METHOD OF STATEMENT 1. Project Start 2. Plan Capacity and work load 3. Scheduling of Activities 4. Materials and Services Approval Required 5. Design and Engineering 6. Obtain Materials and Service Approval 7. Purchasing 8. Inspection and testing satisfactory (after Completed) 9. Shipping to site 10. Site works 11. Outstanding Activities 12. Technical Completion 13. As Built Drawings and Final Documents 14. Preliminary Acceptance 15. Final Receipt and Release 16. Final Acceptance 17. Project Complete PERMISSION AND PERMITS TO WORK 1. Permission from Saudi Arabia Governments (work related only) 2. Permission from SEC -EOA permit to work PTW (work & activity related only) ENGINEERING DESIGN CRITERIA AND REQUIREMENTS 1. ENVIRONMENTAL CONDITIONS 2. SOIL THERMAL RESISTIVITY TESTING AND COMMISSIONING PLAN 1. Pre-Commissioning Activities 2. In or directed by Commissioning plan 3. Factory Acceptance Test (FAT) 4. Site Acceptance Test (SAT) 5. SEC-EOA Acceptance 6. Other (if any) 7. Commissioning Test Plans 8. In or directed by Commissioning plan 9. Setting to work Initial Adjustments 10. Inspections 11. Initial Testing and Final Testing 12. Submittal Of Operation and Manual PROCUREMENT PLAN 1. Material Requirement and Identification 2. Process control and Inspection 3. Long Lead Items 4. Vendor and Manufactures Qualification 5. Material Requisition 6. Submittal, Review Approval, Inspection and Acceptance PURCHASING 1. Purchase Order (PO) 2. Purchase Requisition (PR) Submittal 3. Inspection Test and Satisfactory 4. Factory Acceptance Test (FAT) 5. SEC-EOA Acceptance 6. Released For shipment certificate 7. Shipping and Delivery 8. Site Acceptance Test (SAT) 9. Rectification (if necessary) 10. SEC-EOA Acceptance 11. Inspection and Receiving at Store 12. Installation of Approved Materials and Equipment’s CONTRACTOR/COMPANY’S CONSTRUCTION SITE OFFICE AND FACILITY 1. Electricity Connection/Electrical Wiring 2. Telephone Connection 3. Water Supply Connection 4. Drainage Connection 5. Quality of Temporary WORK 6. Star Safety and Health Management System 7. Housekeeping and Cleanliness 8. Demobilization 9. Security Arrangement QUALITY ASSURANCE/QUALITY CONTROL REQUIREMENTS 1. Quality Management 2. PROJECT Quality Plan / Quality Program] 3. Procurement Control 4. Quality Audit 5. Non-Conformance Control 6. Corrective Action 7. Quality Records 8. Control of Inspection, Measuring and Testing Equipment 9. Document Control 10. Material/Equipment Handling, Storage, Identification and Control 11. Inspection Checklist and RFI Formats (depends on activity as per schedule -C) 12. Field Testing/Inspection and Construction/Installation Control 13. Quality Control Plan/Inspection and Test Plan 14. Manufacturers/Suppliers 15. Quality Assurance and Quality Control Services [Independent Inspection Agency] 16. Release for Shipment Certificate 17. Receipt Inspection 18. Independent Testing Laboratory 19. Inspection by COMPANY REPRESENTATIVE 20. COMPANY’s Quality Assessment (Audit) Right 21. Quality Control on CONTRACTOR’S Workmanship 22. Additional Requirements (if any) 23. Operation and maintenance manuals 24. Technical data manuals 25. Test record book POWER CABLE INSTALLATION 1. Cable Pulling Tension and Sidewall Pressure Calculations 2. Preparation of Trench 3. Running Out of Cables 4. Cable Splicing and Terminations 5. General Requirements 6. Certification of Splicing Personnel 7. Cable Tagging 8. Installation of Link Box CABLE TRENCHES AND DIRECTIONAL DRILLING REQUIREMENTS A. General Requirements B. Other Underground Utilities C. Trenching in High Water Table Areas D. Maintenance of Cable Trenches E. Other Trenching Requirements F. Horizontal Directional Drilling G. CABLE DUCTBANKS H. General Requirements I. Bell Ends J. Testing and Cleaning CONCRETE 1. Surfaces Below Grade 2. Surface above Grade 3. Concrete Bonding Agent 4. Concrete Formwork 5. Ties and Anchors 6. Concrete Test 7. Curing 8. CONCRETE ENCASED DUCTBANKS 9. ASPHALT CONCRETE PAVEMENT 10. Tack Coat 11. Bituminous Paving Mixture 12. Asphalt Concrete Mix Design 13. REINFORCING STEEL 14. BACKFILL MATERIALS TRENCH REINSTATEMENT TO SUB-BASE A. Sand Backfill B. Cable Protection C. Cable Tiles D. Steel Wire Mesh E. Warning Tape F. Warning Post ASPHALT REINSTATEMENT A. General Paving Requirements for Hot Asphalt Mix B. Placing of Mixture C. Compacting the Mixture D. Compaction and Testing Requirements CABLE ROUTING INSIDE SUBSTATION BASEMENT ROOM A. Responsibility During Installation B. Access to Substation Entry (all related permits) C. Work Procedure and methods OTHER INSTALLATION REQUIREMENTS D. Responsibility During Installation E. Access to Public and Private Properties F. Traffic Diversions ELECTRICAL TESTS FOR NEW 69kV XLPE CABLES (After completing cable installation) A. Cable Jacket Test B. Conductor Continuity and Phasing Tests C. Metallic Shield Continuity Test D. Cable Insulation Test by Megohmmeter E. Cable Profile Radar Test F. High Voltage AC Test or VLF Test G. Grounding Resistance Measurement at Link Boxes and Splices/Terminations at H. Link Boxes and Contact Resistance of each Cad Weld Joint. I. Cable Impedance Measurement J. Mutual Impedance test K. Conductor Resistance and Shield Resistance Test