Quality Plan
Maintenance Procedures
SWMS

Download Method Statements

Home
Privacy
Support
Cart
Editable Documents Full Catalog

SEARCH
Search …
Join for Latest Articles
Enter your email address & Click Join:
JOIN
Recent Publications
ACS Access Control Electronic Security System
Installation & Testing Method Statement
Method Statement for Piling Work using the Diesel
Hammer
Steel Bar Reinforcement Rebar Fabrication and
Installation Method Statement
Sheet Pile Installation Method Statement
SWMS Safe Work Method Statement for Electrical
Conduit Installation Prior to Pouring Concrete
Popular Categories
Civil Method Statements (81)
 Electrical Method Statements (45)
 Fire Fighting Systems (17)
 HVAC Method Statements (43)
 Occupational Health and Safety (23)
 Oil & Gas Systems (12)
 Plumbing Method Statements (36)
 Technical Guides (31)
 Testing & Commissioning (60)

Popular Tags
AV System block work method statement block work
procedure CCTV ceramic floor tiles Clean Agent System
Commissioning COMMISSIONING PROCEDURE Dampers
Demolition Works Drainage piping Electric Water
Heaters excavation safe work Fire Dampers Fire Fighting
System Fire Suppression System HVAC Ductwork HVAC
Method Statement Installation Installation Method
Statement installation Procedure Lightning Protection
System Method Of Statement method statement Method
Statement For Testing & Commissioning
Precommissioning Precommissioning & Commissioning
Safe Method of Statement Safe Method Statement safe
work for excavation safe work method of statement Safe
Work Method Statement Sanitary Wares SMDB's
Specifications swimming pool civil works SWMS Testing
& Commissioning Testing & Commissioning Method
Statement Testing and Commissioning Tower Crane
Foundation UPS System UPS Testing Procedure Variable
Frequency Drives water supply piping
You May Like!
Contract Master
Schedule
Preparation
Project

Management
Procedure
$3.49
Meta
Log in
 Entries feed
 Comments feed
 WordPress.org
Job Safety Analysis JSA for Lifting Activity – Loading unloading using
Crane and Boom Truck
Below is a precise Job Safety Analysis JSA for Lifting Activity that includes the loading and unloading of materials using
Crane and Boom Truck.

JOB STEPS
Preparation and
compliance to work
permit requirements
Preparation of
working area
Arrangement of
rigging gears material
Set-up for Loading
Unloading (Crane and
Boom Truck)
Loading and
Unloading by using
Crane & Boom Truck
Emergency Response
Heat Stress
Clean up / House
keeping
POTENTIAL HAZARD
(What can cause harm?)
CONTROL MEASURE
(What can be done to prevent it from going
wrong?)
Missed information between
supervisors and workers regarding
safety factors and work instructions
1. Secure permit and all related documents prior
to work.
2. Conduct tool box meeting prior to activity
3. All workers need to be trained and must have
training passport.
Slip, Trip
Public traffic
Pedestrians
1. Remove all tripping hazards from the work
area.
2. Watch where you are walking.
3. Proper barricade of the working radius and
install Lifting Operation signage.
4. Assign personnel to control/guide any vehicle.
5. Flagman/spotter to remain vigilant of errant
pedestrians and personnel.
6. Where pedestrian crossings are within the
working area either shut the pedestrian crossing
or make the crossing safe for pedestrian use.
Harm to personnel due to usage of
Defective or
Home Made Rigging gears & Tools
Unsafe condition and improper
position of task
Improper housekeeping and
arrangement of materials causing
Slips, Trips, falls
All Rigging gears or tools shall be kept in good
condition. They must be kept clean & stored
properly. Defective rigging tools shall be
removed from site or disposed.
Wear appropriate PPE at all times.
Manual handling shall be covered in daily TBT and
be implemented on site
Assign a two man crew to lift heavy materials.
Observe proper work ergonomics.
Access and egress must be clear, no obstruction
All materials must have a safe distance of 1.2
meters away from the excavation.
Punch point
Un-authorized entry
Slip, Trip and Fall
Keep hands out of pinch point while Set- up
rigging gears and paid.
Provide proper Barricade and Lifting Signage’s to
stop unauthorized entry.
Remove all unused materials and tools from
working area, make sure lifting radius should be
clear and clean.
Un-authorized entry
Slip, Trip and Fall
Personnel Struck by Swinging load
Personnel Struck by Falling load
Hitting people or existing facility.
Punch point
Crane losing balance.
Fire and electrocution
Mechanical failure
Weather Condition
Poor maintenance of equipment.
Ground stability.
Exceeding safe working load.
Unauthorized entry in working area.
Work without work permit.
Crossing under the suspended load.
Provide proper Barricade and Lifting Signage’s to
stop unauthorized entry.
Remove all unused/ unwanted materials and tools
from site.
Make sure that the area is level and compacted.
Make sure that the outriggers are fully extended.
Make sure that supervisor conduct toolbox
meeting before the activity. Make sure that all the
workers know the hazards involve in the activity.
Make sure that the slings, belts and shackles are
inspected and color coded.
Make sure that the Rigger and Operator is
competent person and, has a valid Certification.
Valid License required for Operator.
Daily crane Inspection checklist must be
accomplished by the Crane Operator.
The crane must have valid Approved 3rd Party
inspection certification sticker on it.
Never access the safe working load in any
condition.
Make sure that the Crane/boom truck is parked
away from the overhead power lines.
Never allow anybody to cross under the
suspended load.
Minimum 2 tag lines shall be used to control
suspended load
Practice ergonomics I manual lifting safety.
Check rigging before lifting.
Make sure that area is barricaded and sign boards
are placed.
Serious injury, illness
Equipment accident/fire
Fatality
Lost work day
In case of emergency all work shall be stopped
immediately and Emergency response plan shall
be activated.
Emergency telephone numbers must be posted at
site.
Wind speed and direction shall be monitored
through wind sock with wind meter.
Mobile phone available with Supervisors & Safety
personnel at Site
All the workers to be trained on ERP and how to
evacuate.
Work during hot weather, (fainting,
collapse, cramps, fatality, heat
stroke, heat exhaustion, and other
heat related illnesses
Training about heat stress management,
acclimatization for workers,
provide cold drinking water at site at all times;
availability of approved rehydration solution when
needed,
sufficient rest break interval.
Sharp objects
Wear protective gloves
Be attentive and alert.
Dispose off material in appropriate manner.
Close out work permit return to office daily.
