materials Article Evaluation of the Pullout Behavior of Pre-Bored Piles Embedded in Rock Kyungho Park 1 , Daehyeon Kim 2, * , Gyudeok Kim 3 and Wooyoul Lee 3 1 2 3 * Citation: Park, K.; Kim, D.; Kim, G.; Lee, W. Evaluation of the Pullout Behavior of Pre-Bored Piles Embedded in Rock. Materials 2021, 14, 5593. https://doi.org/10.3390/ Department of Civil Construction Engineering, Chosun College of Science & Technology, Gwangju 61453, Korea; parkgeo@cst.ac.kr Department of Civil Engineering, Chosun University, Gwangju 61452, Korea Department of Construction, KL Engineering Co., Jangsung 57241, Korea; kgd125@hanmail.net (G.K.); ewoo10@naver.com (W.L.) Correspondence: dkimgeo@chosun.ac.kr; Tel.: +82-062-230-7607 Abstract: The subject of this study is dry process caisson tube method cofferdam (hereinafter called C.T cofferdam). This C.T cofferdam is designed to use the skin friction of the drilled shaft embedded into the rock for stability of buoyancy. A pre-bored pile embedded in the bedrock was pulled out due to the buoyancy of the C.T cofferdam at the pier (hereinafter called P) 2 of the OO bridges under construction, to which this was applied. In this study, in order to solve this problem, the adhesion force applied with the concept of skin friction and the pre-bored pile of drilled shaft according to domestic and foreign design standards were identified; the on-site pull-out load test was used to calculate the pull-out force; and the skin friction of the drilled shaft and pre-bored pile embedded into the bedrock were compared and analyzed. In addition, the pull-out behavior of the pre-bored pile embedded in the bedrock was analyzed through numerical analysis. The adhesion strength tested in the lab was 881 kN for air curing of concrete and 542 kN for water curing of concrete, and the on-site pull-out test result was 399.7 kN. As a result of the numerical analysis, the material properties of the grout considering the site conditions used revealed that the displacement of the entire structure exceeded the allowable limit and was unstable. This appears to have lowered the adhesion strength due to construction issues such as ground complexity and both seawater and slime treatment, which were not expected at the time of design. ma14195593 Academic Editors: Eddie Koenders Keywords: dry process caisson tube method cofferdam; skin friction; pre-bored pile; pull-out load test; grout and Tomasz Sadowski Received: 30 June 2021 Accepted: 13 September 2021 Published: 26 September 2021 Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. Copyright: © 2021 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https:// creativecommons.org/licenses/by/ 4.0/). 1. Introduction 1.1. Research Background and Purpose End-bearing and skin friction behavior of piles subjected to axial loads are important factors in predicting the bearing capacity of structures. However, the ISO 19902 [1] regulations on offshore steel structures do not suggest an accurate calculation equation for the evaluation of friction-bearing capacities at the tip and circumferential surface of piles embedded in bedrock. The Korean structural foundation design standard (Ministry of Land, Infrastructure, and Transport [2]) briefly mentions the end-bearing capacity for compression but does not suggest any formula for calculating the skin friction of the pile foundation embedded in the rock. Therefore, when designing offshore structures, the equation for calculating the skin friction of drilled shafts embedded in the bedrock, which is the most similar mechanism to the required calculation, is applied. Due to the fact that the bearing capacities of a drilled shaft and pre-bored pile are very different, it is easy to overestimate or underestimate the skin friction of the pile. Therefore, due to incorrect evaluation, the safety of the structure may be impaired and errors may occur in the prediction of the behavior of the pile foundation. In order to construct the Materials 2021, 14, 5593. https://doi.org/10.3390/ma14195593 https://www.mdpi.com/journal/materials Materials 2021, 14, 5593 2 of 21 structure safely and economically, it is necessary to study the support behavior of the pre-bored pile embedded in the bedrock. C.T cofferdam is designed to use the skin friction of drilled shafts embedded in the rock to ensure buoyancy stability. However, due to the buoyancy of C.T cofferdam, a problem occurred in which the pre-bored pile was pulled out. To solve this problem, firstly, we analyzed the skin friction of the drilled shaft according to domestic and foreign design standards. Secondly, a lab test was performed on the adhesion force, in which the concept of a pre-bored pile was applied. Thirdly, the pull-out force was calculated through the pull-out load test (ASTM D3689-07 [3]) and both the skin friction of the drilled shaft and pre-bored pile embedded in the bedrock were compared and analyzed. Finally, the pull-out behavior of the pre-bored pile embedded in the bedrock was analyzed through numerical analysis. 1.2. Research Trends Many researchers have been conducting studies on the bearing capacity of piles for a long time. In the case of soft ground and weathered rock, the basic design theory is established based on the results of field tests. However, past studies on pile foundations embedded in bedrock mainly focused on drilled shafts and there are very few studies on pre-bored piles. When calculating the ultimate bearing capacity of a drilled shaft embedded into rock, design standards and bearing capacity calculation equations that were proposed overseas (FHWA [4]; FHWA [5]; and Canadian Geotechnical Society [6]) are applied. In Korea, overseas design standards and bearing capacity calculation equations were modified to match domestic standards and were applied to the structural basic design standards and road bridge design standards (Ministry of Land, Infrastructure, and Transport [2]). Previous overseas studies on skin friction of pre-bored piles embedded in bedrock were reviewed. Maertens [7] evaluated the performance of piles by installing steel pipe piles on weathered rocks but they only evaluated limited field conditions. Shakir-Khalil [8], Shakir-Khalil [9], and Nezamian et al. [10] studied the adhesion strength and adhesion behavior between concrete and steel pipes when steel pipes are filled with concrete. Moon et al. [11], a previous study in Korea, determined the skin friction of steel pipe piles embedded in bedrock by the skin friction between the surface of the steel pipe and the grout. Moon et al. [12] confirmed that the adhesion strength of the skin friction of the pre-bored pile embedded in the bedrock was about 1 MPa through a model test. Moon and Park [13] also evaluated the effect of the grout mixing ratio on the skin friction of steel pipe piles embedded in bedrock. Regardless of W/C, in the case of grout, the adhesion strength was about 540~560 kPa. Kim et al. [14] proposed that the load-settlement curves and axial load distributions of piles, as well as the load-transfer curves (t-z curves), are obtained on the main surface of a steel pipe pile. In addition, the N-value obtained from the standard penetration test for the strata, the compressive strength of the bedrock, and the soil-cement formed by the injected grout were confirmed to be affected by uniaxial compressive strength. Kim and Kim [15] evaluated the skin friction characteristics of the pre-bored pile embedded in bedrock through the dynamic load test of the pile foundation. Chae et al. [16] proposed an equation for calculating the axial bearing of SDA (separated doughnut auger) pre-bored piles embedded in bedrock. According to the previous domestic and foreign studies related to the calculation of the pull-out force of pre-bored piles embedded in bedrock, the pull-out force of the pre-bored pile is mostly related to the adhesion force of the grout. However, the related design standards are not clear, thus, in practice, the pull-out standards of drilled shafts are applied. In addition, most of the previous studies were limited to the skin friction of steel pipe piles embedded in bedrock among pre-bored piles. Materials 2021, 14, 5593 Materials 2021, 14, 5593 3 of 21 3 of 22 Therefore, in this study, theories and empirical equations similar to the behavior of pre-bored piles were reviewed among the design standards for drilled shafts penetrated into bedrock. What sets this study apart from previous studies is the analysis of the pull-out standards are not clear, thus, piles in practice, thesteel pull-out of drilled concrete), shafts are apforce behavior of composite (upper: pipe,standards lower: reinforced in which plied. In addition, most of the previous wereinlimited to the skin the friction of steelpiles. the lower reinforced concrete piles are studies embedded bedrock among pre-bored pipe piles embedded in bedrock among pre-bored piles. 