AFRICAN DEVELOPMENT FUND STUDY FOR NATIONAL TRANSPORT SECTOR MASTER PLAN UPDATE COUNTRY : ANGOLA Appraisal Team Regional Director : Mr. C. OJUKWU, ORSB Sector Director : Mr. A. OUMAROU, OITC Team Leader : Mr. T. HARADA OITC DEPARTMENT August 2013 TABLE OF CONTENTS I – STRATEGIC THRUST & RATIONALE ....................................................................... 1 1.1. Study linkages with country strategy and objectives ...................................................... 1 1.2. Rationale for Bank’s involvement .................................................................................. 1 1.3. Donors coordination ........................................................................................................ 2 II – STUDY DESCRIPTION .................................................................................................. 2 2.1. Background ..................................................................................................................... 2 2.2. Study objective ................................................................................................................ 3 2.3. Study components ........................................................................................................... 4 2.4. Technical solution retained and other alternatives explored ........................................... 4 2.5. Study type ....................................................................................................................... 4 2.6. Study cost and financing arrangements .......................................................................... 4 2.7. Study’s target area and population .................................................................................. 5 2.8. Participatory process for study identification, design and implementation .................... 6 2.9. Bank Group experience, lessons reflected in study design ............................................. 6 2.10.Key performance indicators ........................................................................................... 6 III – STUDY FEASIBILITY................................................................................................... 6 3.1. Economic and financial performance ............................................................................. 6 3.2. Environmental and Social impacts .................................................................................. 6 IV – IMPLEMENTATION ..................................................................................................... 7 4.1. Implementation arrangements ......................................................................................... 7 4.2. Monitoring ...................................................................................................................... 8 4.3. Governance ..................................................................................................................... 8 4.4. Sustainability................................................................................................................... 8 4.5. Risk management ............................................................................................................ 8 4.6. Knowledge building ........................................................................................................ 9 V – LEGAL INSTRUMENTS AND AUTHORITY ............................................................. 9 5.1. Legal instrument ............................................................................................................. 9 5.2. Conditions associated with Bank’s intervention ............................................................. 9 5.3. Compliance with Bank Policies ...................................................................................... 9 VI – RECOMMENDATION................................................................................................. 10 Appendix I. Country’s comparative socio-economic indicators Appendix II. Table of ADB’s portfolio in the country Appendix III. Key related projects financed by the Bank and other development partners in the country Appendix IV. Map of the Study Area Currency Equivalents As of July 2013 Currency Unit UA 1.0 UA 1.0 US$ 1.0 = = = = Angolan Kwanza (AON) AON 144.13 US$ 1.50 AON 95.84 Fiscal Year 01 January – 31 December Weights and Measures 1metric tonne 1 kilogramme (kg) 1 metre (m) 1 millimetre (mm) 1 kilometre (km) 1 hectare (ha) = = = = = = 2,204 pounds (lbs) 2.200 lbs 3.28 feet (ft) 0.03937 inch (“) 0.62 mile 2.471 acres Acronyms and Abbreviations ADB ADF CSP CFB EU GOA JICA Pre-F/S SADC TOR UA USAID = = = = = = = = = = = = African Development Bank African Development Fund Country Strategy Paper Caminhos de Ferro de Benguela (Benguela Railway) European Union Government of Angola Japan International Cooperation Agency Preliminary Feasibility Study Southern African Development Community Terms of Reference Unit of Account United States Agency for International Development i Loan Information Client’s information BORROWER : The Republic of Angola EXECUTING AGENCY : Ministry of Transport Financing plan Source Amount (UA) Instrument ADF Government of Angola TOTAL COST 2.90 million 0.38 million 3.28 million Loan Counterpart fund ADB’s key financing information Loan currency Interest type Interest rate spread Commitment fee Other fees UA N/A 1% 0.5% Tenor Grace period FIRR, NPV (base case) EIRR (base case) 30 years 8 years N/A N/A 0.75% on the amount disbursed and outstanding from time to time Timeframe - Main Milestones (expected) Concept Note approval Study approval July 2012 September 2013 Effectiveness Last Disbursement