HOT WORK PERMIT Permit Number Permit Valid From: 26/11/2022 To: 02/12/2022 1. ACTIVITY: 3. PRECAUTIONS TO BE TAKEN (Tick box) DEPARTMENT: Piping Before Starting: COMPANY:DAESHIN PLANT AREA:LAYDOWN LOCATION: HDEC PIPING (AG WORKSHOP). Toolbox talk to be conducted TASK DESCRIPTION: Post weld heat treatment for pipes (PWHT). Work to be provided with safe access and egress Work area isolation barriers to be in place EQUIPMENT TO BE USED: Generator, Welding Machine, PWHT Machine, Hand held Lifting equipment certified induction, Heat Tracing, Temperature gauge. All lifting devices to be visually examined before use Discipline Hoses and electrical extension cables to be protected/secure Performing Party Issuing Authority PTW Coordinator Company/Department DAESHIN PLANT HDEC/Piping Mobile # 07833224838 Signature Y.H Lee 2. TASK QUESTIONS – Does your work; (tick box) Generate heat or sparks (grinding, cutting, welding) HDEC/HSE YES Require electrical or combustion engine equipment (ignition sources) within a SIMOPS or Commissioning area? Require excavation deeper than 300mm, but less than 1,200mm? Require excavation deeper than 1,200mm? Require entry into a space that is not designed for human occupancy and has restricted access/egress? Require using radiography equipment (e.g. soil density testing, NDT) Require energization or de-energization of equipment, systems, or sub-systems? Require work on electrical equipment, instrumentation, systems or sub-systems? Require lifting of loads more than 40 t, over or near live lines, during night, by tandem lift? Require the removal of gratings or opening of floor decking? Affected Discipline Managers Consulted Discipline Civil Building Mech. Piping Instr. Sign Elec. M.G C.C.A C.C.B HDEC PIPING UG Comm. LAYDOWN Others Sign Mobile # 2 Day or Shift Date Issuing Authority Performing Party 3 27/11 Date Site/local traffic to be routed away from the work area Area to be free of flammable/combustible materials During Work: Access to work area to remain restricted Equipment maintenance checks to be carried out PPE to be worn at all times Plant refueling procedure to be followed Proper rest breaks to be observed Plant/equipment operators to be certified After Work: Check work area to ensure barriers and lights are in place All equipment to be removed and area made safe De-watering pumps fueled and in place where needed 4. ACCEPTANCE AND AUTHORIZATION – (This counts as day one of the permit) PERFORMING PARTY I am fully aware of the PTW requirements relevant to the Name: Y.H Lee work I am executing and confirm that I will ensure that all Sign: relevant safety control measures remain effectively in Mobile: 07833224838 place throughout the validity of this permit. ISSUING AUTHORITY I have physically confirmed that each of the identified Name: control measures required by this permit have been put in place. The performing party is authorized to commence Sign: the work under this permit within its validity period. Mobile : 4 28/11 Date NO All equipment to be turned off when work site left unattended Mobile # Affected Area Construction Managers Consulted AREA YES 5 29/11 Date 6 30/11 Date 7 01/12 Date Closed 02/12 Date 03/12/2022 Risk Assessment / JSA Form Hot Work Activity: Project / Site location: Date Description of Work: Review Date 20-OCT-2022 After 6 Months Post weld heat treatment for pipes (PWHT). Ref No. Localized Shutdown: IBRUP-BASRA REFINERY LAYDOWN – UG WORKSHOP, HDEC PIPING □ Required □ Not Required Piping Contractor Department Rev No. HSE-JSA-2021- Localized Shutdown: □ Required □ 0 Not Required Supervisor Y.J KIM 07835769787 Supervisor Lee H.S 07833224838 HSE supervisor Abdullah 0781 474 2880 DAESHIN PLANT Subcontractor IBRU HSE Plan and safety procedures are to be followed at all times. Minimum PPE to be worn at all times. General safety condition requirements: This JSA to be available at all points of work – operatives must be informed of this JSA and understand the risks involved in the works. Tool box talk / pre-job brief to be given at the start of each work shift and before starting a new task or activity. Summer