PROGRESS REPORT PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001) 9 FEBRUARY 2023 - 19 FEBRUARY 2023 (A) PROJECT DETAILS PROJECT TITLE : GANGWAY INSTALLATION ON M3DR-A CLIENT : TANJUNG OFFSHORE SERVICES RIG : GHAZI 461 LOCATION : M3DR-A CONTRACT NO : TOSPGPO22-2242 COMPANY : OCEAN VANTAGE ENGINEERING SDN BHD POB : 20 PAX (B) CONTRACTOR DETAILS 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. TING KEE SHENG – WORKPACK ENGINEER JOANNES ANAK USIT – RIGGING SUPERVISOR RAYMOND LAMI ANAK LINGKONG – BANKSMAN ALEN PENGIRAN PANEL – RIGGER MILTONESE SANDA ANAK MAURICE – RIGGER ALEXANDER TINUS – RIGGER KELLY ESAK – RIGGER GREGORY ANAK MANG – SCAFFOLDER LVL 3 MOHAMMAD AFIQ BIN IKHWAN – SCAFFOLDER LVL 2 RICKY ANAK BUNSIE – SCAFFOLDER LVL 1 SYLVESTER ANAK SIMON – WELDER/FITTER KEVIN BALAN RICKY – BANKSMAN JENNERICK ADAM BALA – RIGGER FAIRUS ANAK DORIS – RIGGER FREDERICK GUNGGANG ANAK DAWIE – SCAFFOLDER LVL 2 SEMUNI JEFFERY LENYAP – SCAFFOLDER LVL 2 KELLY KULEH YUSAK – WELDER/FITTER RAYMOND ANAK SEDAI – HABITAT TECHNICIAN ELDON LIHAN LAWRENCE – HABITAT TECHNICIAN MATHIUS HOLLY ANAK ELIAM – NDT INSPECTOR (C) HSE STATISTICS DESCRIPTION CUM. PREVIOUS CURRENT TOTAL CUM Lost Time Injury (LTI) 0 0 0 Restricted Work Case (RWC) 0 0 0 Medical Treatment Case (MTC) 0 0 0 First Aid Case (FAC) 0 0 0 Near Miss 0 0 0 Fire / Explosion Cases 0 0 0 (D) PROGRESS PERCENTAGE M3DR-A MAIN DECK CUTTING WORK : M3DR-A CELLAR DECK CUTTING WORK : SCAFFOLDING PREPARATION WORK ON M3DR-A MAIN DECK : PRIMARY LINES INSTALLATION ON M3DR-A MAIN DECK : SCAFFOLDING PREPARATION WORK ON M3DR-A CELLAR DECK : SUPPORT LINES INSTALLATION ON M3DR-A CELLAR DECK : SCAFFOLDING PREPARATION WORK ON M3DR-A BOAT LANDING : SUPPORT LINES INSTALLATION ON M3DR-A BOAT LANDING : GANGWAY INSTALLATION : SCAFFOLDING PAP INSTALLATION ON BLOOMING WISDOM : OVERALL PROGRESS : 100.00% 100.00% 100.00% 0.00% 100.00% 0.00% 100.00% 0.00% 0.00% 0.00% 50.00% PROGRESS REPORT PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001) 9 FEBRUARY 2023 - 19 FEBRUARY 2023 (E) PROGRESS UPDATE • • • • Finalise location of gangway on M3DR-A. Install scaffolding on work areas for upcoming gangway installation. Mark, cut & crop deck to access support beams as slings tie points. Finalise and obtain approval for scaffolding PAP design / workplan. (F) LOOK AHEAD PLAN • • • • Remob to M3DR-A. Subject to TOS decision and weather window. Prepare & install replacement slings on M3DR-A. Install & secure gangway to M3DR-A. Install & secure PAP to Blooming Wisdom. (G) PROGRESS PICTURES Identify and barricade work zone for gangway installation. Concerned work area highlighted in red. Platform preparation work. Marking, cutting and cropping of deck plates to access support beams as tie points for gangway slings. Total of 4 access points have been cut and removed for the new set of gangway replacement slings. Red box indicates deck cut out for tie points on M3DR-A main deck & cellar deck. PROGRESS REPORT PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001) 9 FEBRUARY 2023 - 19 FEBRUARY 2023 Perspective view and draft of the gangway location on M3DR-A. PROGRESS REPORT PREPARATION WORK FOR GANGWAY INSTALLATION (OVE–PR-001) 9 FEBRUARY 2023 - 19 FEBRUARY 2023 Preparation of scaffold type PAP design. Design cleared to proceed as per approval from OIM & DSV. Scaffolding PAP structure ordered to be dismantled prior to towing to shelter on 19 February 2023. Structure to be rebuilt as required by OIM or DSV.