Rock Mechanics and Rock Engineering https://doi.org/10.1007/s00603-018-1430-4 ORIGINAL PAPER The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines Johan Wesseloo1 Received: 5 June 2016 / Accepted: 2 February 2018 © Springer-Verlag GmbH Austria, part of Springer Nature 2018 Abstract Mining-induced seismic hazard assessment is an important component in the management of safety and financial risk in mines. As the seismic hazard is a response to the mining activity, it is non-stationary and variable both in space and time. This paper presents an approach for implementing a probabilistic seismic hazard assessment to assess the current hazard state of a mine. Each of the components of the probabilistic seismic hazard assessment is considered within the context of hard rock underground mines. The focus of this paper is the assessment of the in-mine hazard distribution and does not consider the hazard to nearby public or structures. A rating system and methodologies to present hazard maps, for the purpose of communicating to different stakeholders in the mine, i.e. mine managers, technical personnel and the work force, are developed. The approach allows one to update the assessment with relative ease and within short time periods as new data become available, enabling the monitoring of the spatial and temporal change in the seismic hazard. Keywords Induced seismicity · Seismic hazard · Seismic hazard assessment · Spatial assessment · Hard rock underground mines 1 Introduction The management of seismic hazard in any seismically active mine is an extremely important task due to the safety risks, as well as the direct and indirect financial risks. The level of mine-induced seismicity is expected to increase as mines reach greater depths. In Australia, the deepest mines are currently operating at depths of about 1600 m. In Canada, depths of about 3000 m are reached, whilst in South Africa operating levels are now nearing 4000 m. Wesseloo (2013) argues that, due to the stochastic nature of mining-induced seismic events, seismic hazard should be assessed probabilistically. Probabilistic evaluations also allow one to quantitatively integrate hazard over space and over time, which is not possible with, for example, qualitative seismic hazard evaluation (e.g. Hudyma and Potvin 2004, 2010; Kaiser et al. 2005; McGaughey et al. 2007). Probabilistic seismic hazard assessment in crustal seismology and earthquake engineering has a long history, and * Johan Wesseloo johan.wesseloo@uwa.edu.au 1 Australian Centre for Geomechanics, The University of Western Australia, Crawley, Australia the principles and general approaches are well established and understood. Many similarities exist between crustal seismicity and mining-induced seismicity, and many concepts and theories can be borrowed from crustal seismology, as is evident from Gibowicz and Kijko (1994). Some of the components of probabilistic seismic hazard assessment applied to mines are discussed in the Canadian Rockburst Research Handbook (Mining Research Directorate 1996). In contrast to crustal seismicity, mining-induced seismicity is a consequence of human activity and is directly related to the mining activity (Fig. 1). Mining engineers can also influence the seismic hazard with, for example, mining method, mining sequence and preconditioning. Another difference between crustal seismicity and mining-induced seismicity is the fact that the mining activity changes the geotechnical conditions which give rise to the seismicity. Over time, the mining-induced stress concentration and rock competency change, resulting in a complex spatio-temporal seismic hazard regime. For example, a highly stressed volume of rock may, in a later stage of mining, be completely de-stressed, changing from a volume with high seismic hazard to a volume with insignificant hazard. The temporal change in seismicity must also be considered in studies of seismicity induced by human activity 13 Vol.:(0123456789) J. Wesseloo Fig. 1 Drop in the rates of seismic activity during 2010 Christmas break in a gold mine in South Africa (Mendecki and Lotter 2011) that are not related to mining. Convertito et al. (2012), for example, propose a technique for time-dependent probabilistic seismic hazard analysis to be used in geothermal fields to monitor the effects of ongoing field operations. Lasocki (2005) recognises the importance of accounting for the transient nature of mining-induced seismicity and suggests that probabilistic characteristics of future seismic source zones could be predicted based on the characteristics of historical source zones. It should be noted that Lasocki (2005) considered a scenario where the hazard assessment is performed at a scale and distance greater than the seismic source zones. For such a scenario, the overall seismic hazard is a result of a superimposition of the contributions of the individual sources, and reasonable results may be achieved. In contrast, for the assessment of the in-mine seismic hazard, sufficiently reliable prediction of the probabilistic characteristics of future seismic sources is currently not possible for many mining scenarios. This paper presents a method for the probabilistic assessment of the in-mine spatial distribution of the current seismic hazard in hard rock mines and considers different ways to present and communicate the hazard. 2 The Current Seismic Hazard State in Mines The hazard assessment method proposed here entails the quantification of the current hazard state. This is conceptually different from other hazard assessment approaches and therefore requires further clarification. The word “current” refers to the fact that this hazard assessment is not an assessment of the hazard for a specific future time period, but an assessment of the hazard to which the mine is currently subjected. “Hazard state” refers to the fact that the hazard assessment is a quantification of the overall spatial variation of higher and lower hazard throughout the mine and does not concern itself with short-term 13 fluctuations as opposed to, for example, the approach of Rebuli and van Aswegen (2013). For our purposes, the current hazard state can be defined as follows: The current seismic hazard state is the event size that can be expected to occur with a confidence of P, with a continuation of recent seismic conditions at the timescale under consideration. It should be noted that the phrase “with a continuation of recent seismic conditions at the timescale under consideration” is not an assumption. The transient nature of mining-induced seismicity makes the addition of the phrase a necessary part of the definition. Within the mining environment, we can safely assume that current conditions will not continue into the future for any substantial period. This does imply, though, that the assessment is valid for as long as the future seismic conditions, over the timescale of interest, remain reasonably constant. 3 Calculating the Current Seismic Hazard State A summary of the different components involved in the probabilistic seismic hazard assessment in crustal seismology is given by Kijko (2011): • Parameterisation of seismic source zones. • Temporal and magnitude distribution of seismicity for each source zone. • Calculation of the ground motion prediction equation and its uncertainty. • Integration of uncertainty in earthquake location, mag- nitude and strong ground motion relationship to obtain the probability of exceeding a specified ground motion parameter at least once. The definition of seismic source zones is somewhat subjective; there are some examples where the interpretation of the seismic response and hazard has been distorted because of an incorrect definition of the zones. Wesseloo (2013) mentions an occasion where events that occurred near a major fault in the hanging wall, and events near the same fault’s inferred location in the footwall, were assumed to be from a single source. The rock mass responses in these two areas were markedly different, and the hazard in the footwall was subsequently overestimated. The identification of seismic source zones is important, and a careful evaluation of possible zones will enhance the seismic hazard assessment. The approach taken here is to develop a robust method that will require minimal user input and be insensitive to user input. A grid-based, rather than a zone-based, approach is followed. The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines Two important components to the hazard assessment, namely, the spatial evaluation of the frequency–magnitude distribution and event rate density, are quantified using the grid-based approach. The variation of the b-value is evaluated using the method discussed in Wesseloo (2014), whilst the recent historical seismic density rate is obtained using the method discussed in Wesseloo et al. (2014). The last component mentioned by Kijko (2011) is the integration of the strong ground motion relationships and their uncertainties into an overall estimate of the probability of exceeding a specified strong ground motion. 