Completion October 2013 August 2016 August 2015 ii Study Summary 1. Study Overview Study for National Transport Sector Master Plan Update comprises 2 components: 1) National Transport Sector Master Plan Update incorporating existing plans and studies to a) formulate an overall strategy and policy for the nationwide transport network, composed of roads, railways, inland waterways, ports and airports in Angola, b) elaborate a nationwide and integrated transport network for the future, connecting the existing transport infrastructure, and c) identify and select priority projects with justifications, and 2) Preliminary Feasibility Study (Pre-F/S) on the Railway Link between the existing railway named “Caminhos de Ferro de Benguela (CFB)” and Zambia. An optimum route for a railway link connecting CFB and Zambia among different options will be selected, based on traffic data, natural, social and economic information, and environmental and social aspects, as well as economic and financial analysis of the optimum route. The first component will be completed within 15 months from the beginning of the consultancy services, whereas the latter will take 6 months. The study will cost UA 3.28 million, of which UA 2.90 million will be an ADF loan. The direct beneficiaries of the study are the Ministry of Transport and the Ministry of Urbanism and Construction including the transport-related entities under the ministries. The National Transport Sector Master Plan Update will enable the Government of Angola (GOA) to timely and properly make decisions and take actions toward better transport infrastructure and services, while the Pre-F/S on the Railway Link between CFB and Zambia will provide a basis for the GOA’s next actions for development of the railway link, including the private sector involvement. 2. Needs Assessment The Bank’s intervention in the study is timely, because 1) Angola, at the final stage of rehabilitation, is now urgently requiring new perspectives on a nationwide and integrated transport network for the future, connecting the existing transport infrastructure, and 2) the Pre-F/S on the Railway Link should be commenced as soon as possible in light of the enhanced interests by the both governments of Angola and Zambia and the fact that some studies have been already done on the Zambian side. 3. Bank’s Added Value The Bank will be able to support the GOA in the study not only financially but also technically, having experience of interventions in similar studies for other member countries. Also, the Bank will be able to provide the GOA with advice for the Pre-F/S on the Railway Link between CFB and Zambia, as it has on-going interventions in the transport sector in Zambia. 4. Knowledge Management The study will unveil the current situation of the transport sector in Angola which is not well known so far, despite its importance in the regional context. The study is expected to identify future Bank’s intervention, such as financing for priority projects to be identified in the National Transport Sector Master Plan Update, as well as financing for the full-scale feasibility study and detailed engineering design on the Railway Link between CFB and Zambia whose TOR shall be elaborated by the Pre-F/S. iii Result-based Logical Framework Country and study name: Angola – Study for National Transport Sector Master Plan Update Purpose of the study : to carry out studies that will provide GOA with a clear vision of transport infrastructure development up to 2025 PERFORMANCE INDICATORS KEY ACTIAVITIES OUTPUTS OUTCOMES IMPACT RESULTS CHAIN Indicator (including CSI) Socio-economic development, poverty reduction and regional integration through an improved and sustainable transport system GDP growth rate GOA is capable to timely and properly make decisions and take actions for the transport sector Institutional framework in place to ensure transport infrastructure development based on the studies Component 1: National Transport Sector Master Plan Update prepared Baseline [2012] Target 6.8% (IMF forecast) 7.5-8.5 % (Target of the longterm strategy “Angola 2025”) [2015-2025] None Establishment of the institutional framework [2015] None Study reports submitted and approved Study reports Component 2: the Preliminary Feasibility Study on the Railway Link completed COMPONENTS Component 1: Preparing the National Transport Sector Master Plan Update Component 2: Carrying out the Preliminary Feasibility Study on the Railway Link between CFB and Zambia Component 3: Provision of the Technical Assistance Component 1 [2015] Component 2 [2014] Costs (million UA) Studies Technical assistance Financial audit Base cost Price escalation Study cost Component 4: Carrying out the Financial Audit iv 2.66 0.19 0.03 2.88 0.40 3.28 MEANS OF VERIFICAT ION GOA’s statistics GOA’s document Study reports produced RISKS/MITIGATI-ON MEASURES Risk Failure to allocate enough budgets to develop and maintain the transport infrastructure Mitigation measures GOA’s efforts with the assistance of development partners Risk GOA’s decreasing commitment to implement the outputs of the studies Mitigation measures Regular dialogue and follow-up by the Bank and other development partners Risk 1. Delays in the procurement 2. Delays in the implementation, not meeting quality standards Mitigation measures 1. Realistic contract award plan 2. Precise ToR and efficient monitoring INPUTS Sources of financing (million UA) ADF Loan 2.90 [88%] GOA 0.38 [12%] Total 3.28 [100%] Study Timeframe Board Approval Signature of Loan Agreement GPN Publication TA (Procurement) Shortlisting Evaluation Award of Contract Technical Assistance Services Study Shortlisting Issuance of RFP Receipt of Proposals Evaluation