Uploaded by Abdullah AL nairab

06 Section 6 - Bill of Quantities

advertisement
Design & Build for Fit-out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Section 6 –
Bill of Quantities
Section 6 - Bill of Quantities
Bill Nr. 1
Preliminaries
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 1/1
PRELIMINARIES
NOTES :
(1) The work shall be done during day time
and night time according to CAM/ADA requirements.
(2) If CAM decides to cancel any items listed
in the Bills of Quantities, the Contractor
shall not claim any compensation related to
the works not executed. The amount for items cancelled
will be deducted from the final Contract Sum.
(3) Contractor shall provide the quantities
according to the design, international and
Macau regulations and site requirements,
and the unit prices for reference. The
contract is based on lump sum fixed price.
(4) The lump sum amount is the Contract
Price, in which the Contractor is deemed to have included
all costs, expenses and profit necessary for the Contractor's
proper execution and completion of all the designs, works,
services and others in accordance with the Contract.
(5) No Change in the quantities described in the Bills of
Quantities proposed in the Contractor's Proposal shall entitle
the Contractor to any additional payment, provided that such
change is found necessary for the Contractor's proper execution
and completion of all the designs, works, services and others in
accordance with the Contract.
(6) The above items (1) to (5) apply to the
whole Bills of Quantities
TOTAL - Bill Nr. 1
Carried to Collection MOP$
- BQ.1/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 1
Preliminaries
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 1/2
PRELIMINARIES
A
Provision of temporary hoardings and/or
covered walkway with temporary lighting
where necessary, to meet the requirements
of CAM and the Airport Operator; maintain
and remove away from site upon completion
of the works or as instructed by CAM.
Any existing hoarding should be
dismantled, kept in good conditions and
returned to CAM
item
B
Provision of project signboards
item
C
Environmental mitigation measures
item
D
Safety precautions
item
E
Site cleaning
item
F
Contractor's workshops, offices and storage sheds
item
G
Site survey
item
H
Extra care required to carry out works in the interception area
between Extension Building and Macau International Airport Terminal
item
TOTAL - Bill Nr. 1
Carried to Collection MOP$
- BQ.1/2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 1
Preliminaries
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 1/3
PRELIMINARIES
A
Contractor's all Risks insurance
item
B
Employees' compensation insurance
item
C
Professional indemnity insurance for
professional suppliers and sub-contractors
to meet the requirements of CAM
item
Professional indemnity insurance for
designers and/or design checkers to meet
the requirements of CAM
item
E
Plant and tools
item
F
Temporary water supply
item
G
Temporary lighting and power
item
H
Temporary site services
item
J
Temporary site office including all necessary equipments and facilities
item
K
Application for permit(s) as required by CAM or any other
Macau statutory bodies/government department(s)
item
Working platform and scaffolding
item
D
L
M O&M manual, as-built documents, T&C report, labeling
item
N
Site security
item
O
Site project management
item
P
Site debris clearance
item
Q
BIM model
item
R
Traffic and passengers diversion works
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 1
Carried to Collection MOP$
- BQ.1/3 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 1
Preliminaries
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Amount (MOP$)
Bill Nr. 1
PRELIMINARIES
COLLECTION
Page Nr. BQ.1/1
......................
Page Nr. BQ.1/2
......................
Page Nr. BQ.1/3
......................
TOTAL - Bill Nr. 1
Carried to General Summary MOP$
- BQ.1/4 -
Section 6 - Bill of Quantities
Bill Nr. 2
Design of the Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 2/1
DESIGN OF THE WORKS
NOTES :
The Contractor's Designer shall prepare
all design in full compliance with all
relevant statuory requirements and the
specifications, Design Requirement Brief and
the tender document and drawings. He shall
prepare and submit all relevant design
reports, calculation and drawings as
necessary in good quality to the client for consent.
A
Design of Demolition works
item
B
Design of Architectural works
item
C
Design of Plumbing & Drainage system
item
D
Design of Fire Services system
item
E
Design of Electrical Services system
item
F
Design of MVAC System
item
G
Design of ELV Systems and Airport Systems
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 2
Carried to Collection MOP$
- BQ.2/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 2
Design of the Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 2/2
DESIGN OF THE WORKS
A
Contractor's Other Costs
Contractor's other costs for any item
of work or obligation which is
necessary for the completion of the
Design of the Works as required by the
Contract, but not separately itemised
elsewhere in this Bill Nr. 2
(Bidder to provide detailed breakdown of
the Contractor's Other Costs below)
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 2
Carried to Collection MOP$
- BQ.2/2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 2
Design of the Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Amount (MOP$)
Bill Nr. 2
DESIGN OF THE WORKS
COLLECTION
Page Nr. BQ.2/1
......................
Page Nr. BQ.2/2
......................
TOTAL - Bill Nr. 2
Carried to General Summary MOP$
- BQ.2/3 -
Section 6 - Bill of Quantities
Bill Nr. 3
Demolition and A&A Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 3
DEMOLITION AND A&A WORKS
Demolition of existing part of Passenger
Terminal Building adjacent to the new
extension. The cut-off line of the demolition
work shall suit the existing site conditions and
the necessary alterations of existing PTB for
integrating the new extension and the existing PTB.
The Contractor shall provide temporary finish linings,
covers, flashing plate, etc. for the cut-off line to
match the existing finishes of the PTB to the
satisfaction of CAM. Provide a temporary
weather proof external enclosure during
the construction work. Demolition
of existing E&M services to suit
existing site conditions and the design
of the extension shall be carried out
without interruption to the normal
operation of the passenger terminal.
Disposal of all construction
waste and debris.
A
Room 11065 (Departure Level Canteen)
Including all necessary demolition works and making good,
builder's works for construction of service corridor,
additional access door and access control system,
and all necessary modifications to building services works.
item
B
Room 12061 (Mezzanine Level Access Card Office)
Including all necessary demolition works and making good,
builder's works for modification and extension of office and counter,
additional building services for extension of office,
and all necessary modifications to building services works.
item
C
Diversion of existing E&M services for carrying out
demolition works and reinstatement if necessary
item
Necessary reinstatment works
item
D
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 3
Carried to General Summary MOP$
- BQ.3/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/1
ARCHITECTURAL WORKS
According to the approved drawings, furnish and
install all building materials for the following area,
including all partition brick walls shown in the drawings.
