Uploaded by Prem Kiran

Method Statement for Trial pit

advertisement
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 1 of 17
EMPLOYER
BAUER
ENGINEER
KN INTERNATIONAL
PROJECT TITLE
BAUER ASSEMBLY YARD
DOCUMENT TITLE
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR ETISALAT MANHOLE
WORKS
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 2 of 17
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous
cover pages are hereby superseded and are to be destroyed.
Rev. No.
Rev. Date
00
13-09-2022
Prepared By
AL MASAOOD
Checked By
Review by
Approved by
Revision
NMDC
NMDC
Description
MFZ
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 3 of 17
Contents
1.
SCOPE AND OBJECTIVES ........................................................................................................ 4
2.
DEFINITIONS AND ABBREVIATIONS ....................................................................................... 4
A.
ABBREVIATIONS ........................................................................................................................ 4
NMDC .................................................................................................. ERROR! BOOKMARK NOT DEFINED.
OSHAD .................................................................................................................................................. 4
ABU DHABI OCCUPATIONAL AND HEALTH CENTER ....................................................................... 4
HSE 5
HEALTH, SAFETY & ENVIRONMENT .................................................................................................. 5
ERP 5
EMERGENCY RESPONSE PLAN ......................................................................................................... 5
PTW 5
PERMIT TO WORK ................................................................................................................................ 5
MS
5
HSEMS .................................................................................................................................................. 5
PPE 5
TBT 5
3.
REFERENCES ............................................................................................................................ 5
3.1
CODES AND STANDARDS................................................................................................................. 5
3.2
DRAWINGS ..................................................................................................................................... 5
3.3
DOCUMENTS .................................................................................................................................. 5
3.4
REQUIRED APPROVALS ................................................................................................................... 5
4
MATERIALS .................................................................................................................................... 6
4.1
OTHER RESOURCES ................................................................................................................. 6
PLANT & EQUIPMENT - THIS SECTION INCLUDES EQUIPMENT TO BE USED –................................................................ 6
5 MANPOWER .......................................................................................................................................... 6
6.
CONSTRUCTION PROCEDURE ................................................................................................ 7
PROCEDURES .......................................................................................................................................... 7
6.1
SITE PREPARATION......................................................................................................................... 7
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 4 of 17
7.
QUALITY ASSURANCE.............................................................................................................. 8
8.
HEALTH AND SAFETY ............................................................................................................... 8
8.1
EMERGENCY ARRANGEMENTS ......................................................................................................... 9
8.2
HAZARDS FACED WHEN CARRYING THE WORKS. ............................................................................... 9
9.
GENERAL.................................................................................................................................... 9
9.1
ORGANIZATIONAL RESPONSIBILITIES ................................................................................................ 9
9.1.1 THE PROJECTS MANAGER .............................................................................................................. 9
9.1.2 THE QA/QC ENGINEER ................................................................................................................ 10
9.1.3 SITE ENGINEER & FOREMAN ........................................................................................................ 10
9.1.4 QHSE MANAGER / SAFETY OFFICER.............................................................................................. 10
9.2
DISTRIBUTION............................................................................................................................... 10
9.3
STATEMENT OF INTENT ................................................................................................................. 11
10.
APPENDIX .................................................................................................................................... 11
10.1 APPENDIX B - RISK ASSESSMENT .................................................................................................. 11
1. SCOPE AND OBJECTIVES
This document describes the methods and resources to be deployed for the open excavation and backfilling
for the Trial Pit to identify the Etisalat sleeve location and depth prior to obtain NOC for Etisalat cabling works
at Bauer Assembly Yard Project.
2. DEFINITIONS AND ABBREVIATIONS
ABBREVIATIONS
MNGC
AL MASAOOD NATIONAL GENERAL CONTRACTING, Dubai
OSHAD
ABU DHABI OCCUPATIONAL AND HEALTH CENTER
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 5 of 17
HSE
HEALTH, SAFETY & ENVIRONMENT
ERP
EMERGENCY RESPONSE PLAN
PTW
PERMIT TO WORK
MS
METHOD STATEMENT
HSEMS
HEALTH, SAFETY AND ENVIRONMENT MANAGEMENT SYSTEMS
PPE
PERSONAL PROTECTIVE EQUIPMENT
TBT
TOOLBOX TALK
3. REFERENCES
3.1 CODES AND STANDARDS
•
•
•
•
•
Federal law 8 of 1980
Ministerial order 32 of 1982
ADNOC Safe Working Guide line to works near the Gas Pipe line
OSHAD regulations
Consultant’s project specifications
3.2 DRAWINGS
•
•
•
Proposed LV cabling Route Layout_ attached
Consultant approved IFC Structural Drawings
Consultant approved Architectural Drawings.