of Proposals Award of Contract Mobilization Implementation of Study TA (Study Management) Shortlisting Issuance of RFP Receipt of Proposals Evaluation of Proposals Award of Contract Mobilization Technical Assistance Services Financial Audit Shortlisting Issuance of RFP Receipt of Proposals Evaluation of Proposals Award of Contract Mobilization Financial Audit Services TA: Technical Assistance Sep * 2013 Oct Nov Dec Jan 2014 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2015 Feb Mar Apr May Jun Jul Aug Sep Oct * * * 2 1 1 2 3 19 * * * 1 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1 2 3 4 5 6 7 8 9 10 11 12 * * * * * * v 13 14 REPORT AND RECOMMENDATION OF THE MANAGEMENT TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO THE REPUBLIC OF ANGOLA TO FINANCE THE STUDY FOR NATIONAL TRANSPORT SECTOR MASTER PLAN UPDATE Management submits the following Report and Recommendation on a proposed loan for UA 2.9 million on loan to finance the Study for National Transport Sector Master Plan Update in the Republic of Angola. I. STRATEGIC THRUST & RATIONALE 1.1. Study linkages with country strategy and objectives 1.1.1 The strategic pillars of the Country Strategy Paper (CSP) 2011-2015 are Pillar I: Stimulus to the Competitiveness of the economy and Pillar II: Support to Economic Infrastructure Development. Transport is one of the two sectors which are given priority in terms of financing infrastructure development. The outcome of the study will enable the Government of Angola (GOA) to timely and properly make decisions and take actions for the transport infrastructure development which will enhance the competitiveness of the economy of Angola and the region. The study area including the railway link is identified in the CSP 2011-2015. 1.1.2 Angola does not have a Poverty Reduction Strategy Paper (PRSP) but launched a long-term strategy named “Visão 2025” in 2010. Another long term vision named “Angola 2025”, published by the Ministry of Planning, articulates the vision of transport infrastructure development: “construction of an integrated transport network at the national level based on a comprehensive and integrated level of road, rail, maritime and air transport...”. The proposed study is to elaborate a nationwide and integrated transport network for the future, connecting the existing transport infrastructure, which is in line with the foregoing vision. 1.2. Rationale for Bank’s involvement 1.2.1 The Bank will be able to support the GOA in the studies not only financially but also technically, having experience of interventions in similar studies for other member countries. Also, the Bank will be able to provide the GOA with advice for the Preliminary Feasibility Study (Pre-F/S) on the Railway Link between Caminhos de Ferro de Benguela (CFB) and Zambia, as it has on-going interventions in the transport sector in Zambia. Close communication between the Bank and the GOA through the presence of Angola Country Office will be favourable for the smooth implementation of the studies. 1.2.2 The intervention in the studies is timely, because 1) Angola, at the final stage of rehabilitation, is now urgently requiring new perspectives on a nationwide and integrated transport network for the future, connecting the existing transport infrastructure; and 2) the Pre-F/S on the Railway Link should be commenced as soon as possible in light of the enhanced interests by the both governments of Angola and Zambia and the fact that some studies have been already done on the Zambian side. 1 1.3. Donors coordination 1.3.1 The Bank has not yet provided support for the transport sector in Angola. The World Bank financed a program named “Emergency Multi-sector Recovery – Phase2” which includes rehabilitation of 150 km of trunk roads and 600km of feeder roads. EU financed the “Feasibility Study Western Part TAH 9 Beira Lobito” including a feasibility study that covers a 1,161-km road section on Lobito Corridor within Angola and the Democratic Republic of Congo (DRC). JICA carried out a study to prepare a rehabilitation project in Port of Namibe, including a preliminary design, implementation plan and cost estimates, based on which a grant aid for development of a multi-purpose terminal is currently under consideration. Most of the railway rehabilitation has been funded by China. 1.3.2 Donor activity in Angola has shifted in the last two years to an increased presence in cross-cutting areas such as environment, decentralization, private sector development, and regional integration. There is no formal donor coordination, but informal meetings are held occasionally. A thematic Working Group meets when needed. With the opening of the Bank’s Country Office in Angola, the Bank aims to play a bigger role in this Working Group. Table 1.1 Overview of Major Donor Assistance in Angola Size Sector or subsector* Transport GDP N/A Exports N/A Labor Force N/A Players - Public Annual Expenditure (2008-2011 average)** Donors Amount(US$ mil.) % EU 64.0 33.3 USAID 44.5 23.1 World Bank 35.8 18.6 Italy 26.2 13.6 Norway 21.9 11.4 Total 192.4 100.0 Level of Donor Coordination Existence of Thematic Working Groups Existence of SWAPs or Integrated Sector Approaches ADB's Involvement in donors coordination*** Y N M**** * as most appropriate , ** The figures are for all sectors (the figure for the transport sector is not available), *** for this sector or sub-sector, **** L: leader, M: member but not leader, none: no involvement II STUDY DESCRIPTION 2.1. Background 2.1.1 Transport sector in Angola: After 27 years of conflict that ended in 2002, political stability and peace set the ground for an economic boom in Angola fuelled by increased oil production. The increasing revenues have enabled Angola to intensively rehabilitate its transport infrastructure, namely roads, railways, ports and airports up to now. However, Angola is still facing shortage of transport infrastructure and low service quality despite the intensive rehabilitation. Thus, it seems to be reaching a turning point from the era of 2 rehabilitation of deteriorated infrastructure into the era of development of infrastructure required for the country’s further economic growth in future. 