Evaluation of Treatment Process of 17.3 MLD Tukucha Khola WWTP in Nepal (1) Plant Components:- The plant components specified in the Contract and the compliance are compared in Table 1 below. The plant components are specified in Section 6 – The Employer Requirements and Annex 5 of Section 6 of the Basic Design Report (Section 4.3 Purification Components, Section 4.4 Treatment Sections). The Contractor provisions were verified using Drawing No 815 129 PEE 700 L 001 00 Rev R0. (2) Notes: a. The verification in Table 1 is mainly to confirm the inclusion of the treatment component as per the ERQ but not to confirm its compliance with the specification. b. The no compliance does not mean that the performance objective has not been met since it is a design-build plant. The comments require the Contractor to justify/clarify his proposal, which may or may not be accepted. Table 1: Comparison of Tender Requirements and Compliance by the Contractor General Contract Requirements Contractor Provision Remarks Channel/pipe from Tukucha Khola to the site of the WWTP Interceptor channel provided in the drawing Interceptor channel/pipe details are not provided. It is not required for process design evaluation; However, control of flow to the WWTP should be necessary for its proper operation Debris removal mechanism for water released to Bagmathi Khola from Tukucha Khola Not shown in the drawing Not required for process design evaluation; Flow measuring in Tukucha Khola is required to establish treated and nontreated volumes Not shown in the drawings Not required for process design evaluation; The WWTP and Sludge processing are on two sides of the Bagmati River, and a syphon connects them The Contractor proposes the connection via a bridge Consider as a more convenient option than a syphon considering the flooding and construction The system should be built to be for the operational safety of 50-year flooding Not included in the process design reports This is important to civil design. However, the hydraulic profile, static head, pump selection, etc., can affect the decision to raise the groud. Also, the SBR unit top slab is to be turfed and accessible to people Pre-Treatment and SBR System Contract Requirements Contractor Provision Remarks Acceptance channel with a stone trap (one unit) Not included in the drawings ERQ requires the stone trap; whether a provision for future connection of trunk sewer should be provided now shall be decided Automatically raked coarse screen with washing and compacting of the screenings (Mechanical) (two units) Two mechanical Coarse Screen both operating basis are provided Provided in accordance with ERQ Coarse screening (Manual) (one unit) One unit is provided Provided in accordance with ERQ Conveyor stretching course screen channels The Contractor proposed one unit of screw conveyor/compactor The Contractor complies with the requirement; Screening bins (two units) Contractor two containers of 1m3 each The Contractor complies with the requirement; However, 1 m3 container when full will be difficult to lift and manage manually Sewage inflow lifting pumps (operation mode 3+1), including piping and fittings (valves, non-return valves) The Contractor provided four pumps on three working one standby basis Provided in accordance with ERQ; Valve chamber provided Pumps are centrifugal submersible ERQ requires pumps to be VFD type Valve arrangement shall be verified with mechanical/ piping design Flowmeter type MID (one unit) Not provided in the drawing Required as per the ERQ Compact pre-treatment units, including fine screen and aerated grit trap and floated grease collection channel (three units) Fine screen station is provided with three units on two working one standby basis; containers are also provided; oil and grease collection will take place at grit channels Compiled with the ERQ; The 1 m3 container, when full, will be difficult to lift and manage manually; Grit washing and classifying (two units) Three units are provided, including the standby units Compiled with the ERQ Automatic valves for the distribution of the wastewater to the SBRs (four units) The Contractor provided a distribution chamber with sluice gates; The distribution arrangement is unclear; whether the sluice gates are automated (actuators) is also not mentioned. Four units are based on four SBR units Two distribution chambers are provided as the SBR units are built as twin units SBR (four units) Four units are provided Compiled with the ERQ Fine bubble aeration system Four working units are provided with Compiled with the ERQ Contract Requirements Contractor Provision Remarks (membrane tubes), including air supply pipes (four units) one standby Mixer (minimum 2 / SBR) Eight mixers are provided, two in each tank Compiled with the ERQ Excess sludge pump (minimum 2 / SBR) Two excess sludge pumps are provided per tank, one duty and one standby basis Compiled with the ERQ Purified water decanters (2 / SBR) The proposal seems to be one decanter fixed or floating per each tank The ERQ requirement for two decanters is not met Outflow piping with all fittings Not provided the details Nor required for process evaluation. Can be included in the mechanical/ piping design Effluent flowmeter (MID) (0ne