3.3 DOCUMENTS
•
•
Adnoc Guidelines
Approved Material specifications and technical data
3.4 REQUIRED APPROVALS
•
Approval of location and setting out must be obtained from ADNOC/ Authorised Team ( Royal
Gas) prior to proceeding with the works.
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Page
: 6 of 17
Shop drawings
Method statement
•
•
4
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
MATERIALS
The following list of material will be required within the scope of this method statement.
4.1 OTHER RESOURCES
PLANT & EQUIPMENT - THIS SECTION INCLUDES EQUIPMENT TO BE USED –
4.1.1 Plant and Equipment:
- Hand Showel
- Wheel Loaders
- Ladder
- Measuring Tape, Total Station, Dumpy Level etc.
4.1.2 Power Tools – N/A
4.1.3 PPE – Safety Hardhat, Hi-Viz Jacket, Safety Glasses, Gloves, Steel Toe Capped Boots, Water
Barriers/ safety Cones.
5
MANPOWER
As required, the following is provided indicatively:
S. No.
Position/Role
Quantity
Resource
1
Project Manager
1
Contractor
2
Site Engineer
1
Contractor
3
Foreman
1
Contractor
4
Safety Officer
1
Contractor
5
Surveyor
1
Contractor
6
Skilled Labourer
As required
Contractor
7
General Labourer
As required
Contractor
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
6.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 7 of 17
CONSTRUCTION PROCEDURE
PROCEDURES
6.1 SITE PREPARATION
6.1.1
6.1.2
Existing Services - construction team would investigate and acquire information about site
services that might have been placed/embedded below the ground. Services, wherever found
shall be rerouted and protected to place will not affect site activities.
Setting out – surveyor would conduct the site survey to mark/stake-out the lines and levels of
the objective excavation as indicated in the approved drawing.
The responsibility for carrying out this Method Statement and execution shall be that of the Project
Engineer, unless otherwise specifically mentioned in this procedure.
The Quality Engineer/ Project Engineer shall be responsible for inspection & testing.
6.2 EXCAVATION
6.2.1
The area to be excavated shall be identified and properly marked and clear before starting the
works.
6.2.2
The depth of excavation shall be periodically checked by a surveyor to avoid over-excavation.
the bank of the excavated area shall be sloped 30 degrees and shall be maintained to avoid a
collapse of the bank into the excavated area.
6.2.3
All excavated material shall be kept a minimum of 1.0 meter from the edge of excavation or
shall be stockpiled to the area designated by the Engineer.
6.2.4
The excavation of the trial pit shall be done by hand tools as per the ADNOC safety works
guidelines. (with in the 3 m radius from the gas pipe)
6.2.5
For all excavation activities, adequate safety barriers, signboards, advance warning signs
would be used.
6.2.6
All the trial pit excavation activity shall be done in under the supervision and witness by the
Royal Gas/ ADNOC.
Excavation shall be carried out to the lines & levels shown on the drawings and adequate, working
space shall be considered, Slopes & formation surfaces he trimmed true to the required profiles.
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
•
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 8 of 17
The sides of excavation for structures such as basements & foundations shall be adequately
supported. Furthermore, the sides shall be battered/ left exposed/ externally supported as per
site conditions
•
Vertical excavations in soft soil shall be supported or battered suitably, if the depth is more
than 1200 mm. The decision of angle of batter shall be as per conditions, angle of repose, site
conditions or as agreed by the Q Engineer in addition to the formal approval. The approval
shall be taken from the consultant if required. If the worker at the bottom of excavation is to
work in sitting or lying down position, buddy shall be provided to guard. Buddy shall stand
outside the trench & keep the worker in his sight all the time.
6.3 BACKFILLING
6.3.1
After completion of the compaction under blinding, tie beams and ground slab. Backfilling shall
commence using similar excavated material. Care shall be taken to remove bolder, vegetations
and any other deleterious materials.
6.3.2
Prior to backfilling, the compacted surface shall be accepted by the Engineer.
6.3.3
The thickness of the backfill shall not be greater than 300mm.
6.3.4
The sub-grade once approved, the excavated materials or any material source approved by the
Engineer shall be placed in layers not more than 300 mm thick followed by compaction test when
the surface level is ready.
6.3.5
Backfilling followed with compaction shall continue till the final level is achieved.
7. QUALITY ASSURANCE
QA/QC shall ensure that method statement and project specifications have always been followed. QA/QC shall
ensure the coordination of all necessary trades for the successful carrying out of work as per the approved
method statement.