2.1.2 Needs of a master plan for the transport sector: The recent rehabilitation of transport infrastructure has been implemented based on the Public Investment Plan (PIP) with a list of a number of facilities to be rehabilitated. However, the transport infrastructure development in Angola from now on will not be the same as the rehabilitation which was to return the existing infrastructure once deteriorated to its previous condition. It should be well planned and implemented with a clear strategy, priority and justification based on thorough surveys and analysis, with which GOA will effectively allocate the state budget, induce the private sector’s investment, and obtain the development partners’ fund as needed. In addition to transport infrastructure development, it is required to improve the transport service and its sustainability by addressing various issues, such as transport safety, road maintenance, the serious traffic jam in Luanda and so on. One of the major reasons why the transport sector is still facing a lot of problems despite the country’s considerably high economic indices is limited capacity of government institutions. For the reasons above, an integrated national transport sector master plan, built on existing plans and studies, is highly required, highlighting improvement in the transport infrastructure and services, so that GOA will be able to timely and properly make decisions and take actions for the transport sector. 2.1.3 Railway link between CFB and Zambia: CFB is a railway connecting Port of Lobito and a DRC border named Luau. Currently, the section between Lobito and Huambo is operational, whereas the remaining section is under rehabilitation and will be operational by the end of 2013. GOA and Government of Zambia (GOZ) intend to establish a direct railway link between CFB and an existing railway in Zambia, whose length will be roughly 300 km in Angola and 554 km in Zambia. The railway link, which would boost the growth of Port of Lobito, facilitate Zambia to export its mineral resources through an alternative route, as well as facilitate Angola to export its oil products from Lobito to Zambia, is a very important and urgent issue for Angola in the light of the political commitment where the Lobito Corridor development has reached an advanced consensus between the two governments. However, no study has been carried out so far on the Angolan side, whereas in Zambia a concessionaire has already carried out a pre-feasibility study on some sections within the missing link. In this situation, GOA is now very keen on a study on the railway link, so as to have a basis for the GOA’s next actions for development of the railway link, including the private sector involvement. 2.1.4 It is on this basis that GOA requested the Bank in December 2012 for assistance in carrying out a study to prepare an updated National Transport Sector Master Plan as well as a preliminary feasibility study on the railway link between CFB and Zambia. 2.2. Study objective The study objective is to provide GOA with an integrated master plan built on existing plans and studies with a clear strategy, priority and justification in terms of transport infrastructure development including the Railway Link between CFB and Zambia, so that GOA can have a clear vision of infrastructure development up to 2025, the target year of the “Visão 2025”. 3 2.3. Study components The study components are summarized below: Table 2.1 Study Components No. Component Name Estimated Cost (UA mil.) 2.14 1 National Transport Sector Master Plan Update 2 Pre-F/S on the Railway Link between CFB and Zambia 0.52 3 Technical Assistance 0.19 4 Financial Audit 0.03 2.4. Component Description formulate an overall set of strategies and policies for the nationwide transport network, composed of roads, railways, inland waterways, ports and airports elaborate a nationwide and integrated transport network for the future, connecting the existing transport infrastructure, along the strategies and policies mentioned above, and identify and select priority projects with justifications select an optimum route for a railway link connecting CFB and Zambia among different options, based on traffic data, natural, social and economic information, and environmental and social aspects, as well as economic and financial analysis of the optimum route [Procurement] assist the executing agency in procurement process for the study [Study management] assist the executing agency in monitoring study activities and reviewing various reports prepared An audit by external independent auditors to express an opinion on the financial statements provided to the Bank and provide reasonable assurance that the funds have been applied for the intended purposes with due attention to economy and efficiency Technical solution retained and other alternatives explored The proposed study will provide GOA with tools for making decisions and taking actions required for improvement of transport infrastructure and services. 2.5. Study type The study is a standalone operation that will be financed by a loan from the ADF, through the lending facilities of the Bank's windows for performance-based country allocations (PBA). 