Uploaded by Asmerom Mosineh

Wro Hibist Residence to 27m road to Yegnban river

advertisement
THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA
MINISTRY OF URBAN DEVELOPMENT
AMHARA NATIONAL REGIONAL STATE
UIIDP PROJECT
PARTIAL ENVIRONMENTAL IMPACT ASSESSMENT
REPORT OF DEBRE MARKOS CITY ADMINISTRATION
DRAINAGE PROJECT
FROM WRO HIBIST RESIDENCE TO 27M ROAD TO
YEGNBAN RIVER
October 2021
Debre Markos
1
Table of Contents
Title
Page
1.1 Objectives............................................................................................................................................... 6
1.2 General Objective ............................................................................................................................. 6
1.3 Specific Objective .............................................................................................................................. 6
2. Methodology ............................................................................................................................................ 7
4. Assumption .............................................................................................................................................. 7
5. Policy, Legislative and Institutional Frameworks................................................................................ 7
5.1 Policy Framework ............................................................................................................................. 8
5.1.1. The constitution of the Federal Republic of Ethiopia ............................................................ 8
5.1.2. Environmental Policy of Ethiopia ........................................................................................... 9
5.1.2 World Bank Safeguard Policies ................................................................................................ 9
5.2. Legal Frameworks ......................................................................................................................... 10
5.2.1. Federal Level Proclamations.................................................................................................. 10
5.2.2. Regional Level Proclamations................................................................................................ 10
5.2.2.1 Environmental Impact Assessment Proclamation ............................................................. 10
5.3 Institutional Framework ................................................................................................................ 11
5.3.1. Federal Environmental Protection Authority (EPA)........................................................... 11
5.3.2 Environmental Protection, Land Administration and Use Authority ................................ 11
5.3.3 City Administration ................................................................................................................. 11
6. Project Justification .............................................................................................................................. 11
7. Baseline Environmental Conditions of Project Area ...................................................................... 12
7.1 Bio-Physical Environment ............................................................................................................ 12
7.2 Socio Economic Environment ...................................................................................................... 13
7.3 Climate .......................................................................................................................................... 13
8.1 Potential Positive Impacts ............................................................................................................. 13
8.1.1Construction Stage ...................................................................................................................... 13
Employment ........................................................................................................................................ 13
8.1.2 Operation Stage .......................................................................................................................... 13
8.2 Potential Negative Impacts ........................................................................................................... 14
8.2.1Construction Phase...................................................................................................................... 14
2
8.2.2 Operation Phase ......................................................................................................................... 14
Accident and Safety Risk .................................................................................................................... 14
8. Mitigation Measures ....................................................................................................................... 14
8.1 Construction Phase........................................................................................................................ 14
8.2 Operation Phase ............................................................................................................................ 15
9. Environmental Management Plan ................................................................................................... 15
Table 9.1 Environmental Management Plan ..................................Ошибка! Закладка не определена.
10. Environmental Monitoring ................................................................................................................ 18
Table 10.1 Environmental Monitoring Plan ...................................Ошибка! Закладка не определена.
11. Nature of Public Participation ........................................................................................................... 21
Conclusion ................................................................................................................................................. 21
Reference ................................................................................................................................................... 22
Reference
Appendix
List of Tables
Table 9.1 Environmental Management Plan …………………………..16
Table 10.1 Environmental Monitoring Plan---------------------------------18
3
Acronyms
ANRS
Amhara National Regional State
CIP
Capital Investment Plan
EIA
Environmental Impact Assessment
EIS
Environmental Impact Statements
EPE
Environmental Policy of Ethiopia
EPLUA
Environmental Protection, Land Administration Authority
ESIA
Environmental and Social Impact Assessment
IDA
International Development Association
IEE
Initial Environmental Examination
MSE
Micro Small Enterprise
ULGDP
Urban Local Government Development Project
4
Executive Summary
The city of Debre Markos planned different infrastructure and service delivery projects in 2014 financial
year cobblestone road, gravel, drainage, shed and park are the main projects which is planned to
construct. From these projects open masonry drainage project which is located on kebele 07
administration is the one. The proponent of this project is Debre Markos City Industry Development and
City Service office and this IEE is prepared by Debre Markos City Industry Development and City
Service office, Hosing and Infrastructure core process. Wro Hibist Residence to 27m road to Yegnban
river is 280m length. No drainage system in this area and there is flooding risks to the local residents.
Prioritization is given at kebele and city administration level during planning so the city administration
decided to construct proper drainage system to reduce flooding risk. The drainage system is an open
masonry and the total estimated cost of the project is 1352375.08 Birr and the implementation of the
project will start on December 2014EC.
To construct open masonry drainage excavation work, cart away, compaction of masonry wall and after
compaction constructing the drainage as per the design are the main activities during construction.
Plastering and pointing, Back fill and compaction are main activities during finishing. Finally the open
masonry drainage will be covered with Bazola as per design on road junctions.
During different project phase before, during construction and operation there might have positive and
negative impacts and IEE report identify the major positive and negative impacts of the proposed project.
The major positive impact of the project includes employment, improve flooding risk, increase aesthetic
value and reduce soil erosion problem of the area and the major negative impacts which are identified
during IEE study includes Disposal site acquisition, Accident and Safety risks and flooding risks. There
are different mitigation measures recommended to reduce or minimize the negative impacts of the
proposed project which includes allocating appropriate relocation cost, use excavated soil for back fill
purpose or fill eroded gullies, construct cover slab, allocating the appropriate maintenance cost,
participation of the local community in keeping clean the culverts and open-ditch, improve the waste
(liquid and solid waste) management system of the town and timely cart away of the spoil. The mitigation
measures are monitored by setting different methods and parameters on site and at office level with
different frequency. It also identifies responsible body of monitoring including kebele administration,
local residents, city service office and zone EPLUA.
5
1. Background
Debre Markos is one of the newly 18 UIIDP participating cities in Ethiopia and one of the newly 6 cities
in Amhara region.
The city has planned different infrastructure and service delivery projects under its capital investment
projects. Cobble stone road, Gravel road, Drainage, Greenery, Shed and street light are the main
infrastructure and service delivery projects which are planned for the year 2013 EC. These projects will
be financed by IDA (UIIDP) and by the City Administration, Road Fund and other development partners.
Open Masonry Drainage is one of the projects which the city has planned to construct in different kebeles
of the city administration. The city has 89.69 km open drainage until 2014 E.C. The implementation of
masonry drainage project will create employment opportunities; improve flooding risks and reduce the
problem of soil erosion.
However, the project may have negative environmental and social impacts and before implementing the
proposed drainage project considering environmental issues through Environmental and Social Impact
Assessment (ESIA) is mandatory. Environmental and social impact assessment is the major thing which
is to be study before the construction of any project.
The adverse environmental issues likely to develop during project construction and operation phases
could be minimized by making necessary provision in the project design and adopting Environmental
Management Plan (EMP). This IEE report organized as per the Environmental impact assessment
guideline and it consists executive summary, introduction, approach to the study, policy, legal and
administrative framework, baseline information, description of the project, environmental impacts
mitigation measures ,environmental management plan, environmental monitoring, nature of public
participation and conclusion and recommendation.
1.1 Objectives
1.2 General Objective
The objectives of the environmental impact assessment study is to assess and clearly identify the potential
negative and positive impacts of the project and propose mitigation measures to reduce or avoid the
adverse impacts while enhancing the beneficial ones and integrate them into the project activities.