3.1 The Upper Limit of Magnitude, MUL 3.1.1 The Meaning of MUL in Mining The term “Mmax” is used to define the region-characteristic maximum possible event magnitude or as the upper limit of event magnitude for a given region (Kijko and Singh 2011) and defines the upper asymptote of the frequency–magnitude distribution. In the mining industry, the term “Mmax” is also used for three other concepts, namely, the largest recorded event in a dataset, the fitted frequency–magnitude relationship at N = 1 and the distribution of the largest expected magnitude. To avoid confusion, we will refer to this value as the upper limit of magnitude, MUL. In crustal seismology, the value of M UL is generally assumed to be constant for a particular seismic source zone. However, in the mining environment the value of MUL is not a constant and is influenced by a number of factors, for example, rock mass conditions, mining-induced stress state, the mining sequence and mining layout. In addition, MUL is expected to increase with the extraction ratio (Mendecki 2012). For these reasons, we define MUL as the upper limit of the next largest event. The influence of each of the mentioned factors on MUL is currently unknown, resulting in an unknown reliability in the assessment of MUL. As MUL forms an upper limit of the frequency–magnitude distribution, the probability of exceeding MUL is, per definition, zero. When assessing the probability of exceeding a specified magnitude P[M > ML], under-estimation of MUL leads to larger errors than overestimation of MUL by the same amount (“Appendix 1”), i.e.: ]| ]| | [ | [ |𝜀P M > ML|MUL − Δ𝜀 | = 𝜀P− > 𝜀P+ = |𝜀P M > ML|MUL + Δ𝜀 | | | | | (1) where MUL = the upper limit of magnitude; M = magnitude; ML = magnitude under consideration; εP = the error in probability of exceeding ML; Δε = the error in estimation of MUL; εP+, εP−= the error due to overestimation and underestimation of MUL, respectively. The value of εP+ is always conservative, whilst εP− is always optimistic. For these reasons, a conservative estimate of MUL is necessary. 3.1.2 Statistical Methods for the Estimation of MUL Several statistical methods for the estimation of MUL from seismic records in crustal seismology are discussed in detail by Kijko and Singh (2011). These include an approximate and exact solution to the Kijko–Sellevoll (K–S) method, and Bayesian adaptations to the Tate–Pisarenko (T–P) and K–S methods. The exact solution to the K–S method and the two Bayesian methods is computationally intensive and produces results similar to the approximate and non-Bayesian solutions and is therefore excluded from routine calculations. Kijko and Singh (2011) also propose formulations for the assessment of the standard deviation of MUL as a function of the resolution of the magnitude for which a value of 0.1 was used. Lasocki and Urban (2011) quantified the bias and variance of the K–S method’s estimates for MUL which we use to apply bias and variance corrections to the K–S method estimates. To ensure conservatism in the estimation of MUL, the expected value plus the standard deviation is used as the estimate of MUL. The maximum value obtained from the following, discussed in detail by Kijko and Singh (2011), is used: Tate–Pisarenko (T–P), Kijko–Sellevoll, order statistics, Robson–Whitlock, Robson–Whitlock–Cooke and Cooke 1980. The statistical methods assume that the magnitude values are reliably recorded and that the shape of the inverse cumulative distribution of magnitude is a result of the statistical distribution only. This condition is, however, not always met as many in-mine seismic systems under-record the seismic moment of larger events due to sensor frequency range limitations and, as a result, exhibit a nonlinear (on the log-linear scale) frequency–magnitude distribution, as shown in Fig. 2a. Figure 2a shows the frequency–magnitude distribution (inverse cumulative distribution of magnitude) of recorded data from a mine network with only 50 Hz sensors. The downward curvature of the distribution is not a result of the statistical distribution of magnitude but of the under-recording of the moment by the sensors. Also shown in the figure are two theoretical lines—the straight Gutenberg–Richter relationship assumed as the true distribution of magnitude, and a theoretical assessment of the effect of under-recording using analytical formulations (Boore 1986; Di Bona and Rovelli 1988; Mendecki 2013b; Morkel and Wesseloo 2017). The effect of different lower frequency limits of the sensors is illustrated in Fig. 2b. For databases subjected to under-recording, optimistic values of MUL will result from the use of the statistical methods. 13 J. Wesseloo 8 Magnitude of largest recorded event 7 Theorecal “true” distribuon 6 5 4 3 2 1 0 range applicable to mining -1 Theorecal “recorded” distribuon (thick line), and, distribuon of recoded data (points) -2 0 1 2 Log(L); 3 4 5 L = Largest dimension of causive acvity McGarr et al. 2002 Australian and Canadian Mines Fig. 3 Maximum magnitude (Richter scale) and maximum dimension of causative activity after McGarr et al. (2002) with the addition of four mine sites from Australia and Canada (a) mines were obtained from government seismological institutions. The largest dimension of the mine at the time of the occurrence of the events was obtained from mine survey data. Although the mine site data are limited, they fit the general trend for induced seismicity. Estimating an upper bound to this data provides an empirical relation to estimate MUL in the absence of reliably recorded large event data. The relation shown in Fig. 3 can be written as follows: Theorecal “true” distribuon (2) where MUL = the upper limit of magnitude; L = the largest spatial dimension of the human influence. It should be noted that the largest dimensions of mines L may vary between, say 500 and 5000 m (log(L) of 2.7 to 3.7) with associated values of MUL ranging between about 4 and 6. The database includes only two points below log(L) of 3, both of which have relatively low magnitudes. This highlights the importance for expanding the empirical database used to populate Fig. 3. MUL = 1.85 ⋅ log (L) − 0.5 100 Hz Theorecal “recorded” distribuons 50 30 15 4.5 1 (b) Fig. 2 Effect of sensor frequency limits on the frequency–magnitude distribution (inverse cumulative distribution of moment magnitude) of recorded seismic datasets (Morkel and Wesseloo 2017) 3.1.3 Empirical Methods for the Estimation of MUL McGarr et al. (2002) compiled a dataset of large induced earthquakes with the largest associated dimension of human influence for each of them. Their data are presented in Fig. 3 with the addition of four data points from hard rock metalliferous mines in Australia and Canada. The event magnitudes for these 13 3.2 Frequency–Magnitude Distribution Several formulations of the frequency–magnitude distribution which include an upper limit value for magnitude exist. Utsu (1999) provides a review of the relationships and expresses these in the following generalised form: (3) where 𝜙(M) is an increasing function of M. The well-known truncated Gutenberg–Richter relationship frequently used in crustal seismology can be written in this form with: log(n) = A − b ⋅ M − 𝜙(M) The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines 𝜙(M) = 0 for M ≤ MUL A − b ⋅ M for M > MUL (4) This paper limits itself to the use of the truncated Gutenberg–Richter relationship as this is the formulation most commonly used in mining seismology (e.g. Gibowicz and Kijko 1994; Kijko and Funk 1994; Malovichko 2017; Mendecki 2012, 2013a; Mendecki 2008). The hazard assessment framework discussed here is not dependent on the particular formulation of the frequency–magnitude distribution and can easily be extended to include any other formulation. When evaluating the frequency–magnitude distribution for the purpose of hazard assessment, it is important to ensure that a clean database is used. The characteristics of blasts are different from those of seismic events, and several discrimination techniques have been proposed for the removal of blasts from mine databases (e.g. Dong et al. 2016; Malovichko 2012; Vallejos and McKinnon 2013). The removal of orepass noise on an individual event basis has not yet satisfactorily been addressed. Currently, the most practical approach to addressing this problem is to limit data for hazard assessment in the vicinity of orepasses to periods when orepasses are not in use (i.e. apply a time filter). For the purpose of hazard assessment, however, it is not necessary to separate orepass noise from other events on an individual basis since statistical approaches can be applied. Such approaches aim to obtain the statistical characteristics of underlying superimposed populations. Woodward and Tierney (2017) propose a method for simultaneously inverting the parameters of the frequency–magnitude relationships for both the orepass noise and seismic events. The parameters for the frequency–magnitude distribution of the events obtained this way can be used for hazard assessment. 