No matter mentioned or not, the corresponding
items and the necessary materials, fittings, accessories,
works, etc., should also be included to completely
execute the detailed works:
A
B
C
Room No.G-001 area and the corresponding items are as follows:
Floor:Carpet(F4), 30mm thk. marble(F6);
Skirting:500mm(H) x 1.2mm #316 s.s. plate skirting
(same as existing PTB)(S3);Wall:Stone paint
up to false ceiling(W4);Ceiling:Baffle ceiling(C9);Remarks:
Dia. 50mm s.s. bumper rail fix on the skirting
/ floor (same as existing PTB)(R3);
Provide Seating system(R12);
Design layout and provide planters (Qty. refer to existing PTB)
(refer to appendix 2)(R13);
Design layout and provide Trash bin (Qty. refer to existing PTB)
(R14);Design layout and provide Boarding gate counter
(refer to appendix 3)(R15);Provide carpet (refer to appendix 7)
(R27); Revise / updated existing ceiling hung signage at
NEW PTB public area(R28);Design and provise all rooms
signage(R29)。 (refer to appendix 8)
lot
Room No.G-002 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6);Skirting:
500mm(H) x 1.2mm #316 s.s. plate skirting (same as existing PTB)
(S3);Wall:Stone paint up to false ceiling(W4);
Ceiling:Baffle ceiling(C9);Remarks:Dia. 50mm s.s. bumper
rail fix on the skirting / floor (same as existing PTB)(R3);
Provide immigration counter include divide s.s. handrail
(same as existing)(R16);Revise / updated existing ceiling
hung signage at NEW PTB public area(R28);Design and
provise all rooms signage(R29)。
lot
Room No.G-003 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8);Wall:Emulsion paint on
6mm thk. internal plaster up to false ceiling / full height (W3);
Ceiling:Emulsion paint on 6mm thk. Internal plaster ceiling
(C2); Remarks:Design and provise all rooms signage
(R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/2
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.G-004 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:20mm thk marble
on wall plaster with tile adhesive up to false ceiling(W2)
,Ceiling: Aluminium ceiling strip(C5);Remarks:
Design refer to arrival landside north washroom
(refer to appendix 4)(R17);Design and provise all
rooms signage(R29)。
lot
Room No.G-005 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on
6mm thk. internal lime up to false ceiling / full height(W3)
,Ceiling: 600x600mm acoustic ceiling tile with exposed grid
(C1);Remarks: Interior design and provide all furniture
(R11);Design and provise all rooms signage(R29)。
lot
Room No.G-006 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on
6mm thk. internal lime up to false ceiling / full height(W3)
,Ceiling: 600x600mm acoustic ceiling tile with exposed
grid(C1),Remarks:Design and provise
all rooms signage(R29)。
lot
Room No.G-007 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3)
,Ceiling: 600x600mm acoustic ceiling tile with exposed grid
(C1), Remarks:Design and provise all rooms signage(R29)。
lot
Room No.G-008 area and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor screed(F2)
;Wall:Ceramic tile on wall plaster with tile adhesive up to
false ceiling (overall 25mm thk.)(W1),Ceiling:
Aluminium ceiling strip(C5),Remarks:Design and provise all
rooms signage(R29);Design layout and provide all sanitary ware
(Refer to BOH washroom at existing PTB )(R30)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/3
ARCHITECTURAL WORKS
A
B
C
Room No.G-009 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks: Design and provise all rooms signage(R29)。
Room No.G-010 area and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor screed
(F2),Skirting:300mmx100mm(H) homogeneous tile skirting(S2)
,Wall:Emulsion paint on 6mm thk. internal plaster up to flase
ceiling / full height(W3),Ceiling: 600x600mm acoustic ceiling
tile with exposed grid(C1),Remarks:Interior design and
provide all furniture(R11);Design and provise all rooms signage
(R29)。
Room No.M-001area and the corresponding items are as follows:
Floor:Carpet(F4);Wall:Wood veneer finsih with acrylic
letter with back LED and LED light strip(W7),
Ceiling:Wood ceiling strip(C6),Remarks:Interior design
refer to sterile corridor design proposal (refer to appendix 5)(R19)
,Design and provide the carpet at the loading bridge(R24)
;Revise / updated existing ceiling hung signage at NEW PTB
public area(R28);Design and provise all rooms
signage(R29)。
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /3 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/4
ARCHITECTURAL WORKS
A
B
C
D
Room No.1-001 area and the corresponding items are as follows:
Floor:Carpet(F4), 30mm thk. marble(F6);Skirting:
500mm(H) x 1.2mm #316 s.s. plate skirting (same as existing PTB)
(S3);Wall:Stone paint up to false ceiling(W4);Ceiling:
Baffle ceiling(C9);Remarks: Dia. 50mm s.s. bumper rail fix on
the skirting / floor (same as existing PTB)(R3);
Provide Seating system (R12);
Design layout and provide planters (Qty. refer to existing PTB)
(refer to appendix 2)(R13);Design layout and provide
Trash bin (Qty. refer to existing PTB)(R14);
Design layout and provide Boarding gate counter
(refer to appendix 3)(R15);Design and provide filming wall
artwork on curtain wall(Option) (refer to appendix 6)(R23);
Provide s.s. bumper rail at escalator (same as existing PTB)(R25)
;Design and provide marble floor in lift car (lift no. S1, P13, P14)
(R26);Provide carpet (refer to appendix 7)(R27);
Revise / updated existing ceiling hung signage at NEW PTB
public area(R28);Design and provise all rooms
signage(R29)。 (refer to appendix 8)
lot
Room No.1-002 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8);Wall: Emulsion paint on
6mm thk. internal plaster up to false ceiling / full height(W3);
Ceiling:Emulsion paint on 6mm thk. internal plaster(C2),
Remarks:Design and provise all rooms signage(R29)。
lot
Room No.1-003 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:20mm thk marble on
wall plaster with tile adhesive up to false ceiling(W2),
Ceiling: Aluminium ceiling strip(C5);Remarks:High level
interior design, include 2 person sofa, console, mirror and wash
basin(R21);Design and provise all rooms signage(R29)。
lot
Room No.1-004 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:20mm thk marble on wall
plaster with tile adhesive up to false ceiling(W2),Ceiling:
Aluminium ceiling strip(C5);Remarks:Design refer to arrival
