covering both materials and workmanship.
This method is commonly used for Building Works
3.
The Specification is divided into trades. Each trade is then dealt with
separately with separate sections covering materials and workmanship. E.g.:
(a)
Concrete work
(i)
materials
(ii)
workmanship
(b)
Brickwork and Blockwork
(i)
materials
(ii)
workmanship
Specifications
Specifications can be very complex documents, and their role in describing the
project means they have considerable importance throughout the project.
Their role (along with drawings and schedules) in establishing project costs
during the tender process requires them to be as accurate as possible.
There are standard forms of specification compiled by different industry bodies,
to standardise both the language and the use of specifications. In many
instances, complex templates or software suites are available to support
specification writers to develop clear, precise, standard specifications.
Some of the standards that are available include:
• National Building Specification (NBS) - UK
• MasterFormat (CSI) – USA
• NATSPEC – Australia
Class discussion
Describe specifications
Discuss the importance of specification for a project
What are the difference between outline, descriptive, prescriptive and propriety specification.
Download