SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 2 of 12 Revision Summary Date Revision Prepared Checked Approved 08 Nov 09 00 J. Nazeer (HSE) J. Reed (HSE) G. Varghese (QMR) M. Bartolucci (MD) 09 Oct 17 01 F. Jabbour (HSE) C. Mastan (GAO) G. Varghese (QMR) D. Quintarelli (CEO) Description of Revision 01 The impact of the revision may be deemed Low. The following amendments were made in this revision: • Updated to Latest Corporate format for work instructions • Updated reference documents; • Updated Work Permit Forms; • Added two new Work Permit Forms; This Work Instruction supersedes the document “Work Permit system” (Doc. No. WI-SPSA-HSE-017-E) Rev. 00, dated 08 November 2009. This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 3 of 12 TABLE OF CONTENTS 1. 1.1 1.2 1.3 1.4 1.4.1 1.4.2 INTRODUCTION OBJECTIVES OF THE DOCUMENT AREA OF APPLICATION METHODS OF IMPLEMENTATION REFERENCE DOCUMENTS INTERNAL REFERENCES EXTERNAL REFERENCES 4 4 4 4 4 4 4 2 DEFINITIONS, ABBREVIATIONS AND ACRONYMS 5 3 ROLES AND RESPONSIBILITIES 5 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 4 4.1 5 5.1 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 5.1.6 5.1.7 5.1.8 5.2 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5 5.3 5.4 5.5 CONSTRUCTION MANAGER FIELD HSE COORDINATOR SUBCONTRACTOR CONSTRUCTION MANAGER SUBCONTRACTOR HSE MANAGER SUBCONTRACTOR RECEIVING AUTHORITY (ORIGINATOR) ISSUING AUTHORITY (VALIDATOR) GAS TESTER (SAFETY SUPERVISOR/OFFICER) WORK PERMIT COORDINATOR OPERATING AUTHORITY (OPERATOR) SUBCONTRACTOR PERFORMING AUTHORITY (PERFORMER) DESCRIPTION OF ACTIVITIES 5 5 6 6 6 6 7 7 7 7 8 GENERAL PRINCIPLES 8 OPERATING PROCEDURE 9 FUNCTION OF THE WORK PERMIT SYSTEM COLD WORK (GENERAL WORK PERMIT) HOT WORK CONFINED SPACE ENTRY RADIOGRAPHY WORK EXCAVATION WORK ELECTRICAL WORK GRATING HANDRAIL REMOVAL AND OPEN HOLE CERTIFICATE LIFTING CERTIFICATE ISSUANCE AND APPROVAL OF WORK PERMIT FORMS BEFORE ISSUING THE WORK PERMIT VALIDATOR AND ORIGINATOR WORK PERMIT RECEIVER AUTHORITY (ORIGINATOR) WORK PERMIT ISSUING AUTHORITY (VALIDATOR) WORK PERMIT PERFORMER RIGHT TO STOP WORK AND CANCEL PERMITS CLOSING WORK PERMITS FILING WORK PERMITS 9 9 9 9 9 10 10 10 10 10 10 10 10 10 10 11 11 11 6 UPDATING 11 7 ARCHIVING, DOCUMENT STORAGE AND TRACEABILITY 11 8 ATTACHMENTS 11 This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 4 of 12 1. INTRODUCTION OBJECTIVES OF THE DOCUMENT 1.1 The scope of this document is to establish minimum guidelines and responsibilities for issuing/receiving of work permits and to provide recommendations on how to plan and execute potentially hazardous jobs in a safe manner. When issued, these permits served as official records of conditions and requirements agreed upon by the validator and originator. They list minimum safety precautions to be taken and hazards which must be controlled. The purpose of this document is to ensure that a safe work environment is achieved by providing management control over the various work activities carried by Snamprogetti Saudi Arabia Ltd. and Subcontractors which may be potentially hazardous within the designated fenced areas known as Construction Areas. This procedure defines the administration arrangements of the work permit system only for the construction activities phase and shall not be used for the commissioning activities phase. However, some construction activities will be carried out in the areas not under the direct responsibility and control of the Snamprogetti Saudi Arabia Ltd., and then during this phase, it will be managed under the control procedures of the client. Where work is to be carried out by Snamprogetti Saudi Arabia Ltd. in areas under the direct control of the client, this work will be undertaken utilizing the work permit system of the area owner. 1.2 AREA OF APPLICATION This Work Instruction applies to Snamprogetti Saudi Arabia Co. Ltd. METHODS OF IMPLEMENTATION 1.3 Upon approval by the CEO, this Work Instruction, supersedes its previous revision (if any), shall take effect immediately and is applicable to Snamprogetti Engineering & Contracting Co. Ltd. that carry out the activity described herein. REFERENCE DOCUMENTS 1.4 1.4.1 • • • • • • • • • • Corporate Standard “HSE Work Permits” (STD-COR-HSE-112-E) Form “COLD WORK PERMIT” (FORM-SPSA-HSE-030-E) Form “HOT WORK PERMIT” (FORM-SPSA-HSE-031-E) Form “CONFINED SPACE ENTRY CERTIFICATE” (FORM-SPSA-HSE-032-E) Form “RADIOGRAPHY PERMIT” (FORM-SPSA-HSE-033-E) Form “EXCAVATION CERTIFICATE” (FORM-SPSA-HSE-034-E) Form “ELECTRICAL CERTIFICATE” (FORM-SPSA-HSE-035-E) Form “GRATINGHANDRAIL REMOVAL AND OPEN HOLE