2.6. Study cost and financing arrangements 2.6.1 The estimated cost of the study, net of taxes and customs duty, will amount to UA 3.28 million, of which UA 2.94 million (90% of the study cost) payable in foreign currency and UA 0.34 million (10% of the study cost) payable in local currency. This cost includes 13.7% provision for price escalation. It was estimated on the basis of the unit prices of similar studies approved lately by the ADF. The estimated study cost is summarized in Table 2.2. 2.6.2 The study will be financed by the ADF and GOA. ADF financing will not exceed UA 2.90 million. This financing represents 88% of the total cost and will cover 98% of the foreign currency cost and 3% of the local currency cost. ADF financing will cover the financial audit and part of the expenditure on the study 1, study 2 and the technical assistance. GOA will contribute UA 0.38 million to study financing, representing 12% of the total cost and will cover 2% of the foreign currency cost and 97% of the local currency cost. The contribution of GOA will cover part of the expenditure on the study 1 and 2 and the technical assistance. 4 Table 2.2 Study Cost Estimates by Component [amounts in million UA equivalents] Foreign Local Total Components Currency Currency Costs Costs Costs Study1 - National Transport Sector Master Plan Update 1.91 0.23 2.14 Study2 - Pre-F/S on the Railway Link between CFB 0.46 0.06 0.52 and Zambia Technical Assistance 0.18 0.01 0.19 Financial audit 0.03 0.00 0.03 Total Base Cost 2.58 0.30 2.88 Price Contingency 0.36 0.04 0.40 Total Study Cost 2.94 0.34 3.28 Note: Exchange rates are provided in the introduction of this report (page (i)). Table 2.3 Sources of financing [amounts in million UA equivalents] Foreign Local Sources of Financing Currency Currency Total Costs Costs Costs ADF Loan 2.89 0.01 2.90 GOA 0.05 0.33 0.38 Total 2.94 0.34 3.28 % Foreign 89% 88% 95% 100% 90% 90% 90% % Total 88% 12% 100% 2.6.3 The study cost by category of expenditure and the expenditure schedule are shown in Table 2.4 and 2.5 below respectively. Table 2.4 Study cost by category of expenditure [amounts in million UA equivalents] Foreign Local Categories of Currency Currency Total Costs % Foreign expenditure Costs Costs Consultancy Services 2.58 0.29 2.87 90% Goods 0.01 0.01 0% Total base cost 2.58 0.30 2.88 90% Price Contingency 0.36 0.04 0.40 90% Total study cost 2.94 0.34 3.28 90% Table 2.5 Expenditure schedule by component [amounts in million UA equivalents] Components 2014 2015 Total Study 1.33 1.33 2.66 Technical Assistance 0.10 0.09 0.19 Financial Audit 0.01 0.02 0.03 Total base cost 1.44 1.44 2.88 2.7. Study’s target area and population Since the study will deal with the whole national transport sector of Angola, the study area is the entire country and the direct study beneficiaries is the Angolan nation who will enjoy the transport infrastructure and services to be developed and improved based on the outcomes of the study. 5 2.8. Participatory process for study identification, design and implementation The transport-related private sector was interviewed and their views and opinions have been incorporated in the study components and the implementation arrangement. The study will require significant consultation especially about project priority and environmental and social aspects, through workshops and public consultations with all relevant stakeholders. The working group to be mentioned in 4.1.2 will be responsible for facilitating all workshops and public consultations. 2.9. Bank Group experience, lessons reflected in study design 2.9.1 Some of the lessons learned pointed out in the current CSP were reflected in the study preparation and design. Regarding the “limited Government interest, capacity and ownership” mentioned in the CSP, the mission team met high officials of the Ministry of Transport and the Ministry of Planning, including the ministers, and confirmed that the study was urgent and of a matter of great interest to GOA. 2.9.2 For the counterpart funds issue, the mission team met the Ministry of Planning and explained the counterpart fund required for this study. On the other hand, the mission team confirmed with the Ministry of Transport, the executing agency, that the ministry would take necessary action to secure the counterpart fund registering under the Public Investment Plan (PIP). 2.9.3 As for the dissemination of the Bank’s procedures to GOA officials, the Bank will have to elaborately explain and disseminate the Bank’s procedures to the executing agency, since the study will be the first intervention of the Bank in the transport sector in Angola. 2.10. Key performance indicators The key performance indicators and expected outcomes upon study completion are indicated in the results-based logical framework. The indicators for the impact and outcomes are: i) the GDP growth rate as a measure of “Socio-economic development, poverty reduction and regional integration through an improved and sustainable transport system” and ii) Establishment of the institutional framework, such as an inter-ministerial committee, to ensure transport infrastructure development based on the National Transport Sector Master Plan Update and Pre-F/S on the Railway Link between CFB and Zambia, as the capability to timely and properly make decisions and take actions for the transport sector. These indicators will be followed and evaluated during the study implementation based on economic reports and GOA’s documents. III STUDY FEASIBILITY 3.1. Economic and financial performance Not applicable in case of study in case of study, but economic and financial analysis will be considered in the Study for National Transport Sector Master Plan Update in particular the pre-F/S on the railway link between CFB and Zambia. 