See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/257305017 Effective Bore Pile Design and Installation Conference Paper · September 2012 CITATIONS READS 0 1,849 1 author: Ademola Bolarinwa Federal University Oye-Ekiti 5 PUBLICATIONS 0 CITATIONS SEE PROFILE Some of the authors of this publication are also working on these related projects: Research Paper View project All content following this page was uploaded by Ademola Bolarinwa on 17 July 2017. The user has requested enhancement of the downloaded file. THE USE OF PILE LOAD TEST TO DETERMINE THE RESIDUAL SETTLEMENT OF A PILE by BOLARINWA ADEMOLA GEOTECHNICAL ENGINEER, PORTSMAN FOUNDATIONS AND CIVIL WORKS, 12B, LUGARD AVENUE, IKOYI, LAGOS, NIGERIA. Abstract This presentation reviews the accepted practice regarding the design, analysis and procedure of pile load testing. A step-by-step guide on pile load test is enumerated and a case study of a pile load test done in Lagos area of Nigeria is discussed. A comparison is made on the designed and load test obtained settlement results. Also, included are general reflections and new trends in the analysis of pile load test results. Introduction The behavior of single piles under axial loading has been examined in detail by many investigators, and their findings were outlined in several publications (Davisson 1972; Meyerhof 1976; Vesic 1977; BS 8004: 1996; Das 1999; Nabil 2001). The load transfer settlement relationship for single piles and pile groups is very complex. Most settlement analysis methods are based on empirical methods and give only a rough approximation of the actual settlement, Gilbert (1991). Calculations of settlement are rarely performed when designing ordinary group pile and when they are done, the methods of calculation range from those using simple rules of thumb to those incorporating detailed finite element analysis. However, the direct method for calculating settlements from pressuremeter tests has been discussed by Frank (2012). A school of thought from http://osp.mans.edu.eg/deepfoundation/ch9.htm explicitly stated the total 1 settlement equation for single bored pile of diameters less than 600mm in a semi-empirical method below; S = Ss + Spp + Sps … (1) Where (Ss) is the elastic compression of pile shaft, (Spp) is the settlement caused by load transferred at the pile tip, (Sps) is the settlement caused by load transferred along the pile shaft. While the design of pile capacity is often verified by full-scale load testing, design for settlement is almost totally without the benefit of full-scale verification. The bearing capacity of a single pile may be estimated in one of three ways namely; (a) by load testing, (b) by static formulae and (c) by dynamic formulae, Scottt (1980). The first, i.e pile load test is a major focus in this paper with a case study. Generally the safe working capacity of a pile is dependent on factors such as pile dimension, its founding depth, geotechnical properties of surrounding soils strata and also method of installation. All these are best determined by a specialist piling contractor. Pile testing is the main part of QA/QC of piling works. Pile Load Test Pile load test is a static load test of a pile or group of piles used to establish an allowable load. The applied load is usually maximum of 150% to 200% of the design safe working load. The primary objectives of pile load test are; • To establish load-deflection relationships in the pile-soil system, • To determine capacity of the pile-soil system, and • To determine load distribution in the pile-soil system. These tests will confirm design assumptions or provide information to allow those assumptions and the pile design to be modified, Geotechnical Engineering Bureau (2007). Pile load testing provides an opportunity for continuous improvement in foundation design and construction practices, while at the same time fulfilling its traditional role of design validation and routine quality control of the piling works. In order to achieve this improvement, data from pile tests has to be collected and analysed to enable the piling industry, both individually and collectively, to make the best use of resources, Federation of Piling Specialist (2006). 