8.
HEALTH AND SAFETY
Workplace inspections will be carried out by the person in charge of the specific activity by Al Masaood
and sub-contractors. Where subcontractors are required to carry out such inspections, the responsible
Al Masaood QHSE Manager/ Safety Officer must have a system of ensuring the adequacy of the
inspection process. Inspections carried out by Al Masaood will be recorded on Safety Observation form.
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 9 of 17
Adequate traffic management will be arranged to avoid traffic congestion at the site entrance and on
work locations. The construction waste will be collected on skips which will be removed by the assigned
subcontractor for the waste collection.
The works will be carried out according to all the requirements set out in the Site HSE Plan, OSHAD
Safety Regulation. For further details refer to the HSE plan.
8.1 EMERGENCY ARRANGEMENTS
In case of emergencies MNGC ERP Plan and flow chart will be followed.
Adequate fire extinguishers will be provided at the workplaces and should ensure that the access
towards it is always maintained. A first aid station with full time first aider should be provided at the
site entrance.
Depending on the situation, the sub-contractors ERT shall keep in close communication and liaise
with one or more of the parties detailed in the Emergency Numbers. (Police, Ambulance, Civil
Defence and principle contractor).
Sub-contractor will follow the site emergency arrangements as detailed in the Principle Contractors
approved HSE documents i.e. Project OSH Plan, Project ERP Plan, Truck operational and Maintenance
Procedure, Heat Stress Management Plan & Policy.
Actions to be taken in the event of an emergency will also posted on the site notice board.
8.2 HAZARDS FACED WHEN CARRYING THE WORKS.
•
•
Traffic arrangement
Use of hand tools and equipment.
Additional hazards involved for the works will be identified, assess the risk and adequate control
measures must be taken to minimize the potential hazards to a level as low as reasonably practicable.
9.
GENERAL
9.1
ORGANIZATIONAL RESPONSIBILITIES
9.1.1
THE PROJECTS MANAGER
•
Takes responsibility for all interfaces and other communications as required during the
execution of all activities.
•
Review the method statements prior to execution and explain the same to his subordinates
ahead of the job plan.
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 10 of 17
•
Manage and lead his workforce to ensure good workmanship and a quality product.
•
Be aware of all test results, test frequencies and approved materials to be used.
9.1.2 THE QA/QC ENGINEER
•
Shall conduct inspections as per the Inspection test plan.
•
Ensure that all the procedures in the method statement are implemented followed.
•
Ensure that all necessary records such as Inspection Request (I.R.), material approval and others
must be in-place prior to commence with the work.
9.1.3 SITE ENGINEER & FOREMAN
•
Shall execute the job as per the approved method statement, drawings, specifications, and Job
Safety Analysis guidance.
•
Issue the correct and approved materials and explains the daily tasks to his workforce.
•
Work hand in hand with the Project Team to deliver a quality output.
9.1.4 QHSE MANAGER / SAFETY OFFICER
•
Advice and assist in ensuring that all the requirements prescribed in the HSE plan are in place.
•
Tools & equipment to be used is in good working order and has the correct up to date
certification, where necessary workers are fully competent to carry out their tasks and are
authorized to do so.
•
Required permits are in place before works commence safe access is provided to the working
area.
•
Accident/incidents and near misses are reported promptly.
•
There is suitable provision of first aid.
•
There are suitable measures for the prevention and control of fire.
•
Site safety inspections are carried out and reported to Al Masaood management.
NOTE: The Job Responsibilities shall be reviewed to suit the project conditions.
All works shall be performed under competent supervision including an HSE representative on site.
9.2 DISTRIBUTION
•
Projects Manager
•
Consultant
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
•
QA/QC Engineer
•
QHSE Manager / Safety Officer
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
: 11 of 17
9.3 STATEMENT OF INTENT
MGNC are committed to comply with national and local regulations and the Client’s requirements to
ensure that the project is delivered on time within budget and to the agreed quality requirements.
The consultant will be notified of any changes required on site and approval will be obtained prior to
the works being carried out.
10. APPENDIX
10.1 APPENDIX B - RISK ASSESSMENT
(See Attached)
Al Masaood National General Contracting.
BAUER ASSEMBLY YARD
METHOD STATEMENT FOR
EXAVATION OF TRIAL PIT FOR THE ETISALAT
MANHOLE.
Doc. No.: 10176-MS-002
Rev. No.: 00
Date
: 13 September 2022
Page
Al Masaood National General Contracting.
: 12 of 17
Download