1.3 Specific Objective
 To assess the benefits and adverse effects of the proposed project
 To propose mitigation measures to reduce the adverse impacts of the proposed project
 To prepare environmental management plan
6
 To implement the proposed mitigation measures that are set in the environmental management
plan
2. Methodology
The ESIA study team used different methodology to undertake the study by reviewing the existing
literatures, policies, proclamations, guideline and site visits.
I.
Site Visits:-An extensive field visit to the project area was conducted to collect primary data on
bio-physical and socio-economic conditions of the project area as well as to identify the existing
environmental issues and the potential environmental effects of the proposed project.
II.
Reviewing of the Existing Literature: -Relevant documents on previous studies as well as
important guidelines relevant to the project were reviewed. Guidelines such as Urban Local
Development Project Environmental and Social Management Guideline, Federal EIA procedural
Guidelines, Amhara region EIA Guidelines, Environmental policies and sectorial environmental
policies, Proclamation on Environmental Impact Assessment were assessed to get relevant
information.
III.
Report Writing: - report is conducted as per the requirement of the environmental impact
assessment guideline produced by World Bank and Amhara region environmental protection, land
administration and use Bureau.
The report is prepared by three individuals with different discipline environmentalist, surveyor, and
Urban Management and UIIDP team as a whole.
3. Approach to the Study
The overall approach to the study is designed as per the ESMG and RSG frameworks in accordance
with the Ethiopian Environmental Impact Assessment requirements and guidelines. Thus, in undertaking
the EIA, National and Regional policies, legislations and guidelines are used to identify the relevant
environmental policies, laws and regulations pertinent to environmental protection and social safeguards
issues, and natural resources management. The objective of the assessment is to assess and identify the
positive and negative impacts and propose the mitigation measures for negative impacts based on
professional opinion and checklist.
4. Assumption
To undertake this study the study team has encountered some problems which includes lack of relevant
data, lack of experience and enough reference material.
5. Policy, Legislative and Institutional Frameworks
The proposed project must be implemented in compliance with the relevant policies, legislatives and
institutional framework. Details regarding the existing policies, legislatives and institutional frameworks
of the Federal, regional and local are outlined below.
7
5.1 Policy Framework
5.1.1. The constitution of the Federal Republic of Ethiopia
The constitution of the Federal Democratic Republic of Ethiopia, issued on Agust21 1995, forms the
fundamental basis for enactment of specific legislative instruments governing environmental matters at a
national level. The Federal Constitution Article 43, 44 and 92 deals with environmental related rights,
obligations and objectives in the country. The most relevant articles are discussed below:
Article 43: The Right to Development identifies citizens’ right to: improved living standards and
sustainable development and participate in national development and to be consulted with respect to
policies and projects affecting their community.
The propose development project is based on the development right of the community that improves the
living standard of them. The community participated at kebele level during planning stage to prioritize
projects based on their development desire.
Article 44: Environmental Rights stipulations that all citizens have the right to a clean and healthy
environment; and those who have been displaced or whose livelihoods have been adversely affected as a
result of state programs have a right to commensurate monetary or alternative means of compensation,
including relocation with adequate state assistance.
The project will improve the environment before and after construction by clearing different wastes and it
also improves the drainage system in order to have a clean and health environment for local people.
Article 92: Environmental objectives are identified as: government shall endeavor to ensure that all
Ethiopians live in a clean and healthy environment. The design and implementation of programs shall not
damage nor destroy the environment. Citizens also have a right to full consultation and to expression of
views in the planning and implementation of environmental policies and projects that directly affect them.
Government and citizens shall have the duty to protect the environment.
Environmental problems which is caused by this open masonry drainage project that directly affect the
local community for those problems the city administration has duty to ensure that all local community
around the project area live in a clean and healthy environment and the local community also have the
right to express their views at planning and implementation of this project.
The project ensures the implementation of all these rights, the right to development, environmental rights
and environmental objectives. Constructing drainage system by consulting the affected and interested
parties is important. The city administration also ensures the protection of the environment to be clean
and healthy by incorporating environmental issues in the design and implementation of the project.
8
5.1.2. Environmental Policy of Ethiopia
The Environmental Policy of the Federal Democratic Republic of Ethiopia, or the Environmental Policy
of Ethiopia (EPE), was approved by the Council of Ministers in April 1997.The EPE’s overall policy goal
may be summarized in terms of the improvement and enhancement of the health and quality of life of
citizens as well as the promotion of sustainable social and economic developments through the adoption
of sound environmental management principles. Specific policy objectives and key guiding principles are
set out clearly in the EPE and expand on various aspects of the overall goal. The policy clearly outlined
the sectorial environmental policies, relevant to environmental management among others are: (i) Soil
Husbandry and Sustainable Agriculture; (ii) Forests, Woodlands and Trees; (iii) Genetic, Species and
Ecosystem Biodiversity; (iv) Water Resources; (v) Energy Resources; (vi) Human Settlement, Urban
Environment and Environmental Health; and (vii) ESIA.
The environmental policy has a number of issues concerning EIA, the importance of EIA to address
social, political and cultural impacts, and also physical and biological impacts, and the public consultation
to be part of the EIA procedures. Inclusion of impact mitigation measures within the design process for
development projects, and accident contingency plans to be incorporated within EIS. Development of a
legal framework for the EIA process, together with a suitable and coordinated institutional framework for
the execution and approval of EIA study and Environmental Audits are important. Development of
detailed technical sectorial guidelines for EIA and Environmental Auditing is essential.
5.1.2 World Bank Safeguard Policies
The city administration ensures the implementation of World Bank safeguard policy frameworks designed
for projects financed by the World Bank as well by city administration.
The safeguards related to this project include, OP/BP 4.01 Environmental Assessment, OP/BP 4.04
Natural Habitats, Environmental and social safeguards contained in the frameworks must be followed and
implemented when developing a project.
The proposed project is a new project which needs environmental assessment and it may also affects
natural habitat so to implement the project the city administration should ensure the implementation of
World Bank safeguard policy framework.
The proposed project may have different negative impacts on the local resident and natural resources by
affecting public utilities, creating safety problem and risk of flooding and health problem and it has also
problem of disposal site acquisition. The city administration will ensure the implement OP/BP 4.04
Natural Habitat World Bank safeguard policy by adopting different mitigation measures to reduce or
minimize the negative impacts of the proposed project.
9
5.2. Legal Frameworks
5.2.1. Federal Level Proclamations
There are several proclamations related to the proper implementation of projects and responses to
environmental concerns. The proclamations include the Environmental Impact Assessment Proclamation
No. 299/2002 which was promulgated in December 2002, the Environmental Protection Organs
Establishment Proclamation No. 295/2002 which was approved in October 2002, the Environmental
Pollution Control Proclamations No. 300/2002 which was passed in 2002, and the Solid Waste
Management Proclamation No. 513/2007 which was instituted in 2007. The former FEPA has published
series of environmental and social impact assessment guidelines for the different sectors outlining the
key issues, principles, procedures and processes to be adopted and adhered to avoid and/or mitigate
potentially negative environmental and social impacts during project planning, implementation and
operation by government, public and private entities. Some of the guidelines are generic and applicable in
different sectors and there are also sector specific guidelines prepared for key environmental and social
issues to adhere during the ESIA analysis in those specific sectors.
EIA proclamation No 299/2002 is directly linked with this proposed project due to the reason that any
project should pass through Environmental Impact Assessment and the proponent of the project should
ensure the implementation this proclamation at federal level.
Organs establishment proclamation No. 295/2002 also important for the proponent in order to identify
which institution will have responsibility for approval and monitoring of the proposed project and the
implementation of the IEE or EIA report.
The proposed project may create solid waste like cart away material due to bulk excavation for this reason
Solid Waste Management Proclamation No. 513/2007 is needed to manage the waste.