CERTIFICATE” (FORM-SPSA-HSE-039-E) Form “LIFTING CERTIFICATE” (FORM-SPSA-HSE-040-E) Form “WORK PERMIT LOG” (FORM-SPSA-HSE-036-E) 1.4.2 • • • INTERNAL REFERENCES EXTERNAL REFERENCES Saudi Aramco Construction Safety Manual, II-1 Saudi Aramco General Instruction (GI. 2.100) Loss Prevention Program This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 5 of 12 2 DEFINITIONS, ABBREVIATIONS AND ACRONYMS SPSA Snamprogetti Saudi Arabia Ltd. Contractor Snamprogetti Saudi Arabia Ltd. Work Permit Is a written form used to authorize jobs that expose workers to serious hazards. It identifies the work to be done, the hazards involved, and the necessary preparations and precautions for the job. Issuing Authority (Validator) Person(s) appointed and authorized by the Construction Manager who is(are) responsible for reviewing the work permit, confirming that the work site has been examined and all precautions to be taken before work commences. Receiving Authority (Receiver) Person(s) who is(are) appointed and authorized by the Subcontractor Construction Manager to receive work permits. Work Permit Coordinator Person(s) appointed and authorized by the Construction Manager to coordinate the issuance of all work permits to identify potentially conflicting work tasks both on geographical and time basis. Operating Authority (Operator) Person(s) who will sign the work permit and verify that all requirements have been met and that the work area is in safe condition for the work to commence. 3 ROLES AND RESPONSIBILITIES The following entities shall ensure the following responsibilities as herein defined: 3.1 CONSTRUCTION MANAGER The Construction Manager shall responsible for: • Ensuring the effective administration of this procedure within construction site activities and shall ensure that this procedure is properly implemented at site • Shall ensure that all work is carried out under the controls of Work Permit System • Ensure that sufficient funds and recourses are made available to ensure the continuity of this procedure for the duration of the works • Nominate a Work Permit Coordinator to ensure that the coordination of permits is administered correctly • Ensure the proper coordination of construction activities between Contractor Construction Manager and Subcontractor Construction Managers • Verify that the Subcontractor Construction Manager is providing the correct information and equipment for the scope of work • Ensure training is given to all persons required to use the Permit to Work • Nominate personnel and authorize them to perform the duties of Permit to Work Signatories • Approve the personnel nominated by the Construction Manager as signatories of the Work Permit System 3.2 FIELD HSE COORDINATOR The Field HSE Coordinator will: • Ensure that all necessary support, advice and guidance are made available to enable this procedure to be properly implemented • Ensure adequate training to all personnel involved in this procedure • Ensure that suitable and sufficient inspections and audits are carried out This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 6 of 12 • 3.3 Evaluate the effectiveness of this procedure and changes amend as is required or becomes necessary to achieve its purpose SUBCONTRACTOR CONSTRUCTION MANAGER The Subcontractor Construction Manager will: • Ensure that sufficient and qualified resources are made available to enable the safe implementation of this procedure • Ensure that all concerned personnel have read and understood this procedure • Ensure that adequate facilities and means are in place for the implementation of this procedure • Identify and communicate in writing the personnel authorized to sign the work permit such as Receiving Authority and Performing Authority 3.4 SUBCONTRACTOR HSE MANAGER The Subcontractor HSE Manager shall: • Ensure that proper instruction, training and supervision are provided at all times • Ensure that suitable and sufficient inspections are carried out by competent personnel, and that proper records are maintained • Ensure that work is carried out in accordance with this procedure • Ensure that the conditions are satisfactory for the work to proceed • Ensure that each item on the permit is accurately filled out and covered • Ensure that personnel understand the requirements on the permit and any unusual conditions connected with the job • Ensure the continuous monitoring of the work area conditions and to stop, the environment and/or equipment to convey pertinent information about the work to the relievers • Advise the Field HSE Coordinator of any irregularities or areas of concern in