3.3 The Considered Timescale When performing the hazard assessment, a data time period on which to base the assessment must first be chosen. This time period must be defined with reference to the mining cycle at different timescales of interest. The selected data period constitutes the “recent history” that defines the hazard state, and the hazard assessment is applicable to any timescale for which the mean seismic rate obtained from the data period is applicable. Lasocki (2008) mentions that earthquake processes are permanent and are controlled by factors that are constant in time and, as a result, are assumed to be Poissonian (stationary and memoryless), with the event rate being governed by the Poisson distribution. Mining-induced seismicity, on the other hand, is anthropomorphic and is spatially and temporally strongly correlated to mining activity and, as a result, is temporally often regarded as a non-Poissonian process. Lasocki (2008) shows that the reported non-Poissonian character of mininginduced seismicity is due to a non-stationary process, rather than it being caused by the inter-relations of event occurrence. He also noted that the process tends towards being stationary when the time period is reduced. Mining-induced seismicity can therefore be described by a Poisson distribution with the rate parameter varying over time. Lehmann and Romano (2005) show that: ∑ ( ∑ ) P(N|𝛬, ΔT) = P ni |𝜆i , Δti ; with N = ni (5) i i where N, Λ, ΔT = number of events, mean event rate and time period for overall time period; ni, λi, Δti = number of events, mean event rate and time period for sub-period i. This implies that for mining-induced seismicity the mean event rate Λ over the time period ΔT adequately describes the temporal seismic process at scale ΔT, irrespective of the individual values of λi over the shorter periods, Δti (Fig. 4). Its implication in terms of hazard assessment can be described as follows. The seismic hazard assessed for period ΔT, based on the overall mean seismic rate, Λ, is equal to the combined hazard from each of the sub-periods with associated rate and time length parameters. In other words, the assessment of hazard over a longer period with mean seismic rate, Λ, is independent of the short-term variations of seismic rate, λi. 3.4 Probabilistic Seismic Hazard Assessment of the Current Hazard State The truncated Gutenberg–Richter formulation can be written as a cumulative and inverse cumulative distribution function, as follows (Kijko and Singh 2011): ⎧0 for M < mmin ⎪ −𝛽 (M−mmin ) F(M) = ⎨ 1−e−𝛽 (M −m ) for mmin ≤ M ≤ MUL UL min 1−e ⎪1 for M > MUL ⎩ (6) ΔT Cumulave number of seismic event { Δt1 Δt2 Δt3 Δt4 Δt5 5 4 3 Λ N 2 1 Time Fig. 4 Representative mean seismic rate over different time periods 13 J. Wesseloo F � (M) = 1 − F(M) (7) where F, F′ = the cumulative and inverse cumulative distribution functions, respectively; β = the power law exponent = b·ln(10); mmin = magnitude of completeness; MUL = upper truncation value of magnitude. The meaning of MUL is discussed in Sect. 3.1.1; M = magnitude. The cumulative probability function of the largest event in a set of n events is given as follows (Gibowicz and Kijko 1994): n (8) The probability of at least one event out of a total of n events having a magnitude exceeding ML is given by: Fmax (M, n) = F(M) P(M > ML|n) = 1 − Fmax (ML, n) = 1 − [F(ML)]n (9) In crustal seismology, for the purpose of forecasting future hazard for a specific time period, the uncertainty in the number of events, n, is taken into account as follows (Gibowicz and Kijko 1994): Fmax (M|Δt) = ∞ ∑ P(n|Δt)[F(M)]n n=0 (10) where P(n|Δt) = the probability of experiencing n events in a future time interval Δt. Generally, P(n|Δt) is defined as follows for a stationary Poisson’s process: P(n|Δt) = (𝜆 ⋅ Δt)n ⋅ e−𝜆⋅Δt n! (11) where λ = mean event rate applicable over period of length Δt; n = number of events within a time interval Δt. This leads to the following relationship for the probability of at least one event exceeding ML (Gibowicz and Kijko 1994): P(M > ML|Δt) = 1 − Fmax (ML|Δt) = 1 − e−𝜆⋅Δt⋅(1−F(ML)) (12) Equations (11) and (12) can be rewritten so that the applicable time period is implicit as the period length over which the mean number of events, n , is applicable: P(n|̄n) = n̄ n ⋅ e−̄n n! (13) P(M > ML|̄n) = 1 − Fmax (ML|̄n) = 1 − e−̄n⋅(1−F(ML)) (14) where n̄ = the mean number of events experienced within a time period Δt. As the mining-induced seismicity is a result of the rock mass’ response to mining and is influenced by the mining activity, it is transient over space and time. Reliable forecasting of P(n|Δt) for any specified future period based on historical data is problematic and, for many mining methods 13 and environments, not currently possible. This component is not important for our purposes as the method proposed here is not an attempt to forecast future hazard for a specific future period, but a method to quantify (or monitor) the current hazard state. For our purposes, we ignore the uncertainty in the number of events for a future time period and assume that n = n̄ . Thus, for the assessment of the current hazard state, we assume: P(M > ML) = 1 − [F(ML)]n̄ (15) where n̄ = the mean number of events applicable to time period Δt. It should be noted that, since 1 − F(ML)n̄ ≥ 1− e−̄n⋅(1−F(ML)) for n̄ ≥ 0 and 0 ≤ F(ML) ≤ 1, the assumption that n = n̄ is conservative for all permissible conditions. The difference between the two formulations (Eqs. 14 and 15) approaches zero for large n̄ and large probabilities, whilst the largest difference between the two formulations occurs for small probabilities and low seismic rate and is inconsequential (“Appendix 2”). Assuming that all other statistical characteristics of sources of seismicity remain the same, the current hazard state is applicable to any future period for which the mean seismic rate obtained from the data period is applicable. For the purpose of calculating the current hazard state, n̄ is calculated from the mean event rate density obtained from the grid-based approach for the data period under consideration (Sect. 3.5). 3.5 The Grid‑Based Approach This section briefly presents the grid-based approach discussed in detail in Wesseloo et al. (2014) and Wesseloo (2014). The approach consists of the discretisation of a volume of interest into a fine regular grid. To each gridpoint, representative seismic parameter values are assigned, based on the events in the neighbourhood of the gridpoint. For the assessment of the seismic hazard state in space for the period under review, the b-value and the event density rate are evaluated. What is regarded as the “the neighbourhood” depends on the resolution of the seismic system and is defined with a maximum search distance, Rmax, when evaluating the parameters for each gridpoint. Different approaches are needed to obtain the b-value and the event rate density. These two approaches are discussed separately in the following paragraphs. 3.5.1 Event Rate Density For obtaining the event density for the period under consideration, each event that occurred within the period of interest The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines carries a unit intensity. The event density is calculated with a variable smoothing function where the kernel bandwidth is linked to the event source size, and the event density at each gridpoint is obtained from the sum of all the values of all the events registered to that gridpoint. This can be expressed as follows: ∑ All gridpoints Fi = ( ) K 𝜃i,j (16) (17) j 𝜃i,j = sj − si hi ( )3 1 − 𝜃 2 if 𝜃 < 1 K(𝜃) = 0 if 𝜃 ≥ 1 1:1 (18) (19) where pj = event density at gridpoint j; s = location vector of the event and gridpoints; K(θ) = kernel function; hi = the influence zone of each event, i. F is a correction factor that ensures that no errors are introduced due to the discretisation of the volume space, i.e. that the following condition is met: ∑ all ridpoints pj ⋅ Vj = N (20) j where Vj = the volume of grid cell j; N = total number of events used in the evaluation of event density distribution. In this calculation, the influence zone for each event, hi, is based on the event size with added ceiling and floor values (Fig. 5). A lower cut-off value equal to the grid spacing is imposed to ensure stability of the method for coarser grid discretisation. This lower limit ensures that each of the more numerous small events are associated with at least one gridpoint. A limiting ceiling value is also introduced for numerical efficiency and stability. The results are not sensitive to the ceiling value. In this study, the source radius as defined by Brune (1970) is used to define the source size. The mean event density rate is obtained as the event density divided by the time length for the period of interest. 3.5.2 b‑Value The grid-based approach for the spatial assessment of the b-value is performed as follows: • Events with magnitudes much smaller than the esti- mate of the overall sensitivity based on the whole data- Fig. 5 Definition of the event influence zone with floor and ceiling values Δ mmin = system sensivity i ( ) 1 ⋅ K 𝜃i,j Fi Data excluded from analysis ∑ All events pj = b 1 Fig. 6 Illustration of frequency–magnitude distribution showing the range of data excluded from the b-value calculations set (mmin − Δ) are excluded from the analysis (Fig. 6). This is done to speed up the calculations by excluding very small events that do not contribute to obtaining the b-value. A Δ of 1 magnitude unit yields satisfactory results. • For each gridpoint, the mmin and b-value are obtained from the closest Nb events. The search distance R is limited to a value Rmax. The algorithm for automatically obtaining the mmin and b-value is outside the scope of this paper, but is discussed in detail in Wesseloo (2014). The data included in the calculation of the b-value for every gridpoint are illustrated in Fig. 7. 