5.2.2. Regional Level Proclamations
5.2.2.1 Environmental Impact Assessment Proclamation
The Amhara National Regional State Environmental Impact Assessment (EIA) Proclamation No.
181/2011 was designed to outline the rules and regulations regarding an EIA. The proclamation defines
an Environmental Impact Assessment as one that reports the usage of and potential damage to
environmental resources due to the site selection, construction, operation and termination of a proposed
project, while presenting methods of mitigating potentially adverse effects.
As of Amhara Regional State Proclamation No 181/2011 EIA is mandatory for all development projects
including construction of drainage project which is one of the proposed project to be implemented in
10
Debre Markos city. This project ensures the implementation of rules and regulation of the EIA
proclamation in order to reduce environmental damage by mitigating the adverse impacts.
5.3 Institutional Framework
5.3.1. Federal Environmental Protection Authority (EPA)
In addition to the EPA, the investment Authority has responsibilities towards the environment. These are
captured in the Federal Negarit Gazeta- Proclamation No. 371996) which states that…. “The intended
investment activity would not be contravening the operational laws of the country and that, in particular,
it complies with conditions stipulated in environmental protection laws”.
With respect to duties, responsibilities and mandates of EPA, it is clearly stated in Environmental Impact
Assessment Proclamation No. 299/2002 sub Article 2 of Article 9 states that “The Authority or relevant
regional environmental agency shall, after evaluating an environmental impact study report by taking in
to account any public comments and expert opinions, within 15 working days.
Sub Article 1 of Article 12 also states that “ The Authority of the relevant regional environmental agency
shall monitor the implementation of an authorized project in order to evaluate compliance with all
commitments made by, and obligations imposed on the proponent during authorization” and sub Article 1
of Article 14 stated that “The Authority shall be responsible for evaluation of an environmental impact
study report and the monitoring of its implementation when the project is subject to licensing, execution
or supervision by a federal agency or when it is likely to produce trans – regional impact”.
5.3.2 Environmental Protection, Land Administration and Use Authority
EPLAUA has been established as a competent agency by proclamation No. 47/2000 and started
implementation of its warranted mandates and duties. In each zone, it has branch offices to implement the
duties and responsibilities vested by same proclamation.
East Gojjam Environmental protection, land administration and use department is responsible for
evaluation and monitoring of impact study and its implementation.
5.3.3 City Administration
Among other, the duties and mandates vested to the City Administration by the Proclamation No.91/2003
are to capacitate cities to be free from environmental pollution; and to conserve natural resources and to
utilize inputs appropriately. The aforementioned objectives and duties of the City Administration help to
guarantee the right of the people to live in a clean and healthy environment.
6. Project Justification
Inadequate infrastructure facilities such as access road, water supply and sanitation, drainage facilities and
public toilets have been worsening the day-to-day activities of the Debre Markos dwellers. Particularly
lack of drainage creates flooding risk and also creates negative health and comfort effect. Properly
11
constructed drainage system increases access for smooth traffic flow, accident free environments,
improve living standard, increases aesthetic value in the city. To improve the drainage system of the city,
city administration planned to construct drainage system in different kebeles and one of the proposed
projects will be implemented in 07 kebele administrations. The project is 280m length extending from
Wro Hibist Residence to 27m road to Yegnban river is 280m.There is no drainage system in this area
and there is flooding risks to the local residents. Prioritization is given at kebele and city administration
level during planning so the city administration decided to construct proper drainage system to reduce
flooding risk. The drainage system is an open masonry. The total estimated cost of the project is
1352375.08 Birr and the implementation of the project will start on December 2014 EC. To construct
open masonry drainage excavation work, cart away, compaction of masonry wall and after compaction
constructing the drainage as per the design are the main activities during construction. Plastering and
pointing, Back fill and compaction are main activities during finishing. Finally the open masonry drainage
will be covered with Bazola as per design on road junctions. Drainage project uses raw materials like
stone, cement and 02 crushed stone or gravel. All raw materials are found from licensed MSEs.
7. Baseline Environmental Conditions of Project Area
7.1 Bio-Physical Environment
The project area is located in 07 Kebele administrations extending from Wro Hibist Residence to 27m
road to Yegnban river is 280m. In the project area there are different infrastructures including electric
light, telephone, water supply, and poor quality eroded earthen road. The road is not comfortable for both
vehicles and pedestrians. This is mainly due to the reason that the road is eroded by the rain because there
is no proper drainage system on the area.
The type of the soil where the project implement is red soil, no cultural or historical heritages found in the
project area, the project area is residential. The living condition of the society in the project area the
majority are low income whereas other are middle income community.
The project needs selected materials like stone, sand, cement and aggregate (02) for mass concrete and
these different materials is covered by contractors. The contractors obtained these materials from different
quarry sites found around the boundary and outside the city administration.
Due to this project infrastructures like electric, water and telephone lines may stop their services. The city
administration proposes a mitigation measure of relocating public utilities before construction and they
may also stop services during construction the city administration ready to help the local residents if
kebele administration confirms that the problem occurs due to the construction of the project for the city
service office the problem will be solved immediately by contacting the responsible party and paying all
related expenses. This drainage will be constructed according to its existing situation or border so it
might not affect assets (land, houses or other) of the local residents.
12
7.2 Socio Economic Environment
The existing project site is surrounded by residential area and the estimated households that will be
benefited by this project is around 250 and a total of 1000 family members will be beneficial. There is no
household that will affect or lose their asset due to this project.
7.3 Climate
The annual rainfall of the city ranges from 1300 to 1380 mm and it rains heavily during the months
between June and October, moderate amounts of rainfall also occur between the months of March and
May as well. The temperature of the city ranges between 15°C and 25. Growing environmental concerns
such as deforestation may, however, severely impact the local climate in the future and is something to
consider as the city develops.
8. Environmental Impacts and Mitigation Measures of the Project
The environmental impacts have been identified based on the analysis of the environmental base line
information and activities that are to be undertaken (during construction, operation and subsequent
operation phase). The proposed project may have both beneficial and adverse impacts on social, economic
and environment. Major positive and negative impacts of this project during construction and operation
phases as well as possible mitigation measures are presented below.
8.1 Potential Positive Impacts
8.1.1Construction Stage
The positive impacts that are assessed to be expected at construction stage of the proposed project are
discussed below.
Employment
Construction of the proposed sub-project on the proposed sites in its construction phase will create
temporary employment opportunity. The total employment opportunity will be 60 from this 40 will be
male and 20 will be female.
8.1.2 Operation Stage
Improve flooding risk and access to road
The drainage system will reduce the flooding risk of the area and it also improving the drainage system
smoothened the surfaces and it will likely reduce flooding across and alongside the road. These measures
will improve traffic conditions and reduces hazards for motorized and non- motorized traffic.
Increasing the Aesthetic value of the area
The proposed drainage increases the aesthetic value of the area by reducing dust emissions and flooding
risks.
Reduce Soil Erosion
Due to the absence of drainage system in the area there is soil erosion and it form gully this proposed
13
project reduce soil erosion and formation of gully.
8.2 Potential Negative Impacts
Construction and operation of the proposed project may also bring a number of adverse impacts to the
natural and social environment.
8.2.1Construction Phase
Impact on Public Utilities
Construction of drainage on the proposed site may results the relocation of public utilities telephone,
electric poles and water lines; that bring temporary disruption of the public utility services provided by
respective public service providing institutions.
Disposal site acquisition
Construction of drainage may result in creation of bulk excavation which disposal may need site to avoid
the waste or spoil soil.