2 Generally, many uncertainties are inherent in the design and construction of piles; it is therefore difficult to predict with accuracy the performance of a pile. The best way to know the pile behavior is to carry out a load test. The significance of a properly conducted load test is that, it furnishes the actual soil resistance at site upon which design can be based reliably. In practice, load tests will determine that the foundation is capable of sustaining working loads with sufficient factor of safety (normally Factor of Safety = 2.5 – 3.0). Load test will also identify the mechanism by which load is transferred to the soil. Basically, there are two types of test conducted for axial types of loading namely; compression tests and tension (pull out) tests. Pile Details and Site Description The tested pile is located within the site at 31/33, Waziri Ibrahim Crescent, Victoria Island, Lagos. Table 1.0 below shows the pile details Table 1.0: Pile Details Auger Pile Diameter Type of test Pile Safe Working Length Load (kN) (m) (mm) A-47 600 Compression 16.0 590 Date of Test 17th – 18th January, 2012. The pile load test was carried out in accordance with BS 8004 “Code of Practice for Foundations” Table 2 below shows the general site characterisation through executed subsoil investigations prior to the design of piles. 4 no geotechnical boreholes were drilled to 60.0m each and 6 no. cone penetrometer test were performed to refusal depth. 3 Table 2: The Generalized Subsoil Profile of the Site From To (m) (m) Generalised Strata Description (Note * Refers to existing ground level.) Cone Resistance Nspt/Cu Values (kg/cm2 ) 0.0* 10.5/12.0 Very loose to loose, fine to medium grained SAND 2 - 135 being organic from 2.0m-6.50m in BH1/BH3, and clayey from 6.4m-11.5m in BH4. 1-9 10.5/12.0 20.0/20.5 Medium dense to dense, fine to coarse grained 5 - 395 gravelly SAND becoming loose at the bottom 1 - 40 20.0/20.5 32.0/38.0 Soft to stiff organic CLAY being silty at the top. 5 - 95 BH-1 has medium dense sand between 25m and 32m. Cu= 68-106 kPa 32.0/38.0 42.0/50.0 Medium dense to very dense, fine to coarse grained 95 - 495 SAND with gravel at places and with lateritic clay and organic material at the top. 13 - 56 42.0/50.0 60.0 Dense to very dense, medium-coarse grained SAND with gravel at places and stiff sandy clay running across the site at depths between 52.5m and 58.5m (Cu=88 - 160kPa). 30 - 55 Preparation of Load Test Platform The test pile was installed such that the top is exactly at the required height and the support surface must be perfectly horizontal. Steel plates are then glued on top of the pile head while ensuring that the lower surface of the protruding parts is clear of the ground surface. The distance between these parts and the ground surface will be such that the test load is not carried by the ground. There should be enough clearance around the pile cap to prevent resistance from the sides or in particular, the base of the cap. A gap of 100 to 150mm is usually adequate below the cap. Equipments and Instrumentation for Pile Load Test Major equipment required for applying compressive load on a test pile generally include, but are not limited to the following: • test beams - primary and secondary 4 • bearing plates • hydraulic jack of appropriate capacity (800tons); connected to hydraulic pump • oil manometer of suitable capacity • kentledge or Dead weights (normally in form of concrete cubes of 1m3 and 24kN or 2.4tons), etc.. • 2 nos. steel reference beams • 2 nos. dial gauges, capable of measuring movements within an accuracy of 0.01mm Arrangement of Load Test Platform The arrangement for an axial compression test is generally done using either; (a) by means of a jack which obtains its reaction from kentledge heavier than the required test load (see Fig. 1 & 2); (b) by means of jack which obtains its reaction from tension piles or other suitable anchors (section 7.5.5.2 of BS 8004;1986). In the case study presented in this paper, the former was applicable i.e (a). Arrangement of the load test equipment for the kentledge method is as follows: a) Two support lines are established equidistant from the test pile position. b) A steel plate of adequate thickness is placed centrally on the pile head and the hydraulic jack placed on the steel plate afterwards. c) A second steel test plate is placed on the hydraulic jacks after which the primary beam is placed over it in a position parallel to the established supports. d) To ensure that there is a clearance between the primary beam and the hydraulic jack, the beam is supported at each end and care is taken to ensure that there is a clearance between it and the hydraulic jack. As a minimum, placement of the beam is such that its top level lies either at the same level as that of the established supports or it is not more than 50mm below this level. e) The secondary cross beams are then be placed over the established supports. 