Project Charter (MOQ Home Improvement)

advertisement
Project Charter (10KW Home Solar System)
Project
Name
Project
Manager
Owner(s)
Start Date
01-February-2023
Mr. Muhammad Omar Qasmi
Prioritization High
Ms Rao Aneeqa
Scheduled
Completion
Date:
30-March-2023
Providing a sustainable and sufficient energy supply is one of the major
challenges for the Government of Pakistan. Over the recent decades, the
need for energy has been on a constant rise due to steady economic growth
and increasing urbanisation in Islamabad. The population of Pakistan is
projected to increase to 245 million by 2030, with around half living in urban
areas. This will require approximately a 3.3% annual increase in the energy
supply. Pakistan is one of the highest energy intensity countries in Asia.
However, until the recent past, renewable energy RE) has remained a low
priority at the policy level. With the RE policy in place, homeowners are
shifting towards RE sources for their residential properties. In this case, we
will design, develop, install, test and commission an on-grid 10KW Home
solar system.
Purpose
4.
5.
6.
The Project Scope would include:
Design of a 10KW On-Grid Home System
Area Survey and Layout/ Sizing
Supply & Procurement of Solar Panels, Inverters, Cables, Installation
Accessories
Installation of Solar System
Testing & Commissioning of Solar System
Handing Over to the Owner
1.
2.
3.
4.
The Scope would not include the following:
Application & Approval to Local Electricity Company for Electricity Meter
Supply of Electricity Meter
No Object Certificate (NOC) from Housing Development Authority
Installation of Electricity Meter
1.
2.
3.
Scope
10KW Home Solar System
1.
2.
Objectives 3.
4.
5.
Successful Installation of 10 KW On-Grid Home System
Electrical Safety Guidelines Documented and Shared
Operating Manuals and Procedures Provided
Net Metering Connection established.
Electricity Generation & Supply Fully Operational
Assumptions
1. Open Roof with no shadowing effects.
2. Supply & Procurement Equipment available locally.
3. The Owner has an NOC from the Housing Development Authority
4. Bi-Electricity Meter Installed
5. Solar Energy Generation through panels observed.
Constraints
1. 70% Advance Payment not received for Equipment Procurement
2. Homeowner not available to Residential building survey.
3. The Distribution Board is at full capacity for additional wiring.
4. Installation would not be possible in monsoon/ rainy days.
Time/Decision
Points
Measurement
Criteria/Quality
1. 15th January 2023 – Approval of Technical & Commercial Invoice by
Owner.
2. 01st – 2nd February 2023 – Area Survey
3. 03rd February 2023 – Develop Layout Design & Technical Equipment
Specification.
4. 10th February 2023 – Order Equipment for Installation
5. 1st – 15th March 2023 – Equipment Installation
6. 30th March 2023 – Handing Over to Owner after successful energisation
1. Solar Panels will be factory Tested as per IEC Standards.
2. Inverter with 5 Years Warranty with operating manuals.
3. Solar Generation to be monitored as per equipment design
via an Online Application for quality check.
Talent Management/Project Teams Toolkit
1
Rev. February 2013
Project Charter
Major Risks 1. NOC from the Housing Development Authority is Not available
2. Bi-Directional Electricity Meters are not available with the local electricity
company.
3. Electricity Meter was not installed after the installation of the 10KW System
4. Owner does not pay 70% advance payment
5. The residential property cannot sustain a 10KW system due to improper civil
structure.
Project Core
Team:
Subject Matter
Experts (SME)
KEY STAKEHOLDERS
Name
Area Surveyor:
Bilal Ahmad
Design Engineer:
Sameer Ali
AutoCAD Expert:
Babar Azam
Installation Manager:
Saleem Philips
Civil Technician:
Decius Metellus
Wiring Technician:
John Adams
Commercial Lead:
Irshad Khan
Solar PV Expert:
Type Name
Project Manager Approval:
Muhammad Omar Qasmi
Steffen Bitterling
APPROVALS
Signature
Sponsor Approval:
Aneeqa Rehman
Date
MOQ
15-12-22
Aneeqa
19-12-22