3.2. Environmental and Social impacts Environment 3.2.1 The category of the Bank’s environmental and social assessment procedures is not applicable for studies. 6 3.2.2 Environmental aspects related to priority projects will be considered in the National Transport Sector Master Plan Update. During the Pre-F/S on the Railway Link between CFB and Zambia, environmental aspects will be identified, if any, for each optional route of the railway link. Also, the Pre-F/S will elaborate Terms of Reference (TOR) for ESIA to be carried out during the full-scale feasibility study subsequent to the Pre-F/S. Climate change 3.2.3 National Transport Sector Master Plan Update will refer to how climate change (mitigation and adaptation) is being and should be addressed in the transport sector. The PreF/S on the Railway Link between CFB and Zambia will identify some components related to climate change resilience to be addressed in the full-scale feasibility study for the railway link. Gender / Social / Involuntary resettlement 3.2.4 Gender/social/resettlement issues related to priority projects will be considered in the National Transport Sector Master Plan Update. During the Pre-F/S on the Railway Link between CFB and Zambia, gender/social/resettlement issues will be identified, if any, for each optional route of the railway link. Also, the Pre-F/S will elaborate TOR for ESIA and RAP to be carried out during the full-scale feasibility study subsequent to the Pre-F/S. IV IMPLEMENTATION 4.1. Implementation arrangements Study implementation 4.1.1 Ministry of Transport will be the executing agency for the study. Gabinete de Estudos, Planeamento e Estatistica (GEPE), Ministry of Transport, will be the focal point liaising with the consultants and the Bank. A Study Coordinator with the relevant experience who is responsible for the day-to-day management of the studies shall be nominated. Technical assistance by a consultant to be hired under ADF, who assists the executing agency in monitoring study activities and reviewing various reports prepared, will be provided to address the capacity constraint. To address the capacity constraint in the area of procurement management a procurement specialist would be recruited under ADF. The Ministry of Transport shall designate a suitably qualified officer to handle financial management aspects of the study. 4.1.2 A working group comprising various authorities and entities involved in road, rail, inland waterways, maritime and air transport sectors including the private sector, will be established. The working group will be responsible for providing technical guidance on the study, monitoring the implementation of the study, reviewing the consultant’s reports and facilitating the consultant’s activities. The GEPE will be the secretariat for the study, and will lead the working group. Procurement 4.1.3 All procurement of goods and works and acquisition of consulting services financed by the Bank will be in accordance with the Bank's Rules and Procedure for Procurement of Goods and Works(May 2008 edition, revised July 2012) and Rules and Procedure for the Use of Consultants (May 2008 edition, revised July 2012), using the relevant Bank Standard Bidding Documents. The Ministry of Transport, through GEPE as focal point, will be responsible for the procurement of goods and consulting services. A detailed procurement arrangement is shown in Technical Annex IV. 7 Disbursement 4.1.4 The Direct Payment method shall be used to disburse funds, i.e, the consultancy services for the study, the technical assistance consultant, the external auditors and suppliers of identified IT equipment (computers and printers) shall be paid directly by ADF upon requisite of all necessary documentation. Financial audit 4.1.5 Study financial statements shall be prepared and audited on annual basis. The audit shall be conducted in accordance with Bank approved auditor TOR, and the audited study financial statements shall be submitted within 6 months after year end. 4.2. Monitoring 4.2.1 Monitoring will comprise technical monitoring conducted by GEPE and the working group mentioned in 4.1.2, supplemented with an individual consultant (technical assistance for study management and monitoring) and supervision missions from the Bank. The timeframe is as shown below. Q3-2013 Study launch Monitoring Process / Feedback loop Launching mission Q1/Q3-2014 Q1-2015 Study works Supervision missions Q3-2015 Study completion Project Completion Report Timeframe 4.3. Milestone Governance In the current CSP, “civil society access to information on public affairs” is raised as one of the governance issues, although the CSP recognizes improvements in it. This study will further improve the civil society access to information on public affairs by improving the transport statistics. 4.4. Sustainability 4.4.1 It is recommended that the Bank maintain a dialogue with GOA concerning the establishment of the institutional framework such as an inter-ministerial committee, as well as endorsement of the outputs of National Transport Sector Master Plan Update as GOA’s official master plan, to ensure transport infrastructure development based on this study. 4.4.2 It is recommended that the sector department of the Bank review the outputs of the Pre-F/S on the Railway Link between CFB and Zambia upon its completion, and prepare as appropriate for the Bank’s funding for a full-scale feasibility study and detailed engineering design on the railway link, so that GOA will be able to proceed to the next step by fully making use of the results of this study. 