Risk Based Inspection Question Bank {A}
1) The Primary Work Products Of The RBI Assessment And Management Approach
And Implementation Of RBI Provides
A. Overall Reduction of Risk and Acceptance of Current Risk.
B. Overall Increase Of Risk And Acceptance Of Risk
C. Overall Reduction Of Risk And Negligence Of Current Risk
D. Over All Increase Of Risk And Negligence Of Current Risk
2) RBI Is Based On
A. Sound, Proven Risk Assessment and Management Principles.
B. Risk Mitigation Principles.
C. HAZOP Principles.
D. PHA Principles.
3) Utilization of RBI Provides A Vehicle for ………………….
A. Continuously Improving The Inspection Of Facilities And Systematically
Reducing The Risk Associated With Pressure Boundary Failures.
4) RBI As An Integrated Management Tool That Complements…………….
A.
PHA And RCM
5) ………….. Produces Inspection And Maintenance Plans For Equipment That Should
Be Implemented To Provide……………And …………….
A.
RBI, Reliable And Safe Operation
6) RP 580 Significantly Targeted At The Application Of RBI In The ……………..And
………….Industry
A.
Hydrocarbon And Chemical Process
7) RP 580 Is Intended To Promote Consistency And Quality In Identification,
Assessment And Management Of Risks Pertaining To………………, Which Could
Lead To……………..
A. Material Deterioration, Loss Of Containment
8) The Risk Assessment Programme Which Focuses On Process Unit Design And
Operating Practices And Their Adequacy Given The Unit’s Current Or Anticipated
Operating Conditions
A.
B.
C.
D.
RBI
PHA
HAZOP
RCM
Risk Based Inspection Question Bank {A}
9) The Program That Are Focused On Understanding Failure Modes, Addressing The
Modes And Therefore Improving The Reliability Of Equipment And Process
Facilities.
A.
B.
C.
D.
RBI
PHA
RCM
HAZOP
10) The Programme That Focused On Maintaining the Mechanical Integrity of Pressure
Equipment Items and Minimizing the Risk of Loss of Containment Due To
Deterioration.
A.
B.
C.
D.
RBI
PHA
RCM
HAZOP
11) ………….. Is Not A Substitute For A Process Hazards Analysis (PHA) Or HAZOP
A.
RBI
B.
PHA
C.
RCM
D.
HAZOP
12) The Following Types Of Pressurized Equipment And Associated Components
Covered By RBI
A.
Rotating Equipment
B.
Turbines
C.
Pressurized Pumps
13) The Primary Audience For RP 580 Is
A.
B.
C.
D.
Inspection And Materials Engineering Personnel
Maintenance Personnel
Only Inspection Personnel
Only Materials Engineering Personnel
14) RBI Requires The Commitment And Cooperation Of The
A.
B.
C.
D.
Total Organization
Inspection
Maintenance
Materials Engineering
Risk Based Inspection Question Bank {A}
15) Out Come Of An Event
A.
B.
C.
Consequence
Risk
Event
16) Consequence Are Always…………. For Safety Aspects
A.
B.
C.
Negative
Positive
Neutral
17) The Reduction in the Ability of a Component to Provide Its Intended Purpose of
Containment of Fluids.
A.
B.
C.
D.
Deterioration
Damage
Degradation
Thinning
18) Occurrence of a Particular Set of Circumstances. Is Called An
A.
B.
C.
Event
Consequence
Risk
19) The Event May Be
A.
B.
C.
D.
Singular Or Multiple
Certain Or Uncertain
Loss Or Gain
Negative Or Positive
20) An Analytical Tool That Organizes And Characterizes Potential Accidents In A
Logical And Graphical Manner
A.
B.
C.
D.
Event Tree
Event
Outcome
Consequence
Risk Based Inspection Question Bank {A}
21) Termination Of The Ability Of A System, Structure, Or Component To Perform Its
Required Function Of Containment Of Fluid (Le Loss Of Containment).
A.
B.
C.
Failure
Risk
Outcome
22) Small Hole, Crack Or Rupture Are Examples Of
A. Failure Modes
B. Failure
C. Loss
Answer Question Bank {A}
1. A
2. A
3. A
4. A
5. A
6. A
7. A
8. A
9. B
10. C
11. A
12. A
13. A
14. A
15. A
16. A
17. A
18. A
19. B
20. A
21. A
22. A
Download