2. Design-Bearing Capacity of Pilesand empirical equations similar to the behavior of Therefore, in this study, theories pre-bored pilesofwere among the design standards for drilled shafts penetrated 2.1. Estimation The reviewed Bearing Capacity of Piles into bedrock. What sets this study apart from previous studies is the analysis of the pullAs shown in Equation (1), the bearing capacity of the pile consists of the end-bearing out force behavior of composite piles (upper: steel pipe, lower: reinforced concrete), in capacity and the skin friction force, and the resistance force of the two elements occurs which the lower reinforced concrete piles are embedded in bedrock among the pre-bored completely at the same time. piles. Q = Qs + Q p = f s As + q p A p u 2. Design-Bearing Capacity of Piles (1) 2.1. Estimation Theskin Bearing Capacity of (kN/m Piles 2 ); A is the major surface area of pile (m2 ); q where f s is theofunit friction force s p shown in Equation (1), the(kN/m bearing2 ); capacity consists of the end-bearing is theAs unit end-bearing capacity and A pofisthe thepile pile cross-sectional area (m2 ). capacity and the skin friction(1)force, and the resistance of the was two elements occurs Theoretical Equation for obtaining bearingforce capacity developed by many completely the same scholars foratsafer and time. more economical construction after Rankine published the earth pressure theory. Although the understanding through = + =of the+overall pile has been improved(1) these efforts, there are many variables affecting the bearing capacity, thus there is a limit to is the major surface area of pile (m2); where is the unit skin friction force (kN/m2); deriving a reliable bearing capacity calculation equation. is the pile cross-sectional area (m2). is the unit end-bearing capacity (kN/m2); and In classifying the bearing capacity calculation equations proposed so far, there is the Theoretical Equation (1) for obtaining bearing capacity was developed by many static-bearing capacity calculation method and the method by static loading and dynamic scholars for safer and more economical construction after Rankine published the earth loading static-bearing capacity equation, basedpile on has experience or theory, is pressuretests. theory.The Although the understanding of the overall been improved mainly used during the design process, although its reliability is somewhat through these efforts, there are many variables affecting the bearing capacity, thus low. there In the construction process, the most reliable on-sitecalculation in situ test methods, such as the static load is a limit to deriving a reliable bearing capacity equation. test and dynamic load test, are mainly applied, equations although proposed it takes a so great time and In classifying the bearing capacity calculation far, deal thereof is the are costly. static-bearing capacity calculation method and the method by static loading and dynamic loading tests. The static-bearing capacity equation, based on experience or theory, is 2.2. Skinused Friction of Pile mainly during the design process, although its reliability is somewhat low. In the construction the skin most friction reliable on-site in situ such as the static Figure 1process, shows the acting on the test skinmethods, of the pile embedded inload the sandy test and test, arefriction mainly applied, it takes great deal of andon the soil. Thedynamic ultimateload unit skin force is although calculated usinga Equation (2)time based are costly. theory considering the friction generated on the surface of a rigid body. 2.2. Skin Friction of Pile f s = Kp0 tanδ (2) Figure 1 shows the skin friction acting on the skin of the pile embedded in the sandy where K isultimate the horizontal earth pressure effective(2) overburden payload soil. The unit skin friction force coefficient; is calculatedpusing Equation based on the 0 is the theory 2considering friction generated on angle the surface (kN/m ); and tan δthe is the internal friction (◦ ). of a rigid body. Figure 1. Skin friction force on the pile. Figure 1. Skin friction force on the pile. Materials 2021, 14, 5593 4 of 21 Assuming that the sand between the ground and pile is in the ultimate fracture state, the friction angle was estimated to be the same as the residual friction angle ∅τcs of the sand rather than the unit weight of the ground and the material of the pile. This value is not significantly different from the value according to the method of Vesic [17]. Meyerhof [18] determined the coefficient of earth pressure. The horizontal earth pressure coefficient considers only the horizontal displacement of the pile foundation. This horizontal displacement affects the surrounding ground so that the soil is compacted and the maximum displacement occurs at the point of contact between the pile and the soil. Meyerhof [19], Poulos and Davis [20], Vesic [21], and Berezantzev [22] proposed a theoretical hydrostatic-bearing capacity calculation method that divided end-bearing capacity and skin friction force. In order to calculate bearing capacity according to the theoretical equation, various ground characteristics are required. In addition, both lab and field tests are required to calculate this. Values that cannot be obtained from lab and field tests should be assumed and applied. Therefore, when using the theoretical equation, uncertainty exists because it assumes variables that cannot be obtained from lab and field tests. It is economically disadvantageous because various soil tests are required. There is also the problem of poor accuracy when applying it to the design. Table 1 shows the theoretical equations of the hydrostatic-bearing capacity currently applied in Korea and abroad. Table 1. Physical properties of reinforcements used for tests. Classification Skin Friction End-bearing capacity Equations Proposers Applicability f s = ac + qKtanδ Tomlinson (1972) Pre-stress and clay soil f s = Kq tanδ = βq Jennings and Burland (1973) Effective stress amnd clay soil f s = λ(q + 2su ) McClelland and Focht (1967) Mixing method and clay soil f s = acu Meyerhof (1976) Clay soil f s = Ks σv tanδ Meyerhof, Colye-Castello, Vesic, API etc Sandy soil q p = p0 Nq ≤ 5Nq tanφ Meyerhof (1976) Sandy soil q p = cNc Meyerhof (1976) Clay soil q p = cNc + σ0 N0 Vesic (1977) Cavity expansion theory q p = Ak γB + Bk q T (q T = a T γD ) Berezantzev (1961) The skin friction of clay soil was calculated by the α coefficient method and β coefficient method (Ministry of Land, Infrastructure, and Transport, 2018). In this study, the skin friction of the pile foundation was calculated by applying the α coefficient method under the undrained condition. Since the α coefficient method is applied when the pile is embedded in the saturated clay layer, it is φu = 0 in the undrained condition, thus δ = 0. At this time, the skin friction of the pile is expressed as the adhesion force between the pile and the ground. f s = cs = αcu (3) where cs is the cohesion force (kN/m2 ); α is the cohesion force coefficient; and cu is the cohesion force in undrained conditions (kN/m2 ). The α value varies depending on the hardness of the clay layer, the type and construction method of the pile, the stratum condition, and the size of the pile. Materials 2021, 14, 5593 2 α is the cohesion force coefficient; and where is is the cohesion force (kN/m the co2); ); where the cohesion force (kN/m α is the cohesion force coefficient; and is is the co2). hesion force in undrained conditions (kN/m 2 hesion force in undrained conditions (kN/m ). 