order to identify any necessary corrective action • Sign the relevant part of the Work Permit where applicable in case of gas test 3.5 SUBCONTRACTOR RECEIVING AUTHORITY (ORIGINATOR) The Subcontractor receiving authority (Originator) has the following responsibilities: • To instruct the Subcontractor Performing Authority (Performer) of the permit requirements and satisfy himself that the Subcontractor Performing Authority has enough information and resource to perform the work safely • Ensures that the Subcontractor Performing Authority understands what, where, and how the work is to be performed • To ensure compliance with the conditions stipulated on the permit • To ensure that the Subcontractor Performing Authority supervises the work group and is satisfied that the persons carrying out the work use the proper tools and equipment for the job • That the Subcontractor Performing Authority informs the work group of the safe working practices • To inform the Issuing Authority of any changes in the condition of the job or the surrounding area, or of any delay in starting the work, so as not to infringe upon any safety factors • Notify the Issuing Authority upon completion of the work 3.6 ISSUING AUTHORITY (VALIDATOR) The Validator of the Permit to Work has the following responsibilities: • To check the completeness and reliability of the submitted forms • To specify the required worksite precautions and controls • To detail required safety equipment • To identify any worksite preparation requirements, if deemed necessary • To ensure that Certificates (attached to Permits as required) for Confined Space work, excavation and electrical works are duly signed by authorized engineers This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 7 of 12 • 3.7 To ensure Gas Test have been completed as required by the Permit GAS TESTER (SAFETY SUPERVISOR/OFFICER) Authorized Gas Tester is responsible for: • Ensuring that the necessary condition monitoring is carried out within the specified time limits and a record of the results is marked upon the Permit to Work • Verify the testing has been done 3.8 WORK PERMIT COORDINATOR The Work Permit Coordinator nominated by the Construction Manager has the responsibility of ensuring that all permits to work are entered into the system in the correct manner. Additionally the work Permit Coordinator shall: • Ensure that all Permits to Work are submitted onetime for entry into the system • Ensure the Permit to Work is completed correctly and that all relevant controls and signatures are added • Permit to Work is properly distributed to the interested parties as indicated; understand the scope and the details of execution of the work • Ensure the necessary checks have been satisfactorily executed before signing the permit to work • Suspend the Permit to Work at any time if the Permit to Work conditions are not complied with • On satisfactory completion of the works, approve the effective closure of the work and sign for acceptance 3.9 OPERATING AUTHORITY (OPERATOR) The Operating Authority is responsible for carrying out all preliminary checks required by the Issuing Authority and will sign the Permit to Work to verify that all requirements have been met and that the work area is in a safe condition for the work to commence. The Operating Authority is nominated by the Construction Manager. Additionally, the Operating Authority shall: • Ensure that all signatories have signed the Permit to Work • Ensure that all instructions training has been given to the work party prior to the work commencing • Inform the Issuing Authority that the work is about to commence in order that this can be notified and recorded as a live permit • Inspect the worksite periodically to ensure there is no change in condition • Suspend the work immediately if there is any breach of this procedure or change in conditions and to notify Issuing Authority for the reason • Ensure a good standard of housekeeping is maintained throughout the work and that all equipment is removed upon completion • Notify the Issuing Authority upon the completion of work • Inform the Issuing Authority of any change in the working conditions of the surrounding areas in the vicinity of the working area 3.10 SUBCONTRACTOR PERFORMING AUTHORITY (PERFORMER) The Subcontractor Performing Authority is the person responsible for supervising the work group carrying out the job and shall hold as a minimum the supervisory grade of a Foreman. The subcontractor Performing Authority is not entitled to start any job without previous approval of the Permit to Work by both