Quality Control Plan UNDP Libya ACRONYMS AND ABBREVIATIONS CAD Computer-Aided Design CQA Construction Quality Assurance CQCO Construction Quality Control Officer CQCP Construction Quality Control / Quality Assurance Plan CQP Contractor Quality Control Plan SME Site Monitoring Engineer HASP Health and Safety Plan NCR Noncompliance Report O&M Operation and Maintenance QA Quality Assurance QC Quality Control QCM Quality Control Systems Manager QMP Quality Management Plan QMS Quality Management System SOW Scope of Work TABLE OF CONTENTS SECTION 1: INTRODUCTION Page 1 1.1 PROJECT SETTING Page 1 1.2 AGREEMENT DESCRIPTION 1.3 QUALITY PROGRAM OVERVIEW 1.4 QUALITY CONTROL AND QUALITY ASSURANCE 1.4.1 Preparatory Phase Meetings 1.4.2 Initial Inspections 1.4.3 Follow-up Inspections 1.4.4 Plans and Specifications 1.4.5 Shop Drawings 1.4.6 Pre-Construction Conference Page 6 1.4.7 Equipment Proposal Page 7 1.4.8 Claims Page 7 1.4.9 Labor Enforcement Page 7 Page 1 Page 3 Page 4 Page 4 Page 4 Page 4 Page 5 Page 6 1.4.10 Storage of Materials Page 7 1.4.11 Contractor’s Payment Estimates Page 8 1.4.12 Defense Materials System Page 8 1.4.13 Rights-of-Way Page 9 1.4.14 Photographs Page 9 1.4.15 Record Drawings Page 9 1.5 1.6 Page 11 APPENDIX D: QUALITY MANAGEMENT PLAN CQCP ORGANIZATION TYPICAL CONSTRUCTION FORMS Page 10 Pre-Concreting Inspection Form Contractors Quality Control Report Approval Form for Materials and Products Request for Inspection Non-Conformity Report SECTION 1: INTRODUCTION Quality Control is very fundamental to the works and services undertaken by UNDP and shall be practiced by all personnel of the Organization in their daily activities. Quality is enhanced by working systematically, according to formalized procedures, designed to prevent or eliminate difficulties from occurring. It shall be the responsibility of Project Managers to ensure that these procedures are implemented consistently and effectively, and that they are reviewed regularly to reflect the requirements of the Contracts throughout the duration of works. E CO TIM ST It shall be the responsibility of the Site Engineers Quality Control Manager (QCM) to constantly monitor the implementation of the Quality Control Plan (CQP) to establish and put into practice necessary systems and procedures, and ensure adherence to the CQP through regular auditing. SCOPE QUALITY The above diagram represents a balanced triangle for the project. Any change to one of the constraints will affect the other constraints, which will require a re-balancing of all of the constraints. 1.2 QUALITY PROGRAM OVERVIEW UNDP is responsible from Quality Control and Contractor is responsible from Quality Assurance rehabilitation projects. The Construction Quality Control Program (CQCP) details the systems and controls that UNDP has put in place so that the quality of the project will meet the requirements specified in the contract documents, approved drawings (if require), BoQ and specifications. UNDP provides definition and overall management of the quality approach to be followed, Engineers and Contractor. The quality of the Project Implementation will be ensured through an integrated system of quality control performed by UNDP and quality assurance provided by Contractor. UNDP site Engineer is responsible for the day-to-day coordination of quality control measures in the field. This Construction Quality Control Plan (CQCP) is a companion document. It establishes: - project procedures and general responsibilities for the quality control (QCP) program; and protocols to ensure that the rehabilitation Projects will be executed in accordance with the related documents. This CQCP has been developed in accordance with the SOW. UNDP will be responsible for constructing the work in accordance with the plans and specifications.. UNDP’s QC is the systematic implementation of a program of inspections and production controls to attain the required standards of quality and to preclude problems resulting from noncompliance. Pursuant to Technical Specification. The CQCP provide for tests and inspections pursuant to various technical specifications. It will define procedures to ensure that activities affecting quality are properly documented and accomplished in accordance with contract documents; written instructions; and industry standards, codes and procedures. Furthermore, the CQCP will define methods for ensuring that activities affecting quality will be accomplished under controlled conditions. Independently of the contractors, UNDP Engineer will provide QC through daily monitoring and scheduled inspections to verify the effectiveness of the contractor’s QC program and assure that