5 ofcon21 The valuevaries variesdepending dependingononthe thehardness hardnessofofthe theclay claylayer, layer,the thetype typeand and The αα value construction method the pile, the stratum condition, and the size the pile. struction method ofof the pile, the stratum condition, and the size ofof the pile. 2.3. C.T Cofferdam Method 2.3. C.T Cofferdam Method The C.T cofferdam method creates acut-off cut-offspace spaceusing usingprefabricated prefabricatedsteel steelcaisson caisson The C.T cofferdam method creates a cut-off space using prefabricated steel caisson and rubber materials when installing, repairing, reinforcing underwater structures. and repairing, oror reinforcing underwater structures. rubber materials when installing, repairing, or reinforcing underwater structures. There are rubber tubes and compression-type rubber packing materials used for the There are rubber tubes and compression-type rubber packing materials used for the cut-off. As shown in Figure 2a, the adhesive rubber tube attached to the end the steel the steel cut-off. As shown in Figure 2a, the adhesive rubber tube attached to the end ofof steel caisson is in close contact with the leveling concrete and creates a pressure greater than concrete and creates a pressure greater thanthan the caisson is is in in close closecontact contactwith withthe theleveling leveling concrete and creates a pressure greater the water pressure to block the external inflow. As shown in Figure 2b, the compressionwater pressure to block the external inflow. As shown in Figure 2b, the the water pressure to block the external inflow. As shown in Figure 2b,compression-type the compressiontype rubber packing compresses the rubber packing attached to the thesteel steel rubber packing compresses the rubber packing attached to the bottom ofbottom the steel caisson type rubber packing compresses the rubber packing attached to the bottom ofofthe caisson with the caisson’s own weight, which is greater than the water pressure, to block with thewith caisson’s own weight, which which is greater than the pressure, to block the caisson the caisson’s own weight, is greater thanwater the water pressure, to block theexternal external inflow theleveling leveling concrete. thisstudy, study, close-fitting typerubber rubber tube external inflow to the leveling concrete. In this study, a close-fitting typetype rubber tubetube C.T the inflow toto the concrete. InIn this a aclose-fitting C.T cofferdam was used. cofferdam was was used.used. C.T cofferdam (a) Compression-type rubber tube (b) Close-fitting-type rubber packing (a) Compression-type rubber tube (b) Close-fitting-type rubber packing Figure 2. Schematic of C.T cofferdam method. Figure Figure 2. 2. Schematic Schematic of of C.T C.T cofferdam cofferdam method. method. Review Design Data 3.3. Review ofof Design Data 3. Review of Design Data 3.1. Site Overview 3.1. Site Overview 3.1. Site Overview InIn the case of of OO Bridge P2,P2, thethe pre-bored pilepile waswas pulled out out by about 0.17 0.17 to 0.34 0.34 m the case OO Bridge pre-bored pulled about In the case of OO Bridge P2, the pre-bored pile was pulled out bybyabout 0.17 toto0.34 due to thetobuoyancy generated at the at bottom of the leveling concreteconcrete and the and C.T cofferdam due thebuoyancy buoyancy generated thebottom bottom theleveling leveling theC.T C.Tcofcofmmdue to the generated at the ofofthe concrete and the was levitated, causing damage todamage the structure. ferdam was levitated, causing to the structure. ferdam was levitated, causing damage to the structure. Figure 3 shows the pull-out ofof the C.T cofferdam at at P2 where thethe problem occurred. Figure 3 shows the pull-out the C.T cofferdam where problem occurred. Figure 3 shows the pull-out of the C.T cofferdam at P2P2 where the problem occurred. (a) P2 C.T cofferdam 90° putout (0.17 m) (a) P2 C.T cofferdam 90° putout (0.17 m) (b) P2 C.T cofferdam 270° pull-out (0.34 m) (b) P2 C.T cofferdam 270° pull-out (0.34 m) Figure 3. Cont. Materials 2021, 14, 5593 Materials 2021, 14, 5593 6 of 21 6 of 22 (c) Site overview of P2 C.T cofferdam 270° (d) Pull-out status of P2 C.T cofferdam Figure3.3. Pull-out Pull-out view viewof ofC.T C.Tcofferdam cofferdamat atP2. P2. Figure 3.2. 3.2. Analysis Analysis of of Pull-Out Pull-Out Force Force of of Pre-Bored Pre-Bored Piles PilesAccording Accordingto toDesign DesignCriteria Criteria With foreign design standards, thethe pull-out forces of Withreference referencetotovarious variousdomestic domesticand and foreign design standards, pull-out forces pre-bored pilespiles and and drilled shafts embedded in rock and compared. When of pre-bored drilled shafts embedded inwere rock calculated were calculated and compared. calculating the design of the C.T cofferdam, the pull-out force of the pile When calculating the structure design structure of the C.T cofferdam, the pull-out force ofapplied the pile was 600 kN. It was checked whether this pull-out force satisfies the design criteria, with applied was 600 kN. It was checked whether this pull-out force satisfies the design criteria, the theoretical equation substituting the actual insertion depthdepth of theofpile 1.92 m). with the theoretical equation substituting the actual insertion the(about pile (about 1.92 m). (1) C.T Cofferdam Design Structural Calculation Results (1) As C.Tshown Cofferdam Design Calculation Resultswas 3665.250 kN, the water load in Table 2, the Structural total weight of C.T cofferdam As shown in Table 2, the total weight of C.T cofferdam was 3665.250 kN, the water inside the tank was 5078.34 kN, the water load inside the watertight part was 548.311 kN, load inside the tank was 5078.34 kN, the water load inside the watertight part was 548.311 and the weight of the leveling concrete was 7591.710 kN. When calculating the load in the kN, and the weight of the leveling concrete was 7591.710 kN. load design structural calculation sheet, the pile resistance was 600 kNWhen (at thecalculating time of thethe design) in the design structural calculation sheet, the pile resistance was 600 kN (at the time of the and the stability of the buoyancy was calculated to be 1.4. Since it is higher than 1.2, the design) and the stability of the buoyancy was calculated to be 1.4. Since it is higher than buoyancy was considered stable. 1.2, the buoyancy was considered stable. Table 2. Stability review for the buoyancy of C.T cofferdam. Table 2. Stability review for the buoyancy of C.T cofferdam. Classification Classification C.T cofferdam weight C.T cofferdam weight Water load inside the tank Resistance Load Resistance Load 3665.250 3665.250 5078.340 Water load inside the tank 5078.340 Water load inside watertight part Leveling concrete weight 7591.710 Water load inside watertight part Leveling concrete weight Resistance of piles (600 kN per pile) Resistance piles (45.2 (600 kN kNper perpile) pile) Pileof weight Buoyancy Selected Load (kN) Selected Load (kN) Pile weight (45.2 kN per pile) Leveling concrete bottom buoyancy 548.311 548.311 7591.710 21,600.000 21,600.000 1630.000 1630.000 29,929.973 Buoyancy Fs (Satety rate) +5078.34 +548.311+7591.71+21,600 29,929.973 Leveling concrete bottom buoyancy FS = 3665.25 = 1.4 > 1.2 29,929.973 3665.25 + 5078.34 + 548.311 + 7591.71 + 21,600 Fs (Satety rate) = 1.4 > 1.2 FS = 29,929.973 the pull-out force of a pre-bored (2) Review of the theoretical equation for calculating pile according to the design criteria (2) Review of the theoretical equation for calculating the pull-out force of a pre-bored Since most of the force of pre-bored piles is generated from the skin friction pile according to pull-out the design criteria of the piles embedded in the bedrock (excluding the sedimentary section at the top of the Since most of the pull-out force of pre-bored piles is generated from the skin friction of the piles embedded in the bedrock (excluding the sedimentary section at the top of the Materials 2021, 14, 5593 7 of 21 bedrock), the skin friction of the piles embedded in the bedrock according to each design standard was calculated. Considering no design standards for estimating the skin friction of pre-bored piles embedded in bedrock have been presented domestically and abroad, referring to the drilled shaft design standards, the skin friction of the bedrock was calculated. To examine the skin friction of main pile, (1) Korean Geotechnical Engineering [23], Ministry of Land, Infrastructure, and Transport [24], (2) Cho [25], and (3) Cho [26] were referred to. As the condition to be reviewed was similar to that of the anchor method, the study of Kim and Jung [27] was also referred to for review. As shown in Table 3, as a result of examining the grouting construction data, the grouting depth was found to be about 1.92 m on average and the skin friction value was calculated based on that value. Table 3. Comparison of the pull-out force applied to the design and design standard values. Classification Existing design data Design standard Structural Foundation Design Standard (2008) Anchor method Allowable Skin Friction of Pile (pull-out, kN) C.T cofferdam design structure calculation sheet (1.0 m embedded in the rock) 600 Pull-out force considering the thread-embedded depth of the pile (2.197 m embedded in the rock) 1209 AASHTO (1996) 200.5 Canadian Geotechnical Society (1985) 356.9 NAVFAC (1982) 931.8 FHWA (1988) Horvath and Kenny (1979) 648.8 FHWA (1999) Horvath and Kenny (1979) 770.4 FHWA (1999) Rowe and Armitage (1984) 746.8 Wiliams et