landside north washroom (refer to appendix 4)(R17);Design
and provise all rooms signage(R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /4 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/5
ARCHITECTURAL WORKS
A
B
C
Room No.1-005 area and the corresponding items are as follows:
Floor:Carpet(F4),30mm thk. marble(F6);Skirting:
500mm(H) x 1.2mm #316 s.s. plate skirting (same as existing PTB)
(S3);Wall:Stone paint up to false ceiling(W4);Ceiling:
Baffle ceiling(C9);Remarks:Dia. 50mm s.s. bumper rail fix
on the skirting / floor (same as existing PTB)(R3);
Design layout and provide planters (Qty. refer to existing PTB)
(refer to appendix 2)(R13);Design layout and provide
Trash bin (Qty. refer to existing PTB)(R14);Design and
provide marble floor in lift car (lift no. S1, P13, P14)(R26);
Revise / updated existing ceiling hung signage at NEW PTB
public area(R28);Design and provise all rooms signage
(R29)。
Room No.1-006 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:Stone paint up to false
ceiling(W4);Ceiling:Emulsion paint on 6mm thk. internal plaster
(C2),Remarks:Design and provise all rooms signage
(R29)。
Room No.1-007 area and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor
screed(F2),Wall:Ceramic tile on wall plaster with tile adhesive
up to false ceiling (overall 25mm thk.)(W1),Ceiling:
Existing ceiling(C4),Remarks:Design and provise all rooms
signage(R29),Design layout and provide all sanitary ware
(Refer to BOH washroom at existing PTB )(R30)。
D
Room No.1-008 area and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor screed
(F2),Wall:Ceramic tile on wall plaster with tile adhesive up to
false ceiling (overall 25mm thk.)(W1),Ceiling:Alminium
ceiling strip(C5),Remarks:Design and provise all rooms
signage(R29),Design layout and provide all sanitary ware
(Refer to BOH washroom at existing PTB )(R30)。
E
Room No.1-009 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),
Wall:Emulsion paint on 6mm thk. internal lime up to false
ceiling / full height(W3),Ceiling: 200x200mm hanging
aluminium grid ceiling(C8),Remarks:Dia. 50mm s.s. bumper
rail fix on the skirting / floor (same as existing PTB)(R3);
Design and provise all rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /5 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/6
ARCHITECTURAL WORKS
A
B
C
D
E
F
Room No.1-010 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 200x200mm hanging aluminium grid ceiling(C8),
Remarks:Dia. 50mm s.s. bumper rail fix on the skirting / floor
(same as existing PTB)(R3);Design and provise all
rooms signage(R29)。
lot
Room No.1-011 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on
6mm thk. internal lime up to false ceiling / full height(W3),
Ceiling: 200x200mm hanging aluminium grid ceiling(C8),
Remarks:Dia. 50mm s.s. bumper rail fix on the skirting / floor
(same as existing PTB)(R3);Design and
provise all rooms signage(R29)。
lot
Room No.1-012 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8),Skirting: Existing finish
(S5),Wall: Existing finish(W5),Ceiling:Existing ceiling
(C4),Remarks:Design and provise all rooms signage(R29)。
lot
Room No.1-013 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8),Skirting: Existing finish
(S5),Wall: Existing finish(W5),Ceiling:Existing ceiling
(C4),Remarks:Design and provise all rooms signage(R29)。
lot
Room No.1-014 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),
Wall:Emulsion paint on 6mm thk. internal lime up to false ceiling
/ full height(W3),Ceiling: 600x600mm acoustic ceiling tile
with exposed grid(C1),Remarks:Design loose furniture
layout only(R9);Design layout and provide reception counter
(R18);Design and provise all rooms signage(R29)。
lot
Room No.1-015 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:Emulsion
paint on 6mm thk. internal lime up to false ceiling / full height
(W3),Ceiling: 600x600mm acoustic ceiling tile with
exposed grid(C1),Remarks:Design loose furniture layout
only(R9);Design layout and provide reception counter
(R18);Design and provise all rooms signage(R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /6 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/7
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.1-017 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),
Wall:Emulsion paint on 6mm thk. internal lime up to false
ceiling / full height(W3),Ceiling: 600x600mm acoustic
ceiling tile with exposed grid(C1),Remarks:Design
loose furniture layout only(R9);Design and provise all rooms
signage(R29)。
lot
Room No.1-018 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:Emulsion paint
on 6mm thk. internal lime up to false ceiling / full height(W3)
,Ceiling: 600x600mm acoustic ceiling tile with exposed grid
(C1),Remarks:Design loose furniture layout only(R9)
;Design and provise all rooms signage(R29)。
lot
Room No.1-019 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:
Emulsion paint on 6mm thk. internal lime up to false ceiling /
full height(W3),Ceiling: 600x600mm acoustic ceiling tile
with exposed grid(C1),Remarks:Design loose furniture
layout only(R9),Design layout and provide reception counter
(R18),Design and provise all rooms signage(R29)。
lot
Room No.1-020 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on
6mm thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(C1)
,Remarks:Design loose furniture layout only(R9)
,Design layout and provide reception counter(R18)
,Design and provise all rooms signage(R29)。
lot
Room No.1-021 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),
Wall:Emulsion paint on 6mm thk. internal lime up to false ceiling
/ full height(W3),Ceiling: 600x600mm acoustic ceiling tile
with exposed grid(C1),Remarks:Design loose
furniture layout only(R9),Design and provise
all rooms signage(R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /7 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/8
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.1-022 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),
Skirting:100mm (H) x 15mm thk. painted hardwood skirting
(S6),Wall:Stone paint up to false ceiling(W4),
Ceiling: Baffle ceiling(C9),Remarks:Interior
design and provide all furniture(R11);Design layout and
provide reception counter(R18);Design and provise
all rooms signage(R29)。
Room No.1-023 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Acoustic panels combines the
