Engineering Justification Paper RIIO-ED2 Programme Level Report Ref No L&S EJP 7 – Enhancements due to fire risk assessments Date 30 June 2021 Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 1 30 June 2021 Table of Contents 1 Summary Table 4 2 Introduction 5 3 Background Information 6 4 Optioneering 8 4.1 Option 1 – Do nothing 9 4.2 Option 2 – On-site FRA at all substation plus remedial work where identified 9 4.3 Option 3 – Mix of Desktop and On-site FRA dependent on risk-level 9 4.4 Option 4 - Carry out a desktop FRA of all substations 10 5 Analysis and Cost 11 6 Deliverability and Risk 13 7 Conclusion 14 Appendix A - ENA Engineering Recommendation S39 15 Table of Tables Table 1-1 Investment Summary 4 Table 3-1 Fire Risk assessment matrix 6 Table 3-2 Substation types 6 Table 4-1 Summary of Options 8 Table 5-1 Substation inspection categories 11 Table 5-2 Fire Risk Assessment enhancement cost delivery profile 12 Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 2 30 June 2021 Acronyms and Abbreviations ALARP As Low As Reasonably Practicable CP Code of Practice EJP Engineering Justification Paper ENA Energy Networks Association ENA ER Electricity Networks Association Engineering Recommendation ENWL Electricity North West Limited FRA Fire Risk Assessment G&P Grid and Primary HV High Voltage Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 3 30 June 2021 1 Summary Table Table 1-1 below provides a high-level summary of the key information relevant to this Engineering Justification Paper (EJP) related to the enhancements ensuing from a structured fire assessment process. Table 1-1 Investment Summary Enhancements due to fire risk assessments Name of Scheme/Programme Enhancements due to fire risk assessments Primary Investment Driver Safety Scheme reference/mechanism or category Multiple projects Output references/type Fire Protection - Substations Cost £7.8m Delivery Year RIIO-ED2 Reporting Table CV14 – Legal & Safety Outputs included in RIIO ED1 Business Plan Yes Spend apportionment ED1 ED2 ED3+ £0.6m £4.4m £2.8m Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 4 30 June 2021 2 Introduction Under the Regulatory Reform (Fire Safety) Order 20051, we have a responsibility to carry out general fire safety precautions for all of our premises to ensure safety of our employees and other personnel on site. Section 8-1 states: “Duty to take general fire precautions 8.—(1) The responsible person must— (a) take such general fire precautions as will ensure, so far as is reasonably practicable, the safety of any of his employees; and (b) in relation to relevant persons who are not his employees, take such general fire precautions as may reasonably be required in the circumstances of the case to ensure that the premises are safe.” In 2017, to assist electricity companies in discharging these duties as they apply to their substations, the Energy Networks Association (ENA) published Engineering Recommendation S39, ‘General fire precautions in substations at 132kV and below and in enclosed cableways.’ A copy of this document is provided in Appendix A. ENA ER S39 includes the following guidance: “Whilst all substations will fall under the Order, it is probable that a generic assessment can be used for substations of similar design (such as modern unit-type distribution substations) located in similar environments. It is likely that most grid and primary substation will need to be individually assessed.” During RIIO-ED1 we have established our Fire Risk Assessment process and carried out 750 assessments at indoor substation sites. This has led to development of policy and an assessment of the work needed to bring the fire risk to as low as reasonably practicable. As a result of this work we have been able to identify the type of assessment required for each site and the expected volume of remediation work resulting from these assessments. We have taken the guidance in ENA ER S39 and published our own Code of Practice (CP) 357, Fire Risk Assessments for Operational Sites, which sets out our approach to fire risk assessments. This document is currently under review to ensure it is current and describes the most effective approach to maintain safety from fire at substations. We have approximately 18,000 ground mounted distribution (HV) substations and around 560 Grid and Primary (132kV and 33kV) sites. To carry out FRAs in the most efficient manner, whilst ensuring that fire risk is properly identified and mitigated, a combination of generic desktop assessments and on-site risk assessments is used. As this programme of work is to ensure the safety of our staff and customers, we are planning to complete all the remedial work identified from the FRAs by the end of RIIO-ED2. Investment in this area in future years will be as required to maintain safety. 1 https://www.legislation.gov.uk/uksi/2005/1541/contents/made Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 5 30 June 2021 3 Background Information The complexity of our Grid and Primary substations requires an individual on-site survey and risk assessment with regards to fire precautions. Likewise, all distribution substations in third party buildings and those within larger buildings also require individual on-site surveys related to fire risk assessments. For distribution substations in outdoor compounds and in smaller standalone buildings, a desktop risk assessment approach has been adopted. There are a large number of these sites (over 75% of our total substation population), which are expected to pose a limited fire risk. If the results of the desk top FRA indicate a Moderate (or higher) risk, as defined in Table 3-1 below, then these sites will then be subject to an on-site FRA. Substations assessed as Negligible or Tolerable risk will not have an onsite FRA. Table 3-1 Fire Risk assessment matrix Likelihood of Fire Low Medium High Potential