the quality and contract requirements are met by the contractors. The Engineer assures that the contractor’s QC is working effectively and that the resulting construction complies with the quality requirements established by the contract. The objectives of this CQCP are to: Describe a quality program to be implemented so that the project is constructed in accordance with the contract requirements and industry standards; Describe guidelines for inspection and documentation of construction activities; Provide reasonable assurance that the completed work will meet or exceed the requirements of the construction drawings and specifications; and Describe how any unexpected changes or conditions that could affect the construction quality will be detected, documented, and addressed during construction. 1.4 QUALITY CONTROL Quality Control (CQC) is required in all UNDP Rehabilitaion & Civil work contracts. The role of the Construction Quality Control Engineer is to assure that the quality requirements of the contract have been satisfied. CQC requires that the UNDP implement the program and use its provisions daily to control quality of the work. Effective CQC requires a serious and concentrated effort on the part of the supervisory and inspection personnel. Contract requirements provide the tools for the accomplishment of the goals, and are as follows: 1. CQC personnel are described as to education, experience, and capability. 2. Before start of construction, the Engineer shall conduct a Mutual Understanding Meeting with the contractor and discuss the contractor’s quality control system. Construction start will be delayed until after the Mutual Understanding Meeting and submittal/acceptance of at least the interim CQC plan. The CQC plan will be viewed with a critical eye. The Construction Quality Control Officer will assure that the CQC Plan and actual CQC staffing are sufficient to obtain the quality of construction designed in the contract plans and specifications. Quality assurance monitors and confirms quality, but quality control must provide it. 1.4.1 Preparatory Phase Meetings CQC held meetings will be held before each definable feature of work to ensure that the documentation is complete, materials are on hand, and the people who are to perform the work understand what they need to know about the feature of work. Both the actual contract specifications and those referenced in the contract specifications must be in the Contractor’s library and available to the CQC inspectors. If CQC does not have the required specifications, the CQC cannot know or enforce these provisions. QA personnel can be helpful to the CQC in obtaining referenced specifications. 1.4.2 Initial Inspections CQC inspections must be conducted in a timely manner—at the beginning of a definable feature of work. A check of the preliminary work will determine whether or not the Contractor, through his CQC organization and the craftsmen involved, thoroughly understands and is capable of accomplishing the work as specified. 1.4.3 Follow-up Inspections Follow-up inspections, also conducted by the Contractor’s quality control staff, occur daily when work is in progress and are for the purpose of assuring that the controls established in the earlier phases of inspection continue to provide work which conforms to the contract requirements. Most of the comments in both the CQC and QA daily reports result from these inspections. In all projects there is work that is ‘cut and cover’—that is, work that cannot be inspected “after the fact”. This includes concrete, where the size, number and location of reinforcing steel cannot be readily determined after the concrete is placed. Most of the underground utilities cannot be inspected after covering. Work of this nature must be closely controlled and monitored. A disadvantage with the system arises from the fact that CQC personnel, as employees of the contractor, are unlikely to readily take actions which will result in delay and expense to the contractor for the sake of quality. For example, if concrete is to be placed with a maximum slump of 6 cm, it is unlikely that a load with 10cm or 12 cm slump will be rejected. If roofing bituminous material is overheated, it is unlikely that it will be rejected. The deficiencies occasioned by these conditions may become latent defects revealed long after any possible contractor liability can be enforced. The Engineer responsible for quality assurance has a vital role in assuring that these and similar situations do not occur. Responsibility for compliance should not be left wholly to the contractor. A Construction Quality Control Officer must closely monitor the CQC program to assure that the 3-phase control system is being correctly performed and that the contractor is effectively controlling all operations. In the event that CQC personnel are not capable and/or are not inspecting properly, the Engineer should be notified immediately, with a view to correcting performance by using one or more of the enforcement tools provided for in the contract. Records and reports will document all facts. 