and Ramadan working hour’s changes are to be observed and details posted at worksite. Paramedical or ambulance facilities to be available. Minimum PPE required: Helmet, safety glasses or goggles, Hi-Viz jacket, overalls, gloves, safety shoes Risk Rating: S = Severity, P = Probability, R = Rating Impact: P – People, E – Environment, A – Asset R - Reputation Impact Risk Activities/Hazards (consequence) Preparation for the job Planning and Obtain 1st Risk Assessment P E A R L C R P B B4 R 2 Control Measures PTW shall be signed by Hyundai prior start of works Action by Residual (Due date) risk L C R 1 B B2 HSE & SUP L 2 C C6 All Staff M is less than adequate PTW Plan the work involving personnel responsible for preparation • Exposed to potentially infective respiratory droplets Coronavirus risks in the work area 2nd Risk Assessment P E R 4 D D16 Pre-shift Temperature check for all involved workers Respiratory/medical masks to be worn constantly during the transportation from the places of accommodation to workplaces. • Personnel illness Regular disinfection of shared workplaces / Containers / Vehicles. Delay or shutdown of Maintain proper personal hygiene level, wash your hand with soap operations or use sanitizer. Avoid touching your eyes, nose, and mouth with unwashed hands. Do not share personal items like: PPE, mobile phones, drinking bottles, crockery, etc. Shared work tools or equipment shall be regularly disinfected. Avoid close contact: like shaking hands, hugging or kissing as a greeting. Avoid unauthorized meetings / gathering of people. Full PPE to be worn all time including masks. Physical distance to be respected when possible. Preventive measure to be discussed at daily TBT. Work task to be planned and assigned with regards of above COVID-19 preventive measures. Mobilization equipment of workers from camp to work area. Embarking and disembarking of workers on Buses/vehicles at relevant designated working areas Access and Egress 1. Vehicle traffic accident 2. Injury to Employee. 3. Struck by A P 4 D D16 2 C C6 Operators & Sup & Workers M 2 C C6 All Staff M 1 B • Check all the condition of the driving vehicles • Slips and trips P A 3 C C9 • Tool Box meeting before start work. • Personal injury • Exit route and safe area to be discussed as part of pre task briefing • Property damage • Carry out tool box meeting before start work. • Provide first aid kit and designated first aider on site. In case of emergency leave worksite and proceed to the nearest muster point according to the Mustering procedure. Panic • Wrong Posture • Improper Manual Manual Handling & Using Hand Tools • Emphasize the training of competency of operator and vehicle driver as per the traffic control procedure. • All the personnel should embark on and disembark from bus in designated area only. • Availability of emergency response (Ambulance and Medical personnel). • Speed limit to followed 20KM/H • Traffic System to be followed Handling • Pinch Points • Manpower injury Back pain • Heavy load damage to the material • Direct injury to the operators P A 3 B B6 • Avoid manual handling if it can be carried out mechanically. • Try lifting one corner, if it’s too heavy use second person or other means (Mechanical) to lift item. • Use of more than one person to lift longer tubes • Consider dual lifting (general rule of thumb if above 25 kg). • Loads that can easily be carried a short distance can often be a problem when carrying long distances – take this into consideration when assessing the weight of the load – (Even a load of less than 25 kg can pose a problem if it has to be carried a long distance or up and down stairs). • Check the route first before lifting. • Correct lifting techniques to be used at all times e.g. lifting using legs with load held close to your body, take a firm grip, maintain straight back, turn body not twisting upper body and avoid overreaching. • All tools provided must be assessed to ensure that they are fit for purpose; the fit for the environment in which they are to be used and they are in good condition. • Visual checks must be completed by