Creation of Quarry/ Borrow pit
Extraction of materials from quarries/borrow pits involve site clearance and movement of construction
materials from local sources to the construction sites, and will result in significant landslide and soil
erosion and possible changes in topography or ground surface relief features.
8.2.2 Operation Phase
Accident and Safety Risk
The construction of open drainage will bring difficulty of crossing especially to nearby residents (elders,
children and disable) and somehow to vehicles that are moving in the surrounding area in the absence of
incorporating appropriate crossing structures.
Risk of Flooding and health problem
During operation periods, luck of periodic maintenance and cleaning of open-ditches that are going to be
constructed within the proposed sites will bring risk of flooding and the drainage lines shall fill with
unmanaged municipal solid waste which could be potential health risk with the absence of proper waste
management.
8. Mitigation Measures
8.1 Construction Phase
Public Utilities
Allocating appropriate relocation cost for the affected public utilities
Timely relocation of those public utilities to their desired locations
Disposal site
Use the excavated soil for back fill purpose
Use the surplus spoil to fill eroded gullies, quarries, borrow pits and depressed areas;
14
Quarry site
The contractors cover all the materials which are needed to construct drainage.
Advise and check the contractor to bought their materials from certified ones
8.2 Operation Phase
Accident and Safety
Construct cover slab for junctions
Risk of Flooding and health problem
Allocating the appropriate maintenance cost;
Participation of the local community in keeping clean the culverts and open-ditch
Improve the waste (liquid and solid waste) management system of the town
Timely cart away of the spoil
9. Environmental Management Plan
Environmental management plan ensure how the environment will be managed during the construction
and operation phases and effective implementation of the identified mitigation measures and it also
identify the responsible bodies in implementing this management plan. The environmental management
plan covers summary of impacts, mitigation measures, responsible institutions, and implementation
schedules.
15
Table 9.1 Environmental Management Plan
Project phase
Before
Construction
16
Project
Activity
Significant
impact
Setting project
boundary and
Identification
of public utility
services
that
may
be
endangered by
the project /
Disruption of
Public Utility
services
-public
consultation
-Sit clearing
-clear right of
way
--
Enhancement/Mitigation Measure
Implementing
Bodies
Timeline for
implementati
on of
mitigation
activities
1 2 3 4
Cost estimate
--
Activity
Unit
Qua
ntity
Allocating appropriate
relocation cost for those
public utilities
Timely relocation of
those public utilities to
their desired locations
Meter
280
- Debremarkos
Urban
Development
and City Service
office
-Contractors
X
--
--
- Debremarkos
Urban
Development
and City Service
office
-Contractors
X
During
Construction
Operation
17
Earth work
-Dust
pollution
-
-Contractors
X X
Earth Work
Dusts
Periodic
wetting or
showering of working
area with water
Contractor
X X
Included in
the bill of
quantity
Acquisition of
disposal site for
waste
Use the excavated soil
for filling purpose
Use the surplus spoil to
fill
eroded
gullies,
quarries, borrow pits and
depressed areas up to 5
killo meter
Contractors
X X
Included in
the bill of
quantity
Open ditch
construction
Accident and
Safety
Open ditch
construction
and level of
awareness of
local residents
on waste
disposal
Risk of
Flooding, water
pollution and
health problem
Construct cover slab for
junctions and residents
worker safety first aid
kits , gaunt and other
equipment
Allocating
the
appropriate maintenance
cost
Participation of the local
community in keeping
clean the culverts and
open-ditch;
Improve
the
waste
(liquid and solid waste)
management system of
the town
Timely cart away of the
spoil
creating awareness on
communicable disease
Construct cover slab for
junctions and residents
worker safety first aid
kits , gaunt and other
equipment
Allocating
the
appropriate maintenance
cost
Participation of the local
community in keeping
clean the culverts and
open-ditch;
Improve
the
waste
(liquid and solid waste)
management system of
the town
Timely cart away of the
spoil
creating awareness on
communicable disease
Industrial
Development
and City Service
Office
Contractor
Industrial
Development
and City Service
Office
Contractor
Local Resident
Kebele
Administration
X Included in
the bill of
quantity
X Included in
the bill of
quantity
10. Environmental Monitoring
Environmental monitoring plan is an important tool to ensure the implementation of mitigation
measures for minimizing adverse impacts and maximizing the beneficial impacts. Environmental
monitoring generates useful information and improves the quality of implementation of
mitigation measures and it also assesses the effectiveness of these measures, or to identify further
corrective action and to detect any impacts that may not have been identified during the EIA
process, it is essential that an Environmental Monitoring Plan is put in place and implemented.
This EMP can be done before construction, during construction and after construction of the
proposed project road project.
The monitoring plan includes the method, parameter, location, frequency and responsibilities for
each of the monitoring activities and provides cost estimates.
18
Table 10.1 Environmental Monitoring Plan
Enhancement/Mitigation measure
Parameters to
Monitor
Location of
Monitoring
Methods of
Monitoring
Frequency
Responsibilitie
s
Cost of
Monitori
ng
Disturbance of
public utilities
Relocating Public Utilities
Number, km of
public utilities that
will be relocated/
Project site
Field
observation
Site Visit
Once in a
week
500
Dust pollution
Periodic wetting or showering of
working area with water
Number of
complains about
dust
Project site
Site Visit
Two times a
day
Debre markos
Urban
Development
and City
Service
Contractors
Number, area of
proper site
selection
Number of dumps
disposed by
duping tracks
Disposal
Site
of Minimize the area of ground
for clearance i.e. land clearing for road
construction should be restricted to
what is absolutely necessary for the
road construction as per the design
Maintain the existing drainage line
before any main and walk way
pavement activities
Avoiding any construction activity
during rainy season
Gully Formation in Advise and check the MSE to
the quarry site
bought their materials from licensed
ones
Excavated
material in m3
Project
Design and
field
observation
on project
site
Excavated
material in m3
Construct cover slab
for junctions and
Number and of
cover slab
Before
Constru
ction
Project Significant Impact
Phase
of Use the excavated soil for filling
purpose
Use the surplus spoil to fill eroded
gullies, quarries, borrow pits and
depressed areas
Acquisition
disposal
site
waste
O
pe
ra
tio
n
Construction
Formation
borrow pit
19
Site Observation and check the
design
250
Daily until Contractors
earth
work
completed
500
Daily until
earth
work
completed
Contractors
350
Observation Site Visit
of
the
Quarry site
Once in Year
Contractors
1000
Project Site
Once in the City service
project life office
Site Visit
Check the
Design and
site visit
Site Visit
600
residents
first aid kits, gaunt
and other safety
equipment
Allocating
the site visit and observation and check
appropriate
maintenance plan ( After assessing
maintenance cost
the asset condition)
Participation of the
local community in
keeping clean the
culverts and openditch;
Improve the waste
(liquid and solid
waste) management
system of the town
Timely cart away of
the spoil
20
constructed
Amount of Budget
allocated ( After
assessing the asset
condition) and
number of
community
participating on
cleaning
City Service
Office
time
Zone PLUA
Daily,
weekly,
monthly,
quarterly,
annually,/
City service
office
Kebele
administration
Zone EPLUA
2580
11. Nature of Public Participation
Public representatives were participated during CIP preparation at kebele level from different categories.
These representatives plan and prioritize the project according to their infrastructural needs.
The participants in the public discussion have represented women and youth associations, Teacher’s
associations, professional associations, religious institutions, Kebele administrations, influential persons,
Edirs, government employees, women’s league, community development groups, NGO’S, chamber of
commerce, PLWHIV /AIDS/, Disabled groups, Sector office workers, MSE. Generally the discussion was
participatory and many participants express their opinions and advices.
