Uploaded by Marbe Canumay

1. TGC-MHD-FIN-WIR-00001

advertisement
WORK INSPECTION REQUEST (WIR)
MIDFIELD TERMINAL BUILDING - ABU DHABI INTERNATIONAL AIRPORT PROJECT
WIR SECTION A - DETAILS OF SCHEDULED INSPECTION BY CONTRACTOR'S CONSTRUCTION
WIR NUMBER:
ITERATION:
TGC-MHD-FIN-WIR-00001
REVISION:
R00
TO:
AECOM
ITP NUMBER:
WIR REFERENCE
ITP ACTIVITY:
SECONDARY ITP REFERENCE:
SECONDARY ITP ACTIVITY:
TERTIARY ITP REFERENCE:
TERTIARY ITP ACTIVITY:
SPECIFICATION REFERENCE:
FORMS NUMBER:
INSPECTION TYPE:
PREREQUISITE WIR:
DISCIPLINE:
SYSTEM:
SUB SYSTEM:
DRAWING REFERENCE:
LOCATION:
01-PIER 1
FLOOR REFERENCE:
L10 , L20
SECTOR:
1.11D, 5.12D, 5.15A
PROPOSED DATE BY ORIGINATOR:
29/03/2022 00:00
LEVEL FROM:
LEVEL TO:
X AXIS:
Y AXIS:
L10,L20
ROOM NUMBER:
C-L20-527-HOLDROOM-5.15A, C-L10-41-ADAC AIRSIDE OFFICE, C-L10-55-INBOUND BAGGAGE SCREEN OFFICE
BIM TAG:
MTB_BuCP_10_ARC-FIN_FFR-L10-0041, MTB_BuCP_10_ARC-FIN_FFR-L10-0055, MTB_BuCP_10_ARC-FIN_FFR-L100055, MTB_BuCP_20_ARC-FIN_FSM-L20-0527-5.15A, MTB_BuCP_20_ARC-FIN_FSM-L20-0527-5.15A
INSPECTION DESCRIPTION:
Mockup Inspection:
1- Cleaning Dusty Carpet - ( Using Special Vacuum)/ Holdroom L20- 527.
2- Cleaning Watermark - ( Using the washing machine) / Room L10-55.
3- Cleaning Oilspots- ( Using the steam & Washing machine)/ Room L10-41.
EQUIPMENT REFERENCE:
SUBCONTRACTOR SITE ENGINEER:
SUBCONTRACTOR:
SUBCONTRACTOR QC INSPECTOR:
SUBCONTRACTOR QC COMMENTS
SECTION FOR ORIGINATORS REFERENCE ONLY:
WIR ORIGINATOR:
INTERNAL REFERENCE:
Mohammad Al Jboor
CONTRACTOR CONSTRUCTION REVIEW
CONTRACTOR CONSTRUCTION ENGINEER:
CONTRACTOR CONSTRUCTION ENGINEER COMMENTS:
INTERNAL REJECTION CATEGORY
WIR SECTION C - ENGINEERS COMMENTS
DISCIPLINE:
✕
CIVIL
✕
ARCH.
✕
STRUCTURAL STEEL
✕
MEP ELECT.
✕
MEP MECH.
✕
MEP SPEC.SYST.
CMA INSPECTOR ASSIGNED:
Joel Dalit
CMA INSPECTOR COMMENTS:
1. Contractor to ensure that the level of cleaning for the future cleaning/inspections is as per the agreed during site walk and
ADAC approval.
2. All carpet cleaning requirement for the entire MTB project that can attained as in mock up approval will not be considered as
dilapidation as agreed.
3. ADAC approval attached.
4. All comments regarding Carpet cleaning to be removed from the Dilapidation report.
5. All areas required Washing & steam cleaning to be highlighted (With Photos) separately with the required area in MTB as
agreed
PRELIMINARY REVIEW BY CMA INSPECTOR:
2-Exceptions as Noted - Revise and Resubmit for Record
CMA ENGINEER ASSIGNED:
Joel Dalit
ENGINEERS COMMENTS
PRELIMINARY REVIEW BY CMA ENGINEER:
2-Exceptions as Noted - Revise and Resubmit for Record
LEAD ENGINEER:
Joel Dalit
LEAD ENGINEER COMMENTS:
LEAD ENGINEER FINAL REVIEW:
LEAD ENGINEER APPROVED DATE:
COMMENT CATEGORY:
2-Exceptions as Noted - Revise and Resubmit for Record
Attached Files
Filename
Upload No.
Uploaded By
1
Mohammad Al Jboor
1
Mohammad Al Jboor
1
Mohammad Al Jboor
1
Mohammad Al Jboor
1
Mohammad Al Jboor
1
Mohammad Al Jboor
1
Mohammad Al Jboor
0041.jpeg
055.jpeg
00411.jpeg
0527.jpeg
527_38204.jpeg
oil spot 41.jpeg
oil spot steam 41.jpeg
1
Mohammad Al Jboor
1
Joel Dalit
watermark55.jpeg
ADAC Approval for Carpet Cleaning Mock-up.pdf
Download