natural appearance of wood with unique features for high quality
acoustics(W8),Ceiling:Emulsion paint on gypsum board
false ceiling(C3),Remarks:Interior design and provide all
furniture(R11);Design and provise all rooms signage(
R29)。
Room No.1-024 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.1-025 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.1-026 area and the corresponding items are as follows:
Floor: Epoxy paint on power floated concrete surface(F7),
Skirting:300mmx100mm(H) homogeneous tile skirting(S2),
Wall: Emulsion paint on 6mm thk. internal plaster up to false
ceiling / full height(W3),Ceiling: 600x600mm acoustic
ceiling tile with exposed grid(C1),Remarks:Design and
provise all rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /8 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/9
ARCHITECTURAL WORKS
A
B
C
D
Room No.1-027 area and the corresponding items are as follows:
Floor:600x600mm high pressure laminated raised floor(F5),
Wall:Emulsion paint on 6mm thk. internal lime up to false
ceiling / full height(W3),Ceiling:Emulsion paint on 6mm
thk. internal plaster(C2),Remarks:Design and provise all
rooms signage(R29)。
lot
Room No.1-028 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:Emulsion
paint on 6mm thk. internal lime up to false ceiling / full height
(W3),Ceiling: 600x600mm acoustic ceiling tile with
exposed grid(C1),Remarks:Design loose furniture layout
only(R9);Design and provise all rooms signage(R29)。
lot
Room No.2-001 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8),Wall: Existing finish(
W5),Ceiling:Existing ceiling(C4),Remarks:Design and
provise all rooms signage(R29)。
lot
Room No.2-002 area and the corresponding items are as follows:
Floor:Carpet(F4),30mm thk. marble(F6),Skirting:
500mm(H) x 1.2mm #316 s.s. plate skirting (same as existing
PTB)(S3);Wall:Stone paint up to false ceiling(W4);Ceiling:
Baffle ceiling(C9);Remarks: Dia. 50mm s.s. bumper rail fix on the
skirting / floor (same as existing PTB)(R3);Provide Seating
system(R12);Design layout and provide planters (Qty. refer to
existing PTB) (refer to appendix 2)(R13);Design layout and
provide Trash bin (Qty. refer to existing PTB)(R14);Design
layout and provide Boarding gate counter (refer to appendix 3)(
R15);Design and provide filming wall artwork on curtain
wall(Option) (refer to appendix 6)(R23);Provide s.s. bumper rail
at escalator (same as existing PTB)(R25);Provide carpet (refer to
appendix 7)(R27);Revise / updated existing ceiling hung signage
at NEW PTB public area (R28);Design and provise all rooms
signage(R29)。 (refer to appendix 8)
lot
E
Room No.2-003 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8);Wall:Emulsion paint on
6mm thk. internal plaster up to false ceiling / full height(W3);
Ceiling:Emulsion paint on 6mm thk. internal plaster(C2),
Remarks:Design and provise all rooms signage(R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /9 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/10
ARCHITECTURAL WORKS
A
B
C
Room No.2-004 area and the corresponding items are as follows:
Floor:Carpet(F4),30mm thk. marble(F6);Skirting:
500mm(H) x 1.2mm #316 s.s. plate skirting (same as existing
PTB)(S3);Wall:Stone paint up to false ceiling(W4);Ceiling:
Baffle ceiling(C9);Remarks:Dia. 50mm s.s. bumper rail fix on
the skirting / floor (same as existing PTB)(R3);Design layout
and provide planters (Qty. refer to existing PTB) (refer to appendix
2)(R13);Design layout and provide Trash bin (Qty. refer to
existing PTB)(R14);Design and provide marble floor in lift
car (lift no. S1, P13,P14)(R26);Revise / updated existing
ceiling hung signage at NEW PTB public area(R28);Design
and provise all rooms signage(R29)。
Room No.2-005 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:Stone paint up to false
ceiling(W4);Ceiling:Emulsion paint on 6mm thk. internal plaster
(C2),Remarks:Design and provise all rooms signage(R29)。
lot
lot
Room No.2-006 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:20mm thk marble on
wall plaster with tile adhesive up to false ceiling(W2),
Ceiling: Aluminium ceiling strip(C5);Remarks:Design
refer to arrival landside north washroom (refer to appendix 4)(
R17);Design and provise all rooms signage(R29)。
lot
D
Room No.2-007 area and the corresponding items are as follows:
Floor:30mm thk. marble(F6);Skirting:500mm(H) x 1.2mm
#316 s.s. plate skirting (same as existing PTB)(S3);Wall:Stone
paint up to false ceiling(W4);Ceiling:Aluminium ceiling strip
(C5);Remarks:Interior design and provide all furniture(
R11);Design layout and provide Trash bin (Qty. refer to
existing PTB)(R14);Design and provise all rooms signage(
R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /10 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/11
ARCHITECTURAL WORKS
A
B
C
Room No.2-008 area and the corresponding items are as
follows:Floor:300x300x8mm non-slip homogeneous tile on
floor screed(F2),Wall:Ceramic tile on wall plaster with tile
adhesive up to false ceiling (overall 25mm thk.)(W1),
Ceiling:Aluminium ceiling strip(C5),Remarks:Design and
provise all rooms signage(R29);Design layout and provide all
sanitary ware (Refer to BOH washroom at existing PTB )(
R30)。
Room No.2-009 area and the corresponding items are as
follows:Floor:300x300x8mm non-slip homogeneous tile on
floor screed(F2),Wall:Ceramic tile on wall plaster with tile
adhesive up to false ceiling (overall 25mm thk.)(W1),
Ceiling:Aluminium ceiling strip(C5),Remarks:Design and
provise all rooms signage(R29);Design layout and provide all
sanitary ware (Refer to BOH washroom at existing PTB )(
R30)。
lot
lot
Room No.2-010 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 200x200mm hanging aluminium grid ceiling(C8),
Remarks:Dia. 50mm s.s. bumper rail fix on the skirting / floor
(same as existing PTB)(R3);Design and provise all rooms
signage(R29)。
lot
D
E
Room No.2-011 area and the corresponding items are as
follows:Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:Emulsion
paint on 6mm thk. internal lime up to false ceiling / full height(
W3),Ceiling: 200x200mm hanging aluminium grid ceiling(
C8),Remarks:Dia. 50mm s.s. bumper rail fix on the skirting /
floor (same as existing PTB)(R3);Design and provise all
rooms signage(R29)。
Room No.2-012 area and the corresponding items are as follows:
Floor: 600x600mm high pressure laminated raised floor(