The local resident around the project area establishes representatives to follow up the project
implementation as well as to facilitate the project by providing financial support.
 During the time of public consaltatition the participants raised the following points
 Why in our village construct cobble road
 During the time of project selection all kebeles people does not participated. So
in our kebele there is un fair distribution of infra structures
 In our kebele there are different social and Industrial infra structure so these
social and industrial infra structure needs accsesable roasd but in our kebele lucks
these infra structure . if the next time the city admenstartion solve these different
problems
12. Conclusion and Recommendation
Conclusion
The proposed project may have positive and negative environmental and social impact associated with;
employment opportunity, increase aesthetic value and reduce the problem of soil erosion and it may also
have negative impacts losses of public utility, accident and safety, quarry and borrow pit and acquisition
of land for disposal of spoil. The anticipated negative environmental and social impacts will be prevented
or minimized by different mitigation measures which include allocating appropriate relocation cost for
those public utilities and timely relocation of those public utilities to their desired locations, construct
cover slabs on junctions and residents. Therefore the initial Environmental examination or partial EIA
report is sufficient for the approval of the sub- project.
21
Recommendation
The city administration, contractors and other responsible bodies should implement the mitigation
measures which are vital for project success and sustainability.
Reference
Environmental Impact Assessment proclamation No 299/2002
Environmental Policy of Ethiopia, EPA Federal Democratic Republic of Ethiopia, Addis Ababa,
1997
General Environmental Impact Assessment Guideline, Amhara National Regional State,
Environmental Protection Land Administration and Use Authority, 2012, Bahir Dar.
Ministry of Urban Development, Housing and Construction Environmental and Social
Management System Guidelines for Urban Local Governments, 2014, Addis Ababa.
Rural Land Administration and Use Proclamation –ANRS Proclamation No 46/2000
22
Annexes
5.1 Environmental screening
The screening determine the schedule of the project whether the project needs EIA or not by
using different checklist.
ULG construction works project name
From Wro Hibist Residence to 27m road to
Yegnban river
Drainage kebele 07 sites
Location/include map/
Amhara region, D/ Markos city administration
Type of activity
new construction
Estimated cost
1352375.08 Birr
Proposed date of works commencement
December 2022
Technical and specification reviewed
/circle answer/
Yes
No
Table1. Site selection:
Physical data
Yes/no answer and bullet lists
preferred
except
where
descriptive details essential.
280
No
No
Yes
Site area in m2
Extension of, changes to existing alignment
Any existing property to transfer to project
Any plans for new construction
Table2. Impact identification and classification
Issues
Site sensitivity
Low
Natural habitats
Water quality , water resource availability and
use
Natural hazards vulnerability ,flood, soil
stability/erosion
Cultural property
Involuntary resettlement
Indigenous peoples
23






Medium
High
Table3. Checklist of impacts
Roads
Potential for adverse impacts
None
Soil erosion or flooding concerns/ e.g, highly
erodible soil or steep gradients/
Number of stream crossings disturbances
Wet season excavation
Creation of quarry sites or borrow pits
Significant vegetation removal
Wildlife habitats or populations disturbed
Environmentally sensitive areas disturbed
Cultural or religious sites disturbed
Economic or physical resettlement required
New settlement pressures created
Others/specify/
Table 4.detailed questions:
Low Medium high
unknown










1.Preminary environmental information : yes/no answers and bullet lists preferred except
where descriptive detail is essential
State the sources of information available at the stage /ULG report, ULG
report
and
ESIA or other environmental study/
observation
Has there been litigation complaints of any environmental nature No
directed against the proponent or ULG construction works project
2. identify type of activities and likely Yes/no answers and bullet lists preferred
environmental impacts:
except where descriptive detail is essential
What are the likely environmental impacts, Environmental impact
opportunities, risks and liabilities associated *soil erosion
with the project
Opportunity
*employment opportunity
3. Determine environmental screening category: Yes/no answers and bullet lists preferred
except where descriptive details essential.
After compiling the above, determine which category the ULG 2
construction works falls, based on environmental impact categories 1
,2, and 3.
4. Mitigation of potential pollution: Yes/no answers and bullet lists preferred except where
descriptive details essential.
Does an ULG construction works project have potential to pollute the No
environment, or contradict any environmental laws and regulations?
Will the ULG construction works project require pesticides use?
NO
24
If so, then the proposal must detail the methodology and equipment incorporated in the design to constrain pollution within the laws and
regulations and to address pesticide use, storage and handling
Does the design adequately detail mitigating measures
5. Environmental Assessment Report or environmental studies required: Yes/No answers and bullet lists
preferred except where descriptive detail is essential
If Screening identifies environmental issues that require an ESIA or a study, No
does the proposal include the ESIA or study?
Indicate the scope and time frame of any outstanding environmental study.
October
Required Environmental Monitoring Plan:
No
If the screening identifies environmental issues that require long term or No
intermittent monitoring (effluent, gaseous discharges, water quality, soil
quality, air quality, noise etc.), does the proposal detail adequate
monitoring requirements?
6. Public participation/information requirements: Yes/No answers and bullet lists preferred except
where descriptive detail is essential
Does the proposal require, under national or local laws, the public to be Yes
informed, consulted or involved?
Has consultation been completed?
Yes
Indicate the time frame of any outstanding consultation process.
Refer to relevant legislative acts in Ethiopia.
7. Land and resettlement: Yes/No answers and bullet lists preferred except where descriptive detail is
essential.
What is the likelihood of land purchase for the ULG construction works No
project?
How will the proponent go about land purchase?
No
Will people’s livelihoods be affected in any way, therefore requiring some No
form of compensation?
Will people need to be displaced, and therefore require compensation and No
resettlement assistance?
Are the relevant authorities aware of the need for a Resettlement Process, No
involving a census, valuation, consultation, compensation, evaluation and
monitoring?
What level or type of compensation is planned?
Who will monitor actual payments?
-
25
5.2 Social safeguards screening
The social impact screening using checklists gives us general information about the project
social impact.
UIIDP investment project name:
Abebe Yigrem residence to Mulugeta residence
Location (include map/sketch):
Amhara region, D/ Markos city administration
Type of activity :
new construction
Estimated Cost: (Birr)
1352375.08 Birr
Proposed Date of Works Commencement
December 2022
Technical Drawing and Specifications Reviewed :
(circle answer):
Yes
No
Table 5: Site Selection:
Physical data:
Yes/No answers and bullet lists preferred except where
descriptive detail is essential.
Site area in m2
280
Extension of or changes to existing alignment
No
Any existing property to transfer to project
No
Any plans for new construction
Yes
Table 6: Impact identification and classification:
Site Sensitivity
Issues
Low
Medium
High

Involuntary resettlement
Checklist of impacts
ULG infrastructure & services: Roads, Footpaths &
Street lighting, Water supply, etc.
Potential for Adverse Impacts
None
Economic or physical resettlement required

New settlement pressures created

Other (specify):

26
Low
Med
High
Unknown
Table 7: Detailed questions
Public participation/information requirements: Yes/No answers and bullet lists preferred except where
descriptive detail is essential.
Does the proposal require, under national or local laws, the public to be informed,
consulted or involved?
yes
Has consultation been completed?
yes
Indicate the time frame of any outstanding consultation process.
September
Refer to relevant legislative acts in Ethiopia.
Land and resettlement: Yes/No answers and bullet lists preferred except where descriptive detail is
essential
What is the likelihood of land purchase for the ULG investment project?
-
How will the ULG go about land purchase?
-
Will people’s livelihoods be affected in any way, therefore requiring some form of No
compensation?