operatives on tools prior to their B2 Forman & Workers L use. • Tools are required to be suitable for the purpose for which they will be used Eye Damage Hot Work Cutting, Grinding Cuts & Burns Sparks Hot Slag Open Flame Electricity P A 3 D D12 Gas Hot Surfaces Hot work Eye Damage Welding Hot Slag Open Flame Electricity Gas Hot Surfaces P A 4 D D12 good working order prior to use Contain your sparks as far as possible Barricade area below when welding overhead Remove / Protect all combustibles in the vicinity Always have a fire extinguisher at hand Inspect all cords and plugs for damage before use Put all hot off cuts from cutting work out of harm’s way During welding operations, proper welding gloves and full-face, UV-ray protective shield shall be worn to prevent injuries to the operator All small tools shall be inspected prior to use and found to be in good working order prior to use Contain your sparks as far as possible Barricade area below when welding overhead Remove / Protect all combustibles in the vicinity Always have a fire extinguisher at hand Inspect all cords and plugs for damage before use Put all hot off cuts from cutting work out of harm’s way HSE Site Supervisor 2 D D8 Workers & M Techinichin HSE Site Supervisor 1 D D4 Workers & welder L - Injury or possible P A 4 D D16 -All equipment must be visually inspected before use for signs of damage to fatality cables (worn or frayed), casings, plugs, etc., -Electric Shock -Trip devices (must be tested before use. Never stand on a damp or wet 2 D D8 Forman & Worker M Operators & HSE M surface when using electrical equipment and keep equipment clean and dry Operating Portable Electrical -Trip hazards tools (chipping & wood cutter,grinder,drill) -Appropriate guards / covers must be fitted to avoid contact with moving parts. - Wear correct PPE for tool and task -Injury by contact - Use tools only on the correct power supply as instructed on the maker’s label -Electrical Overload... - Before using check to see it is properly earthed, unless it is • Fire/explosion. an approved type that does not require earthing • Burns. -, Generator fitted with overload trip switches. • Electrocution • shall wear appropriate PPE – face shield, earmuff, goggles adequate to their job Ground condition Soft soil Failure of equipment Hand injury Collapsing of out Riggers P A 3 D D12 Use of adequate PPE Lack of competency: Selection of craftsman to do Personal injury & worker injury -Equipment damage P the job - Damage to the facilities A 2 C C6 Mix chemical material Works too close to persons within the same working area Heat stroke serious suffering from thirst, inhalation of sand dust Machine strikes another vehicle or person in the P A 4 D Stacking area should be compacted Equipment must be checked daily D16 Designated responsible person shall -Ensure that the personnel are competent and all work activities is carried out in a safe manner and any other statutory regulation requirement are complied with before any work activities commence. -Conduct Toolbox meeting, -Review the Method statement and Job hazard analysis to all craftsmen involve in the work activities -Ensure personnel clearly understand about the specific work activities. BASRAH UPGRADING Responsible person will conduct inspection and monitor the work activities. -Responsible person must ensure safety standard and work procedure is strictly adhering to. -IITS (Instruction, Information, Training, Supervision) Ensure that all equipment is having valid QP certificate to work in the vicinity. Make sure all operators know safe limitations of their equipment. Assigned a competent banksman when equipment is moving at the working area. Heat stress management program when working during extreme high temperature Follow mid-day break rules Providing sunshade shelter Providing enough cold drinking water Periodic resting system for workers Applying of rotation of workforce / shift working 2 C C6 1 C C3 Operators & HSE M Construction manager M - HSE Supervisor - Site Supervisor 1 D D4 - Foreman - Permit H vicinity Inhalation of harmful dust and fumes and