F5);Wall:Emulsion paint on 6mm thk. internal lime up to
false ceiling / full height(W3);Ceiling: 600x600mm
acoustic ceiling tile with exposed grid(C1),Remarks:Design
loose furniture layout only(R9);Design and provise all rooms
signage(R29)。
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /11 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/12
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.2-013 area and the corresponding items are as follows:
Floor: 600x600mm high pressure laminated raised floor(
F5);Wall:Emulsion paint on 6mm thk. internal lime up to
false ceiling / full height(W3);Ceiling: 600x600mm
acoustic ceiling tile with exposed grid(C1),Remarks:Design
loose furniture layout only(R9);Design and provise all rooms
signage(R29)。
Room No.2-014 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.2-015 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.2-016 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1)Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.2-017 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks: Interior design and provide all furniture(
R11);Interior design layout(R22);Design and provise all
rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /12 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/13
ARCHITECTURAL WORKS
A
B
C
D
Room No.2-018 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.2-019 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.2-020 area and the corresponding items are as
follows:Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:Emulsion
paint on 6mm thk. internal lime up to false ceiling / full height(
W3),Ceiling: 600x600mm acoustic ceiling tile with exposed
grid(C1),Remarks:Design loose furniture layout only(
R9),Design and provise all rooms signage(R29)。
lot
lot
lot
Room No.2-021 area and the corresponding items are as
follows:Floor:3.0mm thk, vinyl tile on floor screed(F1),
Skirting:100mm (H) vinyl skirting(S1),Wall:Emulsion
paint on 6mm thk. internal lime up to false ceiling / full height(
W3),Ceiling: 600x600mm acoustic ceiling tile with exposed
grid(C1),Remarks:Design loose furniture layout only(
R9),Design and provise all rooms signage(R29)。
lot
E
Room No.2-023 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall: Acoustic panels combines the
natural appearance of wood with unique features for high quality
acoustics(W8),Ceiling:Emulsion paint on gypsum board
false ceiling(C3);Remarks:Interior design and provide all
furniture(R11);Design and provise all rooms signage(
R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /13 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/14
ARCHITECTURAL WORKS
A
B
Room No.2-024 area and the corresponding items are as follows:
Floor:3.0mm thk, vinyl tile on floor screed(F1),Skirting:
100mm (H) vinyl skirting(S1),Wall:Emulsion paint on 6mm
thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(
C1),Remarks:Design loose furniture layout only(R9);
Design and provise all rooms signage(R29)。
Room No.2-025 area and the corresponding items are as follows:Floor:3.0mm thk,
vinyl tile on floor screed(F1),Skirting:100mm (H) vinyl skirting(S1),Wall:
Emulsion paint on 6mm thk. internal lime up to false ceiling / full height(W3),
Ceiling: 600x600mm acoustic ceiling tile with exposed grid(C1),Remarks:
Design loose furniture layout only(R9);Design and provise all rooms signage(
R29)。
C
Room No.3-001 area and the corresponding items are as follows:
Floor:Cement mortar leveling(F8),Wall: Existing finish(
W5),Ceiling:Existing ceiling(C4),Remarks:Design and
provise all rooms signage(R29)。
D
Room No.3-002 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15 mm thk. painted
hardword skirting (S6);Wall:Wood veneer finish (W6);
Ceiling:Emulsion paint on gypsum board false ceiling (C3);
Remarks:Interior design and provide all furniture(R11);
Design layout and provide reception counter(R18);Design
and provise all rooms signage(R29)。 (refer to appendix 8)
lot
lot
lot
lot
lot
E
Room No.3-003 area and the corresponding items are as follows:
Floor: 30mm thk. marble(F6),Wall:Stone paint up to false
ceiling(W4);Ceiling:Emulsion paint on 6mm thk. internal
plaster(C2),Remarks:Design and provise all rooms signage
(R29)。
lot
F
Room No.3-004 area and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor
screed(F2),Wall:Ceramic tile on wall plaster with tile adhesive
up to false ceiling (overall 25mm thk.)(W1),Ceiling:
Aluminium ceiling strip(C5),Remarks:Design and provise
all rooms signage(R29);Design layout and provide all sanitary
ware (Refer to BOH washroom at existing PTB )(R30)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /14 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/15
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-005 and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor
screed(F2),Wall:Ceramic tile on wall plaster with tile adhesive
up to false ceiling (overall 25mm thk.)(W1),Ceiling:
Aluminium ceiling strip(C5),Remarks:Design and provise
all rooms signage(R29);Design layout and provide all sanitary
ware (Refer to BOH washroom at existing PTB )(R30)。
lot
Room No.3-006 area and the corresponding items are as follows:
Floor:300x300x8mm non-slip homogeneous tile on floor
screed(F2),Wall:Ceramic tile on wall plaster with tile adhesive
up to false ceiling (overall 25mm thk.)(W1),Ceiling:
Aluminium ceiling strip(C5),Remarks:Design and provise
all rooms signage(R29);Design layout and provide all sanitary
ware (Refer to BOH washroom at existing PTB )(R30)。
lot
Room No.3-007 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design and provise all rooms signage(R29)。
lot
Room No.3-008 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design and provise all rooms signage(R29)。
lot
Room No.3-009 area and the corresponding items are as
follows:Floor:Carpet(F4),Skirting:100 mm (H) x 15mm thk.
painted hardwood skirting (S6);Wall:Wood veneer
finish(W6);Ceiling:Emulsion paint on gypsum board false
ceiling(C3);Remarks:Interior design and provide all furniture
(R11),Design layout and provide reception counter(
R18);Design and provise all rooms signage(R29)。
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /15 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/16
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-010 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6);Wall:Emulsion paint on 6mm thk.