Will people need to be displaced, and therefore require compensation and No
resettlement assistance?
Are the relevant authorities aware of the need for a Resettlement Process, involving a
census, valuation, consultation, compensation, evaluation and monitoring?
-
What level or type of compensation is planned?
-
Who will monitor actual payments?
-
Actions:
List outstanding actions to be cleared before ULG investment project appraisal.
-
Approval/rejection
. approval
If proposal is rejected for environmental reasons, should the ULG investment project be reconsidered, and what additional data would be required for reconsideration?
Recommendations:
Requires an RAP is to be submitted on date
Requires an Census & Land Inventory to be
submitted on date

27
Does not require further environmental or social
studies
Site map of from Wro Hibist Residence and to 27m Width road to Yegnban river
28
Design from Wro Hibist Residence and to 27m Width road to Yegnban river
29
Drainage project public consultation from Wro Hibist Residence and to 27m Width
road to Yegnban river
30
Annex 3 Lists of Members of the Study Team
No
Name
Field of Study
Position
Address
1
Tiruneh Engida
BA in Geography
Environment and Social
0913411527
Safeguard Officer
2
Zelalem Amare
BSc in Rural Development
Social Safeguard Officer
0920765980
3
Getasew Kehalew
MSc in Urban planer
Urban planer
0913298792
4
Alemu Tesfaw
BSc in Engineering
Project Engineer
0910327316
31
የየየየየ የየየየየ የየየየ የየየየ (Environmental Contract clauses)
የየየየየ የየየየ የየ የ27 የየየ የየየየ የየየየ የየየ የየየየየ የየየ የየየየየ
የየየየ
ይይ ይይይይይ ይይይይ ይይይይ ይይ/ይይይይ ይይይይይይ ይይይ ይይይ ይይይ
ይይይይይይይይ ይይይ
ይ/ይይ ይይ ይይይይይይ ይይይይ ይይይይይ ይይይይይይይይ
ይይይይይይ ይይይይይይይይ ይይይ ይይይይይ ይይ ይይይይይይ ይይይይይ ይይይይ ይይይይ
ይይይይ ይይይይይ ይይይይ ይይይ ይይይይ ይይይ ይይይይይ ይይይ ይይይ ይይ ይይይይ
ይይይይ ይይይ ይይይ ይይይይይ ይይ ይይይይይ ይይይይ ይይይይይይ ይይይይ ይይይ ይይይ
ይይይይይይይይ
ይይይይይይ
ይ/ይይ
ይይይ
ይይይይይ
ይይይይ
ይይይይይይ
ይይይይይይይይይ ይይይይይይይይ ይይይይ ይይይይይይ ይይይ ይይይይ
1 የየየየየየ የየየ የየየየ የየየየየየ የየየየየየ የየየየየ
 ይይይይይይ ይይይይ ይይይይይይ ይይይ ይይ ይይይይ ይይይይይ ይይይይይ
ይይይይ
 ይይይይይይ ይይይይ ይይይ ይይይይይ ይይይ ይይይይይ
 ይይይይይይ ይይይይይይ ይይይ ይይይይይ ይይይይይ ይይይይ
 ይይይይይይይይ ይይ-ይይይይ ይይይይ ይይይይ ይይይይይ ይይይይ +ይይይይይይ
ይይይይይይ ይይ
 ይይይይይይ ይይ ይይይይ ይይይ ይይይይይይ ይይይይይይይ ይይይይይይ ይይይይ
ይየይ ይይይይይይ ይይይይይይ ይይይይ ይይይይይይይይ
2 የየ የየየየ የየየየ የየየ የየየየየ የየየየየ የየየየየየ
ይይይይ ይይ ይይይይይ ይይይይይይ ይይይይይይይ ይይይይ ይይይ ይይይይይይ ይይይይይይ
ይይይይይይ ይይይይ ይይይይ ይይይይይ ይይይይይይ
ይይይይይ ይይይይ ይይይይይይይይ ይይ ይይይይይ ይይይይ ይይይ ይይይ ይይይይይ ይይይይ
ይይይይ ይይይይይ ይይይ ይይይ ይይ ይይይይይ ይይይ ይይይ ይይይይይይይ ይይይይይ
ይይይይይ ይይይይይይይ
I የየየየ የየየየየ የየየየ የየ የየየየየ
 ይይይይ ይይይ ይይይይ ይይይ ይይ ይይይይይ ይይይይ ይይይይይ ይይይ ይይይይ
 ይይይይ ይይ ይይይይይይ ይይይይይ ይይይይ ይይይይይይይ ይይይይ ይይይ ይይይይ
ይይይ ይይይይይ ይይይይይ ይይይይ ይይይይ ይይይይይ ይይይይ ይይይይይ
 ይይይይ ይይ ይይይይይ ይይይይይ ይይይይይ ይይይይ ይይ ይይይይይይ ይይይይ
 ይይይይይይ ይይይይ ይይ ይይይይይ ይይይይ ይይይ ይይይ ይይይይይይ ይይይ
ይይይይ ይ300 ይይይ ይይይ ይይይ ይይይይ ይይይይይይይይ
II ይይይይ ይይ ይይይይይ ይይይይይይይ ይይይ ይይይ ይይይይ ይይይይ ይይይይይይ
32
 ይይይይይ ይይይይ ይይይይይይይ ይይይ ይይይይይ ይይይ ይይይ ይ15 ይይይ ይይይ
ይይይ ይይይ ይይ ይይ ይይይይይ ይይይይይይ ይይ
 ይይይይይ ይይይይይይይ ይይይ ይይይይይ ይይይይ ይይይይ ይይይይይይ ይይ ይይ