skin. Chemical burns and skin irritation. Chemical spillage to the ground Rigging by using chain block and tackles Non-Fixed lifting points. Cuts, bruises, trapped fingers. Dropping of loads Surpass the SWL. Raise to the point of the hook. Clutter the hook and the fittings. Allow the load to swing out of reach. Leave unattended suspended loads. Collapse, fall the load. Uncertified tackles P A R 3 D D12 Ensure strict control measure to separate mechanical plant and enforce swing radius area as a no go area for any person of vehicle in order to avoid collision. Wearing appropriate of dust mask Paramedical / ambulance support available. Ensure to wear suitable respiratory protective equipment such as a P, N, R and N95 respirator when fumes from dust can’t be avoided. Remove person to fresh air if discomfort of appropriate PPE (Safety googles, Safety rubber shoe, Rubber gloves, Dust mask, etc.) Immediate removal of chemical spillage from ground if any Use your experience, knowledge, and training to assess risks and follow procedures. Before operating an overhead manual chain hoist, read the manual and understand how to safely and properly use the overhead manual chain hoist. Inspect the overhead manual chain hoist before use. Do not operate an overhead manual chain hoist that is damaged or has any actual or suspected malfunction. Do not attempt to lengthen or repair the lifting chain. Do not wrap the lifting chain around the load. Do not use an overhead manual chain hoist to lift or support people. Do not operate if the overhead manual chain hoist, its lifting chain, and its hooks are restricted from forming a straight line from hook to hook in the direction of loading. Do not use an overhead manual chain hoist in a way that causes its hooks to be side loaded. Do not use the lifting chain, or the hooks, or any other part of the overhead manual chain hoist as a ground for welding. Do not allow a welding electrode to be touched to the lifting chain, or the hooks, or any other part of the overhead manual chain hoist. Do not remove or obscure any warning labels on the overhead manual chain hoist. Do not allow anyone under a suspended load. Protective gear to be worn at all times, this includes goggles/glasses, ear defenders, and steel toe capped shoes and face masks, correct clothing to be worn at all times. Using certified overhead manual chain hoist and all other accessories. Protect accessories when attach with load. 1 C C3 All workers L Burn Pipes (PWHT) Fire Explosion. Presence of flammable gas. Sparks from faulty equipment. Leak of electric cables. P A R 3 D D12 Keep flammable materials away from the work area. Prepare a fire extinguisher. Fire watch must be kept at the workplace during wok (PWHT) is performed. Make sure gas source have been closed. Put barricade/signage. Changing the damaged equipment. Make checks on all used equipment. Change the damaged electric cable. Always check the cable before use. Only competent person are authorized to do the work. Wear Proper PPE. Ensure the equipment / tool to be used for Heat Treatment (such as Heat Tracings, Cables, terminals, switches and panel etc.) are free from defect and suitable for the temperature ratings of the system. Ensure proper insulation of heat tracing coil and terminals. Keep the area dry ensuring no water spillage. Do not bring any flammable liquid or gas at the location where heat treatment is under progress. Do not touch the pipe segment which is being heat treated. Do not leave the tool or equipment in energized condition when the heat treatment is in progress. Isolate power to the equipment when not in use. Do not change (exceed / decrease) the Temperature or duration of heat treatment without permission from Inspection Engineer. Monitor the temperature in the heat treatment panel. Do not apply rapid heating or cooling of the pipe segment. Refer Heat Treatment Procedure or Contact Inspection Engineer in case of doubt. 