EPC of Onshore Pipelines and Facilities for ASK Development and DG2P Project CFT No. MMC22-5003 Lists of COMPANY ITEMS ITEM NO. A A.1 DESCRIPTION Shipment No. ……./ ……. Exhibit I Annex-1 Quantity (Meters / Nos.) Milestone Date 24” DG2P – Onshore Export Pipeline (NTP#1) GTL01 Pipe 610 mm OD, API 5L X-65, PSL2 & Non-Sour Service, LSAW, Beveled End A.1.1 19.1 mm WT, 3.5 mm 3LPE LOT #2 9,296 A.1.2 19.1 mm WT, 3.5 mm 3LPE, with 90 mm Concrete Weight Coated LOT #2 405 A.1.3 19.1 mm WT, Bare pipe for WQT LOT #1 12 28th August 2024 A.1.4 19.1 mm WT, 3.5mm 3LPE (emergency) LOT #2 120 26th November 2024 A.1.5 19.1 mm WT, Bare pipe for Valve Pup Pieces LOT #1 12 19.1 mm WT, 3.5 mm 3LPE 19.1 mm WT, 3.5 mm 3LPE, with 90 mm Concrete Weight Coated LOT #2 2,599 LOT #2 90 A.2.3 19.1 mm WT, Bare pipe for WQT LOT #1 12 28th August 2024 A.2.4 19.1 mm WT, 3.5 mm 3LPE (emergency) LOT #2 120 26th November 2024 A.2.5 19.1 mm WT, Bare pipe for Valve Pup Pieces LOT #1 12 28th August 2024 A.2 A.2.1 A.2.2 A.3 26th November 2024 26th November 2024 28th August 2024 GTL02 Pipe 610 mm OD, API 5L X-65, PSL2 & Non-Sour Service, LSAW, Beveled End 26th November 2024 26th November 2024 GTL03 Pipe 610 mm OD, API 5L X-65, PSL2 & Non-Sour Service, LSAW, Beveled End A.3.1 14.3 mm WT, 3.5 mm 3LPE LOT #2 63,721 26th November 2024 A.3.2 14.3 mm WT, 4.5 mm 3LPE LOT #2 3,421 26th November 2024 A.3.3 14.3 mm WT, 3.5 mm 3LPE, with 110 mm Concrete Weight Coated LOT #2 2,175 A.3.4 19.1 mm WT, Bare pipe for WQT LOT #1 12 28th August 2024 A.3.5 14.3 mm WT, Bare pipe for WQT LOT #1 24 28th August 2024 A.3.6 14.3 mm WT, 4.5 mm 3LPE (emergency) LOT #2 300 26th November 2024 A.3.7 14.3 mm WT, Bare pipe for Valve Pup Pieces LOT #1 24 28th August 2024 Sub-Total Item 7.0 (Item 7.1 to 7.3) 26th November 2024 82,355 B 14” DG2P – Onshore Export Pipeline (NTP#1) B.1 GSL01 Pipe 356 mm OD, API 5L X-65, PSL2 & Non-Sour Service, HF-ERW, Beveled End B.1.1 9.53 mm WT, 3.5 mm 3LPE LOT #2 20,450 26th November 2024 B.1.2 9.53 mm WT, 4.5 mm 3LPE LOT #2 1,344 26th November 2024 B.1.3 9.53 mm WT, 3.5 mm 3LPE, with 60 mm Concrete Weight Coated LOT #2 542 B.1.4 9.53 mm WT, Bare pipe for WQT LOT #1 24 28th August 2024 B.1.5 9.53 mm WT, 4.5 mm 3LPE (emergency) LOT #2 180 26th November 2024 B.1.6 9.53mm WT, Bare pipe for Valve Pup Pieces LOT #1 12 28th August 2024 Sub-Total Item 8.0 26th November 2024 22,552 C 24” DG2P – Onshore Hot Induction Bend, API 5L X-65, PSL2 & Non-Sour Service, LSAW, Beveled End (NTP#1) C.1 GTL01 – Bend 610 mm OD x 19.1mm WT, 3.5mm 3LPE Coating, TL=1000mm, R=5 OD C.1.1 Bend 30° (spare) LOT #2 6 26th November 2024 C.1.2 Bend 45° (spare) LOT #2 6 26th November 2024 C.1.3 Bend 27° LOT #2 1 26th November 2024 C.1.4 Bend 28° LOT #2 2 26th November 2024 Page 6 of 9 EPC of Onshore