unit) Not provided in the drawing Required as per the ERQ Piloting equipment, instrumentation The Process Description Report provided only limited information on process control The Contractor should submit a description of the process control together with the Process, Instrumentation Diagram (PID) for review by the instrumentation Engineer level meters, dissolved oxygen probes, temperature probes, pH probes Details not available Details can be reviewed later and will not affect the current review of the process design automatic samplers (inflow, outflow) Details not available Details can be reviewed later and will not affect the current review of the process design Blowers with variable speed, FU piloting for oxygen demand and water level depending on the production of compressed air (1 per SBR with the possibility for the cross supply of the SBRs (four units) Four working units with one standby are provided The number of units is Ok; it is not defined whether blowers are VSD Each blower with noise reduction hood Not Defined Required as per the ERQ Associated pipework and ancillary equipment, valves, fittings Not Defined Nor required for process evaluation. Can be included in the mechanical/ piping design Contract Requirements Contractor Provision Remarks Outflow lifting station Purified water pumps, including piping and fittings (valves, non-return valves) to lift the treated water out of the WWTP if gravity flow is not possible in case of a high water level of the receiving water, the Bagmati River The Contractor provided a sump and pumping system in the three working and one standby basis Compiled with the ERQ Sludge Treatment Facilities and Biogas Processing Contract Requirements Contractor Provision Remarks Sludge storage basin (two units) Only one unit provided Not compiled with the ERQ Mixers in the storage basins (minimum 1 / storage basin) (two units) Not clear whether the mixers are provided in the storage basin Not clear from the Contractor proposal Sludge Thicker; The ERQ is not specific about the sludge thinker requirement; It is possible to assume that requirement could be four units, one working and one standby basis for the two basins Provided one working and one standby basis Not compiled with the ERQ, but in line with the Contractor's proposal Sludge pumps (to lift the thickened sludge to the buffering basin on the site of sludge manipulation (minimum 1 / storage basin) (two units) Two pumps are provided, one working, one standby basis Complied with the ERQ but in line with the Contractor's proposal Sludge storage and buffering basin (one unit) Provided Compiled with the ERQ Mixer in the storage basin (one unit) Mixer Provided Compiled with the ERQ Excentric sludge pumps to draw the sludge from the storage basin and lift it through the heat exchanger to the digesters Four screw pumps on two working and two standby basis are provided Compiled with the ERQ A tube heat exchanger (to raise the temperature of the sludge that is Provided Section under Digester described the pumps as excentric screw type; Provided but not specifically mentioned, the type of heating arrangement; but not necessary for Contract Requirements Contractor Provision diverted to the digesters) Remarks process evaluation Digesters with all relevant equipment like the mixer, gas hood, supernatant overflow, piping (internal piping for the injection of excess sludge and drawing of excess sludge at different levels (two units) The contractor proposal is to based on Passavant-Rodiger's digestion process, and two units will be provided It seems to comply with the ERQ as the Contractors written statement confirms that all necessary components of the Digester will be provided Piping for the evacuation of digested sludge from the digesters to the digested sludge storage basin Provided but detailed can be reviewed only with mechanical/ piping drawings Complied with ERQ; not required for process evaluation Sludge dewatering units (e.g. centrifuges) Provided centrifuge units Complied with ERQ Polymer station for the production of polymer solution and polymer adding to the sludge (two units) Provided by the Contractor Complied with ERQ Excentric screw pumps for the conveyance of digested sludge from the digested sludge storage basin to the dewatering units (e.g.centrifuges) (three units on a 2W+ 1Stby basis) Provided Complied with ERQ; Conveyor to transport the dewatered sludge from the dewatering units to the sludge collection containers Provided Complied with ERQ; Biogas drying and desulphurization equipment (two units) A Scrubber unit is provided; Only one unit is included; However, two desulfurization units provided Not complied with ERQ as no standby is proposed for the scrubber unit; however, it does not affect the process evaluation Biogas holder for the storage of biogas produced within half a day (one unit) The biogas holder provided Complied with ERQ; not required for process evaluation Biogas burner to flame the biogas that cannot be stored (one unit) Biogas flare is identified in the drawing; details of the flare are not provided Complied with ERQ; not required for process evaluation Generator for the combustion of biogas and production of energy (one unit) Power Generation Room