Issuing Authority and Operating Authority. The subcontractor Performing Authority is responsible to: • Ensure the work group carrying out the work is fully briefed usually by means of dedicated tool box talk • Ensure that they have clearly understood instructions given, including the scope of their activity and the relevant risks • Remain at the worksite until the completion of the task • After signing the Permit to Work the Subcontractor Performing Authority shall ensure that all copies of This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 8 of 12 • • • 4 the Work permits are correctly distributed and that a copy is retained and posted at the work site Inform the Subcontractor Receiving Authority or Operating Authority of any change in the working conditions of the job, or an delay in starting the work Using proper tools and equipment for the safe execution of the job Ensure the worksite is left in a safe and tidy condition DESCRIPTION OF ACTIVITIES 4.1 GENERAL PRINCIPLES The persons involved in the activities regulated by this Work Instruction operate in compliance with the regulatory and organisational system, and the system of powers and internal proxies. They shall also act in accordance with the law, applicable regulations and in compliance with the principles established below. Traceability – the persons involved in the activities regulated by this Work Instruction ensure - each within their own sphere of responsibility - that the activities and documents pertaining to the process remain traceable, by seeing to it that the respective sources, information and checks can be identified and reconstructed. Furthermore, all documents shall be stored, in compliance with current applicable legislation, using dedicated information systems, whenever available. Confidentiality – without prejudice to the transparency of the tasks performed and the obligations of disclosure imposed on applicable provisions, including those relating to the keeping and updating of lists of persons with access to privileged information, all persons involved in the activities regulated by this Work Instruction are under obligation to ensure the appropriate degree of confidentiality for all information that may come to their attention by virtue of their position. Segregation of Duties – in the activities regulated in this Work Instruction, a segregation of duties and responsibilities must be provided, in order to prevent situations in which activities are concentrated on specific parties, which may contribute to creating conditions of risk with regard to the reliability of the information and the correct performance of duties. In dividing/assigning the activities, incompatible duties between and within the functions shall be segregated in accordance with the segregation principles prescribed by the internal control system applicable to the different entities. In practice, the principle is applied in relation to the nature of the activity concerned and the type and degree of risk associated with it, with a view to preventing the formation of unduly cumbersome organisational structures, especially in entities of moderate size. Conflict of Interest – The relationship of personnel involved in the activities regulated in this Work Instruction with their counterparts shall aspire to the highest standards of ethical behaviour in compliance with the Saipem Code of Ethics. Every effort must therefore be made to avoid all situations and activities which could give rise to a conflict with the company’s interests or which could interfere with a person’s ability to take decisions impartially in the best interests of the company and in full observance of the principles and contents of the Code of Ethics and of the company’s Model, the Anticorruption MSG and, in general, with the correct performance of their duties and responsibilities. Every situation that may constitute or determine a conflict of interest shall be handled in accordance with the Code of Ethics and with the Anticorruption MSG. Anti-corruption Policy – Saipem prohibits all forms of corruption, without exception. In particular, it is forbidden for Saipem personnel to (a) offer, promise, give, pay or authorise anyone to give or pay, directly or indirectly, a financial or other benefit to a Public Official or private citizen; (b) accept a request or demand, or authorise someone to accept the request or demand, directly or indirectly, for anything of value or other utility from a Public Official or private citizen, when in both cases the intention is (i) to induce a Public Official or private citizen to