ይይ ይይይይ ይይይይ ይይይይ ይይይይይ ይይይይይ ይይይ ይይይይ ይይ ይይይይ
ይይይ ይይይይ ይይይይይ ይይ ይይይ ይይይይ ይይይይይይ ይይ
III ይይይይይ ይይይይይ ይይ ይይይይይ ይይይይ ይይይይ ይይይይይይ ይይይይ ይይይይ
ይይይይይ ይይይይይ
 ይይይይይ ይይ ይይይ ይይይይ ይይይ ይይይይይይይይ ይይይይ ይይ ይይይይ ይይ
ይይይ ይይይ ይይይይይይይ ይይይይይይይ ይይይ ይይይ ይይይ ይይይይይ ይይይ
ይይይ ይይ ይይይይ ይይይይይ
 ይይይይ ይይ ይይይ ይይይይ ይይይይ ይይይ ይይይይይይ ይይይይ ይይይይይይ
ይይይ ይይይ ይይይይ ይይይይ ይይይይ ይይይይ ይይይይይ ይይይይ ይይይ ይይ
ይይይይይ ይይይይ ይይ ይይይይ ይይይ ይይይ ይይ ይይይ ይይይ ይይ ይይይይይይ
 ይይይይ ይይይይ ይይይይ ይይይይይ ይይይይይይ ይይይ ይይይ ይይይይይ
ይይይይይይ ይይይይይይይ ይይይይይይይይ ይይይይ ይ10 ይይይይይ ይይይይ
ይይይይ ይይይይይ
 ይይይይ ይይይይ ይይይይይ ይይይይይ ይይይይይ ይይይይይ ይይይ ይይይይ ይይይ
ይይይይ ይይይይ ይይይይ ይይይ ይይይይ ይይ ይይ ይይይይይይ ይይይይ ይይይይ
ይይይ ይይይይ ይይይይ ይይይይይይይይ
 ይይይይይ ይይይይይይይ ይይይይይ ይይይይ ይይይይ ይይይይይይ ይይይይይይ ይይ
ይይይይይ ይይይይይ ይይይይይ ይይይይይ ይይይይይ ይይ ይይ ይይ ይይ ይይይ
ይይይይይ
 ይይይይይ ይይይይይ ይይይይይይይ ይይይይ ይይይይይ ይይይይ ይይ ይይይይይ
ይይይይ ይይይይይ ይይይይ ይይይይይይይ ይይይይይ ይይ ይይይይ ይይይይ ይይይይ
ይይይይይ ይይይይ
2.2 የየየየየ የየ የየየ የየየየየየ የየየየየየ የየየ
ይይይይይ ይይ/ይይይይ ይይይ ይይይ ይይይይ ይይይይይይይይ ይይይይይይ ይ/ይይ ይይ
ይይይ ይይይ ይይይይ ይይይይይይይ ይይይይይይይ ይይይይይ ይይይ ይይይይ ይይይይ
ይይይይይይይ ይይይይይይይ ይይይይይይ ይይይይይ ይይይይይ ይይይ ይይይይ ይይይ
ይይይይ ይይይይይይ ይይይይይ ይይይይይይይይ ይይይይ ይይይይ ይይይይይ ይይይይይይ
ይይይ ይይይይ ይይይይይ ይይይይ ይይይይይይይ ይይይይ ይይይይይ ይይይይይ ይይ ይይይ
ይይይይይይ ይይይይይይ ይይይይይ ይይይይይይይ ይይይ
ይይይይይይ ይይይይይ ይይይይይ ይይ ይይይይይይይ ይይይይይይ ይይይይ ይይይይይ
33
 ይይይይይ ይይይ ይይይይይይይ ይ/ይይ ይይይይ ይይይ ይይይይይ ይይይይይይ
ይይይይይይ ይይ ይይይይይ ይይይ ይይይይይይይ ይይይ ይይይ ይይይይይይይ ይይይይ
ይይይይ ይይይይ
 ይይይይይ
ይይይይ
ይይይይይይይይ
ይይ
ይይይይይይ
ይይ
ይይይይይይይ
ይይይይይይይይይ ይይይ ይይይይይ ይይይይ ይይይይይ ይይይ ይይይ ይይይ ይይይ
ይይይይይይ ይይይይይይ ይይይ ይይይይ ይይይይይ ይይይይይ ይይይይ ይይይይይይይ
 ይይይይይ ይይ ይይይይይ ይይይ ይይይይይይ ይይይይይይ ይይይ ይይይይይይይ
ይይይይይይ ይይይይ ይይይይይይ ይይይይይይይ ይይይይ ይይይይ ይይይይይይ ይይ
 ይይይይይ ይይይይይይይ ይይይይይ ይይይይ ይይይይ ይይይ ይይይይይይ ይይይይይ
ይይይ ይይ ይይይይይይ ይይይይ ይይይይይ ይይይ ይይይ ይይይይይይይይ ይይይይ
ይይይይይይ
 ይይይይይ ይይይይይይ ይይይይይይይ ይይይይይ ይይይይ ይይ ይይይይ ይይይ ይይይይ
ይይይይይ ይይይይ ይይይይይ ይይይይይይ ይይይይይይ ይይይ ይይ ይይይይ
ይይይይይይይይ
 ይይይይይ ይይ ይይይይይ ይይይይ ይይይይይ ይይይይ ይይይይይ ይይይ ይይይ
ይይይይ ይይይ ይይይይይይ ይይይይይ ይይይይ ይይይይ ይይይይይይይ
 ይይይይይ ይይይ ይይይ ይይይ ይይይይ ይይይ ይይይይይ ይይ ይይ ይይይ ይይይ
ይይይይይይ
 ይይይይይይ ይይ ይይይይይይ ይይይይይ ይይይይይይይ ይይይይይይይ ይይይይይ
ይይይይይይይ ይይይይይይይ ይይይይይ ይይይይይ ይይይይይይ ይይይ ይይይይ
2.3የየየየየ የየየየ የየየ የየየየየየ የየየየ የየየየየየ የየየየየየ
 ይይይይይ ይይይ 200 ይይይ ይይይይ ይይይ ይይይይይ ይይይይይ ይይይይይ
ይይይይ 15ይይ ይይይ ይይ ይይይ ይይይ ይይይይ ይይይይይይይ ይይይይ ይይይይ
ይይይይ
 ይይይይ ይይይ ይይይይይ ይይይይይ ይይይይይይ ይ10 ይይይይይ ይይ ይይይ
ይይይይ ይይይይ ይይይይይ
 ይይይይ ይይይ ይይይይይ ይይይይይ ይይይይ ይይይ ይ90 ይይ ይይ ይይይ ይይይ
ይይይይይይ
 ይይይ ይይይይይ ይይ/ይይይ ይይይይ ይይይይ ይይይ ይይይይ ይይይ ይይይ
ይይይይይይይ ይይይይ ይይይይ ይይይይ
 ይይይይይ ይይይይ ይይይይ ይይይይይ ይይይይ ይይይ ይይይ ይይይይይይ ይይ
ይይይይ ይይይይይይይ ይይይይይ ይይይይይ ይይይይይይ ይይይይይ ይይይይይ
ይይይይይይ
 ይይይይ ይይይይ ይይይይ ይይይይ ይይይ ይይይ ይይይይ ይይ ይይይይ ይይይ
ይይይይይ ይይይ ይይይይይ ይይይይይ ይይ ይይይይ ይይይይይይ ይይይይ ይይ
 ይይይይይይ ይይይይ ይይይይይ ይይይ ይይይይ ይይይይ ይይይይይ ይይይይ
ይይይይይ ይይይይ ይይይይ ይይይ ይይይይ ይይይይይ ይይይ ይይይ ይይይይ
ይይይይይይይይይ ይይ ይይይይ ይይይ ይይይይይይ ይይይይ ይይይ ይይይይይ
ይይይይይ
34
 ይይይይ ይይይ ይይይይይ ይይይይ ይይይይ ይይይይይ ይይይ ይይይይ 2 ይይ
ይይይ ይይይ ይይ ይይይይይ ይይይይ
 ይይይይ ይይይ ይይይይይ ይይይይይይ ይይ /ይይይይይይ ይይ ይይይይይይ
ይይይይ ይይይይይ ይይይይ ይይይይ ይይይይይይይ ይይይይይይ ይይይይ ይይይይ
ይይ ይይይ ይይይይይይይ ይይይ ይይይይ ይይይ ይይይይ ይይይይ ይይይይ
3 የየየየየየ የየየየየ የየየየየ የየየየ የየየየ የየየየየ የየ የየየየየ የየየየየ