consequences of fire Low Medium High Negligible risk Tolerable risk Moderate risk Tolerable risk Moderate risk Substantial risk Moderate risk Substantial risk Intolerable risk This desktop FRA is based on the substation size, its construction material (for indoor buildings), its location in relation to other properties, evidence of materials being stored around the substation and evidence of interference or vandalism. The numbers and types of substations in our network is given in Table 3-2 along with the survey category required. Table 3-2 Substation types FRA category Substation type Number Desktop Outdoor distribution 6,002 Desktop Small indoor distribution 8,344 On-site Large indoor distribution 1,182 On-site Buried On-site In a third-party building On-site Grid & Primary 50 2,435 561 Where the result of a desktop FRA is that a substation is Moderate risk, an on-site assessment will be carried out to validate the result of the FRA and identify enhancement works required. On-site assessments look at items such as potential sources of fire, measures to contain fire and risk to people should a fire occur. Currently, no sites have been identified as higher than Moderate risk from desktop FRAs. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 6 30 June 2021 The desktop FRAs in Table 3-2 above have resulted in 1,258 substations being identified as Moderate risk and in need of an on-site FRA. The full breakdown of on-site FRAs required is shown in Table 5-1 below. Additional questions have been added to the routine substation inspection scripts to identify fire risk factors at all substations which will allow validation of the desktop FRAs or will identify where an onsite FRA is required. The on-site and desk-top FRAs identify the fire risk posed by the substation and the on-site FRAs also identify any remedial works to mitigate the identified risks thus ensuring we bring the risk to an ALARP (As Low As Reasonably Practical) condition. Experience of enhancements ensuing from FRAs is that these works include installation of fire resistant doors in place of timber doors, sealing of wall penetrations (i.e. where cables or services go through walls) and improvement to the fire protection of ceilings. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 7 30 June 2021 4 Optioneering A summary of options are given in Table 4-1 with further detail in sections 4.1 to 4.4. Options 2 to 4 differ in their approach to the FRA plan (desk-top, on-site, or a planned mix of both). All these three options include the requirements for remedial work if identified by the FRA. As this is a safety programme to bring all substations to an ALARP level of fire risk, we are planning to complete all remedial work identified from FRAs by the end of RIIO-ED2. Table 4-1 Summary of Options Option Description Advantages Disadvantages 1. Do nothing. Nil cost. We will not have discharged our duty under the Regulatory Reform (Fire Safety) Order 2005 to carry out general fire safety precautions for all our premises. 2. On-site FRA at all substations. Enables a site-specific risk assessment to be completed for each substation with Complete remedial work appropriate remedial works identified. identified and implemented for each as appropriate. Higher cost than a targeted survey and takes longer to complete. Mix of Desk-top and on-site assessment dependent on Risk level. Does not enable a detailed individual site assessment to be made at those sites subject to desktop assessment. Much of the effort would be spent at sites which could be adequately assessed by a Achieves compliance with the desktop survey as being lower regulations. risk. 3. Complete remedial work identified. Focuses effort and resources to those substations more likely to be higher risk. Less expensive than on-site fire risk assessments at all substations and more costeffective. Achieves compliance with the regulations. 4. Desk-top FRA at all sites. Lower cost. Complete remedial work identified. Achieves a level of compliance with the regulations. The complexity some of our installations means that they are non-standard and sitespecific conditions requiring remediation may not be identified. Compliance with the regulation may not occur. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 8 30 June 2021 4.1 Option 1 – Do nothing Failure to carry out FRAs at our substations and implement any remedial work identified will leave us in breach of the Regulatory Reform (Fire Safety) Order 2005. For this reason, this option is discounted. 4.2 Option 2 – On-site FRA at all substation plus remedial work where identified This option enables a site-specific FRA to be carried out at each substation. Following this, any remedial work identified would be carried out. However, analysis of substation location and the nature of their construction shows that over 75% are likely to be lower risk. Carrying out site-specific inspections at all sites will divert resources from sites likely to be higher risk and make it more difficult to carry out assessments and remediation in a timely manner. This approach will be higher cost than a targeted approach supported by desktop assessments, whilst not offering a material improvement in fire safety. For these reasons, this option is discounted. 4.3 Option 3 – Mix of Desktop and On-site FRA dependent on risk-level Option 3 provides for a desktop FRA of substations that can be identified as being likely to be lower risk and focussing of on-site assessments to those sites more likely to be higher risk. It includes the requirements to complete any remedial work identified. By identifying those substations most likely to be at lower risk we can focus our resources on higher risk sites. Detailed on-site FRAs will identify remedial work required to ensure that the fire risk is as low as reasonably practicable and improve safety for our staff and customers. Where desktop FRAs indicate that the fire risk is too high, we will target those sites for an on-site assessment. Additional questions in our routine substation inspection scripts will allow us to continually validate the results of the desktop FRA and identify any changes in and around the substation which cause its FRA to change. This option will allow us to carry out on-site FRAs at the highest risk sites and to implement remedial measures identified in order to bring the fire risk as low as reasonably practicable. This is our preferred option. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 9 30 June 2021 4.4 Option 4 - Carry out a desktop FRA of all substations In this option, we would carry out all FRAs as a desktop exercise. Whilst a lot of our sites are of a standard design, this does not apply to higher voltage substations, larger distribution substations and sites located either adjacent to or within third party buildings. In these cases, their complexity and potential use of non-standard materials can only be identified after an on-site inspection and FRA. Adoption of a theoretical total desktop study has the potential to miss key aspects of a building’s construction. This would produce a risk assessment that is inadequate and hence would not comply with the regulations. This option has been discounted. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 10 30 June 2021 5 Analysis and Cost Section 4 (Optioneering) recommended Option 3 which proposed performing on-site surveys at Grid and Primary substations and those located in third party/larger buildings. Desktop FRAs would be used at outdoor distribution sites or those in standalone buildings to assess the fire risk and indicate whether there would be an additional need for an on-site survey. Analysis of 750 sites where fire risk assessments have been carried out since the start of RIIO-ED1 has shown that 345 (46%) require work to reduce their fire risk. The average cost of this work is £2,927 per substation. The differences in shape, size and construction of sites, means that we have estimated our RIIO-ED2 programme based on the unit cost from the work completed and planned in RIIO-ED1. Not all sites identified for remediation work will be completed during RIIO-ED1 and have therefore been added to the ED2 submission. The data from these substation surveys has been used to identify the scale and cost of work required in RIIO-ED2 to bring the risk of injury from fire at substations to as low as reasonably practicable. The total numbers of substations that required on-site FRA are shown in Table 5-1 below. This is the total volume of survey work which we began in RIIO-ED1. Table 5-1 Substation inspection categories On-site inspections required – substation category Number Moderate risk (from desktop assessment) 1,258 Distribution Complex - Large indoor > 40m2 1,182 Buried 50 Grid & Primary Substations 561 Part of a larger building 2,435 Total 5,486 We have used the percentage of the number of sites requiring remediation work compared to the total number of sites assessed during RIIO-ED1 to be an indication of the number of sites requiring remediation work in RIIO-ED2. We therefore forecast that 46 %, or 2,524 sites, require enhancements after an FRA. We are carrying out enhancements at 208 of these sites during RIIO-ED1 leaving 2,316 sites to address during RIIOED2 & ED3. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 11 30 June 2021 A proposed cost and delivery profile is shown in Table 5-2. Table 5-2 Fire Risk Assessment enhancement cost delivery profile Year RIIO-ED1 2023/24 Cost (£m) 0.6 Totals (£m) ED1: 0.6 Number of sites to remediate 208 Total number of sites (ED1/ED2) ED1: 208 0.9 2024/25 2025/26 0.9 0.9 2026/27 2027/28 ED3 0.9 0.9 2.8 298 298 825 ED2: 4.4 299 298 298 ED2: 1,491 Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 12 30 June 2021 6 Deliverability and Risk In common with all civil works carried out at our substations, this enhancement work will be delivered by our network partners who will resource as required to accommodate this programme. We have commenced this programme during RIIO-ED1 by carrying out enhancements at 208 sites. This will leave 2,316 sites requiring enhancement at an estimated cost of £6.77m (see Table 5-2 above). In a small number of the locations where we have a substation in a third-party building, the necessary enhancements may involve the co-operation of a building owner to give us approval to do work or to carry out works for which they are responsible. As we would be reliant on a third party for approval or completion of these works, there is a risk that they will not be carried out as promptly as desired. Where this occurs, we will deal with each on a case by case basis with due regard to the level of fire risk and the legal position regarding our substation location. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 13 30 June 2021 7 Conclusion We have a responsibility under the Regulatory Reform (Fire Safety) Order 2005 to carry out general fire safety precautions for all our premises. By carrying out desktop FRAs of substations most likely to be at lower risk and undertaking on-site FRAs at higher risk sites we can target our resources for assessment where they will give best benefit. The outcome of the FRAs will indicate the remediation required to meet regulatory standards. Providing the programme of assessment, and the ensuing delivery of enhancements identified from these FRAs, will enable us to comply with legislation and improve safety for our staff and customers in the most cost-effective manner. Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 14 30 June 2021 Appendix A - ENA Engineering Recommendation S39 ENA_ER_S39_Issue 1_(2017).pdf Engineering Justification Paper Enhancements due to fire risk assessments | Ref No.: L&S EJP 7 Page 15 30 June 2021