4.5. Risk management 4.5.1 There is a risk of GOA not committing adequate budget to develop and maintain the transport infrastructure as per the recommendations of the studies. As mitigation measures, GOA is expected to continue to give the transport sector high priority, as well as seek funds from development partners as necessary. 8 4.5.2 There is a risk of GOA underutilizing the outputs of the studies although GOA has demonstrated its commitment to develop the transport sector. As mitigation measures, the Bank together with other development partners will maintain regular dialogue with GOA and encourage to set up an institutional framework within the government to be responsible for the implementation of the study output. In addition, the participation of stakeholders in the Study for National Transport Sector Master Plan Update will ensure the ownership and mitigate this risk. 4.5.3 There is a risk of delays in the procurement and implementation of the studies, due to limited capacity of executing agency and poorly qualified consultants. As mitigation measures, technical assistance is included as a component. Also, GOA needs to prepare precise TOR, carefully evaluate the technical proposals by candidate consultants, and efficiently monitor the study progress, supported by the Bank as needed. 4.6. Knowledge building The Study for National Transport Sector Master Plan Update will unveil the current situation of the transport sector in Angola which is not well known so far, despite its importance in the regional context. Although the Bank has not undertaken sector intervention in Angola, the study, as an upstream activity, is expected to identify future Bank’s intervention, such as financing for priority projects to be identified in the National Transport Sector Master Plan Update as well as financing for the full-scale feasibility study and detailed engineering design on the Railway Link between CFB and Zambia whose TOR shall be elaborated by the Pre-F/S. V LEGAL INSTRUMENTS AND AUTHORITY 5.1. Legal instrument The project will be financed pursuant to an ADF loan agreement between the Republic of Angola and the ADF. 5.2. Conditions associated with Bank’s intervention Conditions Precedent to the Entry into Force of the Loan Agreement 5.2.1 The Loan Agreement will enter into force upon fulfillment by the Borrower of the provisions of Section 12.01 of the General Conditions. Conditions Precedent to First Disbursement of the Loan 5.2.2 The obligation of the Bank to make the first disbursement of the Loan shall be conditional upon the entry into force of Loan Agreement and the fulfillment by the Borrower, in form and substance satisfactory to the Fund, of the following conditions: (i) Provide evidence of the appointment of the study coordinator, whose qualifications and experience shall be acceptable to the Fund; and (ii) 5.3. Provide evidence of the designation of a suitable officer to handle financial reporting, whose qualifications and experience shall be acceptable to the Fund. Compliance with Bank Policies This study complies with all applicable Bank policies. 9 VI RECOMMENDATION This study is to facilitate the Government of Angola’s sound administration, decisionmaking and timely action for development of transport infrastructure that is crucial for further economic growth of the country which is now transitioning from the infrastructure rehabilitation phase to the new development phase. Moreover, this study, which will be an entry point for the Bank’s intervention in the transport sector in Angola, may identify transport infrastructure projects for further Bank’s intervention. Management therefore recommends that the Board of Directors approve the proposed ADF loan of UA 2.90 million to the Republic of Angola for the purposes and subject to the conditions stipulated in this report. 10 Appendix I. Country’s comparative socio-economic indicators Develo- Developing ped Countries Countries 2011 2012 Life Expectancy at Birth (years) 71 61 51 41 31 21 11 1 2012 2011 2012 Angola 2011 106.6 102.8 101.5 101.4 80.0 98.3 98.7 97.9 5.2 2011 103.1 105.1 66.3 65.0 58.6 80.8 86.4 75.5 3.9 Africa 2010 101.9 98.4 42.3 38.5 43.2 67.0 75.8 58.4 5.3 2010 124.5 111.6 31.3 25.5 24.5 70.1 82.7 58.1 3.5 2010-2012 2010-2012 2010-2012 2010-2012 1998-2011 2010 2010 2010 2008-2010 2010 Education Indicators Gross Enrolment Ratio (%) Primary School - Total Primary School - Female Secondary School - Total Secondary School - Female Primary School Female Teaching Staff (% of Total) Adult literacy Rate - Total (%) Adult literacy Rate - Male (%) Adult literacy Rate - Female (%) Percentage of GDP Spent on Education 2009 276.2 730.7 ... 99.5 100.0 99.9 0.4 14.0 95.4 93.0 1.7 3 285 8.2 Angola 2009 112.2 187.6 65.4 86.4 80.0 56.2 0.9 146.0 83.9 83.7 17.4 2 675 2.9 2009 49.2 134.7 53.7 67.3 65.2 39.8 4.6 234.6 81.6 76.5 19.8 2 481 5.9 2008 8.0 135.0 47.3 51.0 24.0 58.0 2.1 310.0 88.0 88.0 15.6 2 079 2.9 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 2008 Health & Nutrition Indicators Phy sicians (per 100,000 people) 2004-2010 Nurses (per 100,000 people)* 2004-2009 Births attended by Trained Health Personnel (%) 2007-2010 Access to Safe Water (% of Population) 2010 Access to Health Serv ices (% of Population) 2000 Access to Sanitation (% of Population) 2010 Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 Incidence of Tuberculosis (per 100,000) 2011 Child Immunization Against Tuberculosis (%) 2011 Child Immunization Against Measles (%) 2011 Underw eight Children (% of children under 5 y ears) 2007-2011 Daily Calorie Supply per Capita 2009 Public Ex penditure on Health (as % of GDP) 2010 Population Growth Rate (%) 2008 0.3 0.7 16.6 16.5 49.3 94.7 45.5 77.9 81.2 11.4 10.1 6.0 7.8 1.7 13.7 71.4 2007 1.3 2.3 28.5 6.0 52.5 