13 J. Wesseloo 3.6 Probabilistic Strong Ground Motion on Excavation Δ overall mmin It is common practice to use the strong ground motion as a proxy for seismic hazard at the excavation, and, in mining, it is common to use the peak particle velocity (ppv) (Potvin and Wesseloo 2013). Milev and Spottiswoode (2005) have made a large number of ppv measurements at the surface of excavations at the TauTona mine, Kloof mine and Mponeng mine using a custom-designed surface-mounted instrument Nb events within distance R local mmin Data excluded from analysis Nb (a) called the peak velocity detector (PVD). “Theoretical” ppv values calculated from the seismic monitoring systems projected at excavation locations were then compared to ppv values measured at the surface of excavations from the PVD instrument. The ratio between the ppv experienced at the surface of an excavation and the theoretical body wave ppv are often called the “site amplification factor”. The site amplification factor varied between about 1 and 25 for each of the three mine sites, suggesting that the site effect may vary significantly, even within a mine. The site amplification factor is likely to be the cumulative effect of different factors which include the radiation pattern, the complex interaction of the body waves with the geology and excavation and the effect of surface waves (Potvin and Wesseloo 2013). Depending on the seismic source mechanism and orientation, different radiation patterns will result in the strong ground motion varying in different directions from the source. The radiation pattern for a double-couple shear mechanism in three dimensions is illustrated in Fig. 8. Colour plots of the theoretical body wave intensity in the vicinity of excavations are shown in Fig. 9. The first two plots in Fig. 9 show the variation for two different slip orientations, whilst the third plot shows the result when the three-dimensional radiation pattern is ignored. The body waves are reflected and refracted, and s- and p-wave conversion occurs as they travel through the rock mass resulting in complex wave forms interacting with the excavations. When the body waves interact with excavations, surface waves are generated and propagate along the surface of an excavation. Durrheim (2012) explains that the fractured zone typically present around excavations at depth creates a contrast in velocity, which contributes to “trap seismic energy as the low velocity surface layer enhances - grid point - events excluded, mag < mmin-Δ - Nb events within distance R used in b-value calculaon - events excluded, enough events found closer to grid point - events too far from grid point, not in the neighbourhood (b) Fig. 7 Frequency–magnitude distribution (a) and a special distribution of events (b) illustrating what data are included and excluded in the determination of the local b-value associated with a gridpoint 13 Fig. 8 Relative 3D distribution of s-wave (a) and p-wave amplitude (b) for a double-couple shear mechanism (Potvin and Wesseloo 2013) The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines Fig. 9 Illustration of the influence of the radiation pattern on the wave intensity in three dimensions; a, b illustrate the difference in ppv′ of diffirence in the slip direction, and c assuming uniform radiation (Potvin and Wesseloo 2013) the formation of surface waves such as Raleigh and Love waves”. Body waves are also reflected off the excavation boundary, and superimposition of the complex waveforms occurs. The complex interaction of the body waves with excavations and geological contacts is illustrated by the experimental work of Daehnke (1997). Figure 10 shows the isochromatic fringes from the photoelastic experiment performed by Daehnke (1997). Local amplification or reduction in ppv is also different for various excavation-to-wavelength ratios (Wang and Cai 2015). The effect of radiation pattern and the reflection and refraction of the seismic waves can be assessed through numerical modelling for a single event (e.g. Hildyard et al. 1995; Hildyard 2007; Mendecki and Lotter 2011; Wang and Cai 2015), but cannot, with current technology, practically be performed as part of a probabilistic process. The relationship between the body wave ppv and the actual ppv at the surface of an excavation can be expressed as follows: ( ) log (ppv) = log ppv� + 𝛿(i, j) (21) where ppv = the ppv at the boundary of the excavation; ppv′ = body wave ppv without any wave–excavation interaction; δ(i, j) = the logarithm of the amplification factor for the specific location i and event j. The site amplification is poorly understood, and for this reason the body wave ppv in the rock mass (denoted here as ppv′) is used as a proxy for vibration intensity. For dynamic ground support design, ppv′ is often used as an input to empirical (Duan 2016; Duan et al. 2015; Heal 2010; Heal et al. 2006), and analytical methods (Mining Research Directorate 1996) with an amplification factor applied separately as part of the design process. For these reasons, we currently restrict ourselves to the evaluation of ppv′. Hazard maps based on ppv′ would be more smeared than a hazard map based on the actual ppv because the localised amplification or reduction in the body wave ppv due to the factors mentioned above is not taken into account. As technology improves, both the assessment of ppv′ and the design methodologies’ reliance on these values need to be improved. 3.6.1 Strong Ground Motion Relationship For the strong ground motion relationship, the following generic formulation is used for which the coefficients should be obtained through back-analysis from recorded data: ( ) ( ) log ppv� = c0 + cM ⋅ M + cR ⋅ log R + cRs ⋅ Rs + cSSD ⋅ log (SSD) + 𝜀 (22) where ppv′ = peak particle velocity of the body wave; M = is the magnitude; ε = an error function; R = the epicentral distance to the site under consideration; Rs = saturation distance; SSD = seismic source parameter, static stress drop, which quantifies the difference between the mean shear stress before and after an event. Neglecting to quantify δ(i,j) of Eq. (21) for every combination of location i and event j results in a dispersion of the actual values about the regression (Lasocki 2005), and this is quantified by the error function ε. This proposed equation includes a saturation distance, Rs, resulting in the saturation of the relationship in the near field. The saturation distance is expected to be proportional to the source size, which for practical purposes can be written as a function of the magnitude. In lieu of data from the near field, formulating the saturation distance as a function of the magnitude is also important to ensure stable results when obtaining site-specific coefficients for the above formulation. Mendecki (2008, 2013a) formulates a strong ground motion relationship using log(potency) as magnitude scale and uses a saturation distance proportional to the cube root of potency. 13 J. Wesseloo 1 1 ; c = 2; cSSD = ; cRs = 0; c0 = −4.32 for R in metres, and 2 R 2 𝜀(P) = qnormal(P, 𝜇 = 0, 𝜎 = 0.405), with M = MR + 1.15 cM = (23) where SSD = the static stress drop in Pa; P = probability of non-exceedance i.e., reliability; qnormal = inverse cumulative normal distribution; μ = mean of error function; σ = standard deviation of error function; MR = Richter magnitude. To obtain the relationship recommended by the CRH for use in design, let P = 0.9 with ε(P = 0.9) = 0.519. Potvin and Wesseloo (2013) extend the relationship used in the CRH to include near-field saturation. The generic formulation can be reduced to that proposed by Potvin and Wesseloo (2013) using the following in addition to the coefficients mentioned above: (a) cRs = 1; Rs = Ro = D ⋅ 10 MR +1.5 3 1.14 ;D= √ 3 SSD ⋅ 1 106 (24) where Rs = the radius of saturation in metres; Ro = source radius in metres; SSD = the static stress drop in Pa; MR = Richter magnitude. 3.6.2 Calculation Process for Probabilistic Assessment of ppv′ (b) Detonaon point Clamped non-cohesive parng plane Open slot Araldite B Makrolon (c) Fig. 10 (a, b) Photoelastic model showing the reflection and refraction of stress wave when; a interacting with a long narrow opening, and b when interacting with a similar opening bounded by two discontinuous planes above and below the opening (after Daehnke 1997). a “stope” in homogeneous medium, b “stope” bounded by non-cohesive parting planes, c definition sketch The generic formulation can be used to express the wellknown far field relationship proposed by the Canadian Rockburst Handbook (CRH) (Kaiser and Maloney 1997; Mining Research Directorate 1996), using the following coefficient values: 13 From the strong ground motion relationship (Eq. 22), the probability of the ppv′ exceeding a specified value, PPV′, for a given magnitude, ML, and a given distance, R, can be obtained. For each grid cell, k, the event rate density, n, and the power law exponent, β, are obtained through the grid-based approach [Fig. 11 a(i)]. The probability density function of the largest event for each grid cell, the derivative of Eq. (8), is given by: ( ) k M|̄nk , 𝛽 k ( ) dFmax k k k (25) fmax M|̄n , 𝛽 = dM The distance between the possible event locations and the target point of interest is taken as the shortest linear distance, i.e.: √ ( )2 ( )2 ( )2 (26) Ri (x, y, z) = xi − x + yi − y + zi − z For every target point, i, and every grid cell, k, the probability of ppv′ exceeding the value of PPV′ is given by: The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines ]k [ P ppv� ≥ PPV� i = zk+ yk+ x+k MUL � � � � ( [ ]) k (m|̄nk , 𝛽 k ) ⋅ P ppv� > PPV� |M, Ri (x, y, z) dMdxdydz fxk (x)fyk (y)fzk (z) ⋅ fmax (27) zk− yk− x−k m− where m = magnitude; m− = the smallest magnitude that could result in any ppv-value of interest; MUL = overall MUL for the whole mine; x−k , yk−,zk− = minimum x, y and z boundaries for grid cell k; x+k , yk+, zk+ = maximum x, y and z boundaries for grid cell k; nk, βk = event density rate and power law exponent for grid cell k; fxk , fyk , fxk = probability density function of event x, y and z location in cell k; k fmax = probability[ density function ]of the magnitude of the largest event; P ppv′ > PPV′ |m, r = the strong ground motion relationship (Eq. 22). Using the discretised volume and assuming a uniform seismic density distribution throughout each grid cell, the discretised formulations of Eq (27) can be expressed as follows with reference to Fig. 11. J L Y ∑ ∑ [ ]k ∑ P ppv� ≥ PPV� i = pMkj ⋅ p𝜀y y j l (28) [ ] ΔM ⋅ Δ𝜀 � � ⋅ P ppv > PPV |Mkj , Rikl , 𝜀y ⋅ L where J, L, Y = total number of bins in the magnitude, grid cell and epsilon, respectively; ΔM, Δε = bin widths for M and ε discretisation. For every grid