O pilartes Project Management QSO-340 Unit 2 – Challenge 1: WBS, Resource, and Schedule 1. Which of the following descrip ons corresponds to a project schedule? Sequencing the ac vi es and tasks for a project 2. Kelly is a project manager and needed to create a work breakdown structure for a new project. Once she completed the process, she realized that she had made some mistakes. Which of the following could be a mistake Kelly made while developing a WBS? Kelly listed the tasks before iden fying the ac vi es. 3. As the project manager involved in upda ng the company’s website, Trevor determines that so ware will be used to develop a new blog. This new so ware would be considered a technology resource. 4. Kyle and his team are determining the resources needed for a project that involves using cats in a video. Which of the following elements would a project manager nego ate for a material contract? Contact a clothing company to provide pet wardrobes 5. Kelly was determining the task Peter would be assigned for the next big project at work. It is best for Kelly to assign this task to Peter before crea ng the project’s schedule so that Kelly can u lize his exper se when es ma ng the me and effort involved. 6. Which of the following considers me and effort in a project schedule? Mary can back the chicken in 30 minutes, but the total cooking me is four hours since the chicken has to marinate prior to baking. 7. The project that started at the beginning of February will be completed by August 31. Which of the following best describes this scenario? Overall me 8. Grace and her team are in charge of cleaning up the local park every spring. Which of the following items would directly impact me es mates for cleaning the park? Amount of work required to remove the trash from the park 9. A network diagram for a project is different from a Gan chart for a project in which of the following ways? A network diagram is be er for comparing rela onships among project ac vi es.