Uploaded by Mahmood Ali

GUIDELINES FOR GAINT CHART

advertisement
GUIDELINES FOR GAINT CHART
In critical method scheduling, there are certain conditions to be fulfilled for the integrity of the
project schedule.
a). Limit duration of the activities.
Activity should not have large durations. Project management institute (PMI) says that activity
duration should not be larger than two control periods in any normal activity. For example, if a
project has two years durations and the schedule is reviewed under control on a monthly basis,
then maximum allowed duration of an activity shall be two calendar months.
b). Limit the use of unnecessary constraints.
We should not use a lot of date constraint. Date constraints are establishing constraint to activity
such as finish no later than etc.
c). Prohibit activities with open end/dangling.
1. Prohibit activity with open ends rule: Each activity should have at least one predecessor,
except the first one and each activity should have at least one successor, except the last
one.
2. Prohibit activities with dangling rule: Each activities start shall be influenced by other
activities and each finish shall influence other activities. Otherwise, the activity would be
called dangling.
Let us see this example:
A
B
FS
C
2SS+2 days
DDAYS
Activity B has both predecessor and successor it fulfills first rule as we seen in prohibit activities
in with open ends. At the same time if we see activity B and the duration of activity b extend it
will not affect or influence its successor activity C. Hence activity B is dangling. To avoid such
dangling activity simple rule shall be followed.
Rule: Activities shall have at least one finish to start or start to start predecessor and at least one
finish to start or finish to finish successor.
d). Prescribe the use of certain logic relationships lag and lead: PMI says that we should use
finish to start relationship for most of the activities. Start to finish relationship shall be used as
little as possible.
Do not use large lag in activity. PMI says that we should be careful with lags and do not use them
instead of activities or completed relationship.
Let’s have an example: We have an activity such as “Design xyz” and another activity like “Build
xyz” and a relationship of FS+20 days. The 20 days are the need for the design approval.
Design xyz
Build xyz
Here we have provided large lag. What is the alternative way to avoid this lag.
Design xyz
Design approval
Build xyz
The lag provided for design approval, build here an activity so, the lag is avoided. In this way large
lag can be controlled.
Similarly, we should not use large lead in the schedule. PMI says that we should be careful with
large leads and use activities instead of them where possible. The reason is mainly leads are
misused in the schedule (Whenever project is delayed planner has tendency to gradually increase
the overlaps or leads to maintain the project completion date without any delay). It does not
mean that we should not use any overlap, but it should be used in a very controlled manner.
Let’s see the example:
Build wall
Paint wall
Here there is an overlap period of 5 days. This is a lead shown in the above example. Let’s look
at how to control this lead. To avoid overlap or lead, the following alternative may be used.
Build wall part 1
Build wall part 2
Paint wall part 1
Paint wall part 2
e). Include all the tasks necessary to complete the scope of work: In addition to regular activities,
adequate time for certain owner activities, including submittal review and procurement of owner
furnished materials or equipment and shall include following task, if applicable.
•
•
•
•
•
Time for permitting or third party
Concrete curing time.
Inspection time and approval.
Layout and its approval.
Holiday.
f). Avoid splitting the activities: It is not advisable to split activities because split activities are
hard to manage, and we can implement an effective logic for them. Whenever we want to split
an activity, we should break it down into two separate activities instead
Split activity
Split activity
Splitting usually happens whenever we reschedule the plan.
Float in the schedule
Float is also called slack, there are two types of floats, free float, and total float.
Free Float: Free float is the duration which an activity can be delayed in start or the finish date
before delaying the successor activity.
Total Float: Total float is the duration which an activity can be delayed in start or the finish date
before delaying the project completion date.
Note: Critical activity always has a free float and total float equal to zero.
Near critical activity: Near critical activity are those whose float (slack) is equal to one shift or
less. These activities have the potential to become critical.
Project schedule compression techniques
There are two types of project schedule compression techniques
1. Fast tracking and
2. Crashing
Fast Tracking: Doing critical activities in parallel thereby reducing the project duration is called
fast tracking scheduling.
Crashing technique: By increasing the resources allocated to critical activities we can reduce
the activity duration thereby reducing the project duration is called crashing the schedule.
Download