Uploaded by Trix Mallari

MATHEMATICS

advertisement
MATHEMATICS, SURVEYING, TRANSPORTATION,
HIGHWAY, PORTS AND HARBORS, SAFETY,
CONSTRUCTION AND ENGINEERING EROSION
1.
If an activity cannot be delayed without affecting
the entire project, it is called a __________ activity?
a.
b.
c.
d.
2.
An ideal vertical curve to join two gradients
a.
b.
c.
d.
3.
Increase
Decrease
Remain Constant
None of the Above
The maximum number of vehicles, passengers,
pedestrians, or the like, which can be
accommodated by a given facility under a given
level of service.
a.
b.
c.
d.
9.
Horizontal ratio
Vertical ratio
Steepness
Wave ratio
A water generated in deep water, when reaching
shoaling waters, changes not only in its height but
also in its length but the period will?
a.
b.
c.
d.
8.
Ebb tide
Spring tide
Low tide
High tide
The ratio of the wave height to its wavelength is
called
a.
b.
c.
d.
7.
Risk
Accident
Hazard
Incident
In many parts of the world, the highest waves reach
their greatest height and the low waters at the
lowest height, soon after the time of full and new
moon, these tides are called.
a.
b.
c.
d.
6.
Planning
Control
Scheduling
All the Above
Any unexpected event that may or may not lead to
an accident?
a.
b.
c.
d.
5.
Circular
Vertical
Parabolic
Horizontal
PERT and CPM are methods for
a.
b.
c.
d.
4.
Critical
Non-Critical
Completed
None of the Above
Capacity
Volume
Mass
Density
Primary consideration in the design of geometric
cross-section highways, runways and taxiways?
a.
b.
c.
d.
Shoulder
Drainage
Railway
Parking
d.
Raw data
11. Any quantitative measures that describe a
characteristic of the population.
a. Statistics
b. Parameters
c. Data
d. Gathering
12. A single application of bituminous material to a
previously prepared or treated surface as a first
step in the placing of bituminous wearing surface
upon this type of base?
a.
b.
c.
d.
Seal coat
Prime coat
Tack coat
Asphalt
13. Describes the degree of stiffness of the mix and can
be directly altered by changing the water cement
ratio.
a.
b.
c.
d.
Workability
Slump
Vebe Test
Compaction
14. Building compound of concrete, it is a fine,
pulverized material consisting of compounds of
lime, iron, silica and alumina.
a.
b.
c.
d.
Cement and Mortar
Portland Cement
Type A Cement
Binding Cement
15. The rate at which water flows through a material is
a function of the materials.
a.
b.
c.
d.
Thermal conductivity
Permeability
Heat Capacity
Caisson
16. The division of an area into districts and the public
regulation of the character and intensity of use of
the land and improvement thereon.
a.
b.
c.
d.
Subdivision
Zoning
Diversion
Village
17. A defined area within the roadway, usually at an
intersection and set off above ground level, from
which traffic is intended to be excluded and which
is used for control of vehicular movements and as
pedestrian refuge.
a.
b.
c.
d.
Traffic control
Traffic Island
Traffic Operation
Traffic Lane
18. A general term denoting a public way for purposes
of vehicular travel, including the entire area within
the right of way.
a.
b.
c.
d.
Street
Highway
Roadway
Sidewalk
19. It is a construction operation that concrete should
be protected so that moisture is not lost during the
early stages of hardening, and it should protect
against injury from subsequent construction
activities.
a.
b.
c.
d.
Scaling
Curing
Sparkling
Ponding
20. A person travelling on foot
10. A point that represents the halfway or separation
point between successive class.
a.
b.
c.
Class mark
Class boundary
Array
a.
b.
c.
d.
Passing
Overtake
Phasing
Pedestrian
21. It is a combination of the likelihood of an
occurrence of a hazardous event with specified
period or in specified circumstances and the
severity of injury or dame to the health of people,
property, environment, or any combination of
these caused by the event.
a.
b.
c.
d.
Accident
Hazard
Risk
Unsafe Acts
22. It is a broad concept which explains how the
different hazards and risks at work may cause an
illness and emphasizes that health programs are
essential in controlling work-related and/or
occupational diseases.
a.
b.
c.
d.
Occupational Health
Safety
Accident
Basic Safety Measurement
23. What is the worst most important environmental
factor in the broad field of coastal engineering?
a.
b.
c.
d.
Sea
Wave
Sand
Coastal Erosion
24. It is a probability of a mechanism that will function
satisfactorily, if the mechanism is to operate
intermittently and briefly, it also refers to
performance on a given occasion. If the mechanism
is to operate continuously, it refers to its
performance for a specific period.
a.
b.
c.
d.
Infinite Set
Standard Deviation
Mean
Reliability
25. It occurs as concrete hardens. Being greater in wet
mixes. Curing helps to limit effects and therefore
concrete in the actual structure should be
thoroughly and continuously moistened for some
considerable period after placing.
a.
b.
c.
d.
Moisture Content
Compaction
Concrete Hardens
Shrinkage
26. The ideal capacity of road in vehicles per hour is
a.
b.
c.
d.
1900 vph
1800 vph
2000 vph
2100 vph
27. Device mounted on a fixed support (permanent
signs) or portable support (temporary signs)
whereby a specific message is conveyed by means
of words or symbols placed or erected for the
purpose of regulating, warning, or guiding traffic
a.
b.
c.
d.
Road Work Signs
Overhead Signs
Traffic Signs
Special Signs
28. A maximum wave height and wave period of the
maximum wave height in a wave train.
a.
b.
c.
d.
Highest Wave
Deep Water Wave
Significant Wave
Gravity Wave
29. What is the process of proportioning the cement,
water, aggregates and additives prior to mixing
concrete?
a.
b.
c.
d.
Curing
Mixing
Batching
Paving
30. These are circumstances or deviations from
standard conditions which could permit an
occurrence of accident or incident.
a.
b.
c.
d.
Risk
Hazard
Unsafe Condition
Unsafe Acts
31. The cost of crashing a network by one unit of time
is always determined by
a.
b.
c.
d.
The sum of the cost per crash hour along
the critical path
The minimum cost per crash hour of all
activities
The minimum cost per crash hour of the
activities on the critical path
None of the Above
32. The Gantt Chart is used mainly ______
a.
b.
c.
d.
As a record-keeping device
To identify immediate predecessor
To determine the resource to complete
each activity
None of the Above
33. It is called the completed specifications
a.
b.
c.
d.
Project Cost
Project Manual
Project Data
Project Manager
34. Most widely used scheduling technique, sometimes
preferred to critical path scheduling. Calculate the
minimum required for a certain task along with the
possible start/finish?
a.
b.
c.
d.
Bidding
Software
CMP (Critical Path Method)
Green Format
35. Normally placed in walls and columns at 2m to 3m
centers vertically.
a.
b.
c.
d.
Vertical Joints
Center to Center Joints
Horizontal Joints
Side Joints
36. Acts to distribute the wheel loads through to the
subgrade and therefore performs most important
function in the design of pavement.
a.
b.
c.
d.
Asphalt
Road Base
Subbase
Subgrade
37. Used as the binder and lais as hot material
a.
b.
c.
d.
Tar
Bitumen
Laser
Cement
38. Ability to dissipate or deaden mechanical vibration.
a.
b.
c.
d.
Fatigue Resistance
Impact Strength
Plasticity
Damping Capacity
39. A graphic presentation of a frequency distribution
of a quantitative variable where vertical rectangles
are erected to the horizontal axis.
a.
b.
c.
d.
Statistics
Histogram
Raw Data
Parameters
40. In the CPM time cost trade of function __________
a.
b.
c.
d.
Cost decrease linearly as time increases
Within the range of feasible times activity
cost increases linearly as time increases.
Cost increase linearly as time increases
None of the Above
41. Of all paths through the network, the critical path
a.
b.
c.
d.
Has the maximum expected time
Has the minimum expected time
Has the maximum actual time
Has the minimum actual time
42. It is the number of times something will probably
occur over the range of possible occurrence.
a.
b.
c.
d.
Probability
Statistics
Surveying
Data Gathering
43. It is defined as the difference between the true
value and the measured value of a quantity.
a.
b.
c.
d.
Pacing
True Value
Errors
Mistakes
44. The angular distance below or above the horizon
measured on the vertical circle through the point.
a.
b.
c.
d.
Altitude
Polar Distance
Meridian
Equator
45. The distance that a wind blows across the water is
called.
a.
b.
c.
d.
Off-shore
Shoal
On-shore
Fetch
46. The difference in height between the mean higher
high water and the mean lower low water is called.
a.
b.
c.
d.
Mean Sea Level
Mean Range
Diurnal Range
Residual Water Level
47. An abnormal rise of the sea level that occurs when
a typhoon passes by. This rise above normal level
on this open coast is due to atmospheric pressure
reduction as well as due to wind stress.
a.
b.
c.
d.
Hurricane
Storm Surge
Tsunamis
Tornado
48. The falling tide is known as
a.
b.
c.
d.
Ebb tide
Flood tide
Neap tide
All the Above
49. It is to level a floor or layer of concrete with a
straight edge using a back-and-forth motion while
moving across the surface.
a.
b.
c.
d.
Floating
Troweling
Screeding
Finishing
50. It is the difference between the actual time and a
given segment of a transportation system and some
ideal travel time for that segment.
a.
b.
c.
d.
Service Time
Travel Time
Queue Time
Delay
51. How long should merging into a lane take?
a.
b.
c.
d.
4 seconds
5 seconds
6 seconds
7 seconds
52. On urban roadways, when trying to turn, stay to
the ________ section of the lane
a.
Right
b.
c.
d.
Left
Behind
Towards
53. This should always be as shown on site plans
orientation purposes. Displaying it prominent is the
standard practice.
a.
b.
c.
d.
Scale
Vicinity Map
North Directions
Legends and Symbols
54. Two angles whose sum is 360 degrees
a.
b.
c.
d.
Conjugate angle
Complement angle
Supplementary Angle
Reflection Angle
55. Typically including fire alarms, extinguishers and
sprinkler systems, fire protection methods and
equipment are installed to protect people and
buildings should a fire occur
a.
b.
c.
d.
Fire Protection
Fire Drill
Fire Fall
Fire Resistance
56. It is a document prepared during key milestones or
near the end of a construction project listing work
not conforming to contract specifications that the
general contractor must complete prior to final
payment but the correction can be made in a few
days.
a. Punch List
b. Master List
c. Check List
d. Material Submittal Sheet
57. It is a type of bar chart that illustrates a project
schedule. Modern types of these show the
dependency relationships between activities and
the current schedule status.
a.
b.
c.
d.
PERT CPM
Gantt Chart
S-curve
Work Breakdown Structure
58. The maximum number of passenger cars that can
pass a given point on a lane or roadway during one
hour under prevailing roadway and traffic
conditions.
a.
b.
c.
d.
Possible Capacity
Traffic Capacity
Practical Capacity
Basic Capacity
59. It refers to an architectural member that is built
deeply into the wall so that the pressure on its
embedded portion counteracts any tendency to
overturn of fall outward. It also projects out from a
wall and acts as a type of bracket to carry weight.
a.
b.
c.
d.
Lintel Beam
Corbel
Awning
Girder
60. It is the ratio of the relative velocity after impact to
the relative velocity before the impact of two
colliding bodies.
a.
b.
c.
d.
Coefficient of Friction
Centrifugal Ratio
Gravitational Attraction
Coefficient of Restitution
61. What office is responsible for zoning of their
respective jurisdictions and final land use and
zoning planes to be submitted to HLURB (Housing
and Land Use Regulatory Board) for approval?
a.
b.
c.
d.
Municipal Planning and Development
Office (MPDO)
City Planning Development Office (CPDO)
Provincial Planning Development Office
(PPDO)
All the Above
62.
Download