Controlling User Manual Prepared by: Vishnu Murthy N Page 1 of 269 Table of Contents CO MODULE OVERVIEW.........................................................................................................6 INTRODUCTION.............................................................................................................................7 COST CENTER ACCOUNTING..............................................................................................10 INTRODUCTION...........................................................................................................................11 MASTER DATA............................................................................................................................12 Cost Element..........................................................................................................................12 Cost Elements Group.............................................................................................................19 Standard Hierarchy...............................................................................................................21 Cost Center............................................................................................................................23 Cost Center Group................................................................................................................28 Activity Type..........................................................................................................................30 Activity Type Group...............................................................................................................33 Statistical Key Figure............................................................................................................35 Statistical Key Figure Group.................................................................................................37 PLANNING...................................................................................................................................39 Cost and Activity Inputs........................................................................................................40 Activity Output/Prices...........................................................................................................44 Statistical Key Figures..........................................................................................................48 Cost Center Budgets..............................................................................................................51 Planning Aids........................................................................................................................53 Plan Assessment Cycle..........................................................................................................57 ACTUAL POSTINGS.....................................................................................................................65 Manual Reposting of Costs....................................................................................................65 Manual Reposting of Revenues.............................................................................................68 Repost Line Items..................................................................................................................70 Statistical Key Figures..........................................................................................................74 PERIOD-END CLOSING................................................................................................................76 Page 2 of 269 Actual Assessment Cycle.......................................................................................................76 INFORMATION SYSTEM...............................................................................................................84 ENVIRONMENT...........................................................................................................................85 Period Lock...........................................................................................................................85 INTERNAL ORDERS.................................................................................................................90 INTRODUCTION...........................................................................................................................91 MASTER DATA............................................................................................................................92 Create Internal Order............................................................................................................92 Internal Order Group..........................................................................................................100 PLANNING.................................................................................................................................102 Overall Values.....................................................................................................................102 Cost and Activity Inputs......................................................................................................104 Planning Aids......................................................................................................................107 BUDGETING..............................................................................................................................111 Original Budget...................................................................................................................111 Supplement...........................................................................................................................113 Return..................................................................................................................................115 Document.............................................................................................................................117 ACTUAL POSTINGS...................................................................................................................119 PERIOD-END CLOSING..............................................................................................................120 Settlement............................................................................................................................120 YEAR-END CLOSING................................................................................................................130 Budget Carry-forward.........................................................................................................130 Commitment Carry-forward................................................................................................132 INFORMATION SYSTEM.............................................................................................................134 PLANT MAINTENANCE ORDERS.......................................................................................135 INTRODUCTION.........................................................................................................................136 MASTER DATA..........................................................................................................................137 Create Plant Maintenance Order........................................................................................137 Page 3 of 269 PERIOD-END CLOSING..............................................................................................................140 Charging of Overheads.......................................................................................................140 Settlement............................................................................................................................148 PRODUCT COST CONTROLLING......................................................................................156 INTRODUCTION.........................................................................................................................157 PRODUCT COST PLANNING......................................................................................................159 Display Materials to be Costed...........................................................................................159 Selection List for Costing Run.............................................................................................162 Edit Selection List for Costing Run.....................................................................................165 Cost Estimate with Quantity Structure................................................................................167 Cost Estimate without Quantity Structure...........................................................................173 Marking Allowance.............................................................................................................178 Marking Standard Cost.......................................................................................................180 Release Standard Cost.........................................................................................................182 PRODUCT COST COLLECTORS.........................................................................................184 INTRODUCTION.........................................................................................................................185 MASTER DATA..........................................................................................................................187 Individual Creation of Product Cost Collector...................................................................187 Collective Creation of Product Cost Collectors..................................................................191 PERIOD-END CLOSING..............................................................................................................193 Charging of Overheads.......................................................................................................193 Variance Calculation...........................................................................................................202 Settlement............................................................................................................................206 PROFITABILITY ANALYSIS.................................................................................................214 INTRODUCTION.........................................................................................................................215 PERIOD-END CLOSING..............................................................................................................219 Assessment Cycle.................................................................................................................219 PROFIT CENTER ACCOUNTING........................................................................................225 Page 4 of 269 INTRODUCTION.........................................................................................................................226 MASTER DATA..........................................................................................................................227 Profit Center........................................................................................................................227 Standard Hierarchy.............................................................................................................230 Profit Center Group.............................................................................................................232 Account Group.....................................................................................................................234 Assignment Monitor............................................................................................................236 ACTUAL POSTINGS...................................................................................................................243 Profit Center Document......................................................................................................243 Statistical Key Figures........................................................................................................246 Period-End Closing.............................................................................................................249 Transferring Payables/Receivables.....................................................................................256 Transferring Assets..............................................................................................................258 Transferring Material Stocks...............................................................................................261 Balance Carry-forward.......................................................................................................263 INFORMATION SYSTEM.............................................................................................................266 Page 5 of 269 Controlling CO Module Overview Page 6 of 269 Controlling Introduction The Controlling Module of SAP R/3 deals with tasks like Cost Center Accounting (create required master data, planning of cost, planned activity prices and period-end closing activities), Internal Orders (create required master data, planning, budgeting, period-end closing activities and variance analysis), Product Costing (calculation of standard cost estimate, actual cost and variance analysis), Profitability Analysis (profitability by customer, customer group, product, product group, profit center, plant, sales order, sales organization, country etc.), and Profit Center Accounting (Profit & Loss Account and Balance Sheet by Profit Center). SCOPE: The following components of CO are covered in different sections of this document: 1. Cost Center Accounting o Master data Cost Element Cost Element Group Standard Hierarchy Cost Center Cost Center Group Activity Type Activity Type Group Statistical Key Figures Statistical Key Figure Group o Planning Cost and Activity Inputs Activity Output/Prices Statistical Key Figures Page 7 of 269 Controlling Cost Center Budgets Planning Aids Allocations o Actual Postings Manual Reposting of Costs Manual Reposting of Revenues Repost Line Items o Period-End Closing Assessment Cycle o Information System Reports for Cost Center Accounting o Environment Period Lock 2. Internal Orders o Master Data Special Functions Order Group o Planning Overall Values Cost and Activity Inputs Planning Aids o Budgeting Original Budget Supplement Return Document Availability Control Page 8 of 269 Controlling o Actual Postings Manual Reposting of Costs Manual Reposting of Revenues Repost Line Items o Period-End Closing Settlement o Year-End Closing Budget Carry forward Commitment Carry forward o Information System Reports for Internal Orders o Environment Period Lock 3. Product Cost Controlling o Product Cost Planning Material Costing Information System o Cost Object Controlling Product Cost by Period Product Cost Collector Period-End Closing Information System Environment 4. Profitability Analysis