al. (1980) 659.6 Rowe and Armitage (1987) 1774,3 Horvath and Kenney (1979) 819.9 Carter and Kulhawy (1988) 770.9 Reynolds and Kaderabek (1987) 3460.5 Gupton and Logan (1984) 2307.8 Reese and O‘Neil (1987) 1730.8 Rosengerg and Journaeaux (1976) 1489.7 Putout resistance of anchor 292.8 Friction of ground and grout 566.7 Maximum adhesive force of tensile material and grout 791.1 Remark Depth embedded in the rock 1.92 m Diameter of the pile 0.6 m 3.3. Adhesive Force Analysis of Pile and Grout 3.3.1. Adhesive Force Concept of Pile and Grout The skin friction failure of the pre-bored pile embedded in the bedrock appears in four forms, as shown in Figure 4. These are the shear failures between the pile-filling material and the pile; the adhesion failure between the rock and the pile-filling material; the shear failure of the rock mass itself; and finally the shear failure of the pile-filling material itself. Where the shear failure with the least resistance occurs, it leads to skin friction failure. Materials 2021, 14, 5593 Since the uniaxial compressive strength of most rocks is generally hig uniaxial compressive strength of the grout, shear failure usually occurs in th material before the shear failure of the rock and the skin friction of the pile e the rock is determined by the adhesion strength between the pile and the pi 8 of 21 terial. Figure 4. Pull-out fracture modeling of pre-bored piles. Figure 4. Pull-out fracture modeling of pre-bored piles. Since the uniaxial compressive strength of most rocks is generally higher than the uniaxial compressive strength of the grout, shear failure usually occurs in the pile-filling Moon etthe al.shear [12]failure studied thefriction W/Cof(water/cement, hereinafter material before of thethe rockeffect and theof skin the pile embedded in the rock is determined by the adhesion strength between the pile and the pile-filling material. ratio of the pile-filling material and the fine aggregate mixing ratio on the u Moon et al. [12] studied the effect of the W/C (water/cement, hereinafter called pressive strength, and the uniaxial compressive strength of the pile-filling W/C) ratio of the pile-filling material and the fine aggregate mixing ratio on the uniaxial about 7–36 strength, MPa depending on the mixingstrength ratio. Moon et al. [11] measured compressive and the uniaxial compressive of the pile-filling material was about 7–36 MPa depending on theafter mixing ratio. Moon et al. [11] measured load of 50% displacement at the pile head injecting grout with a W/Ctheratio and displacement at the pile head after injecting grout with a W/C ratio of 50% into basalt perforated with a diameter of BX (BX is a casing standard of out diameter of 5 perforated with a diameter of BX (BX is a casing standard of out diameter of 59.0 mm for standard penetration tests) and inserted a structural steel diameter pipe (outer dia used for standard penetration tests) and inserted a structural steel pipe (outer of 48.6 mm). skinfriction friction ofofthe steel pipe pipe pile embedded in the bedrock was determined mm). TheThe skin the steel pile embedded in the bedrock was de by the adhesion strength of the steel pipe and the grout, and the unit ultimate skin friction the adhesion strength of the steel pipe and the grout, and the unit ultimate was in the range of 0.92 to 1.04 MPa. was in range of 0.92 to 1.04 In athe study by Moon and Park [13],MPa. in the absence of fine aggregate, the unit ultimate skin In friction was 0.54 0.56 MPa regardless of W/C. Table 4 shows of ourfine field aggregate, conditions a study by to Moon and Park [13], in the absence the (D = 0.6 m in diameter and 1.92 m in rock penetration condition) using the unit ultimate skin friction was 0.54 to 0.56 MPa regardless of W/C. Table 4 shows our fiel skin friction values determined in a previous study by Moon et al. [11] and Moon and (D = 0.6 diameter in rock penetration condition) using the Park [13].m Asin shown in Tableand 4, this1.92 is themresult of calculating the allowable skin friction. The allowable friction was about 651.1 kN. study by Moon et al. [11] an skin friction skin values determined intoa 1109.29 previous Materials Materials 2021, 2021, 14, 14, 5593 5593 Materials 2021, 14, 5593 99 of of 22 22 Park Park [13]. [13]. As As shown shown in in Table Table 4, 4, this this is is the the result result of of calculating calculating the the allowable allowable skin skin friction. friction. The allowable skin friction was about 651.1 to 1109.29 kN. 9 of 21 The allowable skin friction was about 651.1 to 1109.29 kN. Table Table 4. 4. Allowable Allowable skin skin friction friction between between tension tension member member and and grout. grout. ClassificaTable 4. Allowable skin friction between tension member and grout. Classification tion Allowable Allowable Skin Skin Friction Friction Classification Allowable Skin Friction Test Test Methods Methods Test Methods = = × × × × × × = 920 × × × 1.92 Qu =×f 0.6 ×π D×L = 920 × ×× 1.92 s0.6 Moon et al. = 3,327.89 kN π × 0.6 × 1.92 Moon et al. =Q3,327.89 kN u = 920 × 3,327.89 [11] = 3327.89 kN Moon et al. [11] 3,327.89 [11] = = = = = = 1,109.29 1,109.29 Qa = Q = 1109.29 kN 33u = 3327.89 3 FS Test conditions: W/C: 50% Test W/C: Test conditions: conditions: W/C: 50% 50% = = × × × × × × Qu =× f 0.6 ×π D×L = 540 × × 1.92 s0.6 = 540 × × ×× 1.92 Moon Moon and and Q = 540 × π × 0.6 × 1.92 = 1,953.33 kN u = 1,953.33 kN Moon and Park Park = 1953.33 kN Park 1,953.33 1,953.33 [13] 1953.33 u = = = 651.11 [13] Qa = Q = 651.11 kN = = [13] FS 33 = =3 651.11 Test conditions: W/C: 60~120% Test conditions: W/C: 60~120% Test conditions: W/C: 60~120% 3.3.2. Lab Test for Measuring Adhesion Strength 3.3.2. 3.3.2. Lab Lab Test Test for forMeasuring MeasuringAdhesion AdhesionStrength Strength The skin friction of the pre-bored pile embedded rock should be by The pile embedded in in the rock should be evaluated by the Theskin skinfriction frictionofofthe thepre-bored pre-bored pile embedded in the the rock should be evaluated evaluated by the adhesion and skin friction occurring on the surface of the grout and pile foundation, adhesion and skin friction occurring on theon surface of the of grout pile foundation, rather the adhesion and skin friction occurring the surface the and grout and pile foundation, rather than of ground and In during on-site than those the ground grout. In grout. addition, during on-site construction, it should beit rather thanofthose those of the the and ground and grout. In addition, addition, during on-site construction, construction, it should that is due seawater in the considered that the adhesion isadhesion reduced due to seawater inflow in theinflow drilling slurry, should be be considered considered that the the adhesion is reduced reduced due to to seawater inflow inhole, the drilling drilling hole, and aa poor W/C Therefore, in evaluate friction the and poor W/C Therefore, in order to evaluate theto frictionthe of skin the pre-bored hole,a slurry, slurry, andratio. poor W/C ratio. ratio. Therefore, in order order toskin evaluate the skin friction of ofpile, the pre-bored pile, five reinforced concrete pile samples collected at the work site were used. five reinforced concrete pile samples collected at the work site were used. In using this pile, pre-bored pile, five reinforced concrete pile samples collected at the work site were used. In pile, grout underwater at 70% the W/C ratio the the groutthis is poured underwater at 70% of the W/C and adhesive strength of the In using using this pile, the the grout is is poured poured underwater at ratio 70% of of thethe W/C ratio and and the adhesive adhesive strength of the pile foundation and grout in the bedrock was inspected for 28 pile foundation and foundation grout in theand bedrock inspected 28 inspected days by air curing. strength of the pile groutwas in the bedrockfor was for 28 days days by by air air curing. curing. (1) Blending process (1) process (1) Blending Blending process In order to apply a mixing ratio similar to the field conditions, the W/C ratio was set In order to aa mixing similar the field conditions, the ratio was set In order to apply mixing ratio similarofto tothe thepile field conditions, the W/C W/Cfrom ratiothe was set to 70% and groutapply was poured onratio the surface foundation, collected field to 70% and grout was poured on the surface of the pile foundation, collected from the field to 70%both and grout was poured on conditions, the surface of pile foundation, thepiece field under air and underwater asthe shown in Figure 5. collected Similarly,from a test under both under both air air and and underwater underwater conditions, conditions, as as shown shown in in Figure Figure 5. 