103.4 53.2 67.3 69.2 20.9 7.8 46.4 66.7 2.6 230.0 62.4 2007 2.3 3.4 40.0 3.6 77.3 100.0 49.8 58.1 59.1 33.3 10.9 71.4 111.3 4.2 417.8 31.6 Africa 2007 2.7 4.1 45.9 2.5 93.9 98.2 23.0 51.5 53.0 40.2 13.7 96.8 156.6 5.2 450.0 14.4 2006 2012 2012 2012 2012 2012 2012 2012 2012 2012 2012 2012 2012 2012 2012 2010 2012 Angola 2006 Demographic Indicators Population Grow th Rate - Total (%) Population Grow th Rate - Urban (%) Population < 15 y ears (%) Population >= 65 y ears (%) Dependency Ratio (%) Sex Ratio (per 100 female) Female Population 15-49 y ears (% of total population) Life Ex pectancy at Birth - Total (y ears) Life Ex pectancy at Birth - Female (y ears) Crude Birth Rate (per 1,000) Crude Death Rate (per 1,000) Infant Mortality Rate (per 1,000) Child Mortality Rate (per 1,000) Total Fertility Rate (per w oman) Maternal Mortality Rate (per 100,000) Women Using Contraception (%) GNI Per Capita US $ 4500 4000 3500 3000 2500 2000 1500 1000 500 0 2006 35,811 1,244.6 75.7 23.4 38 657 71.7 43.9 0.911 ... ... 2005 98,458 5,807.6 46.0 70.0 3 304 68.7 39.1 0.694 ... 22.4 2005 30,323 1,070.1 40.8 34.5 1 609 37.8 42.5 0.502 ... 40.0 2004 1,247 20.2 60.2 15.7 4 060 36.6 45.8 0.439 148 54.3 2005 Basic Indicators Area ( '000 Km²) 2011 Total Population (millions) 2012 Urban Population (% of Total) 2012 Population Density (per Km²) 2012 GNI per Capita (US $) 2011 Labor Force Participation - Total (%) 2012 Labor Force Participation - Female (%) 2012 Gender -Related Dev elopment Index Value 2005-2011 Human Dev elop. Index (Rank among 186 countries) 2012 Popul. Liv ing Below $ 1.25 a Day (% of Population) 2000-2011 2004 Africa 2004 Angola 2003 Year Africa Infant Mortality Rate ( Per 1000 ) 120 100 80 60 40 20 0 last update : 2010 I Angola 2009 Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports. Note : n.a. : Not Applicable ; … : Data Not Available. 10.8 -0.2 40.4 11.4 2008 10.7 0.4 28.7 3.1 2007 7.6 0.6 23.0 1.2 2006 3.3 0.2 46.8 1.4 2005 2011 2000-2009 2011 2009 2004 Environm ental Indicators Land Use (Arable Land as % of Total Land Area) Annual Rate of Deforestation (%) Forest (As % of Land Area) Per Capita CO2 Emissions (metric tons) Africa May 2013 Appendix II. Table of ADB’s portfolio in the country On-Going Portfolio In Angola (UA millions) EFFECTIVE DATE CLOSING DATE TOTAL COST TOTAL DISBU RSED % DISBUR SEMEN T PROJECT SECTOR APPROVAL DATE Bom Jesus Calenga Rural Development Project 24/11/2005 14/09/2006 31/12/2012 17.20 7.8 45.66% P-AO-A00-001 Agriculture and Rural Development Environmental Sector Support Project Environment 11/03/2009 17/12/2009 31/12/2015 12.00 2.2 18.46% Finance 14/11/2007 04/09/2008 31/12/2012 5.90 0.4 7.81% Water and Sanitation 28/11/2007 04/04/2009 30/06/2013 12.00 0.7 6.10% Governance 23/02/2011 May 2011 30/07/2013 5.17 0.2 4.17% 52.27 11.04 16.44% P-AO-CZO-001 Financial Support Management Project P-AO-KFO-002 Sumbe Water Supply Sanitation And Institutional Support Project P-AO-E00-003 Institutional Capacity Building Poverty Reduction Project GRAND TOTAL COMMITMENT II Appendix III. Key related projects financed by the Bank and other development partners in the country (1) Study on Urgent Rehabilitation Program of Ports: JICA (2005 - 2006) A study team conducted surveys and compiled a report, which proposed a short term port rehabilitation plan for 2010, an urgent rehabilitation program of port facilities, and an action program for the improvement of port management and operation. The study report concluded with a variety of recommendations such as: (a) rehabilitation and modernization of ports, (b) strengthening port administration, management and operation, (c) future development of Port of Luanda, and (d) preparation of Master Plan of Angolan Ports. (2) Grant Aid for Urgent Rehabilitation of Ports in Angola: Japan (2008-2010) Development of a multi-purpose terminal as the urgent rehabilitation program in Port of Namibe based on the above study. (3) Angola Emergency Multi-sector Recovery – Phase 2 : The World Bank (Effective in 2008 – Closing in 2013) A program to assist the government to: (a) facilitate agricultural marketing in specific areas with high agricultural potential that have been affected by the conflict, (b) reconstruct and rehabilitate critical infrastructure, and (c) strengthen capacity of participating ministries and agencies for improved governance and transparency and of local governments for future decentralization. The program includes rehabilitation of 150km of trunk roads and 600km of feeder roads, and Sector Strategy (Water, Power and Transport) to be produced by the ministries involved. (4) Preparatory Study on Namibe Port Rehabilitation: JICA (2010 –2011) A study to prepare a rehabilitation project in Port of Namibe, including a preliminary design, implementation plan and cost estimates. A grant aid for development of a multipurpose terminal is under consideration. (5) Feasibility Study Western Part TAH 9 Beira Lobito: EU (2011 –2012) This study is composed of (a) feasibility study of the selected road sections including comprehensive environmental and social impact report, (b) recommendation for trade and transport facilitation measures for the corridor, (c) recommendation for program to implement regionally approved standards, policy and financing system of road maintenance in the region and for vehicle and axle load regulations and management, (d) development of a proper structured infrastructure database for the SADC region. The feasibility study covers the road section Kuito – Luena – Luau – Angola/DRC border – Mutshatsha – Kolwezi (1,161 km) . III Appendix IV. Map of the Study Area CFB Source: Country Report – Angola, March 2012, Economic Intelligence Unit IV Railway Link