is provided; Generator details are not included Complied with ERQ; not required for process evaluation (3) Comments on Flow, Influent Quality, Waste Loads and Treated Effluent Quality a. Daily average and peak flows used in the design are in accordance with ERQ b. ERQ provided influent quality for BOD, COD, TSS, TKN, NH4-N, and Ptotal the values used in the design are compatible; in addition the design report included inflow quality for VSS. It is assumed that VSS was computed on the same basis used in the ERQ to compute wastewater characteristics and acceptable. c. The design minimum and maximum temperature are in accordance with the ERQ d. Waste loads; although some parameters have very small deviations to the values provided in ERQ. The values used in the design are acceptable. (4) Purification Requirement a. The purification requirements of water quality parameters are acceptable except the higher pH value should be corrected to 8.5 (no impact on process design calculation in this case) b. There are minimum purification efficiencies provides as percentage of influent quality which should be checked in the design; In this case the TOC level should be estimated. The ERQ requirement is The Works must comply both with the limit values and with the minimum purification efficiency standards specified in Table 3 in ERQ. (5) Upgrade Requirement a. ERQ requires that the Contractor to ensure that its layout includes provision for the Employer to upgrade the WWTP for nutrient in the future (residual volume in the SBRs) although no preparatory works have to be done with this project. b. Accordingly it is necessary to illustrate in the layout arrangement / land utilization that the enough area is available within the allocated land for WWTP is available to implement nutrient removal or that the designed SBR units can be adopted for nutrient removal (6) Required Sludge Quality The design values set for stabilized and dewater sludge is Dry Solids concentration 25% and Loss of Ignition 60%; The ERQ requirements are Dry Solids concentration ≤ 25% (acceptable) and Loss of Ignition ≤ 55% (not acceptable; as it is a schedule of performance requirement) (7) MPS Inlet Chamber Dimensioning Reviewed and no objection. It is good if bid more details on how the dimensions are arrived at is explained. For e.g. the Length = 2 x width of mechanical screen channels + width of manual screen channel + 2 x width of walls separating the channels Water depth is taken as 1.5 meters it should corresponds with the inflow arrangement from Tukucha Khola. Details of inflow arrangement from Tukucha Khola are not provided yet. Note: the following comments are prior to my review of the hydraulic calculations. It is possible some of these comments are covered/ explained in the hydraulic design calculations. (8) Trash and Course Screen Channels (Mechanical) The ERQ design criterion requires (Annex 4 Section 4.65.5 Table 10) the clear spacing between bars to be less than 10mm. In the design the spacing used is 20mm. Water depth considered is 0.70 meters. However, the MPS inlet chamber water level is 1.5 meters. It seems that you have planned the screen channel bottom to be 0.7 meters below the top water level of the Inlet chamber and allow very mild slope to the screen channel. I have checked the flow velocities and other hydraulic parameters for the screen channel based on this assumption. However, I could not but get the values computed in the design report. Provide the following information. (a) Hydraulic arrangement between the Inlet Chamber and the channel (the profile). (b) I suggest to use specified bar spacing in the ERQ unless there can be reasonably good argument for using 20mm; 15-20mm is the values usually adopted in sewerage systems but in this case they may have proposed 10mm to protect the fine screens more than the pumps. . (9) Trash and Course Screen Channels (Manual) The ERQ design criterion requires (Annex 4 Section 4.65.5 Table 10) the clear spacing between bars to 20mm. In the design the spacing used is 30mm. The description provided for mechanical screens apply. (10) Screens, Conveyor and Compactor These aspects will be probably reviewed by the mechanical engineer as well. I have no objection. The main concern is the size of the container it would be very heavy and difficult to handle. The ERQ specified arrangement/mechanism for lifting but large size containers are very difficult to handle unless EOT crane and can lift and unload to the collection truck directly. . (11) Screens Channel The width of the screen channels 1.2 meters (mechanical) and 1.7 meters (manual) and length of the channel 5.1 meters would be adequate despite verifications requested in (8) and (9). However, channel bottom may require level adjustments such as small drop at the downstream of the screen and rise at the end to compensate for free fall to pump sump (if free fall is allowed) (12) MPS Sump The review of pump sump and pump selection are as follows. (a) The pumps are selected to remove maximum hourly flow (accepted) (b) Accordingly three pumps with 720 m3/hr capacity are provided which allow pumping out of 2160 m3/hr (c) The effective volume of sump is 137.5 m3. Accordingly it takes only 3.8 minutes to empty the