5. Similarly, Similarly, aa test test piece piece was prepared. was was prepared. prepared. Table 5 shows the concrete mixing ratio for the lab pull-out test. Table Table 55 shows shows the the concrete concrete mixing mixing ratio ratio for for the the lab lab pull-out pull-out test. test. Table 5. Mixing ratio for lab pull-out test. Classification Water (mL) Cement (g) Water curing of concrete: 28 days, 2 EA 490 700 Grout Material (g) 70 Air curing of concrete: 28 days, 3 EA 490 700 70 Materials 2021, 14, 5593 erials 2021, 14, 5593 10 of 21 (a) Compounding material (b) W/C 70% blend (c) Air curing of concrete (d) Test piece 11 o Figure 5. Test piece production process. Figure 5. Test piece production process. (2) Test (2) process Test process The lab was conducted toconfirm confirm adhesion strength of the of surface The test lab test was conducted to thethe adhesion strength of the surface the pileof the p foundation grout.As Asshown shown in 6a,6a, the the surface of the of grout cut into cm × foundation andand grout. inFigure Figure surface thewas grout was4 cut into 4 cm 4 cm sizes and the epoxy was coated on the surface of the pull-out equipment; the grout 4 cm sizes and the epoxy was coated on the surface of the pull-out equipment; the gro was as shown in Figure 6b. As shown in Figure 6c, the pull-out force was tested to evaluate was as shown in Figure 6b. As shown in Figure 6c, the pull-out force was tested to evalua the adhesion strength. Figure 6d is a view after the test. the adhesion strength. Figure 6d is a view after the test. Materials 2021, 2021, 14, 14, 5593 5593 Materials 11 11 of of 22 21 (a) Cutting the grout surface (b) Epoxy coating (c) Pull-out test (d) After pull-out test Figure force. Figure 6. 6. A A view view of of the the test test to to check check the the adhesion adhesion force. (3) Test results (3) The Testadhesion results strength of the three points of the air curing of concrete was in the range of 0.65–0.81 MPa and the adhesion of the twoofpoints the water curing was of concrete was The adhesion strength of the three points the airofcuring of concrete in the range in range MPa of 0.43–0.47 Tableof6the shows adhesion of the member, of the 0.65–0.81 and theMPa. adhesion two the points of the strength water curing oftensile concrete was in the and the calculation results of thethe allowable friction of the test piece. the grout, range of 0.43–0.47 MPa. Table 6 shows adhesionskin strength of the tensile member, the Even the experimental are different, the test results grout, andthough the calculation results ofmethods the allowable skin friction of the test applying piece. air curing ofEven the concrete are similar to those of previous studies, thus the results areapplying considered though the experimental methods are different, the test results air reliable. In the case of the water curing of concrete, it represents 60% of the adhesion curing of the concrete are similar to those of previous studies, thus the results are considered strength curing of concrete and when considering various variables (slurry, seareliable. of Inthe theair case of the water curing of concrete, it represents 60% of the adhesion water inflow, etc.) the field,and the when adhesion strength is expected to be lower. strength of the airoccurring curing ofinconcrete considering various variables (slurry, seawater inflow, etc.) occurring in the field, the adhesion strength is expected to be lower. Materials 2021, 14, 5593 12 of 21 Table 6. Allowable skin friction according to the adhesion between the pile and grout. Classification WT-1 Qu = f s × π × D × L Qu = 430 × π × 0.6 × 1.92 = 1555.4 kN 1555.4 u Qa = Q = 518.4 kN 3 FS = WT-2 Qu = f s × π × D × L Qu = 470 × π × 0.6 × 1.92 = 1700.12 kN 1700.12 u Qa = Q = 566.7 kN 3 FS = AT-1 Qu = f s × π × D × L Qu = 810 × π × 0.6 × 1.92 = 2929.99 kN 2929.99 u = 976.66 kN Qa = Q 3 FS = AT-2 Qu = f s × π × D × L Qu = 730 × π × 0.6 × 1.92 = 2640.61 kN 2640.61 u Qa = Q = 880.2 kN 3 FS = AT-3 Qu = f s × π × D × L Qu = 650 × π × 0.6 × 1.92 = 2358.72 kN 2358.72 u = 786.24 kN Qa = Q 3 FS = Water curing Air Curing Avgerage Allowable Skin Friction Allowable Skin Friction 542.55 kN 881.03 kN 3.4. Results of Pull-Out Load Test There are many design standards for designing C.T cofferdams with a pull-out force of 600 kN or more, but most of these standards are for drilled shafts. Since this study used the design standard of pre-bored piles based on empirical equations that have not yet been clearly established, various reviews are needed. In general, the pile load test for the bearing capacity test was performed according to the standard after the pile construction was completed and the dynamic load or static load test was performed within 5% of the number of piles. However, since there was no similar guideline in the pull-out load test, the pull-out force for the pre-bored pile at the point was measured to examine the pull-out problem that occurred at the research site. The most accurate measurement of pull-out force was 217 kN in the pull-out load test performed on the T1 pile of P2 at the OO Bridge in April 2018. However, this was tested 13 days after the grout was placed and 78.7% of the measured value was set as the allowable pull-out force by referring to the Basic Structure Design Standards and Explanations, Road Bridge Design Standards, and other references (Table 7). Table 7. Re-examination of allowable pull-out force according to the results of the pull-out load test. Classification Re-examination of Allowable Pull-Out Force Allowable Pull-Out Force 1 Qu = 651.1 kN (at Offset Point) On-site pull-out test P2 Qu = 651.1 ÷ 0.787 = 827.3 kN Qu = 827.3 ÷ 2 = 413.6 kN 2 Qu = 629.2 kN (at 0.25 in) Qu = 629.2 ÷ 0.787 = 799.4 kN Qu = 799.4 ÷ 2 = 399.7 kN 399.7 kN The correction value was calculated by referring to the ACI 208R-92 standard and estimating the uniaxial compressive strength according to the material age. The on-site ultimate pull-out test value was 629.2 MPa and the safety side’s age of 12 days was applied in consideration of the curing time and pull-out test time. Therefore, the correction factor according to the age of the concrete for 12 days was 0.828 and here, again, 5% was corrected for the water curing of concrete; the final correction factor was 0.787. The calculated pull- Materials 2021, 14, 5593 13 of 21 out force was 629.2 MPa/0.787 = 799.95 MPa and the short-term load safety factor of 2 was applied here; the final pull-out force was calculated as 399.7 kN. The allowable pull-out force reviewed based on the on-site pull-out load test was 399.7 kN, which is very different from the pull-out force of 600 kN applied to the design. It is agreed that poor W/C ratio, due to the inflow of seawater, slurry, and excessive inflow of seawater into the drilling hole at the site, is the cause of lowering the adhesion between the pile and the grout. A total of 399.7 kN from the pull-out load test is about 60% of the allowable pull-out force f 600 kN applied to the design and therefore it is agreed that the pre-bored pile was pulled out due to the lack of the design load. In addition, in comparing the results of the pull-out load test with the theoretical results, the results are most similar to those of CGS (1985). This study compared the uniaxial compressive strength of rock and concrete, which is similar to the concept of estimating the skin friction of a pre-bored pile embedded in bedrock, thus it seems to show similar results to our experiment. 3.5. C.T Cofferdam Stability Review In order to estimate the skin friction of the pre-bored pile embedded in the rock, the original design, analysis of the research data, review of the design criteria, adhesion strength test of the pile foundation and grout, the results of the field pull-out load test were reviewed. Based on this, the stability of C.T cofferdam was reviewed by recalculating the pull-out force similar to when calculating to the field conditions. As a result of examining the stability of C.T cofferdam as shown in Table 8, the minimum safety factor is satisfied when the pull-out force of the pile foundation is at least 500 kN. Table 8. Results of C.T cofferdam stability review according to the recalculation of the pull-out force. Classification Safety Factor (Standard 1.2) Remark Original design (1.0 m rock-bottom embedded) 600 1.4 stable Estimated value Grout air curing of concrete (1.92 m rock depth) 881 1.7 stable Site conditions lacking Grout placed in water (1.92 m rock depth) 542 1.3 stable Only the conditions for placing it in water were taken into account On-site experiment On-site pull-out test (1.92 m rock depth) 399 1.1 instable Test methods have high reliability Design data Designer review (2.197 m rock depth) 1210 2.0 stable Cast-in-place pile standards Various research standards (1.92 m rock depth) 680~1160 1.4~2.0 stable Air curing of concrete Various design standards (1.92 m rock depth) 220~1700 0.8~2.6 stable~ instable Cast-in-place pile standards Existing design Lab experiment P2 Pile Pull-Out Force (kN) Previous research Materials 2021, 14, 5593 14 of 21 While the pull-out force of the original design was designed based on 600 kN, as a result of the on-site experiment test, it was found to be unstable at 399 kN. In addition, when reviewed by various design standards, it was unstable at 220–1700 kN. Therefore, considering various variables (slurry, seawater inflow, etc.) occurring at the site, the adhesion strength can be further lowered, thus the depth of penetration of the rock and the W/C ratio should be sufficiently considered when designing. 