o Master Data o Actual Postings o Information System Page 9 of 269 Controlling o Environment 5. Profit Center Accounting o Master Data o Actual Postings o Information System o Environment Page 10 of 269 Controlling Cost Center Accounting Cost Center Accounting Page 11 of 269 Controlling Cost Center Accounting Introduction Cost Center Accounting is creating and managing the master data, cost planning, actual postings, information systems and environment. Using cost center accounting: Manage information for cost centers, cost centers group, cost elements, cost elements group, activity types, activity types group, statistical key figures and statistical key figures group. Cost center planning or budget by cost elements. Reposting of actual cost elements, Revenues and line items. Standard reports for actual or plan cost and variance analysis. The Cost Center Accounting is divided in to following sub components: Master data Cost Center Planning Actual Postings Information System Environment Page 12 of 269 Controlling Cost Center Accounting Master Data Master data is the data, which is created and used often as master records and this information provides the basis for cost center accounting. Cost Element The costs in Controlling (CO) are stored under specific cost elements. Cost elements are of two types 1) Primary cost elements 2) Secondary cost elements. All primary cost elements have their corresponding number in the General Ledger (GL) of Financial Accounting (FI) while secondary cost elements exist exclusively in CO. The types of the cost elements are explained in detail below: Page 13 of 269 Controlling Cost Center Accounting PRIMARY COST ELEMENTS Cost Element Category1: These cost elements have their corresponding GL accounts in FI. It means each time there is a Journal Voucher (JV) for the GL account corresponding to the cost element the amounts enters CO. At the time of FI entry the reference of the cost center / internal order / maintenance order etc. need to be given. With this the cost object gets a debit under the cost element for the amount entered in FI entry. Cost Element Category 11: The cost elements of this type are revenue GL accounts. For example, the revenues booked at the time of billing are booked in CO under cost element of this type. Cost Element Category 12: The sales deduction GL accounts have cost element of type 12. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Cost Element Individual Processing Create Primary Transaction Code: KA01 Page 14 of 269 Controlling Cost Center Accounting Screen Shot for Create Primary Cost Element: Initial Screen After entered the cost element, valid from and valid to date click on enter button to get the detailed screen of cost element. Page 15 of 269 Controlling Cost Center Accounting Screen Shot for Create Primary Cost Element In the above screen, name of the cost element, description and cost element category to be entered and click on save button to save the master data. Page 16 of 269 Controlling Cost Center Accounting SECONDARY COST ELMENTS Cost Element Category 21: This is the settlement cost element. Suppose an internal order is to be settled to the cost center and all the cost elements of the internal order need to be clubbed in the receiver cost center under cost element. The settlement profile of the sender cost object need to have the cost element of this type for settlement. At the time of settlement, the sender cost object gets credit and the receiver gets debit under this cost element. Cost Element Category 41: This is an internal activity allocation type of the cost element. This cost element is attached in the activity type master data. Whenever production planning (PP) confirms the activity, the product cost collector gets debited and the cost center where the product cost collector is executed gets credited under this cost element. Cost Element Category 42: The assessment type of the cost element is used during the assessment cycle execution. The receiver cost object gets debited and sender cost object gets credited under this cost element. The individual cost elements of the sender loses their identity in the assessment. Cost Element Category 43: This is overhead type of the cost element. This cost element is maintained in the credit key of the costing sheet. When the costing sheet is executed on the product cost collector the debit for the product cost collector and credit for the cost center maintained in the credit key takes place under this cost element. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Cost Element Individual Processing Create Secondary Transaction Code: KA06 Page 17 of 269 Controlling Cost Center Accounting Screen Shot for Create Secondary Cost Element: Initial Screen After entered the cost element, valid from and valid to date click on enter button to get the detailed screen of cost element. Page 18 of 269 Controlling Cost Center Accounting Screen Shot for Create Secondary Cost Element: Basic Screen In the above screen, name of the cost element, description and cost element category to be entered and click on save button to save the master data. Using the same path, already created cost elements could be displayed and changed. Further, the changes made could be displayed using the same path. Page 19 of 269 Controlling Cost Center Accounting Screen Shot for Change, Display and Delete Secondary Cost Element The cost element can be deleted from the tables provided not posting has been made therein. Page 20 of 269 Controlling Cost Center Accounting Cost Elements Group Cost elements can be grouped under various cost elements groups depending upon the reporting, planning and other requirements. Cost element group CIDS is used as comprehensive cost element group for FFP. The company should make it sure that each newly created cost element is assigned to any one of the sub nodes of this group. At periodical intervals the completeness check should be carried out to verify that all the cost elements are assigned to the group. The path for completeness check is: Extras Check and Help Functions Check Completeness Transaction Path: Accounting Controlling Cost Center Accounting Master Data Cost Element Group Create Transaction Code: KAH1 Screen Shot for Create Cost element group: Initial Screen After entered the cost element group, click on enter button to get the detailed screen of cost element group. Page 21 of 269 Controlling Cost Center Accounting Screen Shot for Create Cost element group: Structure The above screen is used for creating cost element groups in different levels and assigning cost elements. In the above screen, enter the cost element group and click on save button to save cost element group. Page 22 of 269 Controlling Cost Center Accounting Standard Hierarchy All the cost centers of the controlling area are arranged in the form of standard hierarchy, which is made of multiple nodes. The cost centers can be assigned to the last nodes of the hierarchy. The nodes are automatically created as the cost center groups. The hierarchy is designing by creating nodes at same, lower levels to the existing nodes. A lower level node and cost center can’t be assigned to a node. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Standard Hierarchy Display Transaction Code: OKEN Page 23 of 269 Controlling Cost Center Accounting Screen Shot for Display Standard Hierarchy (Cost Center Group): Structure Page 24 of 269 Controlling Cost Center Accounting Cost Center The cost center is an organizational unit in a controlling area representing a clearly delimited location where costs occur. The organizational division can be made on the basis of functional, settlement-technical, activity-technical, spatial, and/or responsibilityrelated standpoints. Cost centers are used for differentiated assignment of overhead costs to sales activities (cost calculation functions) and in order to carry out differentiated controlling of costs occurring in an organization (cost controlling function). All the cost centers of the controlling area are arranged in a sequence called standard hierarchy. Each cost centers master data must contain the name of the node of the hierarchy to which cost center is assigned. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Cost Center Individual Processing Create Transaction Code: KS01 Screen Shot for Create Cost Center: Initial Screen Page 25 of 269 Controlling Cost Center Accounting Screen Shot for Create Cost Center: Basic Screen After entered the required data, click on tab Control for the control data as below: Page 26 of 269 Controlling Cost Center Accounting Screen Shot for Create Cost Center: Indicators After entered the required data, click on tab Address for the enter the address of the cost center. Page 27 of 269 Controlling Cost Center Accounting Screen Shot for Create Cost Center: Address After entered the required data, click on tab Communication for communication to the cost center. Page 28 of 269 Controlling Cost Center Accounting Screen Shot for Create Cost Center: Communication After enter the required data, click on save button to save cost center master data. Page 29 of 269 Controlling Cost Center Accounting Cost Center Group All the nodes of the standard hierarchy are automatically created as the cost center group. Any additional cost center groups can be created, changed, displayed using this transaction. A cost center can be assigned to multiple cost center groups for different purposes. However, a cost center can be assigned to only one node of the standard hierarchy. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Cost Center Group Create Transaction Code: KSH1 Screen Shot for Create Cost Center Group: Initial Screen Page 30 of 269 Controlling Cost Center Accounting Screen Shot for Create Cost Center Group: Structure Page 31 of 269 Controlling Cost Center Accounting Activity Type The activity type divides the specific activities provided by a cost center along cost allocation lines. Valuation of activities is made with an allocation price calculated based on the managerial strategy chosen. A cost center can be assigned one, multiple, or no activity types. Here the integration with the Production Planning (PP) module and Controlling (CO) module starts. The activity types are confirmed by PP for the product cost collector. The activity is confirmed in the units mentioned in the activity type master record. For example packed pizza have Case as the unit of measurement of the activity type. For a given day the production of pizza is 1000 cases. This quantity gets multiplied with the rate maintained in the cost center accounting for the activity type. The product cost collector gets debit and the pizza cost center gets credit under the cost element assigned to the activity type. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Activity Type Individual Processing Create Transaction Code: KL01 Page 32 of 269 Controlling Cost Center Accounting Screen Shot for Create Activity Type: Initial Screen After entered the Activity Type, Valid From and Valid To, click on enter button to get the detailed screen of Activity Type as below: Page 33 of 269 Controlling Cost Center Accounting Screen Shot for Create Activity Type After enter the required data, click on save button to save Activity Type master data. Page 34 of 269 Controlling Cost Center Accounting Activity Type Group Activity Types can be grouped under various Activity Types groups depending upon the reporting, planning and other requirements. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Activity Type Group Create Transaction Code: KLH1 Screen Shot for Create Activity Type Group: Initial Screen After entered the Activity Type Group, click on enter button to get the detailed screen of Activity Type Group as below: Page 35 of 269 Controlling Cost Center Accounting Screen Shot for Create Activity Type Group After enter the required data, click on save button to save Activity Type master data. Page 36 of 269 Controlling Cost Center Accounting Statistical Key Figure The statistical key figures (SKF) are used as the basis for internal allocations in the assessment cycles. Some of the SKF used for allocation purposes are labor hours and machine hours etc. of each cost centers. For example, the cost of the town cost centers are allocated among production cost centers on the basis of the number of employees in the receiver cost centers. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Statistical Key Figure Individual Processing Create Transaction Code: KK01 Screen Shot for Create Statistical Key Figure: Initial Screen After entered the Statistical Key Figure, click on enter button to get the detailed screen as below: Page 37 of 269 Controlling Cost Center Accounting Screen Shot for Create Statistical Key Figure: Master Data After enter the required data, click on save button to save the master data. Page 38 of 269 Controlling Cost Center Accounting Statistical Key Figure Group Similar to other master records, the statistical key figures can also be grouped under groups. Transaction Path: Accounting Controlling Cost Center Accounting Master Data Statistical Key Figure Group Create Transaction Code: KBH1 Screen Shot for Create Statistical Key Figure Group: Initial Screen After entered the Statistical Key Figure, click on enter button to get the detailed screen as below: Page 39 of 269 Controlling Cost Center Accounting Screen Shot for Create Statistical Key Figure Group After enter the required data, click on save button to save the master data. Page 40 of 269 Controlling Cost Center Accounting Planning Groups: Planning can be carried out either at the individual or group levels for all the master data (Cost Element, Cost Center, Activity Types, Statistical Key Figures). Benefits of the Groups: The usage of the groups is a time saving device because the relationship among different master data can be established on the same screen. It is not necessary to complete the initial screen for each constituent of the group. For example: labor cost is to be planned for the all the cost centers. In the initial screen the name of the cost center group and the cost elements need to be mentioned. The labor cost can be planned for all the cost centers using the arrow on the screen. Types of the planning: Each planning screen has the option of 1) Free Planning 2) Form Based planning. For example, we have assigned four cost elements to a group. We are in the process to plan cost elements for cost centers. In the former case, the planning screen for a cost center will be empty and we have to manually input the requisite cost elements numbers and their values for planning. While in the second case all the four cost elements numbers will be automatically displayed in the planning screen of the cost center and we need to simply key in the amounts. Distribution Key: Normally all the planning is done on a yearly basis. Distribution keys are used to break down the yearly figures into monthly ones. Seven types of the distribution keys have been defined by the system. If none of the distribution keys meets our requirements, then user defined distribution keys can be created through IMG settings. Distribution key number 2 divides the planned values to all the months on equal basis. This key is used in FFP. Page 41 of 269 Controlling Cost Center Accounting Cost and Activity Inputs This feature is used to plan the cost elements for he cost centers. There are two types of planning: 1) Activity dependent planning. 