cell, k, the probability distribution of the largest magnitude is known, and for every magnitude bin, j, the probability of Mkj can be assessed [Fig. 11 b(iii)]. The distance Rikl is known for every combination of target point, i, and sub-cell, l, of any grid cell, j [Fig. 11b(i)]. For any given Rikl and Mkj, the strong ground motion relationship can be evaluated and the ppv′ calculated for every ε bin, y (Fig. 11 b(iv)). The ppv′ijkly and its associated probability are calculated for every combination, ijkly, from which the full ppv′ probability curve can be obtained. With the evaluation of Eq. (28) the exceedance probability of PPV′ at any target point, j, resulting from any grid cell, k, can be obtained. The probability of ppv′ exceeding a prescribed PPV′ at target point, i, due to the hazard at every grid cell, k, can then be calculated as follows: ∏( [ ] [ ]k ) P ppv� ≥ PPV� i = 1 − 1 − P ppv� ≥ PPV� i (29) k In many design approaches, the 90 percentile value of ε is used (Heal 2010; Heal et al. 2006; Kaiser and Maloney 1997; Mining Research Directorate 1996). In industry, a constant value for ε is often used (generally 90 or 95 percentile value). For the approach presented here, however, the full distribution of ε is used as the propagation of the uncertainty quantified by ε, is an important component in a quantitative risk approach. The probabilistic evaluation of the ppv′ on the excavation target point is computationally intensive. The number of calculations scales linearly with both the number of excavation points and the number of gridpoints. In three-dimensional space, the gridpoints scale quadratically with the decreased grid spacing. The high resolution required for a full hazard map requires a large number of calculations. In order to facilitate understanding, the intricacies of code optimisation are ignored in the previous explanation of the calculation process. Several code optimisation techniques can be used to reduce the number of loops and calculations required. The calculation algorithm introduced in an mXrap app (Wesseloo and Harris 2015) was optimised to the point where the map shown in Sect. 4.3.2 could be produced in about 20 s on a standard laptop computer. A detailed discussion of the code optimisation is outside the scope of this paper. 3.6.3 Overall Strong Ground Motion Hazard Associated with Different Areas of the Mine Section 3.6.2 leads to a spatial distribution of exceedance probabilities at different locations in the mine. It is, however, important to also assess the exceedance probabilities for sections of infrastructure in different locations and for different lengths along the infrastructure. Consider, for example, the conceptual mining layout for a longhole stoping sub-level (Fig. 12). A dynamic failure in either the decline, the ore drive or any of the stope drives will each differently impact the economic and safety risk of the mine. If, for example, rockburst damage occurs anywhere along the section of the decline shown in Fig. 12, no access to the ore from that sub-level or any sub-level below is possible for the period necessary for rehabilitation. To quantify this risk, the seismic hazard over the total shown decline length needs to be evaluated. Quantifying the risk of partial ore loss of different quantities will require the evaluation of the seismic hazard over the different lengths of different drives. Similarly, the exposure of personnel to the seismic hazard differs for the different types and lengths of infrastructure. 13 J. Wesseloo Primary stope drive i) i) Secondary stope drive Fig. 12 Conceptual mining layout for a primary/secondary longhole stoping sub-level (Joughin 2017) ii) Annualisation (Secon 4.1) The target points on the excavation are, however, at arbitrary spacing and cannot be assumed to be independent. Two target points far apart may be assumed to be independent, whilst this may not be true for target points close to each other. Since the calculations are performed on target points of arbitrary spacing, an adjustment must be applied to account for the size of an independent unit, SIU (Fig. 13). Gilbert (1986) and Dowding and Gilbert (1988) investigated the dynamic stability of rock slopes and the effect of wave propagation on the stability of slopes. They concluded that, to excite a block, wavelengths greater than four times the block size are required. In a similar vein, we link the SIU to the wavelength with a factor of cλ, i.e.: iii) iii) p[Mk] probability distribution of largest magnitude for given k and bk (Equation 25) iv) iv) Volume normalisation (Section 4.2) SIU = 𝜆o ⋅ c𝜆 v) Spatial distribution of seismic hazard (Section 4.3.1) v) Display of probabilistic strong ground moon hazard map (Section 4.3.2) (a) (b) where SIU = the size of an independent unit; λo = wavelength at the event corner frequency; cλ = a defined fraction of the wavelength. From the Brune model (Brune 1970), one can obtain an estimate of the wavelength at the corner frequency of an event, as follows: √ 3 2 ⋅ 𝜋 3 7 10 2 ⋅(Mw +6) (31) ⋅ ⋅ 𝜆o = 2.34 16 Δ𝜎 Fig. 11 Conceptual illustration of the components of the probabilistic strong ground motion calculation The joint probabilities for nt independent points along the infrastructure can be calculated as follows: P[a ≥ A] = 1 − nt ∏ ( ) 1 − P[a ≥ A]i (30) i=1 Fig. 13 Definition sketch of excavation lengths used in calculated joint probabilities for length Γ 13 The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines where λ o = wavelength at the event comer frequency; Mw = moment magnitude (Hanks and Kanamori 1979); Δσ = static stress drop. For current purposes, cλ is assumed to be 14 , according to the results of Gilbert (1986) and Dowding and Gilbert (1988), and a conservative value for Δσ = 10 MPa is assumed. For other magnitude scales, empirical site-specific relationships between corner frequency, magnitude and static stress drop can be obtained through regression of site data. For the purpose of calculating the joint probabilities, the approach described in Sect. 3.6.2 is adjusted in the following manner. For every target point, i, and every gridpoint, k, the probability of exceeding PPV′ is obtained for every magnitude bin, j, as follows: P[ppv� ≥ PPV� |Mj ]ki = L Y ∑ ∑ l pMkj ⋅ p𝜀y ⋅ y [ ] ΔM ⋅ Δ𝜀 P ppv� > PPV� |Mkj , Rikl , 𝜀y ⋅ L (32) The joint PPV′ exceedance probability for a length of mine infrastructure, Γ, is calculated as follows (Fig. 13): [ ] P ppv� ⩾ PPV� 𝛤 )) ( ( nt Li ∏ ∏ ∏( ) =1− 1 − P[ppv� ⩾ PPV� |Mj ]ki SIUj i=1 j k (33) where Li = the length of mine infrastructure associated with calculation point, i; ­SIUj = the size of the independent unit for magnitude j; Γ = length of mine infrastructure for which the joint probability is calculated; nt = the number of target points within length Γ. 4 Expressing Seismic Hazard The spatial distribution of probabilities presents a difficulty in communicating the true nature of the hazard. The contour/isosurfaces of probabilities can easily be interpreted in a relative sense: “hot” and “cold” volumes showing higher and lower relative spatial probability of occurrence. The spatial probability distribution in units of probability/ unit time/unit volume, however, leads to small numbers that carry little or no meaning for engineers, management and the workforce. For this reason, we need to normalise values for both time and volume. These normalisations are necessary to enable us to directly compare hazard levels of different duration contained within different sized volumes. They also provide a consistent system for communicating the hazard, without which, the management of the seismic hazard is impeded. 4.1 Annualisation of Hazard For the purpose of this study, we normalise the hazard probability to equivalent annualised values. This normalisation leads to a “yearly probability”, but it is important to note that this should not be interpreted as the probability for a physical year (future or historical). It is the probability value appropriate to the timescale for which the mean seismic rate is applicable, expressed in equivalent annualised terms. Annualisation also allows one to calculate the associated risk and evaluate it against corporate accepted annualised risk levels. To enable direct comparison between hazards of different durations, it is necessary to normalise the calculated probability to the same equivalent timescale. This normalisation can be performed as follows: ( ) Tn PTn = 1 − 1 − PTe Te (34) where Tn, Te = the normalised time frame and the original timeframe, respectively; PTn, PTe = the equivalent probabilities expressed for timeframes Tn and Te, respectively. A hazard with a weekly probability of 1% can be expressed with equivalent annualised values as 1 − (1 − 0.01)52 = 40%, whilst a hazard with a biennial probability of 50% can be expressed in equivalent annualised values as 1 − (1 − 0.5)0.5 = 30%. These calculations assume that both the hazards are present over a long time period. If, for example, a hazard with a weekly probability of 1% is only present for 1 week in the year, the yearly hazard would also be 1%. This sometimes leads to misunderstanding in the application of hazard assessments in industry, where a short-lived but repeating hazard is sometimes evaluated in isolation. Seismic hazard in a mine is transient in space and time and although the seismic hazard at a specific location might be short lived, the hazard is of a repeating nature. For example, the hazard associated with the mining of a single stope might only be present during the time it takes to mine that stope, but, a similar hazard might occur due to the mining 13 J. Wesseloo 1 (a) Stopes Historic seismicity Seismicity during “current “ month (b) of the stopes is mined for a month during which a seismic response is induced in the indicated annulus around it. The seismicity in this annulus ceases when mining in this stope is complete. During the following month, the next stope is mined with the associated induced seismicity limited to its surrounding annulus. The argument can be further simplified by assuming a constant b = 1 over the whole volume and the whole year, and by assuming that the total number of events occurring in the annulus of each of the stopes is the same at 1000 events > ML-2. For each stope, the probability of exceeding ML2 is 3.92%, and if evaluated in isolation, may be regarded as acceptable. Cumulating the number of events for all 12 stopes, however, results in the total probability of exceeding ML2 of 38%. In the year, the company is exposed to the total hazard of P[ML > 2] = 38%, even though each stope only has an individual monthly hazard of 3.9%. If exposing the company to the yearly hazard of 38% is not acceptable, by implication, it is not acceptable to expose the company to the hazard associated with every one of those stopes individually. Normalisation can be done to any timescale. Short time periods, however, lead to small numbers, which are in our experience often misinterpreted as small hazards and should be avoided. We propose the use of 1 year (annualisation), as this corresponds with the practice in other branches of engineering, financial risk management and corporate governance (Jonkman et al. 2003; Stacey et al. 2007; Terbrugge et al. 2006; Wesseloo and Read 2009). 4.2 Normalisation to Meaningful Volume (c) Fig. 14 Conceptual mine layout for illustrative example, consisting of 12 stopes with an annulus of seismicity induced by the stoping activity. a Month 1, b month 6, c month 12 of the next stope. Both long-term and repeating hazards can be normalised temporally using Eq. (34). To illustrate this concept, consider a simple fictitious mining scenario that consists of 12 stopes (Fig. 14). Each 13 The same principles also apply to the spatial representation of hazard. Before true comparison between the hazards for two different volume sizes is possible, the hazard must be expressed in values normalised to the same representative volume scale. With the grid-based approach, the hazards in each grid are directly comparable as calculations are performed on a uniform grid. Representing this distribution through space therefore leads to a true spatial comparison. As the mine is exposed to the total hazard, in addition to the representation of the hazard through the whole mining volume, the total hazard for the whole mine or large mining block under consideration must also be provided. 4.3 Displaying Spatial Distribution of Seismic Hazard 4.3.1 Displaying Hazard Through the Rock Mass Volume The display of the distribution of the hazard at any particular time through space is possible with contours and isosurfaces, which gives a qualitative indication of “hot” and “cold” areas. Quantitatively, the meaning of the contour/isosurface The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines Fig. 15 Elevation view and cross section view of Tasmania mine with isosurfaces of hazard rating Fig. 16 Seismic hazard map showing the probability of exceeding ML2 within 50 m Fig. 17 Strong ground motion probability map showing the probability of exceeding ppv′ = 1 m/s 13 J. Wesseloo values is obscure with values in probability per year per ­m3. For this reason, we need to introduce a characteristic volume for normalisation of the volumetric component. One way to express the hazard spatially through the use of contours or isosurfaces is to plot a hazard rating. We can define a hazard rating as the magnitude with an annualised exceedance probability, P, in a characteristic volume, i.e. the magnitude with an exceedance probability P/year/characteristic volume. Hudyma and Potvin (2004) propose a seismic hazard rating with which many mines in Australia and Canada are familiar. The hazard rating values resulting from P = 15%, with the volume of a sphere having a 50 m radius, are similar to the hazard rating values of the Seismic Hazard Scale proposed by Hudyma and Potvin (2004) and were used for the definition of the hazard rating scale used here. Once the probabilistic hazard has been calculated on a grid basis, it is a simple extension to calculate the hazard rating and display it using contours or isosurfaces, as shown in Fig. 15. 4.3.2 Displaying Hazard on Excavations For any point in space, one can easily calculate the probability of exceeding a specified magnitude, ML, within a specified distance, R, i.e. P[m ≥ ML|r ≤ R]. This is computationally efficient compared to mapping probabilistic strong ground motion evaluations and the computations Fig. 18 Conceptual layout of parallel mine excavations with associated probability of exceedance values (Sect. 3.6.2) (a) and spatially cumulative exceedance probability values (Sect. 3.6.3) with subsequent zonation according to the specified risk classes (Sect. 4.3.2) (b) 13 The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines among very small probabilities, with a well-calibrated range limited to between 20 and 80%. Expressing hazards should therefore be done in a way that utilises values in the wellcalibrated range of human cognitive discrimination. For this purpose, the target calculation points are grouped into zones of similar hazard levels. The total exceedance probabilities for each of these zones are calculated with the method discussed in Sect. 3.6.3. The zonation is performed as follows: target points are sor ted wit h increasing hazard as def ined by P[ppv� ≥ PPV� |Mj ]i (Eq 29), i.e. target point 1 having the lowest hazard] (Fig. 18a). For every target point, n t, [ P ppv� ≥ PPV� 1…n (Eq. 33) is calculated, leading to a spat Fig. 19 Strong ground motion probability map showing the total probability of exceeding a ppv′ = 0.6 m/s in different zones according to likelihood classes used in mine site risk matrices scale linearly with the number of points evaluated. A map of P[m ≥ ML|r ≤ R], like that shown in Fig. 16, can therefore be generated efficiently and for large problems. For the example shown in Fig. 16, the annualised probability of experiencing an event of ≥ ML2 within a distance of 50 m from the mine excavations is evaluated and expressed as a contour map. A probabilistic hazard map of ppv′ can be obtained, as discussed in Sect. 3.6.2. This results in a probabilistic ppv′ map as shown in Fig. 17. The example shown in Fig. 17 plots a map of the probability of exceeding a ppv′ of 1 m/s due to any possible event located anywhere in the rock mass surrounding the mine. The probability at each point on the surface is quite small (< 0.2% anywhere in the mine), with only a small section of the mine reaching those levels. Although the hazard distributions and the hazard values are correct, the small values associated with zones on the map are subject to misinterpretation. The interpretation of such contours is generally that there is total probability of 0.1–0.2% of exceeding the design PPV′ in the areas of the highest contour value. There is, however, a 0.1–0.2% chance of exceeding the ppv′ everywhere within that zone—the risk that needs to be communicated to stakeholders should be the integration of that risk over the whole zone. Moreover, Vick (2002) discusses the experimental work by Fischhoff et al. (1977) and Hogarth (1975) and concludes that people have little ability to distinguish tially cumulative exceedance probability map (Fig. 18b). The zonation is based on these cumulative exceedance probability values. A risk class is assigned to each target point, n, according to which class its cumulative exceedance probability value belongs. Risk classes can be defined according to the company risk matrix commonly used on mines leading to the hazard being expressed in terms familiar to all the stakeholders. The results of the zonation process for Tasmania mine are shown in Fig. 19. 5 Discussion and Conclusion The previous sections provided a methodology for assessing the current seismic hazard state in mines and for monitoring the changes in the hazard state on an ongoing basis. Due to the fact that many of the sources of seismic hazard in mines are of a transient nature, the continuous tracking of the change in the seismic hazard state provides valuable information for the management of the seismic hazard. Not all sources of seismic hazard are transient, and, as a result, careful consideration must be given to the data period used for the hazard assessment. Faults, dykes and lithological contact may deform co-seismically as they respond to the mining-induced stress changes. Such sources are stationary and often react to the mining activity on a longer timescale. Depending on the mining method, sequence and layouts, the stress change and associated change in seismic hazard from such sources can occur in relatively short time frames. For pillars and stationary abutments, the associated seismic hazard may increase as loading increases and decrease after complete yielding occurs. Generally, the change in seismic hazard associated with pillars and stationary abutments occurs on a longer timescale. In the vicinity of active mine workings, temporary pillars and abutments result in transient sources. As a result, transient high hazard sources superimpose on stationary sources creating a complex seismic hazard regime changing with mining activity. 