ZOOM MEETING Topic: Challenges and future developments of electricity supply in Ruwa TOPICS TO BE COVERED • • • • • • CURRENT SITUATION CHALLENGES VERY SHORT TERM SHORT TERM SOLUTION MEDIUM TERM SOLUTION LONG TERM SOLUTION CURRENT SITUATION • SUNWAY CITY IS SUPPLIED FROM RUWA CONTROL AT 11KV • CURRENT LOADING AS AROUND 90% • EXISTING BACK FEED IS FROM COLEFORD AND AS AT AROUND 80% VERY SHORT TERM - Coleford CB49 Reconfiguration 1. 2. 3. 4. 5. Uprate first leg – 1300m of UGC Lay and terminate 850m of UGC Uprate 3km of OHL from 50sqmm SCA to 100sqmm SCA 4 Install 1 x 11kV Gang Link Total cost : $240 229.57 SHORT TERM: 11kV Feeders From Lynette 1. FEEDER 1 - 6KM EVENLY SPLIT BETWEEN OHL AND UGC a) TO BE OUT SOURCED TO A CONTRACTOR b) SPECIFICATIONS HAVE BEEN DONE ARE STILL TO APPROVED c) TENDERING WILL PROCEED THERE AFTER d) EXPECT WORK TO BEGIN IN THIS YEAR 2. FEEDER 2 – WORKING TO SECURE WAYLEAVES MEDIUM TERM – Establishment of Sunway City 33/11kV Control 1. Construction of 33/11kV Substation 2. Construction of 33kV feeder from Coleford 3. Upgrading of Coleford 132/33kV to 2 x 90MVA LONG TERM: Upgrading Sunway City Substation 1. Construction of 132kV line from Dema 2. Upgrading of Sunway City Substation from 33/11kV to 132/33/11kV Substation