2) Activity independent planning. In the former type, the planned cost element are specific to the activity types in the cost center while in the second case the planned cost elements are independent of activity types i.e. they are not planned with respect to a specific activity type. In the basic screen the cost centers, activity types and cost elements are filled in for the first type of planning while the activity type box is kept empty in the second type of the planning. Transaction Path: Accounting Controlling Cost Center Accounting Planning Cost and Activity Inputs Change Transaction Code: KP06 Page 42 of 269 Controlling Cost Center Accounting Screen Shot for Change Cost Element Planning: Initial Screen After entered the required data, click on overview screen button to get the detailed screen as below: Page 43 of 269 Controlling Cost Center Accounting Screen Shot for Change Cost Element Planning: Overview Screen In case, the annual figures to be changed monthly, then put cursor on the relevant cost element and click on period screen (F6). Page 44 of 269 Controlling Cost Center Accounting Screen Shot for Change Cost Element Planning: Period Screen After enter the required data, click on save button to save the data. Page 45 of 269 Controlling Cost Center Accounting Activity Output/Prices This feature is used to plan the quantum of activity types in all the cost centers. The rate of the activity types is also maintained in these screens. Dividing the planned amount by the planned activity type gives the rates. Transaction Path: Accounting Controlling Cost Center Accounting Planning Activity Output/Prices Change Transaction Code: KP26 Page 46 of 269 Controlling Cost Center Accounting Screen Shot for Change Activity Type/Price Planning: Initial Screen After entered the required data, click on overview screen button to get the detailed screen as below: Page 47 of 269 Controlling Cost Center Accounting Screen Shot for Change Activity Type/Price Planning: Overview Screen In case, the annual prices to be changed monthly, then put cursor on the activity type and click on period screen (F6). Page 48 of 269 Controlling Cost Center Accounting Screen Shot for Change Activity Type/Price Planning: Period Screen After enter the required data, click on save button to save the data. Page 49 of 269 Controlling Cost Center Accounting Statistical Key Figures This feature is used to plan the statistical key figures for each cost centers. The group of cost centers and statistical key figures can be used for this exercise. Transaction Path: Accounting Controlling Cost Center Accounting Planning Statistical Key Figures Change Transaction Code: KP46 Screen Shot for Change Statistical Key Figure Planning: Initial Screen After entered the required data, click on overview screen button to get the detailed screen as below: Page 50 of 269 Controlling Cost Center Accounting Screen Shot for Change Statistical Key Figure Planning In case, the annual prices to be changed monthly, then put cursor on the statistical key figure and click on period screen (F6). Page 51 of 269 Controlling Cost Center Accounting Screen Shot for Change Statistical Key Figure Planning: Period Screen After enter the required data, click on save button to save the data. Page 52 of 269 Controlling Cost Center Accounting Cost Center Budgets This feature is used to plan the overall costs for each of the cost centers on a yearly basis. The plan for the previous year is automatically copied in this screen, next to the current year’s budget. The monthly planning is calculated automatically by the system based on the distribution key used in the annual value screen. Transaction Path: Accounting Controlling Cost Center Accounting Planning Cost Center Budgets Change Transaction Code: KPZ2 Screen Shot for Change Budget Planning: Initial Screen After entered the required data, click on overview screen screen as below: button to get the detailed Page 53 of 269 Controlling Cost Center Accounting Screen Shot for Change Budget Planning: Period Overview After enter the required data, click on save button to save the data. Page 54 of 269 Controlling Cost Center Accounting Planning Aids Copy Plan to Plan This feature is used to copy the plan costs for all the cost centers by cost element to another period. This feature has got the processing options. While copying the plan figures from one period to another, there is a facility to overwrite the figures, which are already there in the copying period. Then user has to click on Reset and overwrite button. Transaction Path: Accounting Controlling Cost Center Accounting Planning Planning Aids Copy Copy Plan to Plan Transaction Code: KP97 Screen Shot for Copy Planning: Initial Screen After enter the required data, click on execute button for processing. Page 55 of 269 Controlling Cost Center Accounting Screen Shot for Copy Planning: Detail List After getting the above screen, click on back button to leave the screen. Page 56 of 269 Controlling Cost Center Accounting Copy Actual to Plan This feature is used to copy the actual costs for all the cost centers by cost element to another period. This feature has got the processing options. While copying actual figures from one period to another, there is a facility to overwrite the figures, which are already there in the copying period. Then user has to click on Reset and overwrite button. Transaction Path: Accounting Controlling Cost Center Accounting Planning Planning Aids Copy Copy Actual to Plan Transaction Code: KP98 Screen Shot for Copy Actual to Plan: Initial Screen After enter the required data, click on execute button for processing. Page 57 of 269 Controlling Cost Center Accounting Screen Shot for Copy Actual to Plan: Detail List After getting the above screen, click on back button to leave the screen. Page 58 of 269 Controlling Cost Center Accounting Allocations: Plan Assessment Cycle Assessment cycle is used for transferring cost from one cost center (called sender cost centers) to the other cost centers (called receiver cost centers). The other receivers in the cycle could be internal orders, cost objects etc. Various aspects of a cycle are mentioned hereunder: Creation of Assessment Cycle Name: Give the name and the effective date to the cycle and press enter. Text: Enter the text and press attach segment. Name: Give the name to the segment and text. Sender Values: a) Rules: There are three options: (i) Posted Amounts: The basis for the transfer of values from one cost center to the other cost centers is the posted values in the sender cost centers. (ii) Fixed Amount: The sender transfers the values at the predefined rates. (iii) Fixed Rates: The sender transfers the values to the receivers at predefined percentages of the base figures. b) Percentages: The % of the value determined according to the above rule (Rule a) to be transferred to the receivers is mentioned here. c) Actual/ Plan Buttons: Selection of this button is based on the data for which the cycle is to be run. The cycle used for the distribution of the planned cost should have “planned” button while that for actual cost should have “actual” button on. d) Sender Cost Center: The name of the sender cost center or group is to be mentioned. e) Cost Element: The cost elements or group to take part in the distribution, pertaining to the sender cost center or group thereof be mentioned here. f) Receiver Order/ Cost Center/ Cost Object: The name of the receiver cost center/ order/ cost object or group thereof is to be mentioned. Page 59 of 269 Controlling Cost Center Accounting g) Tracing Factor Field Group: The basis on which the values to be distributed among the receivers to be mentioned here. SAP has defined 10 tracing factors. Any one of the suitable bases may be used as tracing factor. h) Selection Criteria: Tracing factor field group chosen above could have more than one value. The factor, which is to take part in the execution of the operation, is called selection criteria. For example, statistical key figure is the tracing factor and the number of labor hours (one of the statistical key figure) in each cost center is the selection criteria. i) More than one segment: If sender’s values are to be transferred to the receivers on more than one basis, multiple segments are used. But in that case, the total amount, which is to be transferred, should not exceed 100%. For example, 50% of the sender cost is distributing on the basis of fixed % and in another segment remaining 50% can be distributed on the basis of variable portions by using Tracing factor SKF. Further, more than one segment can be used in the cycle for the distribution of various costs with the combination. j) Receivers Weighing: Suppose we wish to distribute the costs of the sender cost center to two receiver cost center on the basis of number of employees as the tracing factor. However we wish to charge first cost center at double the rate than the second cost center. In such a case we give receiver weighing of 2 and 1 to first and second cost centers respectively. k) Blocked: If the blocked button is switched on than that particular segment can’t be used for allocation purposes. l) Run: Once the cycle is complete in all respects it could be run periodically. Page 60 of 269 Controlling Cost Center Accounting Path for creation of Plan Assessment Cycle: Transaction Path: Accounting Controlling Cost Center Accounting Planning Allocations Assessment Extras Cycle Create Transaction Code: KSU7 Screen Shot for Create Plan Assessment Cycle: Initial Screen After enter the name of the cycle and start date, click on enter button to get the header data. Page 61 of 269 Controlling Cost Center Accounting Screen Shot for Create Plan Assessment Cycle: Header Data After enter the required data, click on Attach Segment for attaching the segments. Page 62 of 269 Controlling Cost Center Accounting Screen Shot for Create Plan Assessment Cycle: Segment After entering the relevant fields, then click on tab Senders/Receivers for enter the data for sender or receiver cost centers and cost element/group. Page 63 of 269 Controlling Cost Center Accounting Screen Shot for Create Plan Assessment Cycle: Segment (Senders/Receivers) After the above screen, then click on tab Receiver Tracing Factor for enter the % against receiver cost centers. Page 64 of 269 Controlling Cost Center Accounting Screen Shot for Create Plan Assessment Cycle: Segment (Receiver Tracing Factor) If the sender rule is on the basis of variable portions, then the above screen will be looks as below: Page 65 of 269 Controlling Cost Center Accounting Screen Shot for Create Plan Assessment Cycle: Segment (Receiver Tracing Factor) After enter the required data, click on save After save the changes made, click on back button to save the data. button to leave the screen. Page 66 of 269 Controlling Cost Center Accounting Actual Postings Manual Reposting of Costs This feature is used to transfer costs from one cost center to other. Suppose, by mistake an expense has been debited to a wrong cost center. Using this method, the costs can be transferred to the correct cost center. This results in credit for the wrong cost center and debit for the correct cost center. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Manual Reposting of Costs Enter Transaction Code: KB11N Page 67 of 269 Controlling Cost Center Accounting Screen Shot for Manual Reposting of Primary Costs After enter the required data, click on save button to save the data. Page 68 of 269 Controlling Cost Center Accounting Reversal of Reposting of Primary Costs: This feature is used to reverse the entry, which has already posted as above. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Manual Reposting of Costs Reverse Transaction Code: KB14N Screen Shot for Reverse Manual Reposting of Primary Costs Enter the details of Document Date, Posting Date, Reverse Document and Document Text and press enter to get the details. After entering the required details, click on save button to save the document. Page 69 of 269 Controlling Cost Center Accounting Manual Reposting of Revenues This feature is used to transfer revenues from one cost center to other. Suppose, by mistake any revenue has been credited to a wrong cost center. Using this method, the costs can be transferred to the correct cost center. This results in debit for the wrong cost center and credit for the correct cost center. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Manual Reposting of Revenues Enter Transaction Code: KB41N Screen Shot for Manual Reposting of Revenues After enter the required data, click on save button to save the data. Page 70 of 269 Controlling Cost Center Accounting Reversal of Reposting of Revenues: This feature is used to reverse the entry, which has already posted as above. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Manual Reposting of Revenues Reverse Transaction Code: KB44N Screen Shot for Reverse Manual Reposting of Revenues Enter the details of Document Date, Posting Date, Reverse Document and Document Text and press enter to get the details. After entering the required details, click on save button to save the document. Page 71 of 269 Controlling Cost Center Accounting Repost Line Items At the time of posting the transactions in General Ledger (GL) of Financial Accounting (FI), each line item must be assigned a cost center. If cost center assignment of one or more than one line items are to be changed then this feature can be used. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Repost Line Items Enter Transaction Code: KB61 Screen Shot for Enter Line Item Reposting: Initial Screen After this screen, click on execute button for the detailed report. Page 72 of 269 Controlling Cost Center Accounting Screen Shot for Enter Reposting of Line Items: List After this screen, double click on the line item, which would like to change. Then the following screen will appear. Then change the new account assignment (Amount, Text and Cost Center). Page 73 of 269 Controlling Cost Center Accounting Screen Shot for Enter Reposting of Line Items: Individual Processing After enter the required data, click on save button to save the data. Page 74 of 269 Controlling Cost Center Accounting Reversal of Reposting of Line Items: This feature is used for the reversal of reposting revenues, which explained above. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Repost Line Items Reverse Transaction Code: KB64 Screen Shot for Enter Reverse Reposting of Line Items: List After getting the above screen, click on save button to save the document. Page 75 of 269 Controlling Cost Center Accounting Statistical Key Figures Enter Statistical Key Figures: This feature is used to enter the actual statistical key figures on a monthly basis. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Statistical Key Figures Enter Transaction Code: KB31N Screen Shot for Enter Statistical Key Figures After getting the above screen, click on save button to save the document. Page 76 of 269 Controlling Cost Center Accounting Reverse Statistical Key Figures: This feature is used to enter the actual statistical key figures on a monthly basis. Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Statistical Key Figures Reverse Transaction Code: KB34N Screen Shot for Reverse Statistical Key Figures After getting the above screen, click on save button to save the document. Page 77 of 269 Controlling Cost Center Accounting Period-End Closing Allocations: Actual Assessment Cycle Assessment cycle is used for transferring cost from one cost center (called sender cost centers) to the other cost centers (called receiver cost centers). The other receivers in the cycle could be internal orders, cost objects etc. Various aspects of a cycle are mentioned hereunder: Creation of Assessment Cycle Name: Give the name and the effective date to the cycle and press enter. Text: Enter the text and press attach segment. Name: Give the name to the segment and text. Sender Values: a) Rules: There are three options: (i) Posted Amounts: The basis for the transfer of values from one cost center to the other cost centers is the posted values in the sender cost centers. (ii) Fixed Amount: The sender transfers the values at the predefined rates. (iii) Fixed Rates: The sender transfers the values to the receivers at predefined percentages of the base figures. b) Percentages: The % of the value determined according to the above rule (Rule a) to be transferred to the receivers is mentioned here. c) Actual/ Plan Buttons: Selection of this button is based on the data for which the cycle is to be run. The cycle used for the distribution of the planned cost should have “planned” button while that for actual cost should have “actual” button on. d) Sender Cost Center: The name of the sender cost center or group is to be mentioned. e) Cost Element: The cost elements or group to take part in the distribution, pertaining to the sender cost center or group thereof be mentioned here. Page 78 of 269 Controlling Cost Center Accounting f) Receiver Order/ Cost Center/ Cost Object: The name of the receiver cost center/ order/ cost object or group thereof is to be mentioned. g) Tracing Factor Field Group: The basis on which the values to be distributed among the receivers to be mentioned here. SAP has defined 10 tracing factors. Any one of the suitable bases may be used as tracing factor. h) Selection Criteria: Tracing factor field group chosen above could have more than one value. The factor, which is to take part in the execution of the operation, is called selection criteria. For example, statistical key figure is the tracing factor and the number of labor hours (one of the statistical key figure) in each cost center is the selection criteria. i) More than one segment: If sender’s values are to be transferred to the receivers on more than one basis, multiple segments are used. But in that case, the total amount, which is to be transferred, should not exceed 100%. For example, 50% of the sender cost is distributing on the basis of fixed % and in another segment remaining 50% can be distributed on the basis of variable portions by using Tracing factor SKF. Further, more than one segment can be used in the cycle for the distribution of various costs with the combination. j) Receivers Weighing: Suppose we wish to distribute the costs of the sender cost center to two receiver cost center on the basis of number of employees as the tracing factor. However we wish to charge first cost center at double the rate than the second cost center. In such a case we give receiver weighing of 2 and 1 to first and second cost centers respectively. k) Blocked: If the blocked button is switched on than that particular segment can’t be used for allocation purposes. l) Run: Once the cycle is complete in all respects it could be run periodically. Page 79 of 269 Controlling Cost Center Accounting Path for creation of Actual Assessment Cycle: Transaction Path: Accounting Controlling Cost Center Accounting Period-End Closing Single Functions Allocations Assessment Extras Cycle Create Transaction Code: KSU1 Screen Shot for Create Actual Assessment Cycle: Initial Screen After enter the name of the cycle and start date, click on enter button to get the header data. Page 80 of 269 Controlling Cost Center Accounting Screen Shot for Create Actual Assessment Cycle: Header Data After this screen, clink on Attach Segment for attaching the segments. Page 81 of 269 Controlling Cost Center Accounting Screen Shot for Create Actual Assessment Cycle: Segment After entering the relevant fields, then click on tab Senders/Receivers for enter the data for sender or receiver cost centers and cost element/group. Page 82 of 269 Controlling Cost Center Accounting Screen Shot for Create Actual Assessment Cycle: Segment (Senders/Receivers) After the above screen, then click on tab Receiver Tracing Factor for enter the % against receiver cost centers. Page 83 of 269 Controlling Cost Center Accounting Screen Shot for Create Actual Assessment Cycle: Segment (Receiver Tracing Factor) If the sender rule is on the basis of variable portions, then the above screen will be looks as below screen: Page 84 of 269 Controlling Cost Center Accounting Screen Shot for Create Actual Assessment Cycle: Segment (Receiver Tracing Factor) After getting the above screen, click on save button to save the document. After save the changes made, click on back button to leave the screen. Page 85 of 269 Controlling Cost Center Accounting Information System Various reports of the cost centers are available on the screens. Transaction Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Choose Report Transaction Code: S_ALR_87013611 TO S_ALR_87013648 Screen shot for Reports for Cost Center Accounting Page 86 of 269 Controlling Cost Center Accounting Environment Period Lock This feature is used to lock the transactions for a period. With this facility usage of the transaction is prevented for the locked periods. The locking facility is available for both the plan and actual transactions. Transaction Path: Accounting Controlling Cost Center Accounting Environment Period Lock Change Transaction Code: OKP1 Screen Shot for Change Period Lock: Initial Screen After enter the Controlling Area, Fiscal Year and Version, click on Actual to get the detailed screen as below: Page 87 of 269 Controlling Cost Center Accounting Actual Period Lock: Screen Shot for Change Actual Period Lock: Edit Click the cursor on the period, which is to be locked and then click on Lock Period and click on save button to save the changes made. Page 88 of 269 Controlling Cost Center Accounting After getting the initial screen and the required data, click on Plan to get the detailed screen as below: Plan Period Lock: Screen Shot for Change Plan Period Lock: Edit Click the cursor on the period, which is to be locked and then click on Lock Period and click on save button to save the changes made. Page 89 of 269 Controlling Cost Center Accounting Actual Period Unlock: Screen Shot for Change Actual Period Lock: Edit Click the cursor on the period, which is to be unlocked and then click on Unlock Period and click on save button to save the changes made. Page 90 of 269 Controlling Cost Center Accounting After getting the initial screen and the required data, click on Plan to get the detailed screen as below: Plan Period Unlock: Screen Shot for Change Plan Period Unlock: Edit Click the cursor on the period, which is to be unlocked and then click on Unlock Period and click on save button to save the changes made. Page 91 of 269 Controlling Internal Orders Internal Orders Page 92 of 269 Controlling Internal Orders Introduction Internal Order Accounting is creating and managing the Master Data, Cost Planning or Budgeting, Actual Postings, Information Systems and Environment. Using Internal Orders you can Manage information for revenue and capital internal orders. Internal Order Planning or budget by cost elements. Standard reports for actual or plan cost and variance analysis. The Internal orders divided in to following sub components: Master data Planning Budgeting Actual Postings Information System Environment Page 93 of 269 Controlling Internal Orders Master Data Master data is the data, which is created and used often as master records and this information provides the basis for internal order accounting. Create Internal Order This feature is used to create internal order master data and enter the settlement rule. Internal orders of two types: Revenue and Capital internal orders. After entering the required fields in the master, save the order. System will generate an internal order number. Transaction Path: Accounting Controlling Internal Orders Master Data Special Functions Order Create Transaction Code: KO01 Page 94 of 269 Controlling Internal Orders Screen Shot for Create Internal Order: Initial Screen After enter the Order Type IN01, click on enter button to get the detailed screen as below: Page 95 of 269 Controlling Internal Orders Screen Shot for Create Internal Order: Master Data After entered the required data, click on tab Control data to release the internal order. Page 96 of 269 Controlling Internal Orders Screen Shot for Create Internal Order Master data: Control data After getting this screen, click on System status “Release” to release the order. After release the order, click on General data to enter the details as below: Page 97 of 269 Controlling Internal Orders Screen Shot for Create Internal Order Master Data: General data After entered the general data, click on Settlement Rule to enter the details as below: Page 98 of 269 Controlling Internal Orders Screen Shot for Create Internal Order Master Data: Maintain Settlement Rule After entering the above data, click on save button. System will generate one internal order number. After creating the order, order can be displayed by using the following path. Page 99 of 269 Controlling Internal Orders Transaction Path: Accounting Controlling Internal Orders Master Data Special Functions Order Display Transaction Code: KO03 Screen Shot for Display Internal Order: Master data The following path is used for change the master data of internal order. Page 100 of 269 Controlling Internal Orders Transaction Path: Accounting Controlling Internal Orders Master Data Special Functions Order Change Transaction Code: KO02 Screen Shot for Change Internal Order: Master data After making the necessary changes, click on save button to save the changes. After creating the internal orders, they can be grouped for reporting purpose. Page 101 of 269 Controlling Internal Orders Internal Order Group This feature is used to create internal order master data and enter the settlement rule. Internal orders of two types: Revenue and Capital internal orders. After entering the required fields in the master, save the order. System will generate an internal order number. Transaction Path: Accounting Controlling Internal Orders Master Data Order Group Create Transaction Code: KOH1 Screen Shot for Create Order Group: Initial Screen After entered the Order Group, which is to be created click on enter button to get the detailed screen as below: Page 102 of 269 Controlling Internal Orders Screen Shot for Create Order Group: Structure After entered the required details, click on save button to save the changes. Page 103 of 269 Controlling Internal Orders Planning Overall Values This feature is used for planning the annual costs for internal orders. Transaction Path: Accounting Controlling Internal Orders Planning Overall Values Change Transaction Code: KO12 Screen Shot for Change Overall Planning: Initial Screen After entered the Order number and Version, click on enter button to get the detailed screen as below: Page 104 of 269 Controlling Internal Orders Screen Shot for Change Overall Plan Values: Annual overview After entered the Plan amount by year, click on save button to save the changes. Page 105 of 269 Controlling Internal Orders Cost and Activity Inputs This feature is used for planning the costs by cost elements for internal orders. Transaction Path: Accounting Controlling Internal Orders Planning Cost and Activity Inputs Change Transaction Code: KPF6 Screen Shot for Planning Cost Elements Change: Initial screen After entered the required data, click on Overview Screen (F5) to get the detailed screen as below: Page 106 of 269 Controlling Internal Orders Screen Shot for Planning Cost Elements: Overview screen In case, the annual figures to be changed monthly, then put cursor on the relevant cost element and click on period screen (F6). Page 107 of 269 Controlling Internal Orders Screen Shot for Change Cost Element Planning Change: Period Screen After enter the required data, click on save button to save the data. Page 108 of 269 Controlling Internal Orders Planning Aids Copy Planning This feature is used for copying the planning data of internal orders to another period. Transaction Path: Accounting Controlling Internal Orders Planning Planning Aids Copy Planning Transaction Code: KO14 Screen Shot for Copy Planning: Initial Screen After entered the required data, click on execute button for the detailed screen as below: Page 109 of 269 Controlling Internal Orders Screen Shot for Copy Planning: Detail List Page 110 of 269 Controlling Internal Orders Copy Actual to Plan This feature is used for copying the actual data of internal orders to another period as a planning. Transaction Path: Accounting Controlling Internal Orders Planning Planning Aids Copy Actual to Plan Transaction Code: KO15 Screen Shot for Copy Actual to Plan: Initial screen After entered the required data, click on execute below: button for the detailed screen as Page 111 of 269 Controlling Internal Orders Screen Shot for Copy Actual to Plan: Detail List Page 112 of 269 Controlling Internal Orders Budgeting Original Budget This feature is used for budget the annual costs for internal orders. Transaction Path: Accounting Controlling Internal Orders Budgeting Original Budget Change Transaction Code: KO22 Screen Shot for Change Original Budget: Initial Screen After entered the order number, click on enter below: button for the detailed screen as Page 113 of 269 Controlling Internal Orders Screen Shot for Change Original Budget: Annual Overview Enter the budget amount and click on save button to save the data. After saving the above screen, system will generate a controlling document number. Page 114 of 269 Controlling Internal Orders Supplement This feature is used for enter the additional budget amount for internal orders. Transaction Path: Accounting Controlling Internal Orders Budgeting Supplement Change Transaction Code: KO24 Screen Shot for Change Supplement: Initial Screen After entered the order number, click on enter below: button for the detailed screen as Page 115 of 269 Controlling Internal Orders Screen Shot for Change Supplement: Annual Overview After enter the details, click on save button to save the data. After saving the above screen, system will generate a controlling document number. Page 116 of 269 Controlling Internal Orders Return This feature is used for return / deduct the budget amount for internal orders. Transaction Path: Accounting Controlling Internal Orders Budgeting Return Change Transaction Code: KO26 Screen Shot for Change Return: Initial Screen After entered the order number, click on enter below: button for the detailed screen as Page 117 of 269 Controlling Internal Orders Screen Shot for Change Return: Annual Overview After enter the details, click on save button to save the data. After saving the above screen, system will generate a controlling document number. Page 118 of 269 Controlling Internal Orders Document This feature is used for enter the text for original budget / supplement / return for internal orders. Transaction Path: Accounting Controlling Internal Orders Budgeting Document Change Transaction Code: KO2A Screen Shot for Change Document: Initial Screen After entered the Document number, click on enter as below: button for the detailed screen Page 119 of 269 Controlling Internal Orders Screen Shot for Change Document After enter the Long Text and Text, click on save button to save the data. Page 120 of 269 Controlling Internal Orders Actual Postings This feature is same as the Actual Postings of Cost Center Accounting. Please refer the transactions of the following: Transaction Path: Accounting Controlling Cost Center Accounting Actual Postings Page 121 of 269 Controlling Internal Orders Period-End Closing Settlement Settlement of Individual internal orders This feature is used for settlement of individual internal orders as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Individual Processing Transaction Code: KO88 Screen Shot for Actual Settlement: Order After entered the required data, click on execute button to get the below screen: Page 122 of 269 Controlling Internal Orders Screen Shot for Actual Settlement: Order Detail List After getting the above screen, select the order number and click on accounting documents to view the different types of documents. Page 123 of 269 Controlling Internal Orders Screen Shot for Actual Settlement: Documents in Accounting Page 124 of 269 Controlling Internal Orders Reverse the Settlement of individual internal orders This feature is used for reverse the settlement. After reversal of settlement, the accounting entries will be generated and the order balance will come to the original status. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Individual Processing Transaction Code: KO88 Screen Shot for Actual Settlement: Reversal Order After getting the screen, enter the required data and then go to menu “Settlement and click on Reverse”. Page 125 of 269 Controlling Internal Orders Screen Shot for Actual Reversal Order: Documents in Accounting Page 126 of 269 Controlling Internal Orders Settlement of Collective internal orders This feature is used for collectively settle the internal orders. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Collective Processing Transaction Code: KO8G Screen Shot for Actual Settlement: Orders After entered the above details, click on execute button to get the detailed screen as below: Page 127 of 269 Controlling Internal Orders Screen Shot for Actual Settlement: Orders Detail List After getting the above screen, select any order and then click on accounting documents to view the different types of documents as below: Page 128 of 269 Controlling Internal Orders Screen Shot for Actual Settlement: Documents in Accounting Page 129 of 269 Controlling Internal Orders Collectively Reversal of Settlement of collective internal orders This feature is used for collectively reverse the settlement of internal orders. After reversal the accounting entries will be generated and the order balance will come to the original status. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Collective Processing Transaction Code: KO8G Screen Shot for Actual Settlement: Reversal Orders After getting the above screen, enter the required data and then go to menu “Settlement and click on Reverse”. Page 130 of 269 Controlling Internal Orders Screen Shot for Actual Reversal Orders: Documents in Accounting Page 131 of 269 Controlling Internal Orders Year-End Closing Budget Carry-forward This feature is used for carry-forward the budget amount, which is left in the previous year. This transaction will be run once in a year. Transaction Path: Accounting Controlling Internal Orders Year-End Closing Budget Carry-forward Transaction Code: KOCO Screen Shot for Budget Carry-forward for Orders After entered the required data, click on execute button to get the below screen: Page 132 of 269 Controlling Internal Orders Screen Shot for Budget Carry-forward for Orders: Detail Screen Page 133 of 269 Controlling Internal Orders Commitment Carry-forward This feature is used for carry-forward the budget amount, which is left in the previous year. This transaction will be run once in a year. Transaction Path: Accounting Controlling Internal Orders Year-End Closing Commitment Carry-forward Transaction Code: KOCF - Commitment Carry-forward Screen Shot for Commitment Carry-forward for Orders After entered the required data, click on execute button to get the below screen: Page 134 of 269 Controlling Internal Orders Screen Shot for Commitment Carry-forward for Orders Page 135 of 269 Controlling Internal Orders Information System Various reports of the cost centers are available on the screens. Transaction Path: Accounting Controlling Internal Orders Information System Reports for Internal Orders Choose Report Transaction Code: S_ALR_87012993 TO S_ALR_87013019 Screen shot for Reports for Internal Orders Page 136 of 269 Controlling Plant Maintenance Orders Plant Maintenance Orders Page 137 of 269 Controlling Plant Maintenance Orders Introduction The Plant Maintenance (PM) module requires the creation of maintenance orders for each and every maintenance task taken up by the company. The principles of booking of material costs, external services, activity types and overheads remains the same as product cost collectors. The maintenance orders created by the maintenance department are charged with the issues of materials, activity confirmations, external processing charges etc. At the end of the period the overheads are loaded on the orders and finally the order is settled to single or multiple cost centers as per the settlement rule which is maintained in the master data of maintenance order. The settlement transaction passes on the costs of the order to the cost centers. The role of Finance / Costing department about plant maintenance orders is as follows: Charging of Overheads Settlement of Orders Information System Page 138 of 269 Controlling Plant Maintenance Orders Master Data Master data is the data, which is created and used often as master records and this information provides the basis for maintenance orders. Create Plant Maintenance Order This feature is used to create maintenance order master data and enter the settlement rule by the Plant Maintenance module. Transaction Path: Logistics Plant Maintenance Maintenance Processing Order Create (General) Transaction Code: IW31 Page 139 of 269 Controlling Plant Maintenance Orders Screen Shot for Create Plant Maintenance Order Settlement rule has to be maintained as follows: Menu Goto Settlement Rule Page 140 of 269 Controlling Plant Maintenance Orders Screen Shot for Maintain Settlement Rule for PM Orders After entering the above data, click on save button and system will generate an internal order number. Page 141 of 269 Controlling Plant Maintenance Orders Period-End Closing Charging of Overheads Individual Charging of Overheads to PM orders This feature is used for charging overheads to the PM orders at the month end as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Overhead Rates Individual Processing Transaction Code: KG12 Screen Shot for Actual Overhead Calculation: PM Order After entered the Order number, Period and Fiscal Year, click on execute button to calculate the overhead as below: Page 142 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Settlement: Order Detail List Page 143 of 269 Controlling Plant Maintenance Orders Reverse the charging of overheads to PM Orders This feature is used for reverse the charging of overheads. After reversal, the accounting entries will be generated and the order will come to the original status. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Overhead Rates Individual Processing Transaction Code: KG12 Screen Shot for Reversal of Actual Overhead Calculation After getting the screen, entered the required data and then go to menu “Overhead Calculation and click on Reverse”. Page 144 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Reversal of Charging Overheads to PM Orders Page 145 of 269 Controlling Plant Maintenance Orders Collectively Charging of Overheads to the PM Orders This feature is used for charging of overheads collectively to the PM Orders. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Overhead Rates Collective Processing Transaction Code: KG14 Screen Shot for Actual Overhead Calculation: Internal/maintenance orders After entered the above details, click on execute button. Page 146 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Overhead Calculation: Internal/maintenance orders Debits Page 147 of 269 Controlling Plant Maintenance Orders Collectively Reversal of Charging Overheads to PM Orders This feature is used for collectively reverse the charging of overheads to the PM orders. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Overhead Rates Actuals: Collective Processing Transaction Code: KG14 Screen Shot for Reversal of Actual Overhead Calculation for PM Orders After getting the screen, enter the required data and then go to menu “Overhead Calculation and click on Reverse”. Page 148 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Reversal of Charging Overheads to the PM Orders Page 149 of 269 Controlling Plant Maintenance Orders Settlement Individual Settlement of PM orders This feature is used for individual settlement of PM orders at the month end as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Individual Processing Transaction Code: KO88 Screen Shot for Actual Settlement: Order After entered the above details, click on execute button to settle the order as shown below: Page 150 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Settlement: Order Detail List and Documents in Accounting Page 151 of 269 Controlling Plant Maintenance Orders Reverse the Settlement of individual PM Orders This feature is used for reverse the settlement of PM Order. After reversal, the accounting entries will be generated and the order will come to the original status. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Individual Processing Transaction Code: KG12 Screen Shot for Reversal of Actual Settlement After getting the screen, entered the required data and then go to menu “Settlement and click on Reverse”. Page 152 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Reversal of Settlement and Documents in Accounting Page 153 of 269 Controlling Plant Maintenance Orders Collective Settlement of PM Orders This feature is used for collective settlement of PM Orders. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Collective Processing Transaction Code: KO8G Screen Shot for Actual Settlement: Orders After entered the above details, click on execute button to get the detailed screen as below: Page 154 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Settlement: Orders Detail List Page 155 of 269 Controlling Plant Maintenance Orders Collectively Reverse of Settlement of PM Orders This feature is used for collectively reverse the settlement of PM orders. Transaction Path: Accounting Controlling Internal Orders Period-End Closing Single Functions Settlement Collective Processing Transaction Code: KO8G Screen Shot for Reversal of Actual Collective Settlement of PM Orders After getting the screen, enter the required data and then go to menu “Settlement and click on Reverse”. Page 156 of 269 Controlling Plant Maintenance Orders Screen Shot for Actual Reversal of Collective Settlement of PM Orders: Orders Detail List Page 157 of 269 Controlling Product Cost Controlling Product Cost Controlling Page 158 of 269 Controlling Product Cost Controlling Introduction In FFP, the Semi-finished and finished goods are valued at the standard price while all the raw materials, packaging materials, consumable stores and commercial / traded goods are valued at the moving average prices. The system calculates the standard price of the material and updates the value in the accounting and costing views of the material master. The standard cost of the product is calculated by system on the basis of the Bill of Material (BOM), Routing and Costing sheet. On marking the cost estimate the future standard price of the material master gets updated with price. Once the standard cost estimate is released the marked price (future price) becomes the current standard price. The inventories are always valued at this price till the standard cost estimate is revised. The release can be done once in a month. In the next month again the standard cost estimate can be created for the material. This is marked and released again. The new cost estimate becomes the current standard cost estimate and the last months-standard price shifts in the column of past standard cost estimate of the material master. The revision of the standard cost estimate should not be undertaken at frequent intervals. Normally, the standard prices are created and updated at the beginning of the year. Product cost estimate on the basis of Bill Of Material (BOM) and Routing is with quantity structure. Product cost estimate without Bill Of Material (BOM) and Routing is without quantity structure. Product cost estimate can be created for one material at one time. Product cost estimate can be created for a range of materials at one time. The screen/ path for single product and cumulative product cost estimate are different. The documentation is divided in three sections: Section Contents Page 159 of 269 Controlling Product Cost Controlling 1 Product cost estimate for one material 2 Product cost estimate for range of material 3 Other features of Product cost estimate The scope of the Product Costing is as follows: Product Cost Planning Display Materials to be Costed Costing Run Cost Estimate with Quantity Structure Cost Estimate Without Quantity Structure Price Update Information System Cost Object Controlling Product Cost by Period Master Data Period-End Closing Information System Page 160 of 269 Controlling Product Cost Controlling Product Cost Planning Display Materials to be Costed This feature is used for find out the semi-finished and finished goods, which are to be costed. Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Display Materials to be Costed Transaction Code: CKAPP01 Page 161 of 269 Controlling Product Cost Controlling Screen Shot for Display Materials To Be Costed: Initial Screen After entered the required data, click on execute button to get the detailed screen as below: Page 162 of 269 Controlling Product Cost Controlling Screen Shot for Display Materials To Be Costed: Detailed Screen Page 163 of 269 Controlling Product Cost Controlling Selection List for Costing Run This feature is used for creating a selection list of materials, material type and plant for the materials. Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Costing Run Selection List Create Transaction Code: CKMATSEL Page 164 of 269 Controlling Product Cost Controlling Screen Shot for Create Selection List for Costing Run: Initial Screen After entered the required data, click on execute button to get the detailed screen as below: Page 165 of 269 Controlling Product Cost Controlling Screen Shot for Create Selection List for Costing Run: Detailed Screen After getting the above screen, click on save button to save the selection list. Page 166 of 269 Controlling Product Cost Controlling Edit Selection List for Costing Run This feature is used for editing the selection list of materials, material type and plant for the materials. Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Costing Run Selection List Edit Transaction Code: CKMATCON Page 167 of 269 Controlling Product Cost Controlling Screen Shot for Edit Selection List for Costing Run After making the necessary change, click on save button to save the selection list. Page 168 of 269 Controlling Product Cost Controlling Cost Estimate with Quantity Structure This feature is used for calculate standard cost with quantity structure for individual materials. The cost estimate of the semi-finished, finished goods whose BOM and Routings etc. are available in the system, are calculated using this feature. The system reads the constituents of the cost from the following sources: Give the details of costing variant, material, plant, costing version (1) and costing lot size. Press enter. If no lot size is given, the system picks up the same from the costing view of the material master. The system proposes the dates of various parameters as per the date control ID maintained in the costing type view of the IMG settings. The costing type is attached to the costing variant. The dates proposed by the system can be changed manually, if required. The following dates are proposed: Costing Date From: This is the date from which the cost estimate is valid Costing Date To: The date up to, which the standard cost estimate is to be valid. Quantity Structure Date: The date with which the bills of material and recipe are selected. Valuation Date: Dates for which the material values and activity prices are selected for the calculation of standard cost estimate. Once the data are validated by the system the standard cost estimate is generated by system. With this, the system reaches to the screen of standard cost estimate. This screen gives the following information: Page 169 of 269 Controlling Product Cost Controlling Costing Data: Costing variant used, Posting period, Cost Version, Lot Size, Messages and the status of the costing calculation are displayed on the screen. Valuation Data: Valuation Variant, Currency, Costing Sheet used for the calculation of the standard cost is displayed. If overhead group and key are also used, they are also displayed. Cost Component View: The system gives various components views as per IMG settings for the cost component layout. Details: On the front screen, summary of various cost component views are displayed. The details can see by putting the cursor on the view whose details to be seen and pressing cost component on the lower left part of the screen. Similarly the details of the itemization view for each of the cost component view can be displayed. The combination of Total Cost / fixed cost and Total Cost/ Variable cost can be view by press the button on the lower right side of the screen. Page 170 of 269 Controlling Product Cost Controlling Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Cost Estimate with Quantity Structure Create Transaction Code: CK11N Screen Shot for Create Material Cost Estimate with Quantity Structure After entering the above details, press on enter button to get the date control screen as below: Page 171 of 269 Controlling Product Cost Controlling Screen Shot for Create Material Cost Estimate with Quantity Structure (Date Control) In this screen, costing dates to be entered. So that standard cost will be valid for that period. After entering the above details, click on enter to calculate the standard cost. Page 172 of 269 Controlling Product Cost Controlling Screen Shot for Create Material Cost Estimate with Quantity Structure (Display the Cost) After getting the above screen, click on the button “cost components” for cost breakup. Page 173 of 269 Controlling Product Cost Controlling Screen Shot for Create Material Cost Estimate with Quantity Structure (Cost Components) After checking the cost components, click on save button. Page 174 of 269 Controlling Product Cost Controlling Cost Estimate without Quantity Structure This feature is used for calculate standard cost without quantity structure for individual materials. If the bill of material and routing are not maintained for a material, the standard cost estimate is calculated without quantity structure. The routings are maintained for the plants under which the production takes place, so the standard cost estimate is calculated using with quantity structure method. This material is transferred to the other plants using transfer-posting mechanism. The standard price for this material in the transferee plant can’t be calculated with quantity structure method, as the routing is not existed therein. The standard price at the transferee plan is calculated without quantity structure. For example honey is produced in FFPW plant and later on transferred to FFPC plant. The cost in FFPW is calculated with quantity structure and FFPC without quantity structure. The method to calculate standard price without quantity structure is as follows: Costing Variant: PPC1, Material: 40002306, Plant: FFPC, Costing Version: 1, Costing date: from & to, enter, enter valuation date, Category: M, Resource: 40002306, Plant: FFPW, Quantity: 1 and enter The system copies the cost of the material in FFPW plant to FFPC plant. This price is to be marked and released as per the method followed for Cost Estimate With Quantity Structure. The method of calculating without quantity structure is used for calculating standard cost estimates of the materials lying with different sales locations (Plants FFPC, FFPE, FFPN & FFPS). Page 175 of 269 Controlling Product Cost Controlling Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Cost Estimate Without Quantity Structure Create Transaction Code: KKPAN Screen Shot for Create Material Cost Estimate Without Quantity Structure After entering the material number, plant, costing variant and costing version, clink on enter button, then the following screen will appear: Page 176 of 269 Controlling Product Cost Controlling Screen Shot for Create Material Cost Estimate Without Quantity Structure (Date Control) Enter the Costing Date From and Costing Date To and Valuation Date and click on enter button. Page 177 of 269 Controlling Product Cost Controlling Screen Shot for Create Material Cost Estimate Without Quantity Structure: Detail Screen After enter the Category, Resource, Plant and Quantity press the enter button. Then system will bring the cost from the material master. After entered the above details, click on save button. After saving the screen, the following screen will appear: Page 178 of 269 Controlling Product Cost Controlling Screen Shot for Create Material Cost Estimate Without Quantity Structure: Detail Screen After getting the above screen, click on save button to save the cost estimate. Page 179 of 269 Controlling Product Cost Controlling Marking Allowance This feature is used for marking the allowance for the materials which standard cost is going to release. Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Price Update Transaction Code: CK24 Screen Shot for Marking Allowance: Initial Screen After entering the posting period / fiscal year, company code, plant and material (s), click on “Marking Allowance” to get the following screen: Page 180 of 269 Controlling Product Cost Controlling Screen Shot for Marking Allowance: Detail Screen After getting the above screen, click on save button to save the marking allowance. After save the marking allowance, standard cost should be marked as described below: Page 181 of 269 Controlling Product Cost Controlling Marking Standard Cost This feature is used for marking the standard cost for the materials which standard cost is going to release. Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Price Update Transaction Code: CK24 Screen Shot for Marking Allowance: Initial Screen After entering the posting period / fiscal year, company code, plant and material (s), click on “Program Execute” to get the following screen: Page 182 of 269 Controlling Product Cost Controlling Screen Shot for Marking Allowance: Detail Screen After getting the above screen, click on save button for save the marking. After marking a standard cost, standard cost should be released as below: Page 183 of 269 Controlling Product Cost Controlling Release Standard Cost This feature is used for release the standard cost for the materials. Once the standard cost is released, this cannot be reversed. Transaction Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Price Update Transaction Code: CK24 Screen Shot for Release Standard Cost: Initial Screen After entering the posting period / fiscal year, company code, plant and material (s), select “Release” and click on execute button. Page 184 of 269 Controlling Product Cost Controlling Screen Shot for Standard Cost: Detail Screen After getting the above screen, click on save button to save the standard cost. Page 185 of 269 Controlling Product Cost Collectors Product Cost Collectors Page 186 of 269 Controlling Product Cost Collectors Introduction The Product Cost Collectors will be created for the each and every semi-finished and finished goods of the company. Each and every semi-finished and finished goods are having one product cost collector only. Creation of master data for product cost collectors will be done by the Finance / Costing department. The product cost collectors are debited with the consumption of materials and activity confirmation (i.e. number of labor and machine hours spent) to be done by the Production Planning (PP) module. At the end of the period the overheads are loaded on the orders, calculate variance and finally the orders are settled. After settlement of order, the difference between standard cost and actual cost of a semi-finished or finished goods will be debited / credited to the price difference account. The planned costs (standard cost) of the product cost collectors are calculated by the system at the time of the order confirmed. For the calculation of the costs system considers the following factors: a) Quantity of the product cost collector. b) Bill of Material (BOM) for the requisite raw materials packaging materials. c) Routing for the requisite operations to be carried out to complete production. d) Activity prices maintained in cost center accounting. e) Costing sheet for the overheads. Once the PP Module Confirm the operations for the product cost collector following things takes place: 1) All the raw materials and semi-finished products required to manufacture the quantity mentioned in product cost collector are issued to it. The required raw materials are copied from the BOM of the material. However, if the actual consumption of the raw materials is different from the standards, then the quantitative figures can be changed. The debit to the product cost collector takes place at the actual quantity of the raw material multiplied with the moving average rate thereof. The rate used for semi-finished products is the standard costs thereof. Page 187 of 269 Controlling Product Cost Collectors 2) The activity allocation to the product cost collector takes place. The product cost collector gets debited and the cost center on which this is executed gets credited. This debit / credit takes place at actual production multiplied by the standard rate of the activity type maintained in the system. The debit to the product cost collector is accompanied with the credit to the cost center where the work center/resource is assigned. The work center/ resource is assigned in the recipe. 3) The finished goods inventory is taken in the finished goods stocks. The product cost collector is credited and the inventory accounts is debited. The accounting entry is passed at the actual quantity multiplied by the standard cost of the material. The transactions, which are carried out at the end of the period (month end) are: 1) Charging of the overheads as per the costing sheet. 2) Calculation of the variances. These are calculated with Actual Vs. Plan, Actual Vs. Standard. 3) Settlement of the order. This transaction passes on the difference between the actual cost and standard cost of the order to the price difference account. The other side of the transaction hits the factory output account. The values of the price difference account are passed over to the profitability analysis. The role of Finance / Costing department about product cost collectors is as follows: Charging of Overheads Variance Calculation Settlement of Orders Information System Page 188 of 269 Controlling Product Cost Collectors Master Data Master data is the data, which is created and used often as master records and this information provides the basis for product cost collectors. Individual Creation of Product Cost Collector This feature is used to individually create the product cost collector master data. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Master Data Product Cost Collector Edit Transaction Code: KKF6N Page 189 of 269 Controlling Product Cost Collectors Screen Shot for Create Product Cost Collector (Data) Page 190 of 269 Controlling Product Cost Collectors Screen Shot for Create Product Cost Collector (Header) Page 191 of 269 Controlling Product Cost Collectors Screen Shot for Create Product Cost Collector (Production Process) Page 192 of 269 Controlling Product Cost Collectors Collective Creation of Product Cost Collectors This feature is used to collectively create the product cost collector master data. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Master Data Product Cost Collector Collective Entry for Repetitive Manufacturing Transaction Code: KKF6M Screen Shot for Create Multiple Product Cost Collectors for Production Versions: Initial Screen Page 193 of 269 Controlling Product Cost Collectors Screen Shot for Create Multiple Product Cost Collectors for Production Versions: Detail Screen After getting the above screen, click on save button to save the document. Page 194 of 269 Controlling Product Cost Collectors Period-End Closing A Period-end closing activities includes the charging of overheads, variance calculation and settlement of product cost collectors at the month end. Charging of Overheads Individual Charging of Overheads to product cost collectors This feature is used for charging overheads to the product cost collectors at the month end as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Overhead Individual Processing Transaction Code: CO42 Page 195 of 269 Controlling Product Cost Collectors Screen Shot for Actual Overhead Calculation: Product Cost Collector After entered the above details, click on execute button to get the following screen: Page 196 of 269 Controlling Product Cost Collectors Screen Shot for Actual Overhead Calculation: Product Cost Collector Debits Page 197 of 269 Controlling Product Cost Collectors Reverse the charging of overheads This feature is used for reverse the charging of overheads. After reversal, the accounting entries will be generated and the order will come to the original status. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Overhead Individual Processing Transaction Code: CO42 Screen Shot for Reversal of Actual Overhead Calculation: Product Cost Collector After getting the screen, entered the required data and then go to menu “Overhead Calculation and click on Reverse”. Page 198 of 269 Controlling Product Cost Collectors Screen Shot for Actual Reversal of Charging Overheads: Product Cost Collectors Page 199 of 269 Controlling Product Cost Collectors Collectively Charging of Overheads to the Product Cost Collectors This feature is used for charging of overheads collectively to the Product Cost Collectors. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Overhead Collective Processing Transaction Code: CO43 Screen Shot for Actual Overhead Calculation: Product Cost Collectors After entered the above details, click on execute button to get the following screen: Page 200 of 269 Controlling Product Cost Collectors Screen Shot for Collective Actual Overhead Calculation: Product Cost Collectors Debits Page 201 of 269 Controlling Product Cost Collectors Collectively Reverse of Charging Overheads to Product Cost Collectors This feature is used for collectively reverse the charging of overheads to the Product Cost Collectors. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Overhead Collective Processing Transaction Code: CO43 Screen Shot for Reversal of Collective Actual Overhead Calculation: Product Cost Collectors After getting the screen, enter the required data and then go to menu “Overhead Calculation and click on Reverse”. Page 202 of 269 Controlling Product Cost Collectors Screen Shot for Collective Reversal of Charging Overheads to the Product Cost Collectors Page 203 of 269 Controlling Product Cost Collectors Variance Calculation Individual Charging of Overheads to product cost collectors This feature is used to calculate variances for product cost collectors at the month end as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Variances Individual Processing Transaction Code: KKS6 Screen Shot for Variance Calculation Product Cost Collector: Initial Screen After entered the above details, click on execute button to get the following screen: Page 204 of 269 Controlling Product Cost Collectors Screen Shot for Variance Calculation Product Cost Collector: Details Screen Page 205 of 269 Controlling Product Cost Collectors Collective calculation of variances for product cost collectors This feature is used to calculate variances for product cost collectors at the month end as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Variances Collective Processing Transaction Code: KKS5 Screen Shot for Collective Variance Calculation Product Cost Collector: Initial Screen After entered the above details, click on execute button to get the following screen: Page 206 of 269 Controlling Product Cost Collectors Screen Shot for Collective Variance Calculation Product Cost Collector: Details Screen Page 207 of 269 Controlling Product Cost Collectors Settlement Individual Settlement of Product Cost Collectors This feature is used for individual settlement of Product Cost Collectors at the month end as a part of Period-End Closing activities. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Settlement Individual Processing Transaction Code: KK87 Screen Shot for Actual Settlement: Product Cost Collector After entered the above details, click on execute button. Page 208 of 269 Controlling Product Cost Collectors Screen Shot for Actual Settlement: Product Cost Collector Detail List & Documents in Accounting Page 209 of 269 Controlling Product Cost Collectors Reverse the Settlement of Product Cost Collectors This feature is used for reverse the settlement of Product Cost Collector. After reversal, the accounting entries will be generated and the order will come to the original status. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Settlement Individual Processing Transaction Code: KK87 Screen Shot for Reversal of Actual Settlement: Product Cost Collector After getting the screen, entered the required data and then go to menu “Settlement and click on Reverse”. Page 210 of 269 Controlling Product Cost Collectors Screen Shot for Actual Reversal of Settlement and Documents in Accounting Page 211 of 269 Controlling Product Cost Collectors Collective Settlement of Product Cost Collectors This feature is used for collective settlement of Product Cost Collectors. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Settlement Collective Processing Transaction Code: CO88 Screen Shot for Collective Actual Settlement: Product Cost Collectors After entered the above details, click on execute button. Page 212 of 269 Controlling Product Cost Collectors Screen Shot for Collective Actual Settlement: Orders Detail List Page 213 of 269 Controlling Product Cost Collectors Collectively Reverse of Settlement of Product Cost Collectors This feature is used for collectively reverse the settlement of Product Cost Collectors. Transaction Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Period Period-End Closing Single Functions: Product Cost Collector Settlement Collective Processing Transaction Code: CO88 Screen Shot for Reversal of Actual Collective Settlement of Product Cost Collectors After getting the screen, enter the required data and then go to menu “Settlement and click on Reverse”. Page 214 of 269 Controlling Product Cost Collectors Screen Shot for Actual Reversal of collective settlement of Product Cost Collectors Page 215 of 269 Controlling Profitability Analysis Profitability Analysis Page 216 of 269 Controlling Profitability Analysis Introduction Profitability analysis (PA) gives the information about the sales, costs, profit on customer, product, product hierarchy, customer group, sales office, distribution channel, sales organization, country, plant, company code, profit center, controlling area, period, fiscal year etc. parameters. This information will enable the management to analyze the performance of the above parameters called characteristics from sales, profit angles. This information will provide management the necessary information for taking various decisions. This management tool will help management to take the strategic and operational decisions to improve the profits of the company. Operating Concern In financial accounting the company code is the highest organization unit, in controlling the controlling area is the highest node similarly the operating concern is the highest organizational unit in the profitability analysis module. All the transactions are executed with reference to the operating concern. An operating concern is an organizational unit in the company for which the sales market has a uniform structure. It represents the highest reporting level in Profitability Analysis. Profitability Analysis Structure Profitability Analysis OPERATING CONCERN FFP FFPS Cost Center Management CONTROLLING AREA FFP FFP General Ledger COMPANY CODE FFP FFPS Characteristics (profitability segments) Page 217 of 269 Controlling Profitability Analysis The data are stored with reference parameters combination such as customer, product, product hierarchy, customer group, sales office, distribution channel, sales organization, country, plant, company code, profit center, controlling area, period, fiscal year. These parameters are characteristics and combination thereof is called profitability segments. Value Fields The data are stored in GL accounts in FI, cost elements in CO and value fields in PA. The value fields are of two types (a) quantitative (b) amount. Costing-based Profitability Analysis This type of Profitability Analysis is primarily designed to analyze profit quickly for the purpose of sales management. Its main feature is the use of value fields, which represent cost, and revenue element groups, and automatic valuation of data using costing methods. The advantage of this method is that data is always current and therefore provides an effective instrument for controlling sales. The company is using the costing based PA only. Record Type Record type is used to segregate the data according to its source Following record types are used in PA 1. Sales order - A All the sales orders are stored under this record type 2. Direct Posting from FI - B The entire direct posting from FI are stored under this record type E.g. Direct posting of sales invoices through FI 3. Order/project settlement -C All the settlement transactions are recorded under this record type E.g. Settlement of product cost collector (make to stock), the variances transferred to PA are recorded under this record type 4. Cost-center costs - D Page 218 of 269 Controlling Profitability Analysis All the direct posting of Activity allocation to Profitability Segments and Assessment Cycle are recorded under this record type 5. Billing - F All the billing documents generated through SD are recorded under this record type How the transactions flow to Profitability Analysis: Transaction Flow from SD at the time of billing In case of process industry the revenue and the standard cost of the product is transferred to PA at the time of billing document generated. The standard cost estimates of the materials are stored in the cost components defined in product cost planning. These cost estimates are linked with the value fields in the PA. The revenues are booked through multiple condition types defined in SD. These condition types are linked with the value fields in PA. Transaction Flow from PP at the time of order Settlement The variances from Product cost collectors i.e. the difference between the actual costs incurred and the standard cost of the product is transferred to the PA at the time of the settlement of the product cost collector. The variance calculation takes place for each of the cost element booked in the product cost collector. These cost elements assigned to a group are assigned to the value fields. Transaction Flow from CO - CCA The debits to the cost centers takes place by way of postings from FI/ MM etc. and credits with the activity allocation / overhead charging at the standard rates. The variance in the actual costs and the standard absorption rates leaves over/ under absorption in the cost centers. This over/ under absorbed amount is moved to PA through the execution of the assessment cycle defined in PA. The details of the assessment cycle are as stated in the cost center accounting. Page 219 of 269 Controlling Profitability Analysis The sender in this case are cost center and cost elements. However the receiver are various characteristics like product, customer, product group, distribution channel, sales office, sales district, plant, controlling area, company code etc. The basis of allocation can be % method for various segments or amounts lying in the value fields of the profitability segments acting as the receiver. On the execution of the assessment cycle the credit to the cost centers takes place under the assessment cost element mentioned in the segment. The PA gets debited under the characteristics specified in the segment. Page 220 of 269 Controlling Profitability Analysis Period-End Closing Assessment Cycle This function makes it possible to transfer the under absorbed or over absorbed costs of all the cost centers to Profitability Analysis. A cycle can contain sender cost centers from one controlling area and uses value from either costing-based or account-based Profitability Analysis as tracing factors. Transaction Path: Accounting Controlling Profitability Analysis Actual Postings Period-End Closing Transfer Cost Center Costs/Process Costs Assessment Transaction Code: KEU5 Screen Shot for CO-PA Create Actual Assessment Cycle: Initial Screen After this screen, click on enter button to get the header data as below: Page 221 of 269 Controlling Profitability Analysis Screen Shot for CO-PA Create Actual Assessment Cycle: Header Data After this screen, click on Attach Segment for attaching the segments as below: Page 222 of 269 Controlling Profitability Analysis Screen Shot for CO-PA Create Actual Assessment Cycle: Segment After entering the relevant fields, then click on tab Senders/Receivers for enter the data for sender or receiver cost centers and cost element/group. Page 223 of 269 Controlling Profitability Analysis Screen Shot for CO-PA Create Actual Assessment Cycle: Segment (Senders/Receivers) (Page1) Page 224 of 269 Controlling Profitability Analysis Screen Shot for CO-PA Create Actual Assessment Cycle: Segment (Senders/Receivers) (Page2) Page 225 of 269 Controlling Profitability Analysis Screen Shot for CO-PA Create Actual Assessment Cycle: Segment (Receiver Tracing Factor) Page 226 of 269 Controlling Profit Center Accounting Profit Center Accounting Page 227 of 269 Controlling Profit Center Accounting Introduction Profit center accounting module gives the segmental financial results of the company. The information system reports give the information to the management on the functioning of the various divisions of the company. Profit Center Accounting is creating and managing the Master Data, Planning, Actual Postings, Information Systems and Environment. Using Profit Center Accounting you can Manage information for profit centers, profit centers group, statistical key figures and statistical key figures group. Reposting from one profit center to another . The Profit Center Accounting is divided in to following sub components: Master data Actual Postings Information System Environment Page 228 of 269 Controlling Profit Center Accounting Master Data Master data is the data, which is created and used often as master records and this information provides the basis for profit center accounting. Profit Center The screen is used to create/ change/ display the profit centers. The important fields to be entered are name & description of the profit center, Person in charge, department, node of the standard hierarchy, the company codes for which profit center is valid etc. The lock indicator in the profit center master data prevents any posting therein. It follows that postings can’t be made to any of the cost center, orders, material etc., which are assigned to the locked profit center. A list of all the profit centers is given in annexure number 16. Transaction Path: Accounting Controlling Profit Center Accounting Master Data Profit Center Individual Processing Create Transaction Code: KE51 Page 229 of 269 Controlling Profit Center Accounting Screen Shot for Create Profit Center: Initial Screen Page 230 of 269 Controlling Profit Center Accounting Screen Shot for Create Profit Center: Detail Screen After entering the required input data, click on activate (Shift+F1) button. Page 231 of 269 Controlling Profit Center Accounting Standard Hierarchy Similar to the cost center hierarchy the profit centers is to be arranged in the hierarchy called as standard hierarchy. Each profit centers created has to be assigned to any of the last node of the hierarchy. It means that profit centers can’t be assigned to node which itself contain a node therein. The nodes are treated