13 J. Wesseloo Fig. 20 Probabilistic strong ground motion hazard maps showing the migration of inmine seismic hazard over time. Plots of annualised likelihood of exceeding ppv′ exceeding 0.6 m/s based on a hazard period of 3 months 13 The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines Fig. 21 Plots of annualised likelihood of exceeding ppv′ exceeding 0.6 m/s based on different data periods a a 2011-02-01 | 24 Months 2011-02-01 | 12 Months b c e d a) Dissipated hazard sources shown due to long me periods. b) Recent mining acvity in this area. c) Strong reacon to mining of the abutment in this area. d) Recent mining of stopes in new area. e) Hazard around unmined pillar. No mining occurring near this area. 2011-02-01 | 6 Months Limiting the hazard assessment period to short time periods gives more weight to transient sources and results in a better representation of spatial change in seismic hazard associated with the mining activity on a shorter timescale. Extending the hazard data period to long periods will result in a spatial smoothing of the transient hazard and give a better definition of the stationary hazard sources. Seismic hazard assessment, therefore, needs to be performed with reference to the mining cycle at different timescales of interest. As the method can be updated within a relatively short calculation period, a frequent update of the hazard assessment will provide indication of areas where the hazard is fairly stationary or increasing/decreasing rapidly. 13 Acknowledgements My sincere appreciation to Dr Lindsay Linzer and William Joughin for their comments on the original manuscript and to Gerhard Morkel for fruitful discussions during the writing of this paper. I thank the mXrap Consortium (https://mxrap.com/the-mxrap-conso rtium) for their financial support of this work. The support of Paul Harris with the implementation of this work into efficient algorithms is greatly appreciated. This work was not done in isolation and I would like to acknowledge the contribution of my colleagues at the Australian Centre for Geomechanics, through fruitful discussions, suggestions and challenging questions. ∆ ∆ Log scale The migration of the seismic hazard zones over time is illustrated in Fig. 20. For this figure, the data period is kept constant at 3 months and the likelihood zones (similar to Fig. 19) of ppv′ exceeding 0.3 m/s on the ore drives, footwall drives and the declines are shown; only the ore drives are visible from the viewpoint shown in the figure. Figure 21 plots the hazard zones shown in Fig. 20 using different data periods. Using 24- and 12-month data periods includes data from transient sources around mine workings that have dissipated. This results in overestimation of the hazard in these areas. Six month and three month periods show similar results and show the strong reaction to the mining of the abutment in the upper area and the stoping of new areas lower down. A high seismic hazard is also shown in an unmined pillar, whilst no mining activity is occurring near that area. In Australia, the dynamic demand, for which ground support is designed, is often specified in terms of a magnitude occurring at a specified distance (e.g. ML2 at 50 m) or in terms of a design ppv′ that the support is required to withstand. The probabilistic hazard assessment procedure presented here allows for the assessment of seismic hazard in terms of these design demand values. Using this method, areas where ground support is under-designed can be highlighted and appropriate action taken. The method allows for the seismic hazard to be evaluated within the general risk management framework of the mine with the hazard reflected in the company’s risk matrix. UL J. Wesseloo Mmin MUL ML Fig. 22 Inverse cumulative distribution plots illustrating the definition of the factors in Eq. (37) 12 0.5 0.25 Δ εP+ → 0, b = 0.75 Δ Δ Δ Appendix 1: Error in exceedance probability resulting from error in MUL See Figs. 22, 23, 24, 25. The truncated cumulative distribution of event magnitude can be written as follows (Gibowicz and Kijko 1994): Δ Δ Fig. 23 εP+ and εP− as a function of Δ for different Δε 13 The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines 0.01 0.1 CDF of largest event size R 1 10 n = 100 F(ML) Fig. 24 Ratio between Eqs. (40) and (41) with different n and F(ML) values (35) where F = the cumulative distribution functions; β = the power law exponent = b·ln(10); mmin = magnitude of completeness; MUL = upper truncation value of magnitude. The meaning of MUL is discussed in Sect. 3.1.1; M = magnitude. For the mean number of events over the time frame under consideration, n̄ , the exceedance probability of ML can be written as follows (refer to Sect. 3.4 and “Appendix 2”): P(M > ML|̄n) = 1 − [F(ML)]n̄ which can be rewritten as: )n̄ ( −𝛽(𝛿) � Fmax = 1 − 1−e−𝛽(𝛿+Δ) for 𝛿 > 0; Δ > 0 1−e � = 1− Fmax ( 1−e−𝛽(𝛿) 1−e−𝛽(𝛿+Δ) ) n = 100 0.1 0.01 ML - mmin (37) Fig. 25 Comparison between Eqs. (40) and (41) for mmin = − 2, MUL = 3, b = 1 Consider the influence of error, Δε, in the estimation of MUL on the assessment of the exceedance probability for given magnitude M. For an error of Δε in the estimate of MUL the error in the exceedance probability can be defined as: 𝜀P = for 𝛿 > 2; Δ > 0 1 10 (36) Where F′max = the exceedance probability; Δ = MUL – M; δ = M – mmin; n̄ = the mean number of events over the time frame under consideration. These factors are illustrated in Fig. 22. This formulation is independent of the actual value of ML which is implicitly defined by factors Δ and δ. This formulation can further be made independent of δ by writing n̄ as a function of δ and the mean number of events of magnitude ML, n̄ ML , i.e.: n̄ ML 1−F(𝛿,Δ) Inverse CDF of largest event ⎧0 for M < mmin ⎪ −𝛽 (M−mmin ) F(M) = ⎨ 1−e−𝛽 (M −m ) for mmin ≤ M ≤ MUL UL min 1−e ⎪1 for M > MUL ⎩ ML - mmin (38) � � Fmax (Δ + Δ𝜀) − Fmax (Δ) � Fmax (Δ) (39) 13 J. Wesseloo where εP = the error in probability of exceeding ML; Δε = the error in estimation of MUL. With εP+ and εP− denoting εP for positive and negative values of Δε, respectively. The error value εP decreases with increases in b, Δ and n̄ ML. Upper bound estimates for εP can therefore be obtained by assuming lower bound values for b, Δ and n̄ . Figure 23 shows the upper bound of εP as a function of Δ for different values Δε with conservative lower bound estimates n̄ ML → 0, b = 0.75. The error, εP, decreases with an increase in b-value and an increase in n̄ ML and is therefore larger for smaller hazards, reducing with an increase in hazard. Appendix 2: The Effect of Excluding the Uncertainty in the Number of Events Described by the Poisson Distribution Two formulations for the exceeding probability of at least one event exceeding ML are compared here. The first is a formulation used in forecasting future seismicity and includes the uncertainty of the number of events in the future period Δt, which can be written as (Eq. 14): P(M > ML|̄n) = 1 − Fmax (ML, n̄ ) = 1 − e−̄n⋅(1−F(ML)) (40) The second formulation used in this work for the assessment of the current hazard state ignores the uncertainty related to the number of events and assumes a mean number of events to occur. (41) For the formulation in Eq. (42) to be conservative, the following inequality must be true P(M > ML|̄n) = 1 − Fmax (ML, n̄ ) = 1 − [F(ML)]n̄ R= 1 − e−̄n⋅(1−F(ML)) ≤1 1 − [F(ML)]̄n (42) E qu a t i o n E q . ( 4 2 ) h o l d s t r u e fo r a l l for n ≥ 0 and 0 ≤ F(ML) ≤ 1, as shown in Fig. 24. From the figure, it can be seen that the difference between the two formulations approaches zero for large n̄ and large values of F(ML), whilst the largest difference between the two formulations occurs for small values of F(ML) and low seismic rate. A small amount of conservatism will therefore result in areas of high hazard, and lower accuracy with higher conservatism in areas of low hazard. To illustrate this further in the context of this paper, consider the scenario with a magnitude of completeness, mmin, of − 2, MUL = 3, and b = 1. The resulting formulations of Fmax(ML) are compared in Fig. 25. 13 References Boore D (1986) The effect of finite bandwidth on seismic scaling relationships. In: Das S, Boatwright J, Scholz CH (eds) In earthquake source mechanics. American Geophysical Union, Washington, DC, pp 275–283 Brune JN (1970) Tectonic stress and the spectra of seismic shear waves from earthquakes. J Geophys Res 75(26):4997–5009 Convertito V, Maercklin N, Sharma N, Zollo A (2012) From induced seismicity to direct time-dependent seismic hazard. Bull Seismol Soc Am 102(6):2563–2573 Daehnke A (1997) Stress wave and fracture propagation in rock. Ph.D. thesis, Technical University of Vienna Di Bona M, Rovelli A (1988) Effects of the bandwidth limitation of stress drops estimated from integrals of the ground motion. Bull Seismol Soc Am 78(5):1818–1825 Dong LJ, Wesseloo J, Potvin Y, Li XB (2016) Discriminant models of blasts and seismic events in mine seismology. Int J Rock Mech Min Sci 86:282–291 Dowding CH, Gilbert C (1988) Dynamic stability of rock slopes and high frequency traveling waves. J Geotech Eng 114(10):1069–1088 Duan W (2016) An assessment of the significance of factors affecting the occurrence of rockburst damage. Master’s thesis, The University of Western Australia Duan W, Wesseloo J, Potvin Y (2015) Evaluation of the adjusted rockburst damage potential method for dynamic ground support selection in extreme rockburst conditions. In: Potvin Y (ed) International seminar on design methods in underground mining, 17–19 November 2015, Perth. Australian Centre for Geomechanics, Perth, Western Australia, pp 399–418 Durrheim RJ (2012) Functional specifications for in-stope support based on seismic and rockburst observations in South African mines. In: Potvin Y (ed) Proceedings of the sixth international seminar on deep and high stress