internal plaster up to false ceiling / full height (W3);Ceiling:
600x600mm acoustic ceiling tile with exposed grid (C1);
Remarks:Design loose furniture layout only(R9);Design and
provise all rooms signage(R29)。
Room No.3-011 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Wood veneer finish(W6),
Ceiling:Emulsion paint on gypsum board false ceiling(C3);
Remarks:Interior design and provide all furniture(R11);
Design and provise all rooms signage(R29)。(refer to appendix
9)
Room No.3-012 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Wood veneer finish(W6),
Ceiling:Emulsion paint on gypsum board false ceiling(C3);
Remarks:Interior design and provide all furniture(R11),
Design and provise all rooms signage(R29)。(refer to appendix
9)
Room No.3-013 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Wood veneer finish(W6),
Ceiling:Emulsion paint on gypsum board false ceiling(C3);
Remarks:Interior design and provide all furniture(R11),
Design and provise all rooms signage(R29)。(refer to appendix
9)
Room No.3-014 area and the corresponding items are as
follows:Floor:300x300x8mm non-slip homogeneous tile on
floor screed(F2),Skirting:300mmx100mm(H) homogeneous tile
skirting(S2),Wall:Emulsion paint on 6mm thk. internal lime
up to false ceiling / full height(W3),Ceiling: 600x600mm
acoustic ceiling tile with exposed grid(C1),Remarks:Design
layout and provide cabinet with wash basin(R7),Design and
provise all rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /16 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/17
ARCHITECTURAL WORKS
A
B
C
D
Room No.3-015 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Wood veneer finish(W6),
Ceiling:Emulsion paint on gypsum board false ceiling(C3);
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-016 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Wood veneer finish(W6),
Ceiling:Emulsion paint on gypsum board false ceiling(C3);
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-017 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1);
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-018 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
E
Room No.3-019 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting:100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Wood veneer finish(W6),
Ceiling:Emulsion paint on gypsum board false ceiling(C3);
Remarks:Interior design and provide all furniture(R11),
Design and provise all rooms signage(R29)。(refer to appendix
9)
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /17 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/18
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-020 area and the corresponding items are as follows:
Floor:Carpet (F4),Skirting:100 mm (H) x 15mm thk. painted
hardwood skirting(S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-021 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-022 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-023 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-024 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /18 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/19
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-025 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-026 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
Room No.3-027 area and the corresponding items are as follows:
Floor:Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk.
painted hardwood skirting (S6),Wall:Wood veneer finish(
W6),Ceiling:Emulsion paint on gypsum board false ceiling(
C3);Remarks:Design loose furniture layout only(R9),
Design and provise all rooms signage(R29)。
lot
Room No.3-028 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-029 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /19 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/20
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-030 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9);Sound
isolation requirement(R20),Design and provise all rooms
signage(R29)。
Room No.3-031 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9);Sound
isolation requirement(R20),Design and provise all rooms
signage(R29)。
Room No.3-032 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9);Sound
isolation requirement(R20),Design and provise all rooms
signage(R29)。
Room No.3-033 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9);Sound
isolation requirement(R20),Design and provise all rooms
signage(R29)。
Room No.3-034 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9);Sound
isolation requirement(R20),Design and provise all rooms
signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /20 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/21
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-035 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-036 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-037 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-038 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-039 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /21 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/22
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-040 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-041 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-042 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-043 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-044 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /22 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/23
ARCHITECTURAL WORKS
A
B
C
D
E
Room No.3-045 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-046 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-047 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-048 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-049 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
lot
lot
lot
lot
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /23 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 4/24
ARCHITECTURAL WORKS
A
B
Room No.3-050 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
Room No.3-051 area and the corresponding items are as follows:
Floor:Carpet(F4),Skirting: 100mm (H) x 15mm thk. painted
hardwood skirting (S6),Wall:Emulsion paint on 6mm thk.
internal lime up to false ceiling / full height(W3),Ceiling:
600x600mm acoustic ceiling tile with exposed grid(C1),
Remarks:Design loose furniture layout only(R9),Design and
provise all rooms signage(R29)。
lot
lot
Construction of corridor
Construction of a corridor within the existing room 11568
on departure level using the same material and form of
construction as the existing wall
item
Maintaining stability of the remaining parts of the existing wall
during and after construction
item
Sealing any building services passing through the new
corridor wall in the same manner as the existing
building services
item
Any other items (to be inserted by the Contractor):-
TOTAL - Bill Nr. 4
Carried to Collection MOP$
- BQ.4 /24 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Bill Nr. 4
ARCHITECTURAL WORKS
COLLECTION
Page Nr. BQ.4/1
......................
Page Nr. BQ.4/2
......................
Page Nr. BQ.4/3
......................
Page Nr. BQ.4/4
......................
Page Nr. BQ.4/5
......................
Page Nr. BQ.4/6
......................
Page Nr. BQ.4/7
......................
Page Nr. BQ.4/8
......................
Page Nr. BQ.4/9
......................
Page Nr. BQ.4/10
......................
Page Nr. BQ.4/11
......................
Page Nr. BQ.4/12
......................
Page Nr. BQ.4/13
......................
Page Nr. BQ.4/14
......................
Page Nr. BQ.4/15
......................
Page Nr. BQ.4/16
......................
Page Nr. BQ.4/17
......................
Page Nr. BQ.4/18
......................
Page Nr. BQ.4/19
......................
Page Nr. BQ.4/20
......................
TOTAL - Bill Nr. 4
Carried to General Summary MOP$
- BQ.4 /25 -
Section 6 - Bill of Quantities
Bill Nr. 4
Architectural Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Bill Nr. 4
ARCHITECTURAL WORKS
COLLECTION
Page Nr. BQ.4/21
......................
Page Nr. BQ.4/22
......................
Page Nr. BQ.4/23
......................
Page Nr. BQ.4/24
......................