tank and another 3.8 minutes to fill the tank. Thus total cycle time will be 7.6 minutes. (d) Accordingly to above the pumps will switch on and off approximately eight times per hour. (CPHEEO recommendation is 6 on/off cycles per hour). This means little bigger effective volume would be required. (e) The pump sump size is also depending on pump arrangement. It is necessary to provide space between pumps and to provide space for smooth supply of flow to prevent turbulence and inflow of water with entrapped air. It is necessary to use Guidelines by Hydraulic Institute (HI) or manufacturers in this case. I assume that there should be IS standards. However, HI guidelines are used in India as well. Note: May be you have already considered these aspects in sump sizing however as the design report does not indicate such information I have provided these comments. (f) As I understood the pumps provided are fixed speed. The ERQ however ask for one Variable Speed Pump (Section 4.10 Annex 4 ERQ). In my opinion in that case there should be two fixed speed pumps and two variable speed pumps each can deliver 720 m3/hr maximum. (g) Refer to the section 4.10 for the described pump operating philosophy. The proposed approach in the ERQ is to optimize the energy consumption. (h) Refer to the comments and reconsider the pump sump sizing and pump selection. (13) STP Inlet Chamber (I assume this means the distribution chamber to fine screens) Review with the fine screen channel (14) Fine Screen Channel a. Number of fine screens are provided in accordance with the ERQ b. Manufacturers catalog is required to verify the other calculations of the design c. It is not clear of inflow arrangement (internal/ external) and solids removal arrangement and the controlling flow and velocities; flow splitting arrangement to the three fine screening chains. These information is likely to be in the manufacturers installation drawing/ broacher. d. ERQ requires the screen matter to be disposed in endless plastic bags in containers. The design proposal only provides containers. If the design wishes to deviate from the ERQ it can be considered with justification (15) Grit Chamber a) ERQ requires fine screens, and grit removal (including oil and grease removal in the same channel. Accordingly three separate channels are provided. The proposal is compatible with the ERQ. b) The return flow is calculated using mass balance; Could not locate the mass balance calculation. c) The design criteria listed in the document are partly from the ERQ; however, there are additional design criteria and source of which is not provided. d) The details provided in the design report indicates that the Contractor plans to construct the aerated integrated grit removal system at site and incorporate the necessary equipment such as blowers/ air compressor, grit pumps, grit clarifier etc. The information provided for the design is not adequate for the review of the design. Following documents are required for the design review. i. Detailed drawing of the integrated grit and oil/grease removal system ii. The drawing shall include the oil and grease removal (skimming arrangement), grit removal arrangement e) The review of mechanical units will be covered by the Mechanical Engineer in addition. (16) Quantification of Screen matter, Oil Grease and Grit Volumes a) The selection of equipment such as grit classifiers, screw conveyor for screens are based on quantity of screen, grit matter removed. The source of data is mainly the Metcalf and Eddy which mostly relevant to US and Developed Country situations. Therefore it would be better if we based the estimate on Nepal/Indian or developing country conditions/ situations. Grit quantities and screen quantities are high in developing countries due to poor O&M of systems, interconnection of sewer and storm water systems and poor solid waste management. Process Review SBR Plant (17) Distribution Box a. Average and Peak Flow calculation accepted b. It is good that with each unit to briefly explain how it operates. In this case how the wastewater is fed to the SBR reactor; that would enable understand clearly the design parameters and values depicted in the tabular form c. Proposed design values are acceptable (18) SBR System a. Average and Peak Flow calculation accepted b. Design Wastewater Characteristics – following comments should be considered i) Abbreviations should be defined as some abbreviations are not commonly used ii) Assumptions were made in estimating certain parameters such as sBOD, rbCOD it is necessary to provide justification or if the Contractor has carried out analysis of effluent samples then provide support evidence iii) pH in the wastewater analysis is provided as 6.5-7.5 and in the treated effluent as 6.5-8.5; however in SBR design the pH is taken as 5.5-9.0; Is there any reason for wider pH range at this stage; the pre-treatment processes are not affecting pH (as I see it) c. Desired treated effluent characteristics values taken for the selected parameters are correct d. Ambient Conditions – following are the comments i) Temperature values taken are in accordance with ERQ ii) The elevation is taken as 1700 m MSL but as per the report the evaluation is about 1280 m MSL e. c