Items F1 C1 FTB REBAR Computation Concrete: V=1.2(1.2)0.35(16)=8.06m3 Add 10% Allowance VT=8.06(1.10)=8.87m3 Cement=8.87(9.0)=79.83bags Sand=8.87(0.5)=4.44m3 Gravel=8.87(1.0)=8.87m3 H=3+0.4+0.2+0.1+1-0.35=4.35m V=0.20(0.40)4.35(16)=5.57m3 Add 5% Allowance VT=5.57(1.05)=5.85m3 Cement=5.85(9.0)=52.65bags Sand=5.85(0.5)=2.93m3 Gravel=5.85(1.0)=5.85m3 L=[14-2(0.15)-3(0.40)]+[10-2(0.15)-2(0.40)]2+[4-0.20-0.15]+[4-2(0.15)]+[4-0.0.05-0.15] +[12.5 -2(0.35)-0.40]+[10-2(0.15)-0.20]2+[10-0.35-0.15-0.4]+[2.5-0.35-0.05] =92.55m V=0.20(0.30)92.55=5.55m3 Add 10% Allowance VT=5.55(1.10)=6.11m3 Cement=6.11(9.0)=54.99bags Sand=6.11(0.5)=3.06m3 Gravel=6.11(1.0)=6.11m3 25.13(4)=100.52m 100.52 ÷ 6 = 16.75 pcs -12mm dia 25.13(2)=50.26m 50.26 ÷ 6 = 8.38 pcs – 10mm dia 25.13 ÷ 0.15 = 167.53 say 168 pcs L=0.2+0.4+0.075(2)=0.75m 6 ÷0.75 = 8 168 ÷ 8 = 21 pcs – 10mm dia Cement bags Materials and Quantities 10mm Sand Gravel pcs m3 m3 12mm pcs 79.83 4.44 8.87 52.65 2.93 5.85 54.99 3.06 6.11 16.75 8.38 21 WF REBAR RB-1 REBAR S-1 L=[14-2(0.15)-3(0.40)]+[12.5-0.15-2(0.40)]+[1.9+0.15]3+[4-2(0.75)]+[2.4+2(0.15)] +[2+0.15 +0.5]+[3-2(0.05)]+[3-0.60-0.20-0.40]+[3-2(0.60)]+[4-0.60-1.15]+[3.2-0.60-0.65]+[2.5-0.45 -0.80]+[2.5-0.80-0.15]=51.5m V=0.3(0.1)51.5=1.55m3 Add 10% Allowance VT=1.55(1.10)=1.71m3 Cement=1.71(9.0)=15.39bags Sand=1.71(0.5)=0.86m3 Gravel=1.71(1.0)=1.71m3 15.39 0.86 1.71 L=47.74(3)=143.22 No. of full length bar=143.22 ÷ 6 = 23.87pcs – 12mm dia No. of cut bar per 6m = 6 ÷ 0.3 = 20pcs No. of pcs = 47.74 ÷ 0.035=1364pcs No. of full length bar=1364 ÷20 = 68.2pcs-10mm dia L= [14-2(0.15)-3(0.40)]+[10-2(0.15)-2(0.40)](2)+[4-0.15-0.20]+[4-2(0.5)+[12.5-2(0.35)-0.40]+[10-2(0.15)-0.20](2)+[10-0.350.40-0.15]+[2.5-0.35-0.05]+[4.15-0.2-0.15]+[4-0.05-0.15]= 96.35m V= 0.2x0.3x96.35= 5.78m Add 10% allowance Vt=5.78x1.1=6.07 m3 Cement=6.07x9.0=54.63bags Sand=6.07x0.5=3.04m3 Gravel=6.07x1.0=6.07m3 L= (91.15) 4 = 364.6m 364.6 ÷6 = 60 pcs – 12mm dia L= 91.15(2)= 182.3m 182.3 ÷ 6 = 30.38 pcs – 10mm dia L=0.2+0.4+0.025(2)=0.75m 91.15 ÷ 0.75 + 1 = 608.67 say 609 pcs 6m ÷ 0.75 = 8 609 ÷ 8 = 76.13 – 10mm dia Area=[4.15-2(0.05)][2.5-2(0.05)=9.72m3 Thickness=100mm 23.87 68.2 54.63 3.04 6.07 60 30.38 76.13 V=9.72x0.1=0.97 m3 Add 10% allowance Vt=0.97x1.1=1.07 Cement=1.07x9.0=9.63m3 Sand=1.07x0.5=0.54m3 Gravel=1.07x0.5=1.07m3 STAIR SLAB REBAR L=17(0.3)=5.10m H=3+0.4+0.2=3.6m X= X=6.24m Width=0.8m Thickness=0.1m V=0.1(6.24)(0.8)= 0.50 Add 10% allowance= 0.55 Cement= 0.55x9.0=4.95 bags Sand= 0.55x0.5=0.28m3 Gravel= 0.55x1.0=0.55m3 Summation of area = 14.21(2)+18.72+12.10+34.06+2.75+15.21 = 111.26m2 V= 111.26 x 0.1 = 11.13m3 Add 10% allowance = 11.13x1.1= 12.24m3 Cement=12.24(9.0)= 110.16 bags Sand= 12.24(0.5)= 6.12m3 Gravel=12.24(1.0)= 12.24m3 4.95 0.28 0.55 110.16 6.12 12.24 2.9 + 0.2 1 = 15.5 say 16 pcs 4.9(16)=78.4m 78.4 ÷ 6 = 13.06(2)= 26.12pcs – 12mm dia 26.12 4.9 + 0.2 1 = 25.5 say 26 pcs 2.9(26)= 75.4m 75.4÷ 6 = 12.56 (2) = 25.13 pcs – 12 mm dia 25.13 3.9 + 0.2 1 =20.5 say 21 pcs 4.8(21)=94.5m 94.5÷6 = 15.75 pcs – 12 mm dia 4.8 + 0.2 1 =25 pcs 15.75 3.9(25)=97.5m 97.5 ÷ 6 = 16.25 pcs – 12 mm dia 16.25 2.95 + 0.2 1 =15.75 say 16 pcs 4.1 (16) = 65.6m 65.6 ÷ 6 = 10.93 pcs – 12 mm dia 4.1 + 1 = 21.5 say 22 pcs 0.2 2.95(22) = 64.9m 64.9 ÷ 6 = 10.82 pcs – 12 mm dia 10.93 10.82 6.95 + 0.2 1 =35.5 say 36 pcs 4.9(3.6)= 176.4m 176.4 ÷ 6 = 29.4 pcs - 12 mm dia 29.4 0.9 + 0.2 1 =5.5 say 6 pcs 3.05(6) = 18.3m 18.3 ÷6 = 3.05 pcs 12 - mm dia 3.05 + 0.2 3.05 1 = 16.25 say 17 pcs 0.9 (17) = !5.3 m 15.3÷ 6 = 2.55 pcs – 12 mm dia Total 2.55 372.6bags 20.73m3 29.16m3 204.09pcs 240.62pcs