Technical Data Sheet
(External pipe connections, Thermal expansion & Foundation loads)
Project
:
Customer
:
Turbine
:
Sitson A/c Shri Vighnahar SSK Ltd
Sitson A/c Shri Vighnahar SSK Ltd
SST 200, G22
-
28.07.2022
First Issue
SK
ADP
ADP
Rev.
Date
Description
Prepared
Checked
Approved
We reserve the rights in this document and in the information contained therein. Reproduction, use, communication or
disclosure to third parties without express authority is strictly forbidden. © SIEMENS LTD.
Format No: IP-Q-F 3029/C
Rev/Date: 29.12.2014
Power & Gas – Steam turbine
Restricted
Page:
Technical data sheet
Document No.
0-20400-41801-90
2
1. Turbine connection points
No.
Connection
Size
Rating
Joint
Norm
1
Live Steam
6 inch
900 lbs
WNRF
ANSI
2
Exhaust
DN350
150 lbs
WNRF
Siemens
Also refer steam turbine general arrangement drawing 0-04100-E41801A-01_A_002
for orientation of connections.
2. Co-ordinate axis for turbine
Format No: IP-Q-F 3029/C
Rev. Date: 29.12.2014
Power & Gas – Steam Turbine
Restricted
Rev.
-
Document No.
Page:
Technical data sheet
Rev.
0-20400-41801-90
3
3. Thermal movement of connection points
Normal operation
Connections
Movements
ΔX mm
ΔY mm
ΔZ mm
Live Steam
-2.70
7.40
4.10
Exhaust
-1.20
4.10
0.00
No load operation (Full speed-No load)
Connections
Movements
ΔX mm
ΔY mm
ΔZ mm
Live Steam
-2.90
7.40
4.10
Exhaust
-1.30
4.50
0.00
Note:
Thermal expansion calculated with respect to fixed point of turbine as indicated in the
turbine GA with ambient temperature considered as 10°C
4. Maximum allowed external forces and moments on turbine
connections
a. The piping must be connected without pre-stress at ambient temperature by
means of fixed points, supports, springs & hangers etc adjusted in a ways
that the flanges or the weld ends are located in the specified distance and
parallelism.
b. No additional forces are allowed when
connecting the piping to the turbine.
c. Allowed F&M for each connection to be within
(0,F) to (M,0)
Format No: IP-Q-F 3029/C
Rev. Date: 29.12.2014
Power & Gas – Steam Turbine
Restricted
-
Page:
Technical data sheet
Connection
Fx
(N)
+/-
Document No.
Rev.
0-20400-41801-90
4
Allowed forces & moments
Fy
Fz
Mx
My
(N)
(N)
(Nm)
(Nm)
+/+/+/+/-
Mz
(Nm)
+/-
Live Steam
3600
1900
3600
1300
2600
1300
Exhaust
7200
3800
7200
2600
5200
2600
d. The stated forces and moments only refer to the leak proof ness of a flanged
connection with similar nominal bore and pressure stage.
e. For the turbine stability check, the actual forces and moments of the
connecting pipes have to be stated to SIEMENS Ltd.
5. Heat-loss from turbine approximately 5 kW
Format No: IP-Q-F 3029/C
Rev. Date: 29.12.2014
Power & Gas – Steam Turbine
Restricted
-