1.4.4 Plans and Specifications 1. UNDP will prepare the plans and specifications during the bidding period and will: a) Watch for omissions; b) Watch for discrepancies between plans and specifications; c) Check plans and specifications against requirements of which problems occurred on similar jobs; d) Compare elevations, grades and details shown on plans as existing, with those at the actual site; and e) Report all errors, omissions, discrepancies, and deficiencies to the Engineer. 2. Always keep a posted and marked up set of plans and specifications convenient for ready reference. 3. Make sure that the contractor has this same information. 4. Anticipate the Contractor’s operations by reviewing the plans and specifications for each operation before it begins. a) Discuss contract requirements in each Preparatory Phase Meeting with the contractor before each operation begins. b) Highlight and/or make notes of those provisions which need special attention, such as: 1. 2. 3. 4. Unusual requirements. Those which other contractors have overlooked. Repetitive deficiencies. Use the checklists in these guides to help find significant items in the plans and specifications. 1.4.5 Shop Drawings (if required) UNDP checklist for shop drawings: 1. Prepare submittal register, plans, and specifications. Check submittal register for inclusion of all shop drawings required including layouts of equipment, equipment rooms, etc. 2. The contractor is required to enter data onto the submittal register and submit it to the Construction Quality Control Officer. Compare this submittal with the check list. 3. The contractor is required to periodically update the submittal register. 4. Make continual checks of the submittal register to avoid untimely and omitted submittals so as to avoid delay of construction. 5. Compare the shop drawings to the contract requirements and report apparent differences to the Engineer. (Approved shop drawings do not constitute a waiver of a contract requirement.) 6. Make sure each detail on the shop drawing is clearly understood. 7. The contractor must make note on his submittal of items which deviate from contract requirements. 8. Check material being installed against the approved shop drawing. (If the contractor installs unapproved material, inform him in writing that the material, if not subsequently approved, will be removed at his expense.) 1.4.6 Pre-Construction Conference Both the Construction Quality Control Engineer and the Quality Control System Engineer should attend this conference. Minutes of the conference should be available to each of the quality assurance/quality control representatives assigned. The subject of the proposed Quality Control Plan should be well documented. Equipment Proposal UNDP checklist for equipment proposal: 1. Does equipment proposed by the contractor have CQCO approval (more applicable to civil works projects)? 2. Certain equipment requires a safety test or check before initial operation at the site. 3. Some equipment requires a permit or license before use. 1.4.8 Claims 1. UNDP checklist for Claims: 2. Always be alert to possible claims or matters of possible dispute. 3. When it is discovered that a claim or dispute is in the making, the supervisor should be notified immediately. All facts are to be recorded in the quality assurance (QC) daily reports. 4. Make sure that adequate and accurate records of facts, materials, labor and equipment associated with the claim or dispute are on file. 5. Situation photographs may be appropriate to supplement the record. 6. Differing site conditions may be cause for claim — contractor must notify CO in writing before disturbing conditions. 1.4.9 Labor Enforcement UNDP checklist for labor enforcement: 1. Keep informed of the labor provisions of the contracts on which you are working. 2. Always avoid taking part in any labor disputes. 3. Promptly inform your supervisor of any labor problems and disputes. Assist office personnel in assuring that: 4. 5. Each laborer and each machine are classified in accordance with the particular work function. Make spot checks with Contractor’s employees to verify that payments correspond to the work classification being performed. 