የየየየየየ
ይይይይይ ይይይይ ይይ/ይይይይ ይይይ ይይይይይይ ይይይይይይይ ይይይይይይይይ ይይይይ
ይይይይይይይ ይይይይይይ ይይይይይይይ ይይይይ ይይይ ይይይ ይይይይ ይይይይይ ይይይ
ይይይ ይይይይይይይ ይይይይይ ይይይይይ ይይይይይይ
 ይይይይይ ይይይይይይ ይይይይይይይ ይይይይይይይይ ይይይይይ ይይ ይይይይይ
ይይይይይይ ይይ ይይይይ ይይይይይይይይይ ይይይ ይይይ ይይይይይ ይይ ይይይይይ
ይይይይይ ይይይይይይይ ይይይይ ይይይይይይ ይይይይይይ ይይይይይ ይይይይ ይይይ
ይይይይ ይይይይይይ
 ይይይይ ይይይይይ ይይይይ ይይይይይ ይይይይይይ ይይ ይይይ ይይ ይይይይይ
ይይይይ ይይይይ ይይይይይ ይይይይይ ይይ ይይይይ ይይይይይ ይይይይይይይ
ይይይይ ይይይይ ይይይይይይ ይይይይይ ይይይ ይይ ይይይይ ይይይይ
 ይይይይይይ ይይይይይ ይይይይይ ይይይይ ይይይይይይ (ይይ ይይይይ ይይይይይ
ይይይይይይ) ይይይይይ ይይይ ይይይይይይ ይይይይይይይ ይይይይይይ ይይይይይ
ይይ ይይይ ይይይይይይ ይይይይይይ ይይይይ ይይይይይይ
Environmental Managem የየent Plan /የየየየየ የየየየ የየየ/
35
የየየየየ የየየየ የየ የ27 የየየ የየየየ የየየየ የየየ የየየየየ የየየ የየየየየ
የየየየ
ይይይይይ ይይይይ ይይይ ይይይ
/Environmental Management plan/ ይይይ
ይይይ ይይይይይ ይይይይይይ ይይይ ይይይይይ ይይይይይይ ይይይይ ይይ ይይይይ
ይይይይይይ ይይይይ ይይይይ ይይይይይይ ይይይ ይይይይይ ይይይይይይይ ይይይይይ
ይይይይ ይይይይይይ ይይይ ይይይ ይይይይ ይይይይ ይይይይ ይይ ይይይይይ ይይይይይይ
ይይይይ ይይይይይ ይይይይይ ይይይ ይይ ይይይይይይ ይይ ይይይይ ይይይይይይ ይይይይይ
ይይይይይ ይይይይይይይይ ይይይይይይ ይይ ይይይይይይይይይይ ይይይይይ ይይይ ይይይይ
ይይይይይ ይይይይይይ ይይይይይ ይይይይ ይይይይይይይ ይይይ ይይይይ ይይይ ይይይ ይይይ
ይይይይ ይይይይ ይይይይይይ ይይይ ይይይይይይ ይይይይይ ይይይይይይይ ይይ
ይይይይይ ይይይይይ ይይይይይይ ይይይ ይይ
1. ይይይይ ይይይይይ ይይይ ይይይይ ይይይይይይይይይ ይይ ይይይ ይይይይይ ይይይ
ይይይይ
2. ይይይ ይይይይ ይይይይ ይይይይይይ ይይ ይይይይይይይ ይይይይይይ ይይይይይ
ይይይይይይ ይይይይይ ይይይይ ይይይ ይይ ይይይይ ይይይይ
3. ይይይ ይይይይይይ ይይ ይይይይይይ ይይ ይይይ ይይይይ ይይይይይይ ይይይ
ይይይይይይ ይይይይይይ ይይይ ይይይይይ ይይይይይይ ይይይይይ ይይይይ ይይ
ይይይይ ይይይይ
4. ይይይ ይይይ ይይይይይይይ ይይ ይይይይይይ ይይይይይ ይይይይይይ ይይይይይ
ይይይይ ይይይ ይይይይ ይይይይይይይይ ይይይ ይይይ ይይይይ ይይይይይይይይ
ይ/ይይ ይይይይ ይይይይ ይይይይ ይይይይይይይ
5. ይይይ ይይይይ ይይይይ ይይይይይይ ይይ ይይ ይይይይ ይይ ይይይይይ ይይይይይይይ
ይይይይይይ ይይይይ ይይይይ ይይይ ይይይይይ ይይይይይይ ይይይይይይይ ይይይ ይይ
ይይይይ ይይይይ ይይ
6. ይይይይይ ይይ ይይይይ ይይይ ይይይይይይ ይይይይይይይ ይይይይይ ይይይይይ
ይይይይ ይይይ ይይይይ
7. ይይይ ይይይይ ይይይይ ይይይይይይ ይይ ይይይይይይ ይይይይ ይይይ ይይይይ
ይይይይይይ ይይይይይ ይይይይይ ይይ ይይይይይ ይይይ ይይይ ይይይይይ ይይይ
ይይይይይይ ይይይይ ይይይይ ይይይይ ይይ
8. ይይይ ይይይይ ይይይይይይይ ይይይ ይይይ ይይይይ ይይይይ ይይይይይ ይይይይይይይ
ይይይይ ይይይይይ ይይይ ይይይይይይ
36
ይይይይይ
ይይ
ይይይይይ
ይይይ
ይይይይይ
ይይይ
ይይይይ
ይ3ይ
ይይይ
ይይ
ይይይይ
ይይይይይ ይይይይ
ይይይ
ይይይይ
ይይይይይይ
ይይይይ ይይይይ
ይይይይይይይ
ይይይይይ ይይ
ይይይይ ይይይይ
ይይይይይ ይይይይ
-ይይይይይይይ
ይይይይ ይይይ
ይይይ ይይይይ
-ይይይይ ይይይ ይይይይይ ይይይ ይይይይይ ይይ
ይይይይ
-ይይ ይይይ ይይይይይይ ይይይይይ ይይይይ
ይይይይይይይ ይይይይይ ይይይ ይይይይይይይ
ይይይ ይይይይይይይይ ይይይይ ይይይይይይ
ይይይ ይይይይ ይይ ይይይይ
-ይይይይይ ይይይይ ይይይይይ ይይይይይ
ይይይይ
-ይይይይ ይይይይይይይይ ይይ ይይይ
ይይይይይይይ ይይይይ ይይይ ይይ ይይይይይይ
-ይይይይይይ ይይይይይይ ይይይ ይይይይይ
ይይይ ይይይይ ይይይይ
-ይይይይይይይ ይይይ ይይይይይይ ይይ ይይይ
ይይ ይይይይ ይይ ይይይይ ይይይይይይይ ይይ
ይይይይ
-ይይይይይይይ ይይይ ይይይይይ ይይይ 5
ይይይይይ ይይይ ይይይ ይይይ ይይይይ ይይይይ
ይይይ ይይይይ ይይይይ ይይይይይ ይይይ
ይይይይ
-ይይይይ ይይይይይ ይይይይ ይይይይ
-ይይይይ ይይይ ይይይይይይይ ይይ ይ ይይይ
ይይይ ይይይይይይ ይይይይይይ ይይይይይይ
ይይይ ይይይይ
-ይይይይይይይ ይይ ይይይይይ ይይይይይ
ይይይይይ ይይይ ይይይ ይይይይ ይይይ
ይይይይይይይ
ይይይ ይይይይ
ይይይይይይ
ይይይ ይይይይይ
ይይ ይይይይይ
ይይይይ ይይይይ
37
ይይይይይይይ ይይይይይይይይ ይይይይ
ይይይይይይይይይ ይይይይይ ይይይ ይይይይ ይይ
ይይይይይ ይይይይይ ይይ ይይይይይይ ይይይይ
ይይይይይይ ይይይይይይ
ይይይ
ይይ/ይ/ይይይይይይይይይይይ
ይይይይይይይይ/ይ/ይይ
ይይይይይይይይይይይይይይይ/
ይ/ይይ
ይይይይይይይ
ይይ
--
--ይይይይይይይይ ይይይ
ይይይ ይይይ ይይይይይይይይ
ይይ/ይ/ይይ
-ይይይ ይይይይ ይይይይ ይይ
ይይ/ይ/ይይ
ይይይይይይይ
ይይይይይይይ
ይይ ይይይይ
ይይይይይ
ይይይይይይይ
ይይይይይይይ
ይይ ይይይይ
ይይይይይ
ይይይይይይይ
ይይይይይይይ
ይይ ይይይይ
ይይይይይ
38
Download