4. Reviewing the Amount of Pull-Out of Pre-Bored Piles through Numerical Analysis 4.1. Analysis Conditions In order to identify the amount of pull-out of the pile foundation, depending on leveling the concrete base buoyancy, the shape of the pile and field ground conditions were considered, and soil properties of the field were estimated based on the site investigation reports and empirical equations. In this study, two boring investigations were conducted. The sites are composed of sedimentary layers, weathering soils, weathered rocks, and soft rock layers from the top, and the ground water table was GL(-) 8.3 to 8.5 m in the upper plate of the temporary bridge, being distributed in sedimentary layers. Therefore, this ground condition was modeled for numerical analysis. 4.1.1. Analysis Program In this study, Midas GTS (Midas IT. Co.,Ltd., Gyeonggido, Korea), a finite element analysis program, was employed. Midas GTS can perform modeling to consider the ground shape and construction process as much as possible during ground analysis, and can reflect actual field conditions in the light of non-linearity and in-situ ground stress states of various materials used for numerical analysis. For analyzing complex non-linear behaviors of the ground, Midas GTS was equipped with various constitutive elasto-plastic models, as well as with automatic mesh generation. 4.1.2. Drilling Section The ground on the upper plate was investigated from the 270◦ direction to the 90◦ direction of C.T cofferdam to collect the ground data to be applied to the model. Sedimentary layers were confirmed in the current surface, the thickness was distributed as 12.2–16.3 m, and the composition consisted of neutral and fine yarns. The N value measured in the standard penetration test was 1/30 to 12/30 (times/cm) and the relative density was in a very loose to moderately dense state. The weathered soil layer was distributed in the BH-1 hole with a thickness of 1.3 m, the composition was of silt sand, and the condition was dense. The weathered rock layer was in a state of severe weathering and was distributed at a thickness of 4.8–6.4 m, wherein the composition was of silt sand. As a result of the standard penetration test, the N value was 50/10 to 50/3 (times/cm) and the relative density was very dense. The soft rock layer was distributed at a thickness of 2.0 m in the entire borehole and it was observed with the naked eye that the rock condition was severely to moderate weathering. In addition, the rock strength was weak to moderately strong. Figure 7 is a stratum section view used for the analysis section. Materials 2021, 14, 5593 Materials 2021, 14, 5593 15 of 21 15 of 22 Figure 7. Stratum section view. Figure 7. Stratum section view. 4.1.3. Calculation of the Material Properties of the Ground 4.1.3. Calculation of the Material Properties of the Ground The Mohr–Coulomb (MC) model was used for the natural ground and the composite (MC) modelthe was used for pile the natural composite pileThe wasMohr–Coulomb modeled both by applying steel pipe SKK490ground and byand the the reinforced conpile was modeled both by applying thestructure steel pipeofpile by the of reinforced concrete pile specification. The geological the SKK490 site was and composed a sedimentary crete pile specification. The geological of the a sedimentary layer, weathered soil layer, weatheredstructure rock layer, andsite softwas rockcomposed layer, andofits structure was layer, weathered soil layer, weathered rock layer, and soft rock layer, and its structure relatively simple; very soft sand was distributed in the upper original ground. was relatively simple; very soft sand was distributed in the upper original ground. In order to determine the design constant of the ground, the characteristic values In order to determine the design constant theelastic ground, the characteristic valueswere for for the cohesion force, internal friction angle,of and modulus of each stratum the cohesionbased force,on internal friction angle, and elastic modulus of each were calcalculated the ground survey report, empirical equations, andstratum other references. culated based9 on survey report, empirical andanalysis. other references. Tables andthe 10 ground show the ground constants used equations, for numerical The material Tables applied 9 and 10toshow the ground constants for numerical properties the grout and injected into used weathered rock andanalysis. soft rockThe werematerial selected properties applied to the grout and injected into weathered rock and soft rock were in full consideration of the site conditions. The strength of 399.7 kN in the pull-out load setest lected in full45.4% consideration of theof site conditions. Thecuring strength of 399.7 kN the was pull-out was about of the strength 881 kN in the air of concrete, thusin40% used 2 , which load test was about Therefore, 45.4% of the strength of 881 kN inisthe airofcuring of concrete, 40% for safety reasons. 928,000 kN/m 40% the concrete elasticthus modulus 2 2, which is of 2,320,000 kN/mreasons. , was determined the elastic of40% the of grout, considering the was used for safety Therefore, as 928,000 kN/mmodulus the concrete elastic 2, was effects ofofseawater slime, anddetermined was applied the numerical analysis. modulus modulus 2,320,000and kN/m asto the elastic modulus of theThe grout, consid-of elasticity is a factor that greatly amount of elastic and the modulus ering the effects of seawater andaffects slime,the and was applied tosettlement the numerical analysis. Theof elasticity of weathered rocks and soft rocks is not the same. The modulus of elasticity modulus of elasticity is a factor that greatly affects the amount of elastic settlement andof themodulus grout was toof both the weathered rocksoft androcks the soft rock consideration of the the of applied elasticity weathered rocks and is not theinsame. The modulus conditions the application ofboth the grout. offield elasticity of theafter grout was applied to the weathered rock and the soft rock in consideration of the field conditions after the application of the grout. Table 9. Material properties applied to the numerical analysis. Classification Wetting unit weight (kN/m3) Saturation unit weight (kN/m3) Cohesion c (kN/m2) Sedimentary Soil Weathered Rock Soft Rock Leveling Concrete Rebar Concrete Steel Pipe Pile 17 23 25 25 25 78 18 23.5 25.5 25.5 25.5 79 13 30 50 - - - Materials 2021, 14, 5593 16 of 21 Table 9. Material properties applied to the numerical analysis. Classification Sedimentary Soil Weathered Rock Soft Rock Leveling Concrete Rebar Concrete Steel Pipe Pile Wetting unit weight γt (kN/m3) 17 23 25 25 25 78 Saturation unit weight γsat (kN/m3 ) 18 23.5 25.5 25.5 25.5 79 Cohesion c (kN/m2 ) 13 30 50 - - - Internal friction angle φ (◦ ) 0 33 35 - - - Elastic modulus coefficient E (kN/m2 ) 4000 167,500 2,180,000 2,320,000 2,320,000 2.1 × 108 Poisson’s ratio ν 0.38 0.3 0.26 0.2 0.19 0.3 Table 10. Applied material properties of the grout injected into the weathered rock and soft rock. Classification Weathered Rock (Injection Material) Soft Rock (Injection Material) Wetting unit weight γt (kN/m3 ) 23 25 Saturation unit weight γsat (kN/m3 ) 23.5 25.5 Cohesion c (kN/m2 ) 30 50 Internal friction angle φ (◦ ) 33 35 Elastic modulus coefficient E (kN/m2 ) 928,000 928,000 Poisson’s ratio ν 0.3 0.3 4.1.4. Modeling The internally excavated composite pile modeled was composed of a steel pipe pile with a diameter of 600 mm and thickness of 14 mm from the leveling concrete to a depth of 6.5 m, which was a reinforced concrete pile with a diameter of 600 mm from the end of the steel pipe