2 D D8 All workers L • Manual handling Work Completion & • Incorrect tools Housekeeping • Ensure continued housekeeping conducted P E A R 3 B B6 1 B B2 • Use correct and safe tools • Slip, trip, fall Prepared by: Subcon Manager: Reviewed by: HSE Manager: Approved by: Discipline Name: Name: Manager: Signature: Signature: Name: Signature: All staff L STARRT Form (STEP 1) GREETING (Checking In) Hi, how are you, how are you doing? Tick box once completed LINK PROGRESS AND QUALITY TO HSSE THROUGHOUT (STEP 2) TASK PLANNING (THE TASK IDENTIFICATION AND DETAILS) Work Post weld heat treatment for pipes (PWHT). Description Supervisor Name & Contact No J.B Kim 07833224771 Work Area Location Company DAESHIN PLANT Method Statement/JSA number Number of men in work party 10 Permit to Work number Work duration 6:00 am – 5:00 pm Date UG WORKSHOP, HDEC PIPING From To 26-NOV-2022 02-DEC-2022 (STEP 3) TASK PLANNING (COMPETENT PERSONS, TOOLS AND EQUIPMENT NECESSARY TO DO THE TASK) Competent Persons Tools Required Equipment Required Additional PPE Required EX: Radios, Ex: Manlift, compressor, Required Ex Equipment operators, Special testing crane, forklift, truck etc Ex: Fire retardant AMP, VAMP, Vendors etc meters, electric coverall, Safety tools, special tools, harness, Chemical SCBA etc splash goggles etc Generator Grinding machine Face shield Grinder Leather gloves Full PPE Welding Face shield Welder PWHT Machine Welding machine Welder Apron Leather gloves Mask Hand tools (STEP 4) AREA RISK MANAGEMENT (AREA HAZARDS) - LIST ANY NEARBY ACTIVITIES THAT MAY IMPACT THE WORK, (INCLUD ELEVATED AREAS) N/A (STEP 5) RISK IDENTIFICATION AND RISK MANAGEMENT What is the task? List task steps List potential hazards (write List controls (write words words or codes from step 6 or codes from step 6 below) below) H3,H4,H5,H8,H10,H11,H12,H13,H14,H1 C3,C4,C5, PWHT Activity 5,H18,H19,H25,H31 C8,C10,C11,C12,C13,C14,C15,C18, ,C19,C25,C31 H3,H4,H5,H8,H10,H11,H12,H13,H15, C3,C4,C5,C8,C10,C11,C12,C13,C15 Lamination Activity H17,H18,H23 ,C17,C18,C23 H3,H10,H11,H12 C3,C10,C11,C12 House keeping LINK PROGRESS AND QUALITY TO HSSE THROUGHOUT 1 2 (STEP 6) TASK RISK MANAGEMENT (TASK HAZARD AWARENESS, RECOGNITION AND CONTROLS) 1 3 HAZARDS OF THE TASK (H) tick if applicable to task () HOW TO CONTROL THE TASK HAZARDS (C) Tick if applicable to task () 100% tie-up. Green tag on scaffold and lifeline. Awareness of working overhead. Work at Height training Green tag on scaffold. Work at Height training Good housekeeping. Access free from obstructions Tools in good condition. Tool inspected. Right tool for the job Electrical tools in good condition. Inspected and colour coded Barricade. Colour code on rigging gear. Qualified rigger in work team Confined Space Permit. Hole Watchman. Gas Test Artificial lighting. High visibility vest H1 Working at Height C1 H2 Scaffolding C2 H3 Slips Trips and Fall Potential H4 Injury from use of defective or invalid hand tools H5 Electricity H6 Lifting operations C6 H7 Confined Space C7 H8 Poor Lighting / Low Visibility C8 H9 Falling Objects C9 Hard-hat. Good housekeeping. Tied off tools. Awareness of overhead work H10 High Ambient temperature / Physical conditions C10 Water available. Heat stroke flag. Regular breaks. Proper acclimation. √ C11 Managed work breaks. Look out for your buddy C12 Eye protection. Dust masks √ √ √ √ √ H11 Fatigue / Physical tiredness H12 Dust H13 Hot Work / Fire H14 Grinding H15 Manual handling of heavy loads √ √ √ √ √ √ √ √ √ H16 Rotating Equipment C3 C4 C5 C13 C14 Area free of combustible materials. Fire watchman. Fire extinguisher / blankets Correct PPE (Eye protection, face shields, gloves, other) C15 Assess manual lift before starting work. Mechanical lifting C16 Machinery Guarding. Lock Out / Tag Out H17 Hot Surfaces √ C17 PPE (gloves, coveralls). Guarding. Barricades and warning sign H18 Sharp and Jagged Objects √ C18 PPE (gloves, coveralls). bar caps in place H19 Nearby work √ C19 Foreman to co-ordinate, assess and communicate to workers H20 Hydro testing C20 Barricades. Hydro test Permit. shields H21 Pressurized systems C21 Certified equipment. Barricades. Warning signs. Awareness Exposed man-holes & incomplete structures Guarding. Re- Oxygen deficient atmosphere & inert gases C26 H27 Radiation and X-Ray