mining, 38–30 March 2012, Perth, Australian Centre for Geomechanics, Perth, pp 41–55 Fischhoff B, Slovic P, Lichtenstein S (1977) Knowing with certainty: the appropriateness of extreme confidence. J Exp Psychol Hum Percept Perform 3(4):552–564 Gibowicz SJ, Kijko A (1994) An introduction to mining seismology. Academic Press, San Diego Gilbert C (1986) Effect of wave propagation on stability of slopes. Master of Science, Northwestern University, Illinois Hanks TC, Kanamori H (1979) A moment magnitude scale. J Geophys Res Solid Earth 84(B5):2348–2350 Heal D (2010) Observations and analysis of incidences of rockburst damage in underground mines. Doctoral thesis, The University of Western Australia Heal D, Potvin Y, Hudyma MR (2006) Evaluating rockburst damage potential in underground mining. In: The 41st U.S. symposium on rock mechanics, golden rocks 2006, 17–21 June 2006, Golden, Colorado, American Rock Mechanics Association Hildyard, MW, Daehnke A, Cundall PA (1995) WAVE: a computer program for investigating elastodynamic issues in mining. In: The 35th U.S. symposium on rock mechanics (USRMS), 5–7 June 1995, Reno, Nevada, American Rock Mechanics Association Hildyard WM (2007) Manuel rocha medal recipient wave interaction with underground openings in fractured rock. Rock Mech Rock Eng 40(6):531–561 Hogarth RM (1975) Cognitive processes and the assessment of subjective probability distributions. J Am Stat Assoc 70(350):271–289 Hudyma M, Potvin Y (2004) Seismic hazard in Western Australian mines. J S Afr Inst Min Metall 104(5):265–275 The Spatial Assessment of the Current Seismic Hazard State for Hard Rock Underground Mines Hudyma M, Potvin YH (2010) An engineering approach to seismic risk management in hardrock mines. Rock Mech Rock Eng 43(6):891–906 Jonkman SN, van Gelder PHAJM, Vrijling JK (2003) An overview of quantitative risk measures for loss of life and economic damage. J Hazard Mater 99(1):1–30 Joughin WC (2017) Dealing with uncertainty and risk in the design of deep and high stress mining excavations. In: Wesseloo J (ed) Proceedings of the eighth international conference on deep and high stress mining, 28–30 March 2017, Perth, Australian Centre for Geomechanics, Perth, pp 489–507 Kaiser PK, Maloney SM (1997) Scaling laws for the design of rock support. Pure appl Geophys 150(3–4):415–434 Kaiser P, Vasak P, Suorineni F, Thibodeau D (2005) New dimensions in seismic data interpretation with 3-D virtual reality visualization in burst-prone ground. In: Potvin Y, Hudyma M (eds) Sixth international symposium on rockburst and seismicity in mines, RaSiM6, 2005, Perth. Australian Centre for Geomechanics, Perth, Western Australia, pp 33–47 Kijko CW (1994) The assessment of seismic hazards in mines. J S Afr Inst Min Metall 94(7):179–185 Kijko A (2011) Seismic hazard. In: Gupta HK (ed) Encyclopedia of solid earth geophysics. Springer, Dordrecht, pp 1107–1121 Kijko A, Singh M (2011) Statistical tools for maximum possible earthquake magnitude estimation. Acta Geophys 59(4):674–700 Lasocki S (2005) Probabilistic analysis of seismic hazard posed by mining induced events. In: Potvin Y, Hudyma M (eds) Sixth international symposium on rockburst and seismicity in mines, RaSiM6, 9–11 March 2005, Perth. Western Australia, Australian Centre for Geomechanics, Perth, Western Australia, pp 151–156 Lasocki S (2008) Some unique statistical properties of the seismic process in mines. In: Potvin Y, Carter J, Dyskin A, Jeffrey R (eds) Southern hemisphere international rock mechanics symposium, SHIRMS, 16–18 September 2008, Perth. Western Australia, Australian Centre for Geomechanics, Perth, Western Australia, pp 667–678 Lasocki S, Urban P (2011) Bias, variance and computational properties of Kijko’s estimators of the upper limit of magnitude distribution, M-max. Acta Geophys 59(4):659–673 Lehmann EL, Romano JP (2005) Testing statistical hypotheses. Springer, New York Malovichko D (2012) Discrimination of blasts in mine seismology. In: Potvin Y (ed) Proceedings of the sixth international seminar on deep and high stress mining, 38–30 March 2012, Perth, Australian Centre for Geomechanics, Perth, pp 161–172 Malovichko D (2017) Assessment and testing of seismic hazard for planned mining sequences. In: J Wesseloo (ed) Proceedings of the eighth international conference on deep and high stress mining, 28–30 March 2017, Perth, Australian Centre for Geomechanics, Perth McGarr A, Simpson D, Seeber L (2002) Case histories of induced and triggered seismicity. In: William HKPCJ, Lee HK, Carl K (eds) International Geophysics. Academic Press, New York, pp 647–661 McGaughey J, McLeod R, Pears G (2007) Integrated, real-time, 3D GIS-based geotechnical hazard assessment. In: Eberhardt E,Stead D, Tom M (eds) 1st Canada-US rock mechanics symposium, rock mechanics meeting society’s challenges and demands, 27–31 May 2007, Vancouver, Canada, Taylor & Francis Group, London, pp 21–28 Mendecki A (2008) Forecasting seismic hazard in mines. In: Potvin Y, Carter J, Dyskin A, Jeffrey R (eds) First southern hemisphere international rock mechanics symposium, SHIRMS 2008, 16–19 September 2008, Perth. Western Australia, Australian Centre for Geomechanics, Perth, Western Australia, pp 55–69 Mendecki A (2012) Keynote Lecture: Size distribution of seismic events in mines. In: Australian earthquake engineering society conference, 7–9 December 2012, Queensland, Australian Earthquake Engineering Society, pp. 20 Mendecki A (2013a) Keynote Lecture: Characteristics of seismic hazard in mines. In: Malovichko A, Malovichko D (eds) Eighth international symposium on rockbursts and seismicity in mines, RaSiM8, 1–7 September 2013, Saint-Petersburg-Moscow, Geophysical Survey of Russian Academy of Sciences, Mining Institute of Ural Branch of Russian Academy of Sciences, Russia, pp 275–292 Mendecki A (2013b) Frequency range, logE, logP and magnitude. In: Malovichko A, Malovichko D (eds) Eighth international symposium on rockbursts and seismicity in mines, RaSiM8, 1–7 September 2013, Saint-Petersburg-Moscow, Geophysical Survey of Russian Academy of Sciences, Mining Institute of Ural Branch of Russian Academy of Sciences, Russia, pp 978–975 Mendecki A, Lotter E (2011) Modelling seismic hazard for mines. In: Australian earthquake engineering society 2011 conference, 18–20 November 2011. South Australia, Australian Earthquake Engineering Society, Barossa Valley Milev AM, Spottiswoode SM (2005) Strong ground motion and site response in deep South African mines. J S Afr Inst Min Metall 105(7):515–524 Mining Research Directorate (1996) Canadian rockburst research program 1990–1995, a comprehensive summary of five years of collaborative research on rockbursting in hardrock mines. CAMIRO Mining Division, Canada Morkel IG, Wesseloo J (2017) The effect of sensor bandwidth limitations on the calculation of seismic hazard for mines. In: Vallejos JA (ed) Ninth international symposium on rocbursts and seismicity in mines, 15–17 November 2017. Santiago, Chile, Ediarte S.A., pp 42–49 Potvin Y, Wesseloo J (2013) Towards an understanding of dynamic demand on ground support. J S Afr Inst Min Metall 113(12):913–922 Rebuli DB, van Aswegen G (2013) Short term Seismic hazard assessment in S.A Gold Mines. In: Malovichko A, Malovichko D (eds) Eighth international symposium on rockbursts and seismicity in mines, RaSiM8, 1–7 September 2013, Saint-Petersburg-Moscow, Geophysical Survey of Russian Academy of Sciences, Mining Institute of Ural Branch of Russian Academy of Sciences, Russia, pp 323-331 Stacey TR, Terbrugge PJ, Wesseloo J (2007) Risk as a rock engineering design criterion. In: Potvin Y, Stacey TR, Hadjigeorgiou J (eds) Challenges in deep and high stress mining. Australian Centre for Geomechanics, Crawley, pp 19–25 Terbrugge PJ, Wesseloo J, Venter J, Steffen OKH (2006) A risk consequence approach to open pit slope design. J S Afr Inst Min Metall 106(7):503–511 Utsu T (1999) Representation and analysis of the earthquake size distribution: a historical review and some new approaches. Pure appl Geophys 155(2–4):509–535 Vallejos JA, McKinnon SD (2013) Logistic regression and neural network classification of seismic records. Int J Rock Mech Min Sci 62:86–95 Vick S (2002) Degrees of belief: subjective probability and engineering judgement. Am Soc Civil Eng, New York Wang X, Cai M (2015) Influence of wavelength-to-excavation span ratio on ground motion around deep underground excavations. Tunn Undergr Space Technol 49:438–453 Wesseloo J (2013) Towards real-time probabilistic hazard assessment of the current hazard state for mines. In: Malovichko A, Malovichko D (eds) Eighth international symposium on rockbursts and seismicity in mines, RaSiM8, 1–7 September 2013, SaintPetersburg-Moscow, Geophysical Survey of Russian Academy of 13 J. Wesseloo Sciences, Mining Institute of Ural Branch of Russian Academy of Sciences, Russia, pp 307-312 Wesseloo J (2014) Evaluation of the spatial variation of b-value. J South Afr Inst Min Metall 114(10):823–828 Wesseloo J, Harris PC (2015) mXrap software app, mining induced seismicity—grid based hazard assessment, version 1. Australian Centre for Geomechanics, Perth Wesseloo J, Read J (2009) Acceptance criteria. In: Stacey P, Read J (eds) Guidelines for open pit slope design. CSIRO Publishing, Calyton, pp 221–236 13 Wesseloo J, Woodward K, Pereira J (2014) Grid-based analysis of seismic data. J South Afr Inst Min Metall 114(10):815–822 Woodward KR, Tierney SR (2017) Seismic hazard estimation using databases with bimodal frequency–magnitude behaviour. In: Hudyma M, Potvin Y (eds) Proceedings of the first international conference on underground mining technology, 11–13 October 2017, Sudbury, Australian Centre for Geomechanics, pp 219–232