perform improperly any function of a public nature or any activity connected with a business or to reward them for the improper performance of such a function or activity; (ii) to influence an action or omission by a Public Official or any of the Public Official’s decisions in violation of official duty; (iii) to obtain, secure or retain business or an improper advantage in the performance of business activities; or (iv) to violate current laws in any way. This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 9 of 12 Value creation/maximization – all of Saipem’s activities shall be aimed at increasing, in the long term, the value of Saipem’s assets and of its managerial and technological skills and knowledge, as well as at creating value and welfare for all stakeholders Transparency – the persons engaged in the activities regulated by this Work Instruction shall operate in such a way as to guarantee the utmost transparency in the performance of their duties and to provide full and truthful disclosure Continuous Improvement – Saipem assures the continuous improvement of its Processes through a suitable monitoring system. The functions shall promote the monitoring, development and dissemination of the know-how relating to the activities regulated by this Work Instruction. In order to guarantee continuous improvement, performance must be monitored through suitable monitoring and reporting tools Satisfaction of Customer Departments/Functions – The functions involved in the in the task governed by this Work Instruction must enable the achievement of the required performance in terms of reliability, availability and fulfilment of the expectations of customer functions through cooperation and continuous alignment with them, in compliance with the expenditure limits defined by Saipem. Understanding the requirements and needs expressed, the constant monitoring of work performed, and feedback of the effectiveness of the services supplied is the main tools to allow maximization of the satisfaction of the customer departments 5 OPERATING PROCEDURE 5.1 FUNCTION OF THE WORK PERMIT SYSTEM Work permits must be issued, as appropriate for any of the work or combination of the work on specific work on a specific site identified below: 5.1.1 COLD WORK (GENERAL WORK PERMIT) Any work within the construction area of work that will not produce sufficient energy to ignite flammable atmospheres/materials. The Work Permit shall be utilized for all activities other than those capable of generating or using sources of ignition. Use form no. FORM-SPSA-HSE-030-E for cold work permits (PALE BLUE BORDER). 5.1.2 HOT WORK Any work within the construction area of work, wherein the heat generated is of sufficient magnitude and intensity to cause ignition of any flammable liquids, gases or any other material. Common sources of ignition are internal combustion engines, gas cutting torches, welding machines, non-flame proof electrical equipment, grinders, annealing blankets, jack hammers, etc. Form no. FORM-SPSA-HSE-031-E shall be used for hot work permit (RED BORDER). 5.1.3 CONFINED SPACE ENTRY Entry of personnel into any space or structure (i.e., tank, vessel, vault, excavation when 1.2 meter or deeper not normally intended for human occupancy) where entry, movement within, or exit is restricted. Use form no. FORM-SPSA-HSE-032-E (LIGHT GREEN BORDER). 5.1.4 RADIOGRAPHY WORK To control all site radiography and the use of ionizing radiation, form no. FORM-SPSA-HSE-033-E (LIGHT ORANGE BORDER) shall be used. This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 10 of 12 5.1.5 EXCAVATION WORK Form no. FORM-SPSA-HSE-034-E (BROWN BORDER) shall be used for any excavation jobs. 5.1.6 ELECTRICAL WORK An electrical permit (Form no. FORM-SPSA-HSE-035-E) shall be used for any activity to be carried out on live electrical equipment or system. 5.1.7 GRATING HANDRAIL REMOVAL AND OPEN HOLE CERTIFICATE A grating, handrail and open hole certificate (Form no. FORM-SPSA-HSE-039-E) shall be used for any activity that requires the opening of gratings and/or removal of handrails on existing final structures; 5.1.8 LIFTING CERTIFICATE A lifting certificate (Form no. FORM-SPSA-HSE-040-E) shall be used for any lifting activities that are to be carried out. 5.2 5.2.1 ISSUANCE AND APPROVAL OF WORK PERMIT FORMS BEFORE ISSUING THE WORK PERMIT All necessary actions to improve the proposed work and/or possible configuration changes must be completed. The issuer must verify that the receiver is experienced, competent and familiar with the requirements of the Work Permit system and be able to perform the duties associated with receiving work permits. 