Copyright © 2018. John Wiley & Sons, Incorporated. All rights reserved. 396 International Construction Contract Law National Insurance Property Development Co Ltd v. NH International (Caribbean) Ltd. Particular claims usually correspond to damages caused by the employer, the contractor, or external grounds. When proving damages, one has to deal with difficulties based mainly on the three following problems: causation, concurrency, and calculation. The subject of causation will be dealt with in connection with global claims (discussed below in Section 10.6), the subject of concurrency will be touched on in connection with concurrent delay (Chapter 7) and the difficulties with calculation will be dealt with in headquarters overhead claims (also discussed below in Section 10.4.1). Causation, concurrency, and calculation issues lead to uncertainty in the way the tribunals decide about claims for damages. While there is no easy solution that can overcome these difficulties, if the parties are aware of the uncertainty, they can take steps at an early stage to assess the best way to establish the claim before a particular tribunal. This means that the party can carry out the necessary analysis to formulate a robust position and assess the risks that will increase the likelihood of successfully establishing the claim (Ramsey, 2013). The best place to prepare a strong claim is at the construction site itself provided that contemporary records of delay, disruption and their respective effect on costs is updated in the time program and progress reports. An application for damages (whether in a court or via a claim submission), can be both confusing and tedious. Since the purpose of a claim is the recovery of damages, making the application clear, simple, and easily understandable is extremely important. The damages claimed should, whenever possible, reference and tie to the contractor’s accounting documents and records. This provides evidence that can be verified and accessed. Damages that cannot be traced to accounting records are immediately suspect, no matter how reasonable the amount claimed may seem. There is a tendency for damages to be overstated in a claim submission, with the idea that it can later be negotiated down to a more realistic but still acceptable amount. However, this approach is not advisable, as the claimant will lose credibility and will eventually have to explain the discrepancy between the claim amount and the amount sought at trial (Schwartzkopf and McNamara, 2001). There are three types of contractor claims in general, i.e. claims for: • • • 10.2 extension of time (EOT); additional payment; extension of time and additional payment. Claims for extension of time (EOT) In some situations, the contractor can claim extensions of time for completion. It is in fact a defense against contractual penalty/delay damages filed by the employer and a form of risk sharing in some of situations such as extremely adverse weather. The position of the SCL Protocol on the purpose of extension of time is that the benefit to the contractor is only to relieve them of liability for damages for delay for any period prior to the extended contract completion date. The benefit of an EOT for the employer is that it establishes a new contract completion date and prevents time for completion of the works becoming “at large.” Entitlement to an Klee, Lukas. International Construction Contract Law, John Wiley & Sons, Incorporated, 2018. ProQuest Ebook Central, http://ebookcentral.proquest.com/lib/lau-ebooks/detail.action?docID=5448169. Created from lau-ebooks on 2023-04-09 20:03:05. 10. Claim Management 397 Copyright © 2018. John Wiley & Sons, Incorporated. All rights reserved. EOT does not automatically lead to an entitlement to compensation. The parties should attempt—as far as possible—to deal with the impact of employer risk events as the work proceeds in terms of EOT and compensation. Where the full effect of an employer risk event cannot be predicted with certainty at the time of the initial assessment by the contract administrator, the contract administrator should grant an EOT for the then predictable effect. The employer usually claims an extension of the defects notification period in terms of time (under Sub-Clause 2.5 in the FIDIC forms). Under the FIDIC forms (CONS/1999 Red Book), the contractor may claim an extension of time for completion under Sub-Clause 8.4. The contractor is entitled (subject to Sub-Clause 20.1) to an extension of the time for completion if and to the extent that completion is or will be delayed by any of the following causes: 1. Variation (unless an adjustment to the time for completion has been agreed in the variation procedure) or other substantial change in the quantity of an item of work. 2. Cause of delay giving an entitlement to an extension of time under another Sub-Clause (mainly Sub-Clauses 1.9 (late information, instruction, delayed drawings), 2.1 (denied or late access or possession to site ), 4.7 (errors in setting out information), 4.12 (unforeseeable physical conditions), 4.24 (fossils), 7.4 (testing), 8.5 (delays caused by authorities), 8.9 (engineer’s instructions to suspend work), 10.3 (interference with tests on completion),16.4 (termination by contractor), 17.4 (employer’s risks), 19.4 (force majeure), or 19.6 (optional termination)). 3. Exceptionally adverse climatic conditions. 4. Unforeseeable shortages in the availability of personnel or goods caused by an epidemic or governmental actions. 5. Any delay, impediment, or prevention caused by or attributable to the employer, the employer’s personnel (including the engineer who is listed as employer’s personnel under Sub-Clause 1.1.2.6.), or the employer’s other contractors on site. If the contractor considers themselves to be entitled to an extension of time for completion, the contractor shall give notice to the engineer in accordance with Sub-Clause 20.1. When determining each extension of time under Sub-Clause 20.1, the engineer shall review previous determinations and may increase, but shall not decrease, the total extension of time. If the contractor obtains an extension of time, they may be in a position to recover costs associated with the delay. However, there is no link (obligation) between Sub-Clause 8.4 and additional payment. The contractor must keep proper records of the consequences of the event causing the claim in order to prove it. Documentation and reporting must follow the particular contractual provisions. For example, the contractor must keep records of labor, materials, equipment, progress reports, photographic, and video documentation. The importance of a maintained, detailed, and up-to-date time schedule should be noted here. A claim for extension of time for completion is often submitted along with the updated time schedule detailing how and to what extent the claim events have influenced the individual construction works and relationship between activities. Critical paths in the time schedule are then explored together with floats, if any. Klee, Lukas. International Construction Contract Law, John Wiley & Sons, Incorporated, 2018. ProQuest Ebook Central, http://ebookcentral.proquest.com/lib/lau-ebooks/detail.action?docID=5448169. Created from lau-ebooks on 2023-04-09 20:03:05.