pile to the tip. The stratum structure was modeled as shown in Figure 8 based on the BH-2 drilling column. In the numerical analysis, the composite steel pipe pile and reinforced concrete pile were modelled as elastic materials and a leveling concrete base buoyancy of 29,929.973 kN/m2 was applied to the upper leveling concrete upwards. Figures 9 and 10 present the analysis results and show the maximum value of the vertical displacement in each node. The pile end had the maximum displacement in the nodes, as referred to in the boxes in Figures 9 and 10. Materials 2021, 14, 5593 Materials 2021, 14, 5593 17 of 21 17 of 22 Materials 2021, 14, 5593 18 of 22 Table 11. Numerical analysis results. Displacement (cm) Stability (based on 1 inch) Pile tip 0.22 to 0.29 0.29 ≤ 2.54_stable Total displacement 0.70 to 0.77 0.77 ≤ 2.54_stable Pile tip 0.64 to 0.89 0.89 ≤ 2.54_stable Total displacement 2.37~2.61 2.61 ≥ 2.54_unstable Pile tip 0.22 to 0.29 0.29 ≤ 2.54_stable Total displacement 0.70 to 0.77 0.77 ≤ 2.54_stable P2 bridge direction Pile tip Underwater grout Totalsection. displacement Figure 8. Analysis Consider material properties 0.64 to 0.89 0.89 ≤ 2.54_stable 2.37~2.61 2.61 ≥ 2.54_unstable Classification P2 lateral direction Soft rock at 1.92 m P2 lateral direction Underwater grout Consider material properties P2 bridge direction Soft rock at 2.21 m Figure 8. Analysis section. 4.2. Numerical Analysis Review In the case of the P2 lateral direction (90°→270°), as shown in Figure 9a, the pull-out displacement of the tip of the pile foundation was 0.22 to 0.29 cm and the total pull-out displacement of the structure was 0.70 to 0.77 cm during the integral movement, as shown in Figure 9a. It is within safe limits because it is smaller than the safety standard of 1 inch (2.54 cm). Figure 9b is the result of the on-site pull-out load test and the numerical analysis reflects the field conditions. For the modulus of the grout injected in the weathered rock and soft rock, 40% of the modulus of the elasticity of concrete was applied. As a result of the numerical analysis, the pull-out displacement at the tip of the pile foundation was 0.64 to 0.89 cm and the overall pull-out displacement was 2.37 to 2.61 cm. It was higher than 1 inch (2.54 cm) and outside of safety standards. In the case of the direction perpendicular (0°→180°) to the P2 pier, as shown in Figure 10a, the pull-out displacement of the tip of the pile foundation was 0.22 to 0.29 cm and the overall pull-out displacement was 0.70 to 0.77 cm, which is within the safe range. However, as depicted in Figure 10b, considering the field conditions, it was found that the total pull-out displacement of the structure was 2.37 to 2.61 cm, similar to the lateral direction and thus unstable. As a result of the numerical analysis, the integral behavior of the pile foundation and the ground appeared to be stable when the site conditions were not sufficiently considered, but in the numerical analysis considering the site conditions, it was found that the (a) pull-out displacement exceeded the standard of 1 inch and was unstable. Therefore, when designing the skin friction (pull-out Figure 9. Cont.force) of the pre-bored pile embedded in bedrock, the site conditions should be sufficiently considered. Table 11 summarizes the numerical analysis results. Materials 2021, 14, 5593 Materials 2021, 2021, 14, 14, 5593 5593 Materials 18 of 21 19 of of 22 22 19 (b) (b) Figure P2P2 direction, (a)(a) SoftSoft rock condition at 1.92 m and the integrated behavior of both Figure 9. 9. Numerical Numericalanalysis analysisresult resultinin inthe the direction, rock condition at 1.92 1.92 m and and the integrated integrated behavior of Figure 9. Numerical analysis result the P2 direction, (a) Soft rock condition at m the behavior of the pile foundation and ground; (b) The soft rock insertion condition of 1.92 m and the on-site pull-out load test results are both the pile foundation and ground; (b) The soft rock insertion condition of 1.92 m and the on-site pull-out load test both the pile foundation and ground; (b) The soft rock insertion condition of 1.92 m and the on-site pull-out load test reflective this. results are areofreflective reflective of this. this. results of (a) (a) Figure 10. Cont. Materials 2021, 14, 5593 Materials 2021, 14, 5593 19 of 21 20 of 22 (b) Figure perpendicular direction of of thethe P2 P2 pier. (a) (a) SoftSoft rockrock condition at 2.21 m and the Figure10. 10.Numerical Numericalanalysis analysisresults resultsininthe the perpendicular direction pier. condition at 2.21 m and integrated behavior of both the pile foundation and ground. (b) Soft rock penetration condition at 2.21 m, reflecting the the integrated behavior of both the pile foundation and ground. (b) Soft rock penetration condition at 2.21 m, reflecting results of the pull-out load load test. test. the results ofon-site the on-site pull-out For the modeling of pre-bored piles embedded in the rock, material properties of 5. Conclusions weathered rock and soft rock, where the piles are embedded, were compared on the basis In this study, the pre-bored pile of OO bridge pier P2 and the pull-out phenomenon of the material properties of grout materials with a low elastic modulus, as shown Table 9. observed at C.T cofferdam were reviewed according to the design standards of the prebored pile reflected in Review the design. The stability of C.T cofferdam was reviewed by evalu4.2. Numerical Analysis ating the adhesion strength of the grout and ◦concrete surface attached to the bedrock. The In the case of the P2 lateral direction (90 →270◦ ), as shown in Figure 9a, the pull-out following conclusions drawn. displacement of the tipwere of the pile foundation was 0.22 to 0.29 cm and the total pull-out According to the existing design the theoretical equation for skin displacement of the structure was 0.70 todata 0.77and cm during the integral movement, as friction shown embedded in bedrock, most of the allowable skin friction forces were more than kN, in Figure 9a. It is within safe limits because it is smaller than the safety standard of600 1 inch thus it was safe in design. However, in the field, the pre-bored pile showed instability. (2.54 cm). Figure 9b is the result of the on-site pull-out load test and the numerical analysis This means that the skin friction of the drilled shaft during the design and therock prereflects the field conditions. For the modulus of theapplied grout injected in the weathered bored applied the construction were not the same, and it seems have ocand softpile rock, 40% ofduring the modulus of the elasticity of concrete was applied. Asto a result of curred because the pull-out resistance of the pre-bored pile was the lower one the the numerical analysis, the pull-out displacement at the tip of the pile foundation wasof0.64 drilled shafts. to 0.89 cm and the overall pull-out displacement was 2.37 to 2.61 cm. It was higher than As a result of the lab test adhesion strength, the strength during the air curing of 1 inch (2.54 cm) and outside of for safety standards. ◦ ) to the concrete was overestimated as 881 kN compared to◦the pull-out force 600 kN as applied In the case of the direction perpendicular (0 →180 P2ofpier, as shown in during10a, the the design and displacement the strength for the tip water curing of concrete was was 0.22 542 to kN, which Figure pull-out of the of the pile foundation 0.29 cm showed similarpull-out results. displacement However, when variables seawater and the overall wasvarious 0.70 to field 0.77 cm, which(slurry, is within the safeinflow, range. etc.) occurring in the field were taken into consideration, the adhesion strength was exHowever, as depicted in Figure 10b, considering the field conditions, it was found that pected to be lower. the total pull-out displacement of the structure was 2.37 to 2.61 cm, similar to the lateral As aand result of re-examining the allowable pull-out force according to the pull-out load direction thus unstable. test, As thea pull-out is 399.7 kN, which about 66% of theofpull-out force of 600and kN result of force the numerical analysis, theisintegral behavior the pile foundation applied to the design.toThe resultswhen of thethe on-site pull-out load test the theoretical equathe ground appeared be stable site conditions were notand sufficiently considered, tioninwere compared.analysis The method of obtaining theconditions, skin frictionit of thefound pre-bored pilepulland but the numerical considering the site was that the the displacement method of obtaining both uniaxialofcompressive of the rock and the conout exceeded thethe standard 1 inch and