5.2.2 VALIDATOR AND ORIGINATOR The validator and originator are jointly responsible for the safety of personnel and equipment in the area. The validator is responsible for specifying precautions so that the work can be done without injury or loss. The originator is responsible for performing the work in accordance with the conditions and requirements agreed upon with the issuer and specified in the work permit. 5.2.3 WORK PERMIT RECEIVER AUTHORITY (ORIGINATOR) The originator requests the work permits from the work permit validator and complete the initiation part of the work permit form. The originator must participate in any joint site inspection that is conducted. 5.2.4 WORK PERMIT ISSUING AUTHORITY (VALIDATOR) The validator will issue the work permit after he has conducted a joint site inspection with originator as appropriate, performed the necessary gas tests, listed applicable precautions and restrictions, and reviewed all aspects of the job with the receiver. The validator and originator signatures plus any other approvals and signatures must be on the completed form. 5.2.5 WORK PERMIT PERFORMER The Subcontractor performing authority must keep a copy in view at the job site for the duration of the job so that it is available for inspection and cancellation if necessary. The receiver is expected at the job site to adequately supervise the work. If he must leave the jobsite for any reason, the issuer concurs. The alternate receiver must be written on the permit by the issuer. This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 11 of 12 5.3 • • • • • • • 5.4 RIGHT TO STOP WORK AND CANCEL PERMITS The issuer may stop and withdraw a work permit if he determines that safety of the job does not meet the conditions specified on the work permit When work is stopped the issuer must pick up the work permit, write on the permit the reasons for the work cancellation, the time, and other relevant information When the conditions are safe again the issuer may issue a new work permit The receiver has the responsibility to stop work and advise the issuer of his action any time he determines that the conditions of the job do not meet the conditions on the work permit. He and the issuer shall take action to correct deficiencies and resume the job All necessary personnel whose presence adversely affects the safety of the job must be kept away from the job site or work shall be stopped All work permits are cancelled in the event of an emergency, such as a fire or toxic release. Permits may be re-issued once the “all clear” has been declared and the work sites have been returned to their pre-emergency conditions If an unsafe condition develops when neither the validator nor the performer is available at the work site, a performer’s delegate has the authority to stop the job CLOSING WORK PERMITS Work permits shall be closed by both the operator and the performer signing the permit. Both the operator and performer shall conduct a site inspection to ensure that the work area has been returned to its pre-work condition before the work permit can be closed. If the work has not been completed, the work site shall be left in safe and secure condition. 5.5 FILING WORK PERMITS The issuer shall keep the original copy of the work permits for a minimum of three (3) months. 6 UPDATING The functions/departments and the positions involved in the activities regulated by this Work Instruction are responsible for monitoring Company operations that entail the need to update it. These findings are reported to HSE Department that ensures coordination of the activities for updating this document. 7 ARCHIVING, DOCUMENT STORAGE AND TRACEABILITY The functions / departments and the positions involved in the activities regulated by this Work Instruction shall ensure, each for matters under its responsibility and also by means of the information systems used, the traceability of data and information and shall provide for storing and archiving the produced hardcopy and / or electronic documentation, in order to enable the reconstruction of the different steps of the process. 8 ATTACHMENTS The following documents are integral part of this Work Instruction: • Work Permit System Flow Diagram This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved. SNAMPROGETTI SAUDI ARABIA CO. LTD. WORK INSTRUCTION Doc. n. WI-SPSA-HSE-017-E Rev. 01 Date 09 Oct 17 WORK PERMIT SYSTEM Page 12 of 12 Annex 1 – Work Permit System Flow Diagram This document is the property of Snamprogetti Saudi Arabia Co. Ltd. All Rights Reserved.