Inspection Report

advertisement
Ground inspection report No:1
Stage of inspection: Ground inspection
Date of Inspection: 05 / 04 /2023
Maximum Allowable Working Pressure
Least Pressure ( Drum Shell)
Hydraulic Test Pressure
Design Temperature
Saturated Steam Temp.
Maximum Continuous Rating
Total Heating Surface Area
SL.NO
DESCRIPTION
73 Kgs./sq.cm
81.39 Kgs./sq.cm
109.5 Kgs./sq.cm
217° C
289°C
14000 KG/Hr. (Maximum Condition)
578 sq. mtr
Heating Surface Area
Boiler Bank Zone
Water Wall Zone
Inbed Coil
Economiser Coil
307 sq.mtr
75 sq.mtr
53 sq.mtr
143 sq.mtr
DRWING NO
ALT .NO
RELEASE NOTE NO. AND DATE
IBR STAMP
QTY in Pag
Nos
e
1
STEAM DRUM
PZZE30PD02-1
ALT .NO:0
NO: NIL DATED 09/11/2022
JKS
1
1
2
WATER DRUM
PZZE30PD03-1
ALT .NO:0
NO: NIL DATED 09/11/2022
JKS
1
1
3
BOILER BANK TUBES
PZZE30PB01-2
ALT .NO:0
NO: NIL DATED 03/10/2022
JKS
252
2
4
LH & RH BOILER BANK PANEL
PZZE30PB02-1
ALT .NO:0
NO: NIL DATED 10/10/2022
JKS
36
3
5
REAR BOILER BANK PANEL
PZZE30PB03-1
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
1
4
6
MIDDLE BOILER BANK PANEL
PZZE30PB04-1
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
18
5
7
FRONT WATER WALL
PZZE30PW01-1
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
1
6
8
FRONT WATER WALL
PZZE30PW01-1
ALT .NO:0
NO: NIL DATED 10/10/2022
JKS
10
7
9
REAR WATER WALL
PZZE30PW02-1
ALT .NO:0
NO: NIL DATED 28/10/2022
BAB
19
8
10
RH SIDE WATER WALL PANEL
PZZE30PW03-1
ALT .NO:0
NO: NIL DATED 10/10/2022
JKS
2
9
11
LH SIDE WATER WALL PANEL
PZZE30PW04-1
ALT .NO:0
NO: NIL DATED 10/10/2022
JKS
2
9
12
INBED COILS
PZZE30PC01-1
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
74
10
13
INBED HEADER
PZZE30PH01-1
ALT .NO:0
NO: NIL DATED 12/10/2022
JKS
2
11
14
INTEGRAL ECONOMISER COILS AND HEADER ASSEMBLY
PZZE30PE02-1
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
2
12
15
SPARE INBED COILS
PZZE30PC06-2
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
20
13
16
SPARE INTEGRAL ECONOMISER COIL TUBE & BEND
PZZE30PE08-4
ALT .NO:0
NO: NIL DATED 14/10/2022
BAB
11
14
17
RISER & DOWNCOMER
PZZE30PR01-1
ALT .NO:0
NO: NIL DATED 17/11/2022
BAB
SET
15
18
STEAM DRUM MOUNTING
PZZE30PI01-2
ALT .NO:0
NO: NIL DATED 09/1/2023
JKS
SET
16
19
ECONOMISER DRAIN, VENT, CBD, IBD, IBH DRAIN AND
FEED LINK
PZZE30PI02-1
ALT .NO:0
NO: NIL DATED 09/1/2023
JKS
SET
18
20
ECO OUTLET TO STEAM DRUM INLET PIPING
PZZE30PI03-1
ALT .NO:0
NO: NIL DATED 09/1/2023
JKS
SET
19
For M/s DMC Construction
For M/s Thermax Ltd
For M/s Adani Wilmar Ltd
For M/s Director of Boilers,
REMARKS
Inspected the pressure parts from serial no:1 to 19 as per the release notes(Final offering before Despatch) along with approved
drawings and condition found satisfactory.verified the stampings/identification marks and size,found in order. No transit
damage found on pressure parts. Permitted to erect pressure parts as per PPA under supervision of M/s thermax Ltd,Pune.
Name of the owner: M/s Adani Wilmar Ltd
Name of the erector: DMC Construction