5 f) Afterwards, the kentledge is symmetrically placed to span across the cross beams which are supported by the established supports. g) The reference datum beams, each with one end set in concrete and the other free but supported, are placed about 50cm from both sides of the pile head. This will allow the beam to move as its length changes with temperature variation. h) The dial gauges are placed on flat steel plates which are connected to the test pile head by welding, after which glass plates, upon which the needle from dial gauges will rest, are then be taped to the reference datum beams. The general arrangement of load is presented in Fig. 1 – 2. Figure 1: The Typical Compression Pile Load Test Set-up by Kentledge (Dead Weight Method.) 6 Figure 2: A Schematic Section of Pile Load Test Arrangement Pile Load Test Procedure A detailed set of recorded results of load, time and movement measurement in tabular form and graph of load against settlement with indicated stages of loading are found as attachments in the appendix section. The maintained load method is the usual method of carrying out a pile load test especially when the load settlement relationship is required. It involves the application of the load in stages, with the load at each stage being maintained constant until the resulting settlement of the pile virtually ceases before the application of the next load increament. Maximum load to be applied on a single pile for this method will not exceed 2.0 x S.W.L. The load is applied in increments of 25% of the design load. Each load increment is maintained until the rate of settlement is not greater than 0.05mm/30minutes or until a maximum of about 2 hours have elapsed, whichever occurs first. 7 The maximum load is maintained on the pile for 6hours, except in the event that the average rate of settlement is not greater than 0.05mm/30minutes. Unloading of pile is done in decrements of 25% of the maximum load or as specified by the client. A loading scheduled was prepared by the Geotechnical Engineer using the relationship between pressure, force and area. That is, pressure applied by the jack is directly proportional to its applied force (load on pile) and inversely proportional to the cross sectional area of the jack. Table 3.0 below shows the configuration of some available hydraulic jacks we use in practice. Table 3.0: Available Jacks for Pile Load Test Hydraulic Jack Details S/No. Make Model No. Capacity (tons) Effective Area (cm2) Calibration Date. 1. ENERPAC 2501 250 176 Nov. 2010 2. ENERPAC CLASG50012 500 730 Nov. 2010 3. ENERPAC 800 961 Nov. 2010 8 Typical loading schedule prepared for the load test in the case study is shown in Table 4.0 below Table 4.0: Pile Load Test Sequence for Ø600mm Pile Safe Working Load (SWL) : 55.90tons Pile Depth : 16.0m Maximum Load (2.0 x SWL) : 88.50tons Pile No. : A47 Capacity of Hydraulic Jack : 500tons Date : Percentage Applied Loading Pressure Minimum load holding time (tons) (kg/cm2) LOADING UNLOADING SECOND CYCLE LOADING UNLOADING FIRST CYCLE Loading (%) 0 0 0 10 minutes. 25 14.750 19 30 minutes or 0.25mm/hr. 50 29.500 38 30 minutes or 0.25mm/hr. 75 44.250 57 30 minutes or 0.25mm/hr. 100 59.000 76 1hour or 0.25mm/hr. 75 44.250 57 10 minutes or 0.25mm/hr. 50 29.500 38 10 minutes or 0.25mm/hr. 25 14.750 19 10 minutes or 0.25mm/hr. 0 0 0 30 minutes or 0.25mm/hr. 100 59.000 76 30 minutes or 0.25mm/hr. 125 73.750 95 30 minutes or 0.25mm/hr. 150 88.500 114 12 Hours or 0.25mm/hr. 125 73.750 95 10 minutes or 0.25mm/hr. 100 55.900 76 10 minutes or 0.25mm/hr. 75 44.250 57 10 minutes or 0.25mm/hr. 50 29.500 38 10 minutes or 0.25mm/hr. 25 14.750 19 10 minutes or 0.25mm/hr. 0 0 0 30 minutes or 0.25mm/hr. 9 Before and after the application of each stage of loading and unloading, reading is made at two opposite sides of pile head by means of dial gauges. During loading, additional readings are taken at interval of 10 minutes. However, where the rate of settlement does not show any appreciable difference in two consecutive readings, the reading is taken at a reasonable interval or next stage of loading or unloading is performed. The Survey instrument is also used to monitor the settlement as a form of check for the fleximeter readings. Pile Load Test Results and Discussion The compression pile (A-47) with cross sectional diameter of 600mm is tested to a maximum 150% of the proposed safe working load, i.e. test load of 885kN. The design compressive SWL for the pile is 590kN. The test for pile (A-47) was carried out in two cycles, first to design test load of 590kN, then to 1.5 x design test load (1.5 x 590 = 885kN) during the 2nd cycle. Table 5: Pile Load Test Result Summary Pile No. 100% Movement Movement (mm) 125% of SWL (kN) SWL Movement (mm) 150% of SWL (kN) (mm) Residual Movement (mm) 1.01 737.50 1.65 885 3.03 1.41 (kN) A-47 590 In the first cycle, progressive and increasing loads till 100% SWL was applied on the pile and on attainment of the 100% maximum load it was maintained for a period of about 1-hour, during which pile movements as loading progressed were