emissions C27 H28 Work near water / drowning C28 Barricades. Life vests Working with Chemicals / Possibility of Fumes/ Spills Vibrating equipment - impact hammers and compactors H23 H24 H25 Noise H26 C22 √ C23 C24 √ C25 1 4 √ √ √ Face Hard barricades, signage and covers, grating removal permit Safety Data Sheet, Gloves, Coveralls, Aprons, Chemical Suits, material correctly Rotate Operators, Metatarsal protection, Hearing Protection Hearing Protection. Visible Evacuation Alarm Isolations, Confined space permit. Purging barricades Barricades, warning signs, NDE permit H22 √ √ √ √ √ H29 Working inside Client fenced area H30 Proximity to other commissioning activities H33 C30 √ H31 Work in Client area H32 C29 Work on blinded systems and pipes Work in SIMOPS/ Live Line / Red Blind area C31 Client training, respect signs and line labels, when in doubt assume system is LIVE, use Client PTW. Supervisor to communicate with his Front-Line Supervisor (FLS) prior to work and agree work plan and priorities. Use MOPA matrix. Use Client PTW, Read Tags, do not alter Tags. Respect barricades. C32 Spade removal certificate plus Client PTW to be used. C33 SIMOPS PTW to be used H34 Work on or near (With potential of contact with) live electric systems C34 AEP to be present on site. Client PTW. CEP’s to perform the task. Risk Assessment to be conducted. H35 Work on or near live steam systems C35 RA to be conducted. Where practicable LOTO applied and Client PTW √ (STEP 6) TASK RISK MANAGEMENT (TASK HAZARD AWARENESS, RECOGNITION AND CONTROLS) HAZARDS OF THE TASK (H) tick if HOW TO CONTROL THE TASK HAZARDS (C) applicable to task () Tick if applicable to task () H36 Work on or near live gas systems C36 RA to be conducted. Where practicable LOTO applied and Client PTW H37 Work on or near live Nitrogen system C37 RA to be conducted. Where practicable LOTO applied and Client PTW H38 Work on or near live compressed air system C38 RA to be conducted. Where practicable LOTO applied and Client PTW H39 Work on or near live hydraulic system C39 RA to be conducted. Where practicable LOTO applied and Client PTW C40 SDS available and briefed to workers. secondary containment arranged. spill kit and training. PPE including chemical suit if needed (Tyvek Tychem coveralls) C41 Only intrinsically safe radios C42 Communication (Inform to another team) H40 Potential loss of containment H41 Hazardous Area Communication H42 Work in Close/ Proximity to others √ 1 5 √ (STEP 7) UNPLANNED EVENTS (If any of the following occurs, stop work and talk to your supervisor) Nearby work Chemical Excessive Fires and Unusual odors Heat stress hazards spills or noise explosions releases Evacuation Extreme Significant Change in the following work conditions: alarm weather / high near miss winds LINK PROGRESS & QUALITY TO HSSE THROUGHOUT Step (8) INCIDENT (EMERGENCY) PLAN AND ACTIONS Project Emergency Number………………. Emergency telephone number HDEC: 07716220428-07803857788 Nearest Muster point/safety shelter location Alarm code(for communication period) Evacuation Route(supervisor to explain to works) Safety shower/eye washer location Nearest first aid station location: STEP (9) STEP BACK 5 X 5 (ADD FEEDBACK RECEIVED FROM CREWS Project Emergency Number 1 6 Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 1 7 Time Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 1 8 Time Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 1 9 Time Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 2 0 Time Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 2 1 Time Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 2 2 Time Location: TBT Date: I acknowledge receiving and understanding these instructions. I will fully comply with the assigned task requirements. Name Position Badge No. Sign Name 1. 14. 2. 15. 3. 16. 4. 17. 5. 18. 6. 19. 7. 20. 8. 21. 9. 22. 10. 23. 11. 24. 12. 25. 13. 26. Position Badge No Sign I have Briefed my Workers on the Safety Requirements of this Task Supervisor: Signature: Time: : (AM / PM) FIELD AUDIT OF THE STARRT BY MANAGERS/SUPERVISORS Name Signature Contractor EPCC Contractor 2 3 Time