Pipelines and Facilities for ASK Development and DG2P Project CFT No. MMC22-5003 Lists of COMPANY ITEMS ITEM NO. DESCRIPTION ……./ ……. Exhibit I Annex-1 Quantity Shipment No. (Meters / Nos.) Milestone Date C.1.5 Bend 30° LOT #2 1 26th November 2024 C.1.6 Bend 33° LOT #2 1 26th November 2024 C.1.7 Bend 35° LOT #2 1 26th November 2024 C.1.8 Bend 36° LOT #2 1 26th November 2024 C.1.9 Bend 45° LOT #2 7 26th November 2024 C.1.10 Bend 49° LOT #2 1 26th November 2024 C.1.11 Bend 54° LOT #2 1 26th November 2024 C.1.12 Bend 55° LOT #2 1 26th November 2024 C.1.13 Bend 90° LOT #2 1 26th November 2024 C.2 GTL02 – Bend 610 mm OD x 19.1mm WT, 3.5mm 3LPE Coating, TL=1000mm, R=5 OD C.2.1 Bend 30° (spare) LOT #2 2 26th November 2024 C.2.2 Bend 45° (spare) LOT #2 2 26th November 2024 C.2.3 Bend 34° LOT #2 1 26th November 2024 C.2.4 Bend 37° LOT #2 1 26th November 2024 C.2.5 Bend 45° LOT #2 7 26th November 2024 C.2.6 Bend 47° LOT #2 1 26th November 2024 C.2.7 Bend 50° LOT #2 1 26th November 2024 C.2.8 Bend 68° LOT #2 1 26th November 2024 C.2.9 Bend 90° LOT #2 2 26th November 2024 C.3 GTL03 – Bend 610 mm OD x 19.1mm WT, 3.5mm 3LPE Coating, TL=1000mm, R=5 OD C.3.1 Bend 30° (spare) LOT #2 8 26th November 2024 C.3.2 Bend 45° (spare) LOT #2 8 26th November 2024 C.3.3 Bend 27° LOT #2 1 26th November 2024 C.3.4 Bend 29° LOT #2 1 26th November 2024 C.3.5 Bend 30° LOT #2 4 26th November 2024 C.3.6 Bend 31° LOT #2 1 26th November 2024 C.3.7 Bend 33° LOT #2 2 26th November 2024 C.3.8 Bend 37° LOT #2 1 26th November 2024 C.3.9 Bend 39° LOT #2 1 26th November 2024 C.3.10 Bend 45° LOT #2 14 26th November 2024 C.3.11 Bend 50° LOT #2 1 26th November 2024 C.3.12 Bend 51° LOT #2 2 26th November 2024 Bend 53° LOT #2 1 C.3.14 Bend 54° LOT #2 1 26th November 2024 C.3.15 Bend 60° LOT #2 1 26th November 2024 C.3.16 Bend 63° LOT #2 1 26th November 2024 C.3.17 Bend 72° LOT #2 2 26th November 2024 C.3.18 Bend 79° LOT #2 1 26th November 2024 C.3.13 26th November 2024 Page 7 of 9 EPC of Onshore Pipelines and Facilities for ASK Development and DG2P Project CFT No. MMC22-5003 Lists of COMPANY ITEMS ITEM NO. DESCRIPTION ……./ ……. Exhibit I Annex-1 Quantity Shipment No. (Meters / Nos.) Milestone Date C.3.19 Bend 80° LOT #2 1 26th November 2024 C.3.20 Bend 87° LOT #2 1 26th November 2024 C.3.21 Bend 90° LOT #2 3 26th November 2024 Sub-Total Item 10.0 (Item 10.1 to Item 10.3) ITEM NO. DESCRIPTION 104 Shipment No. Quantity (Meters / Nos.) Milestone Date D 20” ASK – Onshore Export Pipeline D.1 APL01 - Pipe 508mm OD, API 5L X-65, PSL2 & Severe Sour Service, LSAW, Beveled End D.1.1 14.3 mm WT, 3.5 mm 3LPE LOT #2 2,636 D.1.2 14.3 mm WT, 3.5 mm 3LPE, with 100 mm Concrete Weight Coated LOT #2 90 D.1.3 14.3 mm WT, Bare pipe for WQT LOT #1 24 28th August 2024 D.1.4 14.3 mm WT, 3.5 mm 3LPE (emergency) LOT #2 120 26th November 2024 D.1.5 14.3 mm WT, Bare pipe for Valve Pup Pieces LOT #1 12 28th August 2024 E E.1 26th November 2024 26th November 2024 Sub-Total Item 9.0 2,882 20” ASK – Onshore Hot Induction Bend, API 5L X-65, PSL2 & Severe-Sour Service, LSAW, Beveled End APL01 – Bend 508 mm OD x 19.1mm WT, 3.5mm 3LPE Coating, TL=1000mm, R=5 OD E.1.1 Bend 30° (spare) LOT #2 2 26th November 2024 E.1.2 Bend 45° (spare) LOT #2 2 26th November 2024 E.1.3 Bend 45° LOT #2 7 26th November 2024 E.1.4 Bend 50° LOT #2 1 26th November 2024 E.1.5 Bend 90° LOT #2 3 26th November 2024 Sub-Total Item 11.0 15 Page 8 of 9 EPC of Onshore Pipelines and Facilities for ASK Development and DG2P Project CFT No. MMC22-5003 Lists of COMPANY ITEMS ITEM NO. DESCRIPTION Shipment No. ……./ ……. Exhibit I Annex-1 Quantity Milestone Date (Meters / Nos.) (Note1) F 24” DG2P – Onshore Export Pipeline (NTP#2) F.1 GTL04 Pipe 610 mm OD, API 5L X-65, PSL2 & Non-Sour Service, LSAW, Beveled End F.1.1 14.3 mm WT, 3.5 mm 3LPE LOT #6 75,373 F.1.2 14.3 mm WT, 4.5 mm 3LPE LOT #6 3,415 31st July 2025 31st July 2025 F.1.3 19.1 mm WT, 4.5 mm 3LPE LOT #6 60 31st July 2025 F.1.4 14.3 mm WT, 3.5 mm 3LPE, with 110 mm Concrete Weight Coated LOT #6 1,797 F.1.5 19.1 mm WT, Bare pipe for WQT LOT #6 12 31st July 2025 F.1.6 14.3 mm WT, Bare pipe for WQT LOT #6 24 31st July 2025 F.1.7 14.3 mm WT, 4.5 mm 3LPE (emergency) LOT #6 300 31st July 2025 F.1.8 14.3 mm WT, Bare pipe for Valve Pup Pieces LOT #6 24 31st July 2025 G.1.1 Sub-Total Item 1.0 81,005 24” DG2P – Onshore Hot Induction Bend, API 5L X-65, PSL2 & Non-Sour Service, LSAW, Beveled End (NTP#2) GTL04 – Bend 610 mm OD x 19.1mm WT, 3.5mm 3LPE Coating, TL=1000mm, R=5 OD 31st July 2025 Bend 30° (spare) LOT #6 8 G.1.G Bend 45° (spare) LOT #6 8 31st July 2025 G.1.3 Bend 30° LOT #6 2 31st July 2025 G.1.4 Bend 31° LOT #6 2 31st July 2025 G.1.5 Bend 32° LOT #6 1 31st July 2025 G.1.6 Bend 33° LOT #6 1 31st July 2025 G.1.7 Bend 38° LOT #6 1 31st July 2025 G.1.8 Bend 39° LOT #6 1 31st July 2025 G.1.9 Bend 42° LOT #6 1 31st July 2025 G.1.10 Bend 43° LOT #6 4 31st July 2025 G.1.11 Bend 45° LOT #6 20 31st July 2025 G.1.12 Bend 48° LOT #6 1 31st July 2025 G.1.13 Bend 50° LOT #6 1 31st July 2025 G.1.14 Bend 51° LOT #6 1 31st July 2025 G.1.15 Bend 57° LOT #6 1 31st July 2025 G.1.16 Bend 61° LOT #6 1 31st July 2025 G.1.17 Bend 74° LOT #6 1 31st July 2025 G.1.18 Bend 81° LOT #6 1 31st July 2025 G.1.19 Bend 82° LOT #6 1 31st July 2025 G.1.20 Bend 83° LOT #6 1 31st July 2025 G G.1 Sub-Total Item 2.0 Note: 31st July 2025 58 1. Delivery date of COMPANY ITEMs for NTP#2 shall be determined by CONTRACTOR to suit the Work Package B3 schedule, refer EXC Annex-1. Delivery date scheduled by Supplier can start since 31 st July 2025. Page 9 of 9