strength was unstable. Therefore, when designing the skin friction ofcalculated the pre-bored pile embedded in bedrock, the crete pile were similar, and(pull-out the skin force) friction by these two methods showed simsite should be sufficiently considered. ilar conditions results as well. Table 11 summarizes the numerical analysis results. As a result of the numerical analysis review, in the case of the integral pull-out behavior of the pile foundation and ground, the displacement of the entire structure was Materials 2021, 14, 5593 20 of 21 Table 11. Numerical analysis results. Classification P2 lateral direction Soft rock at 1.92 m P2 lateral direction Underwater grout Consider material properties P2 bridge direction Soft rock at 2.21 m P2 bridge direction Underwater grout Consider material properties Pile tip Displacement (cm) Stability (Based on 1 inch) 0.22 to 0.29 0.29 ≤ 2.54_stable Total displacement 0.70 to 0.77 0.77 ≤ 2.54_stable Pile tip 0.64 to 0.89 0.89 ≤ 2.54_stable Total displacement 2.37~2.61 2.61 ≥ 2.54_unstable Pile tip 0.22 to 0.29 0.29 ≤ 2.54_stable Total displacement 0.70 to 0.77 0.77 ≤ 2.54_stable Pile tip 0.64 to 0.89 0.89 ≤ 2.54_stable Total displacement 2.37~2.61 2.61 ≥ 2.54_unstable 5. Conclusions In this study, the pre-bored pile of OO bridge pier P2 and the pull-out phenomenon observed at C.T cofferdam were reviewed according to the design standards of the prebored pile reflected in the design. The stability of C.T cofferdam was reviewed by evaluating the adhesion strength of the grout and concrete surface attached to the bedrock. The following conclusions were drawn. According to the existing design data and the theoretical equation for skin friction embedded in bedrock, most of the allowable skin friction forces were more than 600 kN, thus it was safe in design. However, in the field, the pre-bored pile showed instability. This means that the skin friction of the drilled shaft applied during the design and the pre-bored pile applied during the construction were not the same, and it seems to have occurred because the pull-out resistance of the pre-bored pile was the lower one of the drilled shafts. As a result of the lab test for adhesion strength, the strength during the air curing of concrete was overestimated as 881 kN compared to the pull-out force of 600 kN as applied during the design and the strength for the water curing of concrete was 542 kN, which showed similar results. However, when various field variables (slurry, seawater inflow, etc.) occurring in the field were taken into consideration, the adhesion strength was expected to be lower. As a result of re-examining the allowable pull-out force according to the pull-out load test, the pull-out force is 399.7 kN, which is about 66% of the pull-out force of 600 kN applied to the design. The results of the on-site pull-out load test and the theoretical equation were compared. The method of obtaining the skin friction of the pre-bored pile and the method of obtaining both the uniaxial compressive strength of the rock and the concrete pile were similar, and the skin friction calculated by these two methods showed similar results as well. As a result of the numerical analysis review, in the case of the integral pull-out behavior of the pile foundation and ground, the displacement of the entire structure was stable within the allowable value, but when using the material properties of the grout, considering the field conditions, the displacement of the entire structure exceeded the allowable value. This appears to have lowered the adhesion strength due to construction issues such as ground complexity as well as seawater and slime treatment, which were not expected at the time of design. Author Contributions: Conceptualization, K.P.; methodology, software and writing—original draft preparation, D.K.; writing—review and editing and project administration, G.K. and W.L.; funding acquisition. All authors have read and agreed to the published version of the manuscript. Materials 2021, 14, 5593 21 of 21 Funding: This study was supported by Chosun University, 2021. Institutional Review Board Statement: Not applicable. Informed Consent Statement: Not applicable. Conflicts of Interest: The authors declare no conflict of interest. References 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. International Standard. Petroleum and Natural Gas Industries–Fixed Steel Offshore Structures; ISO: Geneva, Switzerland, 2020; pp. 1–8. Structure Foundation Design Criteria; Ministry of Land, Infrastructure and Transport: Sejong, Korea, 2018. Standard Test Methods for Deep Foundations under Static Axial Tensile Load; Designation: D3689-07; American Society for Testing and Materials: West Conshohocken, PA, USA, 2007. Federal Highway Administration. Design and Construction of Driven Pile Foundations; No. FHWA-HI-96-033; Publisher: Washington, DC, USA, 1996. Available online: https://vulcanhammerinfo.files.wordpress.com/2017/08/fhwa-nhi-05-042-043.pdf (accessed on 26 September 2021). Drilled Shaft: Construction Procedures and Design Methods; No. FHWA-IF-99-025; Federal Highway Administration: Washington, DC, USA, 1999. Available online: http://danbrownandassociates.com/wp-content/uploads/2020/02/GEC10-Drilled-ShaftFinal-10-5-18.pdf (accessed on 26 September 2021). Canadian Geotechnical Society. Canadian Foundation Engineering Manual, 3nd ed.; Canadian Geotechnical Society Technical Committee on Foundation: Ottwa, ON, Canada, 1992. Maertens, L. Design and Installation of Steel Open End Piles in Weathered Basalt; International Deep Foundations Congress: Orlando, FL, USA, 2002; pp. 1–16. Shakir-Khalil, H. Push-Out Strength of Concrete-Filled Steel Hollow Sections; The Structural Engineers: Charity, UK, 1993; Volume 71, pp. 230–233. Shakir-Khalil, H. Resistance of Concrete-Filled Steel Tubes to Pushout Forces; The Structural Engineers: Charity, UK, 1993; Volume 71, pp. 234–243. Nezamian, A.; Al-Mahaidi, R.; Grundy, P.; O’Loughlin, B. Push-Out Strength of Concrete Plugs in Tubular Steel Piles; Intl. Offshore and Polar Engineering Conf.: Kitakyushu, Japan, 2002; pp. 60–64. Moon, K.T.; Park, S.R.; Shin, M.G. A Study on the Skin Friction of Steel Pile Embedded in Rock; Korean Society of Civil Engineering Conf.: Seoul, Korea, 2014; pp. 1647–1648. Moon, K.T.; Park, S.R.; Shin, M.G. Mechanical properties of filling materials for bored pile in rock. J. Korean Soc. Civ. Eng. 2017, 37, 637–645. Moon, K.T.; Park, S.R. Evaluation of the Shaft Resistance of Drilled-in Steel Tubular Pile in Rock Depending on the Proportion of Annulus Grouting Material. J. Korean Soc. Civ. Eng. 2018, 38, 51–61. Kim, D.H.; Park, J.J.; Chang, Y.C.; Jeong, S.S. Proposed shear load-transfer curves for prebored and precast steel piles. J. Korean Geotech. Soc. 2018, 34, 43–58. Kim, R.H.; Kim, D.W. Analysis of bearing capacity of rock socketed pre-bored super strength piles based on dynamic load test results. J. Korean Geotech. Soc. 2019, 18, 89–100. [CrossRef] Chae, S.G.; Park, J.H.; Ryu, K.R.; Kim, K.J.; Kim, J.H.; Ha, H.M. Formal introduction and suggestion of the vertical bearing capacity of SDA-buried piles constructed on bedrock. J. Korean Geotech. Soc. 2020, 36, 8–27. Vesic, A.S. Bearing capacity of deep foundations in sand. Highw. Res. Rec. 1943, 39, 112–153. Meyerhof, G.G. The ultimate bearing capacity of foundation. Geotechnique 1951, 2, 301–332. [CrossRef] Meyerhof, G.G. Penetration tests and bearing capacity of cohesionless soils. ASCE J. Geotech. Eng. 1956, 82, 1–19. Poulos, H.G.; Davis, E.H. Pile Foundation Analysis and Design; John Wiley and Sons: New York, NY, USA, 1980; Available online: https://priodeep.weebly.com/uploads/6/5/4/9/65495087/_series_in_geotechnical_engineering__harry_g._poulos_ edward_h._davis-pile_foundation_analysis_and_design-john_wiley___sons_inc__1980_.pdf (accessed on 26 September 2021). Vesic, A.S. Design of Pile Foundation; NCHRP Synthesis of Highway Practice No.42, Transportation Research Record; National Research Council: Washington, DC, USA, 1977. Berezantzev, V.G. Load bearing capacity and deformation of piled foundations. In Proceedings of the Fifth International Conference on Soil Mechanics and Foundation Engineering, Paris, France, 17–22 July 1961; Dunod: Paris, France, 1961; Volume 2, pp. 11–15. Korean Geotechnical Engineering, 4th ed.; Seoul, Korea, 2002. Road Bridge Design Criteria; Ministry of Land, Infrastructure and Transport: Sejong, Korea, 2016. Cho, C.W. Pre-Bored Pile Method; Seoul, Korea, 2006. Cho, C.W. Piling Engineering Practice; ENG Book: Seoul, Korea, 2010. Kim, J.H.; Jung, H.S. Ground Anchor Method for Practitioners; Cialis (CIR): Seoul, Korea, 2016.