TOTAL - Bill Nr. 4
Carried to General Summary MOP$
- BQ.4 /26 -
Section 6 - Bill of Quantities
Bill Nr. 5
Plumbing & Drainage System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 5
PLUMBING & DRAINAGE SYSTEM
Plumbing & Drainage System
A
Supply and install the Plumbing System
item
B
Supply and install the Drainage System
item
C
Spare parts
item
D
Material and drawing preparation and submission
item
E
Statutory submission
item
F
Sample boards
item
G
Interfacing with other E&M system
item
H
Paint works for materials and equipment
item
J
Provision of 24-month operation maintenance and
breakdown service
item
Connection and interfacing with existing
system of the Passenger Terminal Building
where necessary; allow for all cost
associated with liaison with existing
maintenance contractors and the airport
operator
item
Testing and commissioning, including testing
and commissioning together with existing
system where necessary; allow for all cost
for liaison with existing maintenance
contractors and the airport operator
item
M All necessary modification and configuration item
for interface with the existing system
item
K
L
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 5
Carried to General Summary MOP$
- BQ.5/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 6
Fire Services System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 6
FIRE SERVICES SYSTEM
Fire Services System
A
Supply and install the Sprinkler System
item
B
Supply and install the Hose Reel and Fire Hydrant System
item
C
Supply and install the Fire Alarm and Detection System
item
D
Supply and install the Fire Extinguishing System
item
E
Spare parts
item
F
Material and drawing preparation and submission
item
G
Statutory submission
item
H
Sample boards
item
J
Interfacing with other E&M system
item
K
Paint works for materials and equipment
item
L
Provision of 24-month operation maintenance and
breakdown service
item
M Connection and interfacing with existing
system of the Passenger Terminal Building
where necessary; allow for all cost
associated with liaison with existing
maintenance contractors and the airport
operator
N
O
item
Testing and commissioning, including testing
and commissioning together with existing
system where necessary; allow for all cost
for liaison with existing maintenance
contractors and the airport operator
item
All necessary modification and configuration item
for interface with the existing system
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 6
Carried to General Summary MOP$
- BQ.6/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 7
Electrical Services System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 7/1
ELECTRICAL SERVICES SYSTEM
Electrical Services System
Power Supply and Distribution System
A
Approved cables
item
B
KLPE/SWAL/LSOH cables
item
C
Trunkings
item
D
LV Switchboard
item
E
Termination glands
item
F
MCB distribution boards
item
G
Busbar chamber
item
H
Insulated switches
item
J
Miniature circuit breakers
item
K
Combined MCB/RCBO units
item
L
Moulded case circuit breakers
item
M
Automatic change-over switches
item
N
Changeover switch
item
O
Isolating-switches
item
P
Motion sensors
item
Q
Daylight sensors
item
TOTAL - Bill Nr. 7
Carried to Collection MOP$
- BQ.7/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 7
Electrical Services System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 7/2
ELECTRICAL SERVICES SYSTEM
Provide General Lighting and Essential
Lighting System
A
Final circuits
item
B
Luminaries
item
C
Lighting control
item
D
Wiring accessories
item
E
Provide Essential and Emergency Lighting System
item
F
Provide Electrical Loading Estimate
item
G
UPS System Installation
item
H
Provide the complete Electrical
Earthing and Clean Earthing System Facilities
item
Provide Earthing and Lightning Protection System
J
Tinned copper tapes
item
K
Earth terminals
item
L
Test links
item
M
Earth rod electrodes
item
N
Spare parts
item
O
Material and drawing preparation and submission
item
P
Statutory submission
item
Q
Sample boards
item
R
Interfacing with other E&M system
item
S
Paint works for materials and equipment
item
T
Provision of 24-month operation maintenance and
breakdown service
item
TOTAL - Bill Nr. 7
Carried to Collection MOP$
- BQ.7/2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 7
Electrical Services System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 7/3
ELECTRICAL SERVICES SYSTEM
A
An 11kV/LV transformer unit with at least 1600kVA and associated
distribution electrical system
item
B
Electrical calculations
item
C
Connection and interfacing with existing
systems of the Passenger Terminal Building
where necessary; allow for all cost
associated with liaison with existing
maintenance contractors and the airport operator
item
Testing and commissioning, including testing
and commissioning together with existing
system where necessary; allow for all cost
for liaison with existing maintenance
contractors and the airport operator
item
All necessary modification and configuration item
for interface with the existing system
item
D
E
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 7
Carried to Collection MOP$
- BQ.7/3 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 7
Electrical Services System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Amount (MOP$)
Bill Nr. 7
ELECTRICAL SERVICES SYSTEM
COLLECTION
Page Nr. BQ.7/1
......................
Page Nr. BQ.7/2
......................
Page Nr. BQ.7/3
......................
TOTAL - Bill Nr. 7
Carried to General Summary MOP$
- BQ.7/4 -
Section 6 - Bill of Quantities
Bill Nr. 8
MVAC System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 8/1
MVAC SYSTEM
MVAC System
A
Supply and install the MVAC System
item
B
Provide Temperature and Humidity Sensors
item
C
Provide CO2 Sensors
item
D
Provide dry contact from the ventilation RI/O or I/O modules
item
E
Provide mechanical exhaust system
item
F
Provide air purifier
item
G
Spare parts
item
H
Material and drawing preparation and submission
item
J
Statutory submission
item
K
Sample boards
item
L
Interfacing with other E&M system
item
M Paint works for materials and equipment
item
N
O
P
Provision of 24-month operation maintenance and
breakdown service
item
Connection and interfacing with existing
system of the Passenger Terminal Building
where necessary; allow for all cost
associated with liaison with existing
maintenance contractors and the airport
operator
item
Testing and commissioning, including testing
and commissioning together with existing
system where necessary; allow for all cost
for liaison with existing maintenance
contractors and the airport operator
item
TOTAL - Bill Nr. 8
Carried to Collection MOP$
- BQ.8/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 8
MVAC System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 8/2
MVAC SYSTEM
A
All necessary modification and configuration item
for interface with the existing system
item
Any other items (to be inserted by theBidder):-
TOTAL - Bill Nr. 8
Carried to Collection MOP$
- BQ.8/2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 8
MVAC System
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Amount (MOP$)
Bill Nr. 8
MVAC SYSTEM
COLLECTION
Page Nr. BQ.8/1
......................
Page Nr. BQ.8/2
......................
TOTAL - Bill Nr. 8
Carried to General Summary MOP$
- BQ.8/3 -
Section 6 - Bill of Quantities
Bill Nr. 9
ELV Systems and Airport Systems
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 9/1
ELV SYSTEMS AND AIRPORT SYSTEMS
ELV Systems and Airport Systems
A
Closed Circuit Television (CCTV) System
item
B
Public Address (PA) System
item
C
Private Automated Branch Exchange (PABX) System
item
D
Access Control System (ACS)
item
E
Wireless Network (WLAN) System
item
F
Radio Communication System
item
Flight Information Display System (FIDS)
G
Displays
item
H
Remote reboot units
item
J
item
Voice and Data Cabling (VDC) System
Master Antenna Television (MATV) System
K
Allow for set top boxes
item
L
Televisions
item
M
Final circuit in coax cables
item
N
MATV distribution frames
item
O
item
Building Management System (BMS)
TOTAL - Bill Nr. 9
Carried to Collection MOP$
- BQ.9/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 9
ELV Systems and Airport Systems
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 9/2
ELV SYSTEMS AND AIRPORT SYSTEMS
A
Spare parts
item
B
Material and drawing preparation and submission
item
C
Sample boards
item
D
Paint works for materials and equipment
item
E
Provision of 24-month operation maintenance and
breakdown service
item
Connection and interfacing with existing
system of the Passenger Terminal Building
where necessary; allow for all cost
associated with liaison with existing
maintenance contractors and the airport
operator
item
Testing and commissioning, including testing
and commissioning together with existing
system where necessary; allow for all cost
for liaison with existing maintenance
contractors and the airport operator
item
All necessary modification and configuration item
for interface with the existing system
item
F
G
H
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 9
Carried to Collection MOP$
- BQ.9/2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 9
ELV Systems and Airport Systems
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Amount (MOP$)
Bill Nr. 9
ELV SYSTEMS AND AIRPORT SYSTEMS
COLLECTION
Page Nr. BQ.9/1
......................
Page Nr. BQ.9/2
......................
TOTAL - Bill Nr. 9
Carried to General Summary MOP$
- BQ.9/3 -
Section 6 - Bill of Quantities
Bill Nr. 10
Builder's works in connection with Building Services
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 10
BUILDER'S WORKS IN CONNECTION WITH
BUILDING SERVICES
Allow for Builder's works in connection with building services
A
Diversion of existing utility services
item
B
Equipment Room
item
C
Communication and IT Room
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 10
Carried to General Summary MOP$
- BQ.10/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 11
Miscellaneous
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 11
MISCELLANEOUS
Signage
A
Design and install necessary signage
and take down unnecessary signage
for existing PTB and North Extension to suit new layout design.
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 11
Carried to General Summary MOP$
- BQ.11/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 12
Civil Works
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 12
CIVIL WORKS
A
Topographic, utility and geotechnical surveys
item
B
Site clearance and demolition of existing pavement
item
C
Subgrade preparation for Bus Staging Area pavement
item
D
Block paving on sand bedding and lean concrete base
for Bus Staging Area
item
E
Block paving and kerb for footpath island
item
F
Pedestrian canopy for footpath
item
G
Surface water drainage gullies and pipework
item
H
Surface water drainage manholes or manhole alterations
item
J
Line markings
item
K
Perimeter fence
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 12
Carried to General Summary MOP$
- BQ.12/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 13
Decorative solar film replacement on Upper Part of
Glass Façade in the Airside Departure Hall
Rate
Amount
Quantity
Unit
(MOP$)
(MOP$)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Bill Nr. 13
DECORATIVE SOLAR FILM REPLACEMENT ON UPPER
PART OF GLASS FACADE IN THE AIRSIDE DEPARTURE
HALL
Decorative solar film
A
Ascertain the correctness of application area
item
B
Supply of 3M ScotchcalTM Perforated Window Graphic Film
7725-R314 or equivalent subject to CAM’s approval prior
to actual application
item
Printing on the decorative solar film using the design
provided by CAM
item
Application of the printed decorative solar film to
the glass facade
item
C
D
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 13
Carried to General Summary MOP$
- BQ.13/1 -
Section 6 - Bill of Quantities
Bill Nr. 14
Remote Boarding Gate (OPTIONAL)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 14/1
REMOTE BOARDING GATE (OPTIONAL)
Preliminaries
A
Insurance
item
B
Site survey report
item
C
Hoarding
item
D
Notice board & signage
item
E
Site mobilization
item
F
Safety precautions
item
G
Safety precautions
item
H
Material submission
item
J
Shop drawings
item
K
Detailed design drawings
item
L
As-built document
item
M
O & M manual
item
N
T & C report
item
O
Access card
item
P
Provision of 24-month operation maintenance and
breakdown service
item
Design work
Q
Remote boarding gate
item
TOTAL - Bill Nr. 14
Carried to Collection MOP$
- BQ.14/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 14
Remote Boarding Gate (OPTIONAL)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Quantity
Unit
Rate
(MOP$)
Bill Nr. 14/2
REMOTE BOARDING GATE (OPTIONAL)
Fabrication and Site Construction
Works
A
Remote boarding gate
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 14
Carried to Collection MOP$
- BQ.14/2 -
Amount
(MOP$)
Section 6 - Bill of Quantities
Bill Nr. 14
Remote Boarding Gate (OPTIONAL)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Amount (MOP$)
Bill Nr. 14
REMOTE BOARDING GATE (OPTIONAL)
COLLECTION
Page Nr. BQ.14/1
......................
Page Nr. BQ.14/2
......................
TOTAL - Bill Nr. 14
Carried to General Summary MOP$
- BQ.14/3 -
Section 6 - Bill of Quantities
Bill Nr. 15
AVDGS System (OPTIONAL)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Item
Description
Quantity
Unit
Rate
(MOP$)
Bill Nr. 15
AVDGS SYSTEM (OPTIONAL)
A
B
C
D
AVDGS display units; weatherproof; consisting of
various LCD or LED modules for Distance-toRun Indicator, Azimuth Guidance Indicators,
sensor units, Main Display Panels, optical transceivers/ receivers,
surge arrestors and mountings and fixings
item
AVDGS operator control panels with emergency
stop buttons, housings, mountings, surge arrestor and
fixings; including interconnecting cables and conduits
to AVDGS display unit
item
Control cables; cable containiment including
trunkings, conduits, flexible conduits, all
necessary earthing and bonding, fixing and all
necessary accessories; power provision to above equipment
item
All necessary modification and configuration item
for interface with the existing system
item
Any other items (to be inserted by the Bidder):-
TOTAL - Bill Nr. 15
Carried to General Summary MOP$
- BQ.15/1 -
Amount
(MOP$)
Section 6 - Bill of Quantities
General Summary (CORE ITEMS)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Amount (MOP$)
GENERAL SUMMARY (CORE ITEMS)
Bill Nr.
1
Preliminaries
2
Design of the Works
3
Demolition
4
Architectural Works
5
Plumbing & Drainage System
6
Fire Services System
7
Electrical Services System
8
MVAC System
9
ELV Systems and Airport Systems
10
Builder's Works in connection with Building Services
11
Miscellaneous
12
Civil Works
13
Decorative Solar Film Replacement On Upper Part Of Glass Facade In The Airside Departure Hall
TOTAL (MOP$)
- GS(CORE)/1 -
Section 6 - Bill of Quantities
General Summary (OPTIONAL ITEMS)
Design and Build for Fit-Out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Description
Item
Amount (MOP$)
GENERAL SUMMARY (OPTIONAL ITEMS)
Bill Nr.
14
Remote Boarding Gate (Optional)
15
AVDGS system (Optional)
TOTAL (MOP$)
- GS (OPTIONAL)/1 -
Download