recorded, see summary in Table 5.0 above. The percentage increase or decrease in successive loading or unloading was 25%. During the second cycle loading, the test was taken to the maximum test load 1.5xSWL i.e. 885kN which was maintained continuously for 12hours and the corresponding movement was recorded. The full records of load test are found in the appendix section. The load – settlement curve is shown in Fig. 3; load – time curve in Fig. 4, and the settlement/deflection – time curve in Fig. 5 Pile (A-47), under the maximum applied load of 885kN, pile movements recorded for this pile is 3.03mm as shown in the Table 5 above. The test load was then gradually removed over this second and final cycle until the entire test load was fully removed. 10 Figure 3: Load – Settlement Curve for Pile No. A-47 11 Figure 4: Load – Time Graph for Pile No. A – 47 Figure 5: Deflection – Time graph for Pile No. A – 47 12 Table 6: Comparison between Designed and Load Test Settlements Results Design Results Load Test Results Load (tons) Settlement (mm) Load (tons) Settlement (mm) 59.00 1.16 59.00 1.01 73.75 1.74 73.75 1.65 88.50 3.26 88.50 3.03 Note that, 10kN = 1ton. Conclusion This paper has attempted to simplify a direct method of obtaining the residual settlement of a single pile. Comparison of the designed and as built settlement values were also done in order to avoid mispredictions, see Table 6 above for details. The comparison between the designed settlement and load test obtained settlement for Pile No. A-47 under a designed safe working load of 59.0tons shows little or no deviation. Italian software called “KK” was used in computing safe working load for the test pile and corresponding settlements anticipated. The designed settlement at safe working load of 59.0tons for the pile was 1.16mm while the load test obtained settlement was 1.01mm, hence a deviation of 0.15mm. The time required by the pile under the load test at safe working load of 59.0tons to reach a settlement of 1.01mm is 1.66hrs which is considered insignificant considering a long term settlement results. See Table 6 above for a comprehensive analysis of the designed settlement and load test obtained settlement. Figure 3 – 5 also shows a three dimensional representation of a single pile behaviour. The three dimensions being Time, Load and Settlement. The maximum pile movement for Pile No.A-47 under these loading is far less than 10% of the pile diameters i.e. 60mm, the boundary that would have theoretically taken the piles to their plastic limits. The tested pile (A-47) rebounded after the test loads had been fully removed with residual movements/settlement of about 1.41mm recorded after the load was fully removed. This is an indication of a good quality piles with good elastic properties. 13 References British Standard Code of Practice for Foundations BS 8004: (1996). Das Braja M. (1999). “Principles of Foundation Engineering”. 4th Edition, Brooks/Cole Publishing Co., Pacific Groove, Calif. Davisson, M.T. (1972). “High Capacity Piles, Proceedings, Soil Mechanics Lecture Series on Innovations in Foundation Construction” American Society of Engineers, ASCE, Illinois Section, Chicago. Pp 81-112. Federation of Piling Specialists, F.P.S. (2006). “Handbook on Pile Load testing” www.fps.org.uk/fps/piletesting/loadtestinghandbook.pdf (Accessed on 20th July, 2012.) Fleming, W.G.K. (1992). “A New Method for Single Pile Settlement Prediction and Analysis” Geotechnique, Vol. 42, No. 3. Pp 411 – 425. Frank, R. (2012). “Some Aspects of Research and Practice for Foundations Design in France”. Université Paris-Est, Ecole des Ponts ParisTech, UR Navier, Geotechnical teamCERMES.Pp 25 – 42. http://www.sloged.si/LinkClick (Accessed on 2nd June, 2012.) Geotechnical Engineering Bureau. (2007). “Geotechnical Control Procedure” New York State Department of Transportation. Gilbert, G. (1991). “Design of Pile Foundations”. US Army Corps of Engineers. Engineers Manual No. 1110-2-2906. http://osp.mans.edu.eg/deepfoundation/ch9.htm. (Accessed on 29th June, 2012.) Meyerhof, G.G. (1976). “Bearing Capacity and Settlement of Pile Foundations”. J. Geotech. Engrg.Div., ASCE, 102(3), 195-228. 14 Nabil, F.I. (2001). “Axial Load Tests on Bored Piles and Pile Groups in Cemented Sands” Journal of Geotechnical & Geoenvironmental Engineering. Vol.127, No. 9, Pp 766 – 773. New Trends and Developments in Geotechnical Engineering. International Society of Soil Mechanics and Geotechnical Engineering (ISSMGE) International Conference. Vesic, A.S. (1977). “Design of Pile Foundations”. Nat. Cooperative Hwy.Res. Program Synthesis of Pract.No.42, Transportation Research Board, Washington D.C. 15 APPENDIX LOAD TEST RECORDING SHEETS 16 17 18 19 View publication stats