PROGRESS REPORT
PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001)
9 FEBRUARY 2023 - 19 FEBRUARY 2023
(A) PROJECT DETAILS
PROJECT TITLE
:
GANGWAY INSTALLATION ON M3DR-A
CLIENT
:
TANJUNG OFFSHORE SERVICES
RIG
:
GHAZI 461
LOCATION
:
M3DR-A
CONTRACT NO
:
TOSPGPO22-2242
COMPANY
:
OCEAN VANTAGE ENGINEERING SDN BHD
POB
:
20 PAX
(B) CONTRACTOR DETAILS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
TING KEE SHENG – WORKPACK ENGINEER
JOANNES ANAK USIT – RIGGING SUPERVISOR
RAYMOND LAMI ANAK LINGKONG – BANKSMAN
ALEN PENGIRAN PANEL – RIGGER
MILTONESE SANDA ANAK MAURICE – RIGGER
ALEXANDER TINUS – RIGGER
KELLY ESAK – RIGGER
GREGORY ANAK MANG – SCAFFOLDER LVL 3
MOHAMMAD AFIQ BIN IKHWAN – SCAFFOLDER LVL 2
RICKY ANAK BUNSIE – SCAFFOLDER LVL 1
SYLVESTER ANAK SIMON – WELDER/FITTER
KEVIN BALAN RICKY – BANKSMAN
JENNERICK ADAM BALA – RIGGER
FAIRUS ANAK DORIS – RIGGER
FREDERICK GUNGGANG ANAK DAWIE – SCAFFOLDER LVL 2
SEMUNI JEFFERY LENYAP – SCAFFOLDER LVL 2
KELLY KULEH YUSAK – WELDER/FITTER
RAYMOND ANAK SEDAI – HABITAT TECHNICIAN
ELDON LIHAN LAWRENCE – HABITAT TECHNICIAN
MATHIUS HOLLY ANAK ELIAM – NDT INSPECTOR
(C) HSE STATISTICS
DESCRIPTION
CUM. PREVIOUS
CURRENT
TOTAL CUM
Lost Time Injury (LTI)
0
0
0
Restricted Work Case (RWC)
0
0
0
Medical Treatment Case (MTC)
0
0
0
First Aid Case (FAC)
0
0
0
Near Miss
0
0
0
Fire / Explosion Cases
0
0
0
(D) PROGRESS PERCENTAGE
M3DR-A MAIN DECK CUTTING WORK
:
M3DR-A CELLAR DECK CUTTING WORK
:
SCAFFOLDING PREPARATION WORK ON M3DR-A MAIN DECK
:
PRIMARY LINES INSTALLATION ON M3DR-A MAIN DECK
:
SCAFFOLDING PREPARATION WORK ON M3DR-A CELLAR DECK
:
SUPPORT LINES INSTALLATION ON M3DR-A CELLAR DECK
:
SCAFFOLDING PREPARATION WORK ON M3DR-A BOAT LANDING
:
SUPPORT LINES INSTALLATION ON M3DR-A BOAT LANDING
:
GANGWAY INSTALLATION
:
SCAFFOLDING PAP INSTALLATION ON BLOOMING WISDOM
:
OVERALL PROGRESS
:
100.00%
100.00%
100.00%
0.00%
100.00%
0.00%
100.00%
0.00%
0.00%
0.00%
50.00%
PROGRESS REPORT
PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001)
9 FEBRUARY 2023 - 19 FEBRUARY 2023
(E) PROGRESS UPDATE
•
•
•
•
Finalise location of gangway on M3DR-A.
Install scaffolding on work areas for upcoming gangway installation.
Mark, cut & crop deck to access support beams as slings tie points.
Finalise and obtain approval for scaffolding PAP design / workplan.
(F) LOOK AHEAD PLAN
•
•
•
•
Remob to M3DR-A. Subject to TOS decision and weather window.
Prepare & install replacement slings on M3DR-A.
Install & secure gangway to M3DR-A.
Install & secure PAP to Blooming Wisdom.
(G) PROGRESS PICTURES
Identify and barricade work zone for
gangway installation. Concerned
work area highlighted in red.
Platform preparation work. Marking,
cutting and cropping of deck plates to
access support beams as tie points
for gangway slings.
Total of 4 access points have been cut
and removed for the new set of
gangway replacement slings.
Red box indicates deck cut out for tie
points on M3DR-A main deck & cellar
deck.
PROGRESS REPORT
PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001)
9 FEBRUARY 2023 - 19 FEBRUARY 2023
Perspective view and draft of the
gangway location on M3DR-A.
PROGRESS REPORT
PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001)
9 FEBRUARY 2023 - 19 FEBRUARY 2023
Preparation of scaffold type PAP
design. Design cleared to proceed as
per approval from OIM & DSV.
Scaffolding PAP structure ordered to
be dismantled prior to towing to
shelter on 19 February 2023.
Structure to be rebuilt as required by
OIM or DSV.