as profit center groups for reporting purposes. The standard hierarchy is attached in the attachment. Transaction Path: Accounting Controlling Profit Center Accounting Master Data Standard Hierarchy Create Transaction Code: KCH1 Screen Shot for Create Profit Center Group: Initial Screen Page 232 of 269 Controlling Profit Center Accounting Screen Shot for Change Standard Hierarchy (Profit Center Group): Structure After entered the required details, click on save button to save the changes made. Page 233 of 269 Controlling Profit Center Accounting Profit Center Group The profit centers are arranged in the groups for the facilitation of planning and reporting requirements. The nodes in the standard hierarchy are automatically termed as profit center group. The profit centers can be arranged in alternative groups using this screen. Transaction Path: Accounting Controlling Profit Center Accounting Master Data Profit Center Group Create Transaction Code: KCH1 Screen Shot for Create Profit Center Group: Initial Screen Page 234 of 269 Controlling Profit Center Accounting Screen Shot for Create Profit Center Group: Structure After entered the required details, click on save button to save the changes made. Page 235 of 269 Controlling Profit Center Accounting Account Group The GL accounts created in FI and secondary cost elements created in CO are termed as accounts in profit centers. The groups of these GL accounts and secondary cost elements are created/ changed/ displayed in the form of account group using this screen. The Financial Statement version (FFPG) is arranged in the account group of FFPG containing multiple account groups for reporting purposes. Transaction Path: Accounting Controlling Profit Center Accounting Master Data Account Group Create Transaction Code: KDH1 Screen Shot for Create Account Group: Initial Screen Page 236 of 269 Controlling Profit Center Accounting Screen Shot for Create Account Group: Structure After entered the required details, click on save button to save the changes made. Page 237 of 269 Controlling Profit Center Accounting Assignment Monitor The screen is used to monitor the assignment of various materials and cost objects like cost centers and internal orders to the profit centers. This transaction gives the list of assignments of material/ cost objects to the profit centers and the unassigned materials/ cost objects. VARIOUS ASSIGNMENTS Materials: All the materials and plant combination are to be assigned to the profit centers. A material lying in separate plants can be assigned to multiple profit centers. The assignment can be carried out for an individual material, material type, material group, and product hierarchy. Any new assignment over-writes the previous assignment. This value of the stocks are assigned to the profit center where the material + plant combination is assigned to. Non-Assigned: Gives the list of all those materials, which are not assigned to the profit centers. Assigned Material: Gives the list of all those materials, which are assigned to the profit centers. Cost Centers: All the cost centers are to be assigned to the profit centers. Any new assignment overwrites the previous assignment. The cost booked to the cost center from FI/ MM etc. is passed on the assigned profit center. Non-Assigned: Gives the list of all those cost centers, which are not assigned, to the profit centers. Assigned Cost Centers: This transaction gives profit center wise assigned cost center list. The assignment of the cost center is given in annexure 17. Page 238 of 269 Controlling Profit Center Accounting Internal Orders: All the internal orders are to be assigned to the profit centers. Any new assignment over-writes the previous assignment. The cost booked to the internal order from FI/ MM etc. is passed on the assigned profit center. Non-Assigned: Gives the order type wise list of all those Internal orders, which are not assigned to the profit centers. Assigned Orders: This transaction gives list of profit center wise assigned internal orders. Transaction Path: Accounting Controlling Profit Center Accounting Master Data Assignment Monitor Transaction Code: 1KE4 Screen Shot for Profit Center Accounting: Assignment Monitor After getting the above screen, go to menu and select “Assignment Monitor Cost Centers Non-Assigned Page 239 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA: Non-Assigned Cost Centers: Initial Screen After getting the above screen, click on execute button to get the detailed list of cost centers assigned and non-assigned. Screen Shot for EC-PCA: Non-Assigned Cost Centers: Initial Screen Page 240 of 269 Controlling Profit Center Accounting After getting the initial screen for assignment monitor, go to menu and select “Assignment Monitor Materials Assigned Materials” Screen Shot for EC-PCA: Materials Assigned to Profit Centers: Initial Screen After entering the Material Type and Profit center group, click on execute button to get the detailed list as below: Page 241 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA: Materials Assigned to Profit Centers: Detail Screen Page 242 of 269 Controlling Profit Center Accounting After getting the initial screen for assignment monitor, go to menu and select “Assignment Monitor Orders Assigned Orders” Screen Shot for EC-PCA: Orders Assigned to Profit Centers: Initial Screen After entering the Order category, Order Type Profit center group, click on execute button to get the detailed list as below: Page 243 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA: Orders Assigned to Profit Centers: Detail Screen Page 244 of 269 Controlling Profit Center Accounting Actual Postings Profit Center Document This feature is used to pass JV entries in the profit center accounting. The basic principals of passing JV entries in PCA are: Each line to contain GL account, profit center and amount (positive or negative) The balance of the document should be zero i.e. the total of debit or the credits be zero. The document is used to pass manual entries, rectification entries, reposting entries etc. The profit centers are updated online. Transaction Path: Accounting Controlling Profit Center Accounting Actual Postings Profit Center Document Enter Transaction Code: 9KE0 Screen Shot for Create Document: Initial screen Page 245 of 269 Controlling Profit Center Accounting After getting the above screen, click on execute button to get the following screen: Screen Shot for Create Document: Characteristics Enter the company code and click on entry screen (F5) button to get the following screen: Screen Shot for Create Document: Line Items Page 246 of 269 Controlling Profit Center Accounting After entering the required data, double click on the line item to enter the document text. Screen Shot for Create Document Line Items: Document Detail After entered the required data, click on save button. Page 247 of 269 Controlling Profit Center Accounting Statistical Key Figures Enter Statistical Key Figures: This feature is used to enter the actual statistical key figures on a monthly basis. This feature is used to book the parameters as the basis of allocation of values from one profit center to various profit centers. This is similar to booking of SKF for the cost centers. The examples of the SKF for the profit centers are turnover, asset base etc. The SKF can be used to record the values for the information purposes also. The details of this transaction are given in cost center planning of CCA user manual. Transaction Path: Accounting Controlling Profit Center Accounting Actual Postings Statistical Key Figures Change Transaction Code: 9KE5 Screen Shot for Change Statistical Key Figures: Initial Screen After entered the required data, click on execute button. Page 248 of 269 Controlling Profit Center Accounting Screen Shot for Change Statistical Key Figures: Characteristics After entered the required data, click on overview screen (F5) to enter the SKF. Page 249 of 269 Controlling Profit Center Accounting Screen Shot for Change Statistical Key Figures: Cumulative values After entered the required data, click on save button. Page 250 of 269 Controlling Profit Center Accounting Period-End Closing PCA Assessment Cycle: The values (both P&L and Balance sheet related) which can’t be assigned to the strategic business units related profit centers are booked to the common profit centers. At the end of the period these values are allocated to various profit centers using percentage, SKF, cost element as the basis of allocation. The details of the method of assessment cycle are charted out in the user manual of cost center accounting. In FFP the assessment cycles have been designed to allocate the expenses booked in PGCS & Dummy profit centers. The details of assessment cycle are given in annexure 18. Path for creation of Actual Assessment Cycle: Transaction Path: Accounting Controlling Profit Center Accounting Actual Postings Period-End Closing Assessment Transaction Code: 3KE5 After getting the initial screen, go to menu “Extras Cycle Create” Page 251 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA Create Actual Assessment Cycle: Initial Screen After this screen, clink on enter to get the header data. Page 252 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA Create Actual Assessment Cycle: Header Data After this screen, clink on Attach Segment for attaching the segments. Page 253 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA Create Actual Assessment Cycle: Segment After entering the relevant fields, then click on tab Senders/Receivers for enter the data for sender or receiver cost centers and cost element/group. Page 254 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA Create Actual Assessment Cycle: Segment (Senders/Receivers) After the above screen, then click on tab Receiver Tracing Factor for enter the % against receiver cost centers. Page 255 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA Create Actual Assessment Cycle: Segment (Receiver Tracing Factor) Page 256 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA Create Actual Assessment Cycle: Segment (Receiver Weighting Factors) Page 257 of 269 Controlling Profit Center Accounting Transferring Payables/Receivables The values of payables and receivables pertaining to purchases and sales made for a profit center is not updated online. This transaction is to be executed to transfer the values of receivables and payables pertaining to the profit centers. However, it is necessary to execute the transaction of Balance sheet readjustment in FI before this transaction is executed. The path of which is: Accounting Financial Accounting General Ledger Periodic Processing Closing Regroup Calculate Balance Sheet Adjustment Calculate Transaction Path: Accounting Controlling Profit Center Accounting Actual Postings Period-End Closing Transferring Payables/Receivables Transaction Code: 1KEK Screen Shot for PCA: Transfer Payables / Receivables After getting the above screen, select the company code and click on execute button for transfer payables / receivables. Page 258 of 269 Controlling Profit Center Accounting Screen Shot for Call up transfer Payables / Receivables Page 259 of 269 Controlling Profit Center Accounting Transferring Assets Similar to payable/ receivables, the values of fixed assets pertaining to the profit centers are not updated online. At each month end this transaction need to be executed to transfer the values of assets pertaining for each profit center. In the asset master the name of the cost center is maintained, which in turn is assigned to a profit center. With this linkage of asset master to profit center through the cost center the values of assets is assigned to the profit center. The depreciation values are booked to the assigned profit centers online (at the time of execution of the depreciation run). Transaction Path: IMG Accounting Controlling Profit Center Accounting Actual Postings Transferring Selected Balance Sheet Items Generate Opening Balance for Assets Transaction Code: 1KE1 Page 260 of 269 Controlling Profit Center Accounting Screen Shot for PCA: Transfer Assets After getting the above screen, select the company code and click on execute button to transfer assets. Page 261 of 269 Controlling Profit Center Accounting After selecting the fields as per shown in the screen, execute Screen Shot for EC-PCA: Transfer Assets Page 262 of 269 Controlling Profit Center Accounting Transferring Material Stocks Similar to payable, receivables and assets the values of all stocks items like raw materials, stores, semi-finished, finished, packing material etc. are not booked the profit centers, online. This transaction is to be executed to pass on values of the inventories held by each profit center. The material masters and plant combinations are assigned to the profit centers. The stocks of materials lying in each of the plants are assigned to the respective profit centers. The values booked to the profit centers are the closing balance of the inventories lying in the plants at the time of the execution of this transaction. Transaction Path: IMG Accounting Controlling Profit Center Accounting Actual Postings Transferring Selected Balance Sheet Items Generate Opening Balance for Material Stocks Transaction Code: 1KEH Screen Shot for EC-PCA: Transfer Material Stocks After getting the above screen, select the company code and click on execute button to transfer material stocks. Page 263 of 269 Controlling Profit Center Accounting Screen Shot for EC-PCA: Transfer Material Stock to EC-PCA Page 264 of 269 Controlling Profit Center Accounting Balance Carry-forward This feature is used for transferring the closing balances of balance sheet items as an opening balance for next financial year. Transaction Path: Accounting Controlling Profit Center Accounting Actual Postings Period-End Closing 2KES - Balance Carry-forward Transaction Code: 2KES Screen Shot for Profit Center: Carry forward actual balance After entered the details of company code and carry forward to fiscal year, click on execute button for carry forward actual balances. Page 265 of 269 Controlling Profit Center Accounting Screen Shot for Profit Center: Carry forward actual balance After getting the above screen, click on Balance sheet accounts to get the detailed screen as follows: Page 266 of 269 Controlling Profit Center Accounting Screen Shot for Display of Balance Sheet Items Page 267 of 269 Controlling Profit Center Accounting Information System Various reports of the profit centers are available on the screens. The following mentioned report will gives the plan data, actual data and variance for profit centers. Transaction Path: Accounting Controlling Profit Center Accounting Information System Reports for Profit Center Accounting Interactive Reporting Profit Center Group: Plan/Actual/Variance Transaction Code: S_ALR_87013326 Initial screen shot for profit center-wise plan or actual cost After entered the required data, click on execute button to get the detailed screen as below: Page 268 of 269 Controlling Profit Center Accounting Detailed screen shot for profit center-wise plan or actual cost Note: Profit center accounting information system is providing the many standard reports. Transaction Codes: S_ALR_87013326 to S_ALR_87013352. Page 269 of 269