1.4.10 Storage of Materials UNDP checklist for storage of materials: 1. Check to see that adequate space is available for the contractor’s operations and storage areas. 2. Check that approval has been obtained for temporary sheds, buildings, etc., which the contractor proposes to install. 3. See that material and equipment are properly stored and protected. 4. Make sure that safety requirements, especially in the storage of flammable or explosive materials, are adhered to. 5. Make sure that temporary structures are secured against wind damage. 6. Assure that the necessary heating and ventilating systems are provided. 1.4.11 Contractor’s Payment Estimates UNDP checklist for contractor’s payment estimates: 1. Check specifications for method of measurement and payment for each item of work to be accomplished. 2. Be familiar with schedules of prices and methods of measurement and payment. 3. Assist them in preparation of partial pay estimates. a) Make timely measurements of work completed and work accomplished each pay period. It is usually a good idea to seek contractor*s concurrence. b) Keep orderly, neat and accurate records of measurements. 4. Check material on hand for which payment is being made for: a) b) c) d) Fair market value of materials; Conformance with contract requirements (see submittal); Proper storage and protection; and Reduction in quantity by amount of material placed in the work. 5. Be alert to all increases or decreases in quantity of work shown on the unit price schedules. a) Make as accurate an estimate as possible of variations in quantities. b) Report these variations in quantities promptly to the supervisor. 1.4.12 Defense Materials System On applicable contracts, check to see that the contractor is abiding by the rules of the Defense Materials System, using the following checklist: 1. Ensure that the contractor is correctly rating all orders, which are then certified and dated. 2. Confirm that the promised delivery date is noted on each order. 3. Substantiate that each order gives complete information which will enable precise identification and processing channel. Rights-of-Way UNDP will check that all rights-of-way are obtained prior to entrance on property. 1. Require written evidence if contractor-obtained. 2. Check contract provisions if Government-obtained. 3. Know the limits of rights-of-way and locations of benchmarks that may be used to determine location and elevations. 1.4.13 Photographs UNDP checklist for photographs. 1. If allowable, check for photographs of: a) Views of major construction projected during various stages of progress. b) Materials or construction related to changed conditions, claims, or potential claims. c) Work in place for which removal has been ordered because of noncompliance with plans and specifications. d) Construction in which unusual difficulties have been overcome or where the subject is of technical interest. e) New methods of construction. f) Property or material damages. g) Emergency conditions and safety violations. h) Accident scenes. i) Defective work. 2. Check that each picture taken is completely described, identified, and dated. 1.4.14 Record Drawings UNDP checklist for record drawings: 1. The contractor’s record drawings should be reviewed monthly by the Engineer’s staff to ensure that they are correct. 2. Ensure that as soon as a change or addition is made in construction it is noted on the record drawing. 3. See that the following items are considered in the changes for Record Drawings: a) b) c) d) e) Size, type, and location of existing and new utility lines. Layout and schematic drawings of electrical circuits and piping. Dimensions and details transferred from shop drawings. Verification of alignment, cross section, and layout of earthwork. Actual locations of anchors, construction and control joints. etc. in concrete, where they are different from those shown on contract drawings. f) Changes in location of equipment and architectural features. g) Cross out such words, phrases and details for optional or equal requirements and list or detail specifically the items provided. APPENDIX D: TYPICAL CONSTRUCTION FORMS The format, layout, content and method used to fill out the forms will be reviewed periodically during the course of construction and modified as required to ensure that the necessary information required for management of the construction contracts and controlling the progress and quality of the work is being obtained. Concrete Compressive Strength Test Report (CYLINDIRICAL-CUBE) DATE (ASTM C 39) (BS 1881) (DIN 51220) NUMBER : CRUSHING DATE OF SAMPLES CLASS OF CONCRETE : MOULD: STRENGTH - CURE PLACE & ITE SAMP TYPE OF M LE STRUCTURE NU. NU. 1 2 3 4 : MM. CUBE- CYLINDER AGE 3 DAYS AGE 7 DAYS AGE 28 DAYS IF REQUIRED WEIGHT STRENGT WEIGHT STRENGT WEIGHT STRENG H H TH (g) (g) (g) KN kg / cm2 KN kg / cm2 KN kg / cm2 5 6 7 8 9 10 SPECIFICATION : REMARKS: PRE-CONCRETING INSPECTION FORM Explanation : Related Drawings : Formwork Check Reinforcement Check Surveying Check Mechanical Check Electrical Check Supports Ties Waterstops Joint Prepare Cleanliness Form oil Embedments Blockouts Contractor Name Date Size Spacing Laps Concrete Cover Cleanliness Quantity Lining Level Position Embedments Blockouts Notes Embedments Blockouts Notes Contractor Name Date Contractor Name Date Contractor Name Date Contractor Name Date Sign Responsible Engineer Sign Responsible Engineer Sign Responsible Engineer Sign Responsible Engineer Sign Sketch Responsible Engineer Name Date Name Date Name Date Sign Sign Sign Sign Permission Given to Pour Employer’s Representative Name : Date : Sign : Date of Concreting Type of Concrete Name Date Slump Name Date Sign Site Manager Notes : Controls after formwork striking Curing Line Level Position Repairs Employer’s Representative Name : Date : Quality Control Manager Name : Date : Sign : Sign : EARTHWORKS CHECK SHEET STRUCTURE : PLACE : BACKFILL : ITEM SETTING OUT TYPE OF MATERIAL PRE-FILL INSPECTION METHOD OF COMPACTION RESPONSIBLE COMMENT THICKNESS OF LAYERS ACCEPTANCE OF FINISHED LEVEL TEST ON COMPACTED FILL MATERIAL REFERENCE TEST NU. ITEM MOISTURE CONTENT DRY DENSITY PERCENT COMPACTION COMMENTS QUALITY CONTROL REPORT QUALITY CONTROL REPORT (QCR) DAILY LOG CONSTRUCTION REPORT NUMBER 000 of 2 DATE PROJECT CONTRACT NUMBER CONTRACTOR WEATHER QC NARRATIVES Activities in Progress: Did anything develope that may lead to a Change Order/Claim ? Were there any Delays in Work Progress today ? General Comments / QC Issues Verbal Instructions given by Government: Safety: (Inspection made, Deficiencies noted): Safety: Corrective Action taken: Information PREP/INITIAL DATES ACTIVITY START/FINISH QC REQUIREMENTS (Preparatory and initial dates held and advance notice) Page 1 QC PUNCH LIST (Describe QC Punch List items issued, Report QC and QA Punch List items corrected) CONTRACTORS ON SITE (Report first and/or last day contractors were on site) QUALITY CONTROL REPORT (QCR) DAILY LOG CONSTRUCTION REPORT NUMBER 000 of 2 DATE PROJECT CONTRACT NUMBER LABOUR HOURS EQUIPMENT HOURS ACCIDENT REPORTING (Describe accident) Page 2 CONTRACTOR CERTIFICATION QC REPRESENTATIVE’S SIGNATURE On behalf of the contractor, I certify that this report is complete and correct an all equipment and material used and work performed during this Reporting period are in compliance with the contract plans and specifications, to the best of my knowledge, except as noted above. DATE SUPERINTENDENT’S INITIALS DATE APPROVAL FORM FOR MATERIALS AND PRODUCTS APPROVAL FORM FOR MATERIALS/PRODUCTS EMPLOYER: ENGINEER: CONTRACTOR: KABUL SCHOOLS PROJECT Submittal No: Date Submitted: Revision No: Description of Material/Product [including size, class, grade, type, strength, accesories, etc.] : Civil Mechanical Electrical Location of Application [where the material will be used] : Quantity: Spec. Clause [attach relevant parts] : Reference Drawing [attach] : Applicable Standard: Manufacturer : Supplier : Adress : Adress : Phone : Fax : Phone : Fax : Country of Origin : Confirm that the following documents are attached [to be filled by the Contractor] : Manufacturers' Data Test Reports Certificates Samples Manufacturers' Confirmation of Compliance with Specifications/Standards Contractor [name, surname, sign] : ………………………………….. [name, surname, sign] : Recommended Recommended Recommended As Noted Recommended As Noted Not recommended Date/Time :....... / ...... /….. Not recommended QA/QC Engineer RE/Civil / ( ) Engineer Date/Time :...... / ...... / …… Date/Time :...... / ...... /….. Remarks [to be filled by the Engineer ] : IMPORTANT: All parts of this form must be completed. All related copies of the relevant part(s) of the specification(s), drawing(s), manufacturers' technical data, certification(s) and test information must be attached to this form. Where part(s) of this form are not applicable, write/mark "NOT APPLICABLE". REQUEST FOR INSPECTION NONCONFORMITY REPORT NONCONFORMITY REPORT DATE: PROJECT RELATED SECTION SUBJECT SUMMARY OF NONCONFORMITY PREPARED BY DEPARTMENT SUMMARY OF DISPOSITION PLAN APPROVED BY DEPARTMENT DATE USE - AS – IT - IS RESULT REPAIR REJECT ACCEPTED REJECTED CORRECTIVE ACTION COMPLETED Department Quality Control Manager Name Date Signature NCR Record No NCR Date NON-CONFORMITIES LOG Brief Summary of Nonconformance Disposition Close-Out date Date