METHOD STATEMENT FOR PILES

advertisement
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
METHOD STATEMENT
FOR CAST-IN-SITU
BORED PILES
Prepared by
Engineer Muhammad Kamal Khalid, PE, AMIE(Pak)
PEC: CIVIL/21394
Vetted by
Engineer Muhammad Mumtaz Khalid, PE, AMIE(Pak), ASCE
PEC: CIVIL/2415
Dated: 19 December 2022
Page 1 of 9
Doc No:
Revision:
Date:
CHIMBALS (PRIVATE) LIMITED
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
DOCUMENT CONTROL SHEET
DOCUMENT
Method Statement for Static Pile Load Test
PROJECT
Bridge at RD 09+025 at Link Road, Sialkot Kharian Motorway
DOC. CODE:
REVISION
INITIALS
AUTHOR
DATE
INITIALS
VERIFIED
DATE
SOP/MS//BP/01
01
02
MKK
MKK
1 Feb 22
MMK
1 Feb 22
03
04
05
20 Dec 22
MMK
20 Dec 22
Frontier Works Organization
CONTRACTOR
Zeeruk International (Pvt)
Ltd
CONSULTANT
House 456, St 57, Sector
I-8/3, Islamabad , Islamabad
Chimbals (Private) Limited
EXECUTING AGENCY / SUBLET
CONTRACTOR
Office # 5, 2nd Floor, Block D,
Spring North Commercial, Bahria
Phase 7, Rawalpindi
Page 2 of 9
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
1.
General.
Bored piles are steel reinforced concrete elements cast in situ used to
transfer high loads through soil to deeper, more competent soil or rock stratum. Constructed with
conventional rotary kelly bar plant, the drilling tooling is selected to suit the nature of the soils to
be excavated
2.
Purpose. The purpose of this document is to outline the proposed methodology for the
construction of the cast-in-situ bored piles with or without using temporary casings. Aim of the
procedure is to detail the sequence and method of pile construction, identify the hazard, assess
the associated risks involved, develop and implement adequate control measures and to provide
a safe place for safe work.
3.
Company Policy Statement.
a.
The Project Manager will ensure all necessary steps identified in this method
statement are followed in true letter and spirit. Since the stability of structure
depends on deep cast in situ bored piles, it require precision in survey, verticality
in boring, lowering of cage and concreting. In addition, all documentation that is
generated to record the installation activities and to monitor the applicable quality
assurance requirements must be followed.
b.
All personnel will receive a site specific induction. Before any work commences a
method of statement briefing will be conducted by the site management.
Operatives will confirm their understanding by signing the briefing register.
c.
4.
Under no circumstances shall any employee or subcontractor undertake
works/activity they perceive to be unsafe or commence an operation they do not
fully understand.
Relevant Documents, Standards & Codes. Following documents must be read in
conjunction with this method statement:a.
The Institute of Civil Engineers (ICE) – Specification for Piling and Embedded
Retaining Walls
5.
b.
BS 8004: 1986– Code of Practice for Foundations
c.
BS81 10: 1997 – Structural Use of Concrete
d.
Particular Project Specification
e.
Project Quality Plan
f.
Project HSE Plan
Mandatory Plant & Equipment
a.
Drilling Machine (IMT AF200 or equivalent)
b.
c.
Vibro-Hammer (ICE 415 C or equivalent)
50 Ton Crawler Crane (Sumitomo LS118 or equivalent)
Page 3 of 9
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
6.
7.
d.
Excavator
e.
Drilling Buckets and Cleaning Bucket
f.
Welding Machines
g.
Bentonite Recycling Pump
h.
Mud Pump e.g. Varisco Pump or equivalent
i.
j.
Generating Sets 40 kva
Lighting Towers
k.
Bentonite Storage Tanks
l.
Water Tank
Materials to be Used:
a.
Concrete: As per project design and specifications
b.
Steel Reinforcement: As per project design and specifications
c.
d.
Binding Wire
Concrete Spacers (75mm) or equivalent
e.
Flooring Steel Plates
Roles & Responsibilities
a.
The project manager / civil engineer shall be responsible for overall operation
activities for bored piles works, also ensuring that all safety measures are
implemented.
b.
Site engineer shall be responsible also for the coordination and supervision of
construction activities and coordinate with other agencies and ensure that the work
is done as per specification and approved drawings and ensuring all safety
c.
measures are implanted as per project HSE plan.
Owner’s / client's designated site Engineer/ Supervisor shall be supervising closely
the activities designated to them and ensure that all instructions are followed and
all necessary documents are in place prior to commencing the works and safety
procedures of the project is strictly adhered to.
d.
Site QA/QC engineer shall be responsible for monitoring the quality of workman
ship and implementation of project quality requirements.
e.
Site safety personnel are responsible for the enforcement of safety and ensure that
the works are carried out in accordance with company safety procedures and in
compliance with the HSE authorities.
8.
Health and Safety Requirements
a.
A risk assessment for the bored piling works shall be prepared for the project.
b.
All personnel involved in the above activities shall be introduced with the risk
assessment in order to provide them with the required knowledge of the works and
Page 4 of 9
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
to prepare them for the activities. Workers / personnel shall respect the
requirements of HSE plan.
c.
All Operative shall be made aware of the HSE requirement for drilling, steel fixing
and concrete casting works.
d.
Appropriate Personal Protective Equipment's (PPE) shall be available and worn by
e.
all operatives on the project site.
All non-motorized equipment's and tools will be mechanically lifted into the work
area.
f.
9.
Only trained and competent slingers will sling and direct any loads lifting activities.
Bored Pile Construction Work Method. The method of installation of the Bored Cast-
In-Situ Piles is detailed below.
a.
Working Platform:
(1)
(2)
The drilling works will be carried out from a levelled working platform.
Working platform shall be prepared and maintained with suitable
compacted material or suitable matting for the movement of the equipment
(3)
and the ready mix concrete trucks.
The site shall be levelled and spacious enough to allow the machineries to
move freely to each point and every location without any obstruction.
(4)
During the preparation of the working platform and prior to the start of the
drilling, an investigation should be carried out to assure the absence of any
(5)
b.
obstructions at the pile locations.
All utility services, old foundations, obstacles or any objects interfering with
the drilling works shall be removed or diverted.
Survey Works
(1)
A qualified surveyor will be employed to carry out all settings-out and
surveying works.
(2)
The center point of each pile shall be fixed by the surveyor using coordinate
system. These points could also be checked and confirmed by the
consultant/client.
(3)
The points will be marked by fixing steel pegs on the working platform.
(4)
After checking of points, the pegs will be driven into the ground to protect
it from getting disturbed.
10.
Bored Pile Construction Sequence.
The procedure for the construction of the
Cast-In-Situ Bored Piles comprised of the following key elements:
a.
b.
Page 5 of 9
Setting up at the pile location
Placement of the temporary casing (if required)
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
11.
c.
Drilling of the pile
d.
Cleaning of the Socket
e.
Placement of the reinforcement cages
f.
Concreting to level
g.
Removal of the temporary casing
Setting up at the pile location:
a.
Piles will be drilled in a set sequence that minimizes long movements and time
wastage.
b.
A working sequence will be prepared by the site engineer on a daily basis and
submitted to the client/owner 24hrs ahead.
c.
12.
Piles drilled will be concreted on the same day.
Placement of the temporary casing:
a.
The temporary steel casings are used for the pile alignment and for the control of
the soft upper layer.
b.
Wall Thickness of the pipes shall be around 14mm to allow for rigidity.
c.
Length of these pipes will depend on the depth of the soft upper-layer and the
water level.
d.
The condition of these casings shall be free from significant distortion and shall
have a uniform cross section throughout the length.
13.
e.
Casings shall be installed by vibration using a vibro-hammer of sufficient power or
f.
by rotation using the drilling rig.
The Casing will be installed within a maximum deviation from the center point of
the pile of 75mm in any direction.
Drilling of the Piles:
a.
After fixing the casing concentrically to the pile center, the borehole shall be drilled
down to the set toe level in accordance with the approved pile design and shop
drawings by the use of buckets and/or augers mantled on the Kelly bar of the
drilling rig.
b.
Verticality of the holes shall be continuously monitored by the on-board electronic
inclinometer and/or the use of a spirit level placed on the Kelly Bar.
c.
The alignment of the bored pile shall be made vertical to a tolerance of within 1 in
75.
d.
Subsequent to the completion of the drilling, the borehole depth and coordinates
shall be verified with respect to the shop drawings and the project’s coordinates
by the client/consultant.
Page 6 of 9
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
e.
If the consultant is also requiring verification, time shall be allowed for him to
perform his inspection and provide approval.
f.
Inspection time shall not exceed two hours to allow time for concreting at the same
day.
14.
Cleaning of the Socket. There are two methods of cleaning the borehole socket i.e. by
the use of Cleaning Bucket/ Sealed Bucket and by the use of Airlifting (Air Compressor).
15.
Bored Piling Reinforcement:
a.
Once all inspections are conducted and prior to concreting time, the bottom of the
borehole (socket) will be cleaned by the use of a cleaning bucket.
b.
Only after the cleaning of the socket is assured, can the reinforcement cage be
lowered into the hole.
c.
A reference site datum level shall be given by the surveyor to ensure the correct
d.
positioning of the cage with respect to the final cut off level.
The reinforcement for the piles shall be cut and bent on site and/or the workshop,
according to the requirement of the specification and the approved design of the
e.
piles.
Reinforcement cages shall be fabricated as per the shop drawings.
f.
The cages shall be securely fixed manually using tied galvanized wires.
g.
Plastic or PCC spacer or equivalent (75mm) shall be tied to the cage to assure the
adequate concrete cover of the pile.
h.
i.
The reinforcement cage shall be lowered to the required level by the use of a crane.
Cages will be securely suspended in the bore using tie rod and hook system to the
j.
temporary casing.
Hooks will only be removed after the concrete has been casted and prior to the
extraction of the casing.
16.
Casting of Concrete:
a.
The concrete shall be delivered to site by means of truck mixers.
b.
Concrete delivery tickets shall be checked for correctness in accordance with the
approved mix design.
c.
The concrete shall be checked for the slump and temperature.
d.
Cube samples shall then be taken as per specification.
e.
The Concrete shall only be allowed on-site after the quality has been found in
compliance with the specifications.
f.
Concrete shall be supplied to the pile by transit mixers and placed by the full length
tremie pipe method.
Page 7 of 9
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
g.
A mobile concrete pump shall be used to transfer the concrete from the truck mixer
to the pile or if the site permits, the concrete can be directly unloaded into the
trime.
h.
The flexible hose of the concrete pump shall be connected to the tremie pipe that
shall be lowered into the center of the pile by the use of a crane or direct from the
i.
truck mixer to the concrete hopper attached to the tremie pipe.
Concrete shall be poured without interruption to prevent the creation of joints.
j.
The tremie tube size shall not be less than 150 mm.
k.
Tremie pipe shall have sufficient length to reach the toe of the pile.
l.
The tremie pipe shall be inserted at the center of the pile to reach up to the toe.
m.
Bottom of the tremie pipe shall remain throughout the casting process of at least
2m embedded inside the concrete.
n.
The concrete shall be brought up to the working level or minimum 1.0m above cutoff level to ensure good quality and contamination free concrete at pile cut-off level.
o.
After concreting, the temporary casing shall be withdrawn by rotation using the
p.
piling rig or a vibro-hammer.
When the casing is being extracted, a sufficient quantity of concrete shall be
maintained within it to ensure that pressure from external water or soil is exceeded
and that the pile is neither reduced in section nor contaminated.
17.
Disposal of drilling spoils. Spoils/slurry resulting from drilling of boreholes shall be
stored on site and carted away at regular intervals.
18.
Pile Head Breaking:
a.
Upon achieving the required strength of the concrete for the piles, and in
conjunction with the load testing program for the project, the pile heads can be
trimmed to final level.
b.
Piles were casted higher than the final level to control laitance (impurities which
have migrated to the top of the piles) during the construction of the piles.
c.
Cropping of the pile head is required to remove all the additional concrete to the
specified level, while leaving reinforcement bars protruding to the designed length
to allow adequate lap and/or anchorage in the Pile Cap.
d.
Excavation around the piles and as per pile cap dimension shall be prepared.
e.
A maximum of 200mm of soil under the cut-off level shall be excavated.
f.
The cut-off level shall be marked on the pile and then saw cut 1 to 2 inches inside
the pile to limit the breaking surface.
g.
Page 8 of 9
Demolition of the excess concrete above the cut-off level shall be carried out by
operatives using jackhammers.
CHIMBALS (PRIVATE) LIMITED
Doc No:
Revision:
Date:
SOP/MS//BP/01
02
20 Dec 2022
JOB METHOD STATEMENT –CAST IN SITU BORED PILES
h.
The use of a pile cropper can be allowed for the top part of the pile but not for
final breaking to level.
i.
Removal of the concrete to the correct level must not introduce damage to the
pile concrete below the cut-off level, as this will affect the workability of the piles.
19.
Piling Records.
Piling Records, provided by the foreman will be checked by the
site in charge before final submittal to Engineer on the Bored Pile Record Sheet. A sample pile
report record includes the following data:
a.
Pile number
b.
Pile date of completion
c.
Pile diameter
d.
Working platform level
e.
Pile design cut off level
f.
g.
Pile toe level
Concrete top level
h.
Reinforcement cage details (length and bars diameter)
i.
j.
Pile concrete length
Pile bored length
k.
Ground water level
l.
Drilling time and piling rig in use
m.
Concreting time, concrete details and ticket no.
n.
o.
Concrete cube Nos.
Any unexpected